PROGRAMMES COMMISSIONING STRATEGY F3025787 2.1 Table of Contents 1. PURPOSE ...................................................................................................................2 2. KEY PRINCIPLES .......................................................................................................2 3. APPLICATION OF THE KEY PRINCIPLES................................................................4 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4. COMMISSION ..........................................................................................................4 INITIAL AGREEMENT (IA) – STRATEGIC OUTLINE CASE................................................4 AGREEMENT/PROCUREMENT DEVELOPMENT (OBC) ..................................................4 CONTRACTUAL SIGNING/IMPLEMENTATION FBC ........................................................5 IMPLEMENT – DESIGN, BUILD AND TEST (DBT) ..........................................................5 IMPLEMENT - ROLLOUT ............................................................................................6 BENEFITS REALISATION ...........................................................................................6 NSS ROLE AND RELATIONSHIP ..............................................................................6 DOCUMENT CONTROL ........................................................................................................8 DOCUMENT HISTORY .........................................................................................................8 DISTRIBUTION ....................................................................................................................8 F3025787 2.1 eHealth 1. Commissioning Strategy Purpose The purpose of this paper is to outline the key principles in relation to commissioning for the National eHealth Programme. The document has been circulated to eHealth Leads and NSS and feedback obtained to date has been incorporated where considered appropriate. Strategy Board is asked to agree the key principles (section 2) and note the points in relation to application (section 3), NSS relationship (section 4) and the examples covered in the appendix. 2. Key Principles 1. The eHealth Strategy Board will approve and own the Commissioning Strategy. 2. The eHealth PET will approve the commissioning approach in relation to each project/work, and in some cases this may be referred to the eHealth Programme Board Reasons for referring a commission for a project/piece of work to the eHealth Programme Board are as follows: Procurement incurring total boards costs in excess of £2m and/or > £0.5m to an individual NHS Board Complexity and/or sensitivity in one or more of the following impact of NHS Boards LDPs challenges/impacts the strategic eHealth applications and/ or services demands on NHS Boards to fulfil other eHealth commitments requires significant backing from NHS Boards to deliver political implications and/or directive N.B. All at the discretion of eHealth PET 3. The most appropriate commissioning approach should be determined based on the: merits of each project/work in question; stage in the national lifecycle; and particular circumstances The key questions in relation to each commission are as follows: possession and availability of appropriate skills; capacity to deliver; value for money; size and complexity (including political, public, legislative and financial); contracting capability (if a procurement); degree of risk involved; strategic importance / fit; and potential conflicts of interest. 4. Commissions can take on a number of different forms, for example: conducting a market intelligence exercise; creating a scoping report; developing a business case; developing user training material for new processes and systems; implementing a solution; eHealth - Commissioning Strategy Objective: F3025787 2.1 2 eHealth Commissioning Strategy procuring an application and associated services; or undertaking an investigation or audit. 5. Commissions could be awarded to any of the following: - a special board e.g. NSS; - NHS Board (either singly or as a consortium); - private sector (including AOA, Consultancy, other) - although note that an NHSScotland organisation would still have to take the lead in this case; - other public sector body (NES, Telehealth Centre, etc); or - academic sector. 6. The initial commission remit will be developed and the appropriate organisation(s) requested to submit a proposal against this. This will be undertaken primarily through the Head of Programmes working with an appropriate National project board, although the terms of reference and/or or business case development, as appropriate, will be led by the Head of Strategy. 7. eHealth Programme determines the ‘eHealth Commissions’ and agrees the scope, parameters, approach, budget, financial tolerances and any other relevant matters with the commissioned organisation. The details will include the individuals who will undertake the work, to ensure both the capacity of the commissioned organisation to deliver and the capability of the team. 8. The commissioned project manager must be suitably skilled and experienced irrespective of the lead organisation. An external project manager should be enlisted using the AOA contract or another consultancy when appropriate. The external project manager may be supported by an internal ‘assistant project manager’ to provide skills transfer on large projects. 9. There will always be appropriate representation on the national project board (and national programme board if required) from SGHD and the NHS health boards. SGHD will decide the project board membership to cover all stages of the project (this will include benefits realisation for the programme board). 