1 - Sazi Environmental Consulting

Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
1
INTRODUCTION
1.1
BACKGROUND AND PURPOSE OF REPORT
July 2015
Rand Water has had to increase the capacity of its Mapleton Pump Station to supply in the rapidly
increasing water demand of the east of Pretoria and the Ekurhuleni Metropolitan Municipality.
Due to this augmentation of the system, it has become increasingly inevitable to have sufficient
reservoirs with adequate balancing storage at strategic areas, to store pumped water for 24 hours
before dispersing it.
Rand Water subsequently initiated an investigation to determine which sub-system within the
Mapleton System requires the storage reservoir and of what size. The Vlakfontein storage
reservoir, which is directly supplied by the Mapleton Pump Station, was found to be partial
inadequate because of its continuous leakages and the sub-system future projected Annual
Average Daily Demand analysis.
Based on the future projected Annual Average Daily Demand, an additional reservoir is required to
meet the required demand until the year 2055. The proposed Vlakfontein reservoir will be
constructed adjacent to the existing Vlakfontein reservoir.
This Visual Impact Assessment (VIA) is undertaken as part of the Environmental Impact
Assessment (EIA) process being facilitated by Sazi Environmental Consulting, in terms of the
National Environmental Management Act 107 of 1998 (NEMA) for the proposed additional
reservoir as part of the Mapleton System. As such, the purpose of this report is to assess the
proposed activity in terms of the Guidelines for Involving Visual and Aesthetic Specialists in the EIA
Process and the NEMA EIA Regulations of 2010.
1.2
COMPONENTS OF THE REPORT
The aspects addressed in this report are as follows:
a)
Description of the methodology adopted in preparing the report.
b)
Description of the receiving environment.
c)
Description of the view catchment area, view corridors, viewpoints and receptors.
d)
Identification and evaluation of potential visual impacts associated with the proposed
activity and the alternatives identified, by using the established criteria, including potential
lighting impacts at night.
1
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
e)
Identification in terms of best practical environmental option in terms of visual impact.
f)
Addressing of additional issues such as:

Impact on skyline.

Negative visual impact.

Impact on aesthetic quality and character of place.
g)
Assumptions made and uncertainties or gaps in knowledge.
h)
Recommendations in respect of mitigation measures that should be considered by the
applicant and competent authority.
1.3
STUDY METHODOLOGY
As stated previously, this VIA was undertaken in
accordance with the Guideline for Involving Visual
and Aesthetic Specialists in EIA Processes, as
issued by the Western Cape Government’s
Department
of
Environmental
Affairs
and
Development Planning during 20051.
The VIA was undertaken in distinct steps, each of
which informed the subsequent steps. The figure
below summarises the methodology adopted for
undertaking the assessment.
1.4
SUPPLEMENTARY DOCUMENTATION
This report is to be read together with Annexure
2 (Selected observation point viewsheds and
assessments), which provides an identification of
selected
observation
points
and
visual
assessment of the proposed activity from each of
these points.
1
Figure 1: Methodology adopted for the VIA.
No similar policy exists for the Gauteng Province. However, the Guidelines are based upon universally
accepted principles and are therefore applicable to the said project.
2
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
1.5
July 2015
GAPS IN KNOWLEDGE, ASSUMPTIONS AND LIMITATIONS
This assessment was undertaken during the Pre-Project Investigation Process (PPIP) of the project
and is based on the information and Terms of Reference provided by Sazi Environmental
Consulting on 25 May 2015, for the mentioned project.
Assessments of this nature generally suffer from a number of defects that must be acknowledged:

Limited time: A comprehensive assessment requires a systematic assessment of the
environment at different times of the day. Such luxury is not always possible and therefore
most assessments are based on observations made at a specific time of day. Educated
estimates are made, where applicable, based on the knowledge of the area.

Availability of literature: A thorough assessment requires that all relevant literature on
the subject matter is studied, acknowledged and incorporated in the report. Due to a
range of factors, forward planning documents are not always available for all spheres of
government.
