July 17, 2009 BUSINESS PROCESS FOR UTILITY CERTIFICATION Purpose: It is critical that existing utilities (both private and public) are identified early in the development of a project and any required modifications, relocations, or replacements are accounted for in the project budget, construction documents, and schedule. By certifying that the existing utilities have been taken into account, the M-NCPPC will avoid delays and cost overruns as the project is implemented. Note that Park Permit applicants are responsible for all existing utility certifications for work on Park property. Facility Planning Stage: 1. Site information gathering phase: the Project Manager (PM) should identify available information for the presence of on-site or off-site utilities at the project site. The PM should consult with Alchemy records for the site and PDD Survey Chief (Kenny Becraft) to provide any known existing utilities information for the site. The PM should also coordinate with the Park Manager to understand what facilities exist on the site, are currently in use, or are abandoned. 2. Scope of work phase: the RFP for consultant services should require the consultant to contact all public utility companies or agencies to request utility record information for the site and investigate what private utilities may exist on the site. Copies of this information should be forwarded to the PM and documented on the design plans. The RFP should include a requirement for the services of an underground utility locator if needed, to identify any utilities that might affect the design. The PM should not request that the PDD Survey Unit perform this service, as there will be a potential for liability to the Commission, unless the project is an in-house design. For an in-house design, the PM is responsible for identifying utility information and may request in-house survey assistance. 3. Start of Facility Planning: the consultant, or PM for in-house designs, should send the utility record request letters (Attachment C) to all of the public utility companies or agencies in the area and must require written confirmation of the existence or nonexistence of the respective agency utilities in proximity to the project site (a list for Montgomery County utility agencies is compiled – see Attachment A). 4. 30% -50% through Facility Planning: when the extent of utility impact is determined, the design consultant or PM shall contact all of the utility companies that maintain facilities which are determined to be in conflict with the proposed construction and request input 1 regarding how the conflict can be avoided or minimized. PM should also provide a set of plans to Central Maintenance (Arnold Ramsammy) for on-site utility verification. If it is determined that the utility must be relocated, the PM/design consultant must request from the utility company a cost estimate and general timeframe for relocation of the affected utilities. The PM/design consultant must also request “prior right information” for the utility, which includes any recorded easement rights on Commission property or adjacent Montgomery County or State Right-of-Way. This information will help M-NCPPC determine who is responsible for the relocation costs. 5. Final Facility Plan stage: the consultant or PM shall produce a Utility Survey and Relocation Certification (USRC) including all appropriate utility documentation and costs (including contact information) and incorporate the USRC in the Facility Plan report for future use during Detailed Design. Detailed Design Stage: 1. Start of Detailed Design: if there is a significant time lag between the facility planning stage and detailed design stage the consultant or PM (for an in-house design) must confirm that there is no change to the USRC for location or existence of utilities that were identified and documented during Facility Planning, include any information for utilities that have since been installed, and verify that the USRC information is still valid. 2. RFP for Detailed Design: the PM should consider whether additional investigations (test pits, underground utility locator, etc.) may be needed to complete the design. 3. Early in the Detailed Design: the PM should re-establish contact with any affected utility company to understand the requirements for design, construction, and timing of relocations or modifications. 4. 70% through Detailed Design: the PM must send a letter (can be a form letter) to all the utility companies who were identified to be in conflict with the design of the project asking those utility companies to start their relocation design and provide us with updated costs and schedule to complete their work. This request should include a project construction schedule and the date by when M-NCPPC expects their utilities to be relocated. The Construction Manager should be involved with all relocation efforts in order to understand the coordination requirements and timing of the work. 5. Completion of Detailed Design: the PM or design consultant along with the Construction Manager must continue to coordinate the relocation design with the affected utility companies up to completion of final design work. The contract documents must clearly 2 identify the location of all the existing utilities, their relocation design, future temporary or permanent relocations, the responsible party who will be relocating the utilities, and if any of these utilities are to be relocated by the Commission’s contractor. The design plans and contract documents must include exiting utilities to remain, utilities to be relocated, and appropriate bid items for test pits and all applicable relocation work. 6. Contract Documents stage: a Utility Survey and Relocation Certificate (USRC) must be prepared with the signature of the PM or design consultant in coordination with the Construction Manger and must be included in the contract documents for bid. The USRC statement shall include all the efforts documented to locate and coordinate utility work in proximity to the project site for on-site and off-site utilities. The USRC shall also include a list of all utility agencies that were contacted during the design of the project and include those that indicated that no conflict existed or result from the project. A copy of the USRC (a template will be provided in CADD – see Attachment B) must be signed by the PM or design consultant and included on the title sheet of the final plans. In addition, standard notes for utility locations on Park property must be included on the plans (see Attachment B). 3
© Copyright 2024 Paperzz