10. In terms of the standard procurement project lifecycle, the typical approach to leading (L - L either one in italics will apply) on each commission is summarised in the table below. ‘S’ indicates a possible supporting role. Stage SGHD NSS Boards Third Party Commission L S S S Business Case Stage Initial Agreement (Strategic Outline Case) L S S S Business Case Stage Outline Case (OBC) L S S S Business Case Stage Full Case (FBC) S L L S Design build test S L S S Rollout S L L S Benefits realisation S S L S eHealth - Commissioning Strategy Objective: F3025787 2.1 3 eHealth Commissioning Strategy Notes Commission The norm is SGHD is the lead. However there can be projects for which it is appropriate for NSS, an NHS Board or consortium of NHS Boards. to be the lead. Initial agreement and agreement development The lead is determined by SGHD based on the project complexity, cost etc. For some projects SGHD will commission NSS, an NHS Board or consortium of NHS Boards to lead on this work. Design build test and rollout The norm is NSS is the lead. However there can be projects for which it is appropriate for the health board(s) or SGHD to be the lead. Example - a health board solution and approach that is appropriate could be adopted nationally. The next section gives more detail on how these principles would be applied with respect to the typical commissioning approach outlined in the table above. 3. Application of the Key Principles 3.1 Commission SGHD will lead on this stage, with input from the relevant groups/organisations that have an interest in recommending the project. This will be undertaken under the Strategy work stream, to assess the idea against the Programme strategy, blueprint and portfolio. N.B. This will be undertaken under the Strategy workstream, to assess the idea against the Programme strategy, blueprint and portfolio. The Design Authority would have input to check alignment to the architecture roadmap and the Change & Benefits workstream to ensure alignment with the benefits framework 3.2 Initial agreement (IA) – Strategic Outline Case SGHD will lead on all IAs that are strategically important, politically complex or likely to result in a significant national implementation. NSS or NHS Board(s) will lead on all other IAs. In all cases the Strategy workstream will assess the idea against the Programme strategy, blueprint and portfolio. The Design Authority would have input to check alignment to the architecture roadmap and the Commissioning Quality Services to ensure the appropriateness of and agreement with the outcomes and outputs There may be some initial third parties engagement, depending on the project. Substantial representative input from appropriate stakeholder groups to the project team and /or project board will be mandatory. 3.3 Agreement/Procurement Development (OBC) SGHD will lead on all OBCs that are strategically important, politically complex or likely to result in a significant national implementation. NSS or NHS Board(s) will lead on the procurement and all other OBCs. eHealth - Commissioning Strategy Objective: F3025787 2.1 4 eHealth Commissioning Strategy N.B. SGHD may lead on the procurement if there are particular circumstances surrounding the project which make it more appropriate to provide this lead (for example, if NSS does not possess the capacity). Third parties may be engaged at any stage in the lifecycle, depending on the project. Substantial representative input from appropriate stakeholder groups to the project team and/or project board will be mandatory. 3.4 Contractual Signing/Implementation FBC NSS will normally be the lead organisation for sign up to National contracts. However, the role could also be undertaken by an NHS Board or consortium of NHS Boards. Where health board resource is involved, this would normally be funded to ensure the resource is secured. In all complex national procurements, representative health boards will be involved. This will take place in two ways: 1. Lead NHS Board(s) - one or more NHS Boards will be engaged as part of the project team, in order to support requirements definition, evaluation and discussions around services and implementation approach. 2. There will be further representation on the user reference group and the project board from representative NHS Boards. At the project initiation stage, nominations will be sought from NHS Boards that would like to be involved in both 1 and 2 above. The recommendation will be openly discussed with the eHealth Leads group, NSS and the National Clinical Reference Group. The decision will be taken by the appropriate body as determined by the project (cost, complexity, political sensitivity etc). This will be based on need, experience, resources available and capacity to support. 3.5 Implement – Design, Build and Test (DBT) NSS will be the lead organisation for DBT, however the role could be undertaken by a lead NHS Board or consortium of NHS Boards. The concept of lead NHS Board is continued through implementation, with the intent that one or two of the lead Boards from the procurement stage continues to be the lead Board for implementation. This will provide further focus on the solution being fit for purpose, clinical buy-in and end to end service delivery. Maintaining the NHS Board input will be critical to the success of the rollout stage. Decisions made during design need to be universally acceptable to NHS Boards. This will require processes to ensure that all Boards sign-off on the design and test stages – ideally through involvement of the lead Boards with any potential issues highlighted to all Boards. It may require further discussion/input to achieve this sign-off for contentious points. Note should the procurement stage identify prerequisites that the lead Boards