In particular, it was submitted that no detailed plans with regard to the design of the proposed
reservoir was provided. It was, however, communicated that the reservoir would be similar in
form and design to the existing Vlakfontein reservoir. All heights and design forms were therefore
based on the latter.
2
THE AFFECTED ENVIRONMENT
2.1
LOCALITY
The project site is located in the Ekurhuleni Metropolitan Municipality, as part of the Gauteng
Province. The Municipality borders onto the Mpumalanga Province. According to Census 2011,
the municipality has a population of more than 3 million. The population density is approximately
1600 people per km², making it one of the most densely populated areas in the country and
province.
The municipality is an important manufacturing centre in South Africa, and has been described as
‘Africa’s Workshop’.
According to the Ekurhuleni Growth and Development Strategy 2025,
manufacturing accounts for some 28% of total production.
3
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
The project site is, furthermore, located in Region C – one of six Urban Planning and Urban
Management Regions/Zones established in order to more effectively provide for the various
functional areas of Ekurhuleni.
Region C encompasses the north-eastern parts of the Municipality and comprises most of the area
north of the N12, and east of the OR Tambo International Airport. The regional includes areas
such as Bapsfontein, Boksburg North, Northmead, Rynfield, Morehill, Chief Luthuli, Crystal Park,
Mayfield, Etwatwa and Daveyton. The strength of the area lies in the desirability to link the low
income areas of Daveyton and Etwatwa to the OR Tambo International Airport through the newly
proposed growth area in Benoni North. Residential growth is planned to the west of Daveyton –
Etwatwa linking directly to the OR Tambo International Airport (EMM SDF, 2011).
Figure 2: Regional context of the project site.
The project site is situated in a semi-rural area characterised by smallholdings of approximately
2ha in size. Due to its location between the residential areas of Ebotse Golf and Country Estate to
the west, Chief A Luthuli Park to the south and Crystal Park to the north, the area is under
pressure to allow denser residential developments. This is particularly evident in the number of
4
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
subdivisions permitted and group housing developments occurring, particularly on the outskirts of
this neighbourhood.
The project site is located almost in the centre of the smallholding area between 6 th and 7th Road.
The feeder roads of Putfontein and the M44 pass to the east and west of the smallholding area
while the N12 is situated to the south.
The latter connects directly to the OR Thambo
International Airport in the west and Johannesburg further afield.
Immediately adjacent to the project site is the existing 421.23 Mℓ Vlakfontein Reservoir. The
rectangular reservoir, commissioned in 1977, consists of two compartments equal in size. The
reservoir receives approximately 300 Mℓ of water per day through the existing 2100mm diameter
S1 and the newly constructed 2100mm diameter S4 pumped main pipelines from Mapleton Pump
Station (refer to Figure 3). The reservoir supplies potable water to Cristal Park, Daveyton and Hill
Crest, as well as the eastern parts of Tshwane.
Figure 3: Aerial photograph of the existing Vlakfontein Reservoir adjacent to the project site.
Natural resources make a significant and direct contribution to the atmosphere and characteristics
of an area. Unfortunately, the project site and its immediate surroundings are almost entirely
devoid of ecologically-sustainable open spaces. However, due to the age of the smallholding area,
5
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
several mature trees are present on the individual plots, thereby creating its own unique
atmosphere and micro climate.
In the wider context, the landscape is dominated by a relatively flat to undulating terrain only to
be interrupted by the occasional mine mound. There are therefore no prominent hills or ridges
that would offer a potential vantage point over the project site.
The Provincial Growth and Development Strategy (PGDS) 2025 for the Ekurhuleni Municipality
(2007) notes the challenges faced with regards to dating infrastructure. The document recognises
that services infrastructure in the core areas of the municipality is old, inadequately maintained
and subject to frequent breakdowns.
As a result, the Municipality has identified Service
Infrastructure as a Key Focus Area with the objective of creating high quality and well-maintained
services, equitable services throughout the urban areas.
2.1.1 Intrinsic Values of the Region
It is a common principle of planning that each place has a specific intrinsic, instrumental and
systemic value and that such values need to be carefully considered when contemplating the
current and future use of any particular place.
Broadly -speaking, two different philosophical perspectives are possible when considering the
value of any place or object, namely what is it good for? and what is its own good? The first
question relates to its instrumental value, while the second deals with intrinsic value.
Instrumental value uses something as a ‘means to an end’ while intrinsic value refers to being
‘worthwhile in itself’ (Rolston, 1994).
Systemic value relates to the fact that ‘things do not have their separate natures merely in, and for
themselves, but they face outward and co-fit into broader natures. Value seeps out into the system
and the individual lose its status as sole locus of value’ (Rolston, 1994:174). Systemic value refers
to the relations that things have with other things, and to the role they play in larger wholes.
The value system of Region C was determined in the various collaborative, participative processes
undertaken during the drafting of forward planning documentation, policy and guidelines. As
such, the intrinsic value of the area is found in the support services associated with urban
development.
6
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
2.2
July 2015
PROJECT SITE DESCRIPTION
The Vlakfontein project site consists of a portion of approximately 6.15ha of Farm No. 69/90 IR.
The site is located on the block between 6th and 7th Road and borders on North Road in the Van
Ryn smallholdings area.
Figure 4: Aerial perspective of a portion of the project site. Note the existing Vlakfontein Reservoir in the distance.
The site is currently being used to store pipes to be used in Rand Water’s reticulation network.
Despite the relative passive use of the site it is being kept in a neat state. The site is also enclosed
by a visually permeable concrete fence on all three sides bordering on the adjacent roads. On the
boundary bordering on the smallholdings to the south, the property is separated from the
neighbouring properties by means of a vibacrete wall. The photograph above, indicate the current
extent and use of the project site.
As a result of the presence of the existing Vlakfontein Reservoir, the area is traversed by several
pipeline servitudes and servitude areas. These servitudes roughly coincide with the alignment of
the water pipelines as indicated on the Figure below.
7
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Figure 5: Extent of the project site and surroundings.
2.2.1 Landscape Character
The Van Ryn Smallholdings area has a very gentle downward slope in a north-south direction.
Apart from this, no topographical manifestations or characteristics are present in the area. the
height variation of the smallholdings area vary between 1620m and 1660m above mean sea level
– 40m vertical height variation over more than 6km. As for the project site, the latter is virtually
flat at 1662m above mean sea level.
Johannesburg experiences an annual rainfall of approximately 604mm with most rain occurring
during summer. The average midday temperatures range from approximately 16.6°C in June to
26.2°C in January. The region is the coldest during July when the mercury drops to 0.8°C on
average during the night. During the months of June and July veld fires are also very prevalent in
the Gauteng area. Coupled with early morning mist, smoke from veld fires has the ability to cause
poor visibility in the area.
8
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
As illustrated by Figure 5 above, apart from a couple of isolated trees along the periphery of the
project site, the latter is devoid of any large trees.
In terms of the underlying vegetation type, the project site is dominated by Eastern Highveld
Grassland (Gm 12). According to Mucina and Rutherford (2009), this vegetation type is found on
plains between Belfast in the east and the eastern side of Johannesburg in the west and extending
southwards to Bethal, Ermelo and west of Piet Retief.
The vegetation is a short dense grassland dominated by a typical highveld grass composition with
small, scattered rocky outcrops of wiry, sour grasses and some woody species, for example Acacia
caffra, Celtis africana, Diospyros lycioides subsp lycioi-des, Parinari capensis, Protea caffra, P.
welwitschii and Rhus magalismontanum.
Only a very small fraction of the ecosystem is protected in Nooitgedacht Dam Nature Reserve and
Jericho Dam Nature Reserves and is therefore allocated a Vulnerable status.