cannot meet then there would be a change in lead board for implementation. eHealth - Commissioning Strategy Objective: F3025787 2.1 5 eHealth Commissioning Strategy 3.6 Implement - Rollout This will vary by project, depending on rollout approach. The normal case would be: Rollout would be led by the joint team from the DBT lead organisation, lead Board(s) and supplier. The national project team (commonly resources from all of the above) would deploy across all sites, working with the local project team in each case (the size of which would depend on the scale of the project). Each NHS Board will have its own ‘local case’ for the project - based on the national business case and focusing on planning, resourcing and benefits realisation. This will be used to engage the local management board and signed up to by each NHS Board. Rollout considerations will be addressed during the DBT stage. Engaging NHS Boards in this to ensure that practical issues are thought through as early as possible will be critical to successful rollout. On acceptance of a solution in the lead site, it will be rolled on to the next NHS Board/site with the national reference files and national reporting requirements fully pre-built. The aim is to minimise ‘local configuration’ differences. The delivery capacity of the Board will be determined by the level of funding agreed by the NHS Board Chief Executive. Each NHS Board would be accountable to SGHD through their local eHealth delivery plan, as part of the Board’s local delivery plan. This will be agreed with each NHS Board on an annual basis in terms of which solutions and to how many sites they intend to roll out. Overall accountability for delivery will sit with the NHS Board Chief Executive, as part of the local delivery plan, and delegated to the Board’s Director of eHealth. The reporting line (professional relationship) between the NHS Board Director of eHealth and the SGHD eHealth Programme Director will provide a line of accountability for roll out and for delivering benefits. 3.7 Benefits Realisation 4. NHS Boards will take the lead in benefits realisation, although this will be supported by SGHD and NSS as appropriate. Each NHS Board will be accountable to SGHD through their local eHealth delivery plan for delivering benefits. Additional resources are required in order to ensure benefits are realised, this will be built into the business case and supported by SGHD. NSS Role and Relationship The Head of Programmes working with an appropriate National Project Board, will determine ‘eHealth Commissions’ and agree the scope, parameters, approach, budget and any other relevant matters with NSS based on the eHealth programme. eHealth - Commissioning Strategy Objective: F3025787 2.1 6 eHealth Commissioning Strategy NSS ( supplier and statutory body) has the right to reject commissions if it is unable undertake the work for any of the following reasons: insufficient capacity and or expertise it exposes NSS to unreasonable risk as an organisation to raise major project issues that arise during the course of the work. ‘eHealth Commissions’ should have underlying business cases which commit SGHD, and NHS Boards where relevant, to the financial and operational consequences of the investment. The Commission will be formally passed to the commissioned organisation together with appropriate delegated budget from the eHealth Programme Director. The Head of Programmes and project board will continue to work with the commissioned board to receive reports on progress, provide ongoing monitoring and guidance, resolve issues, agree any changes to the original commission, and report progress to the Programme. The Head of Programmes and project board will continue to work with the commissioned board to ensure programme quality standards and management processes are applied. The NHS Board is normally the lead delivery agency for eHealth Projects. However the commissioned board may procure and manage a third party (commercial supplier) to deliver the solution, instead of undertaking it themselves. The commissioned board will be responsible for effective delivery against the agreed commission and achieving VFM within the delegated budget. PET, the Strategy and Programme Boards will be responsible for the content of the commission and its strategic relevance. Albeit ultimate responsibility rests with the Director of eHealth. The commissioned board will input to the strategy only as part of the wider NHS Scotland set of organisations. The commissioned board will receive regular and timely reports from the project manager in order to discharge the governance responsibilities. The Project boards will have responsibility for considering issues that arise The commissioned board will also need to satisfy itself that these recommendations and actions are compatible with their governance and accountability responsibilities. The Project boards will have responsibility for making recommendations to the appropriate eHealth Board (through the eHealth PET). eHealth - Commissioning Strategy Objective: F3025787 2.1 7 eHealth Commissioning Strategy Configuration Management Document Control Title: Programmes - Commissioning Strategy Document ID: Reason for last change Security Class: Author: Owner: Commissioning Strategy Standard Interim eHealth Commissioning Manager - Ian Hamilton eHealth Head of Programmes - Lesly Donovan Scottish Government eHealth Board Approval Approved by: eHealth PET Name Title Signature Date Approved by: eHealth Programme Board Approved by: eHealth Strategy Board Document History Version No. Date Details of Changes included in Update Distribution Version Date Issued to eHealth - Commissioning Strategy Objective: F3025787 2.1 8 Capacity Highlight / Tracking
© Copyright 2026 Paperzz