3
PROJECT BACKGROUND
Rand Water) has had to increase the capacity of the Mapleton Pump Station to enable to supply
the rapidly increasing water demand in the east of Pretoria and Ekurhuleni Metropolitan
Municipality. The existing 421.23 Mℓ Vlakfontein reservoir has to provide adequate balancing
storage to the pumped water. However, it was noted that the reservoir is leaking excessively and
as a result a submersible pump is continuously pumping water out of the submerged outlet
chamber into the S3 pipeline gravitating to Rynfields.
Initially the Vlakfontein – Mamelodi system through the S3/R1/H26 pipelines did not have any
storage reservoir. Few years later it was realized that water takes longer to reach the end users in
the north of Bronberg from the Vlakfontein reservoir in Benoni. Subsequently the existing 100 Mℓ
Bronberg reservoir was constructed. To reduce the risk of experiencing water supply interruptions
through a single large diameter pipeline, S4 and R5 pipelines are being laid from the Mapleton
Pump Station to Mamelodi.
Due to the above-mentioned ongoing augmentation projects, additional reservoir with adequate
balancing storage is required, to increase the storage capacity of the Mapleton System, thus
lessening pumping costs. The recommended reservoir is preferred to be constructed adjacent to
the existing Vlakfontein reservoir. Rand Water strives to have a minimum of 24 hours strategic
9
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
storage in terms of the Annual Average Daily Demand (AADD) for any of its systems (Rand Water,
June 2015).
3.1
DESCRIPTION OF PROPOSED INFRASTRUCTURE
Based on the future projected water demand, it is recommended that an additional 210 Mℓ
balancing storage reservoir be established adjacent to the existing Vlakfontein reservoir. The
Vlakfontein additional reservoir will suffice until the year 2055 up to a compound growth rate for
the area of 2%.
The reservoir capacity has been sized based on projected future water demands. The reservoir
dimensions and placing, as well as that of the inlet and outlet pipes were determined by the
preliminary site levels from desktop topographic survey. Hence the actual placing of the reservoir
on site would be determined by the detailed cadastral and topographic survey. Drainage and
overflow pipes will have to be investigated by the designer. The designer should also ensure that
the proposed reservoir floor and roof levels are at the same elevations as the existing reservoir
(Rand Water, June 2015).
The proposed schematic layout of the additional Vlakfontein reservoir is illustrated by Figure 5
above.
4
POTENTIAL ‘TRIGGERS’ OR KEY ISSUES
A ‘trigger’ is a characteristic of either the receiving environment or the proposed project which
indicates that visibility and aesthetics are likely to be key issues and may require further specialist
involvement (DEA&DP, 2005).
The ‘triggers’, as it relates to the proposed project refer to the following:
Table 1: Potential triggers.
KEY ISSUE
a)
10
FOCAL POINTS
DESCRIPTION
Nature of the Areas with a recognized The landscape character of the area will be
receiving
special
character
environment:
sense of place.
or assessed in determining the expected visual
impact.
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
b)
July 2015
Nature of the Possible visual intrusion The proposed activity is particularly visually
project:
in the landscape.
prominent from defined observation points,
the impact of which will be assessed through
this VIA.
4.1
DEVELOPMENT CATEGORY
Based upon the ‘triggers’ and key issues and the environmental context summarised above, the
proposed activity is categorised as a Category 3 Development.
This categorisation is based upon the Guidelines for Involving Visual and Aesthetic Specialists in EIA
Processes, which lists the following categories of development:
Box 3: KEY TO CATEGORIES OF DEVELOPMENT
Category 1 Development: e.g. nature reserves, nature-related recreation, camping, picnicking,
trails and minimal visitor facilities.
Category 2 Development: e.g. low-key recreation/resort/residential type development, smallscale agriculture/nurseries/narrow roads and small-scale infrastructure.
Category 3 Development: e.g. low density residential/resort type development, golf or polo
estates, low to medium-scale infrastructure.
Category 4 Development: e.g. medium density residential development, sport facilities, smallscale commercial facilities/office parks, one-stop petrol stations, light industry, medium-scale
infrastructure.
Category 5 Development: e.g. high density township/residential development, retail and office
complexes, industrial facilities, refineries, treatment plants, power stations, wind energy farms,
power lines, freeways, toll roads, large-scale infrastructure generally. Large-scale development of
agriculture land and commercial tree plantations. Quarrying and mining activities with related
processing plants.
11
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Based upon the above categorization and the assessment criteria provided in the Guidelines for
Involving Visual and Aesthetic Specialists in EIA Processes it is expected that a ‘minimal visual
impact’ could be expected as a result of the proposed activity (refer to the table below).
The objectives of the VIA described in this report is to:
a)
determine whether such broad impact categorisation is appropriate and if not, to
determine an appropriate category of impact;
b)
formulate and implement measures or interventions that would mitigate any detrimental
impacts to the extent that the activity will be acceptable.
Table 2: Categorization of expected visual impact (DEA&DP, 2005).
Type of environment
Type of development
Category 1
Protected/wild areas of Moderate
international
expected
Areas or routes of high Minimal
Category 3
visual High
or
routes
expected
Category 4
visual Very
Category 5
high Very
high
impact
visual impact visual impact
expected
expected
expected
Moderate
High
visual High
cultural, visual impact visual impact impact
historical significance
Areas
High
or visual impact impact
regional significance
scenic,
Category 2
expected
of Little or no Minimal
expected
visual Very
high
impact
visual impact
expected
expected
expected
Moderate
High
visual High
visual
medium scenic, cultural visual impact visual impact visual impact impact
impact
or
expected
expected
Moderate
High
historical expected
expected
expected
significance
Areas or routes of low Little or no Little or no Minimal
scenic,
cultural
visual
or visual impact visual impact visual impact visual impact impact
historical
expected.
significance/disturbed
Possible
expected
expected
expected
expected
benefits
Disturbed or degraded Little or no Little or no Little or no Minimal
Moderate
sites / run-down urban visual impact visual impact visual impact visual impact visual impact
areas / wasteland
12
expected.
expected.
Possible
Possible
benefits
benefits
expected
expected
expected
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
5
VIEWSHED ANALYSIS
5.1
DOMINANT VIEW CORRIDORS
July 2015
As a first step of this VIA, a survey was undertaken to determine the existence of significant view
corridors associated with the project site. A view corridor is defined as ‘a linear geographic area,
usually along movement routes, that is visible to users of the route’ (DEA&DP, 2005). Accordingly,
only three dominant view corridors were identified in the region, namely:
a)
N12-
The national route connecting Emalahleni with Johannesburg
b)
M44-
The old Pretoria Road connecting all the way to
Bronkhorstspruit in the north.
c)
Putfontein Road-
The road to the south of the project site connecting between
the N12 and the R51.
On a much smaller scale, the roads bordering on the project site could also be regarded as view
corridors.
When determining dominant view corridors, one has to take into consideration the class of the
road, the dominance and nature of the town/settlement/neighbourhood/district in which
direction it travels and the distance from the proposed activity. In this regard, the identified
corridors does not directly relate to the project site. It is only when one enters the smallholdings
area and its network of streets that some of the roads bears a direct relation to the project site.
5.2
RELEVANT TOPOGRAPHIC AND PHYSICAL CHARACTERISTICS
A further key aspect affecting the potential visual impact of any proposed activity is the
topography of the project site and the surrounding environment and the existence of prominent
biophysical features from where the project site is visible. The topography and the major
ridgelines of the area were subsequently determined and mapped by using a Digital Elevation
Model2.
2
A Digital Elevation Model (DEM) is a geographic information system-based outcome generated from contours
for a specific area. In this instance, 20m contour intervals for reference sheet no. 2628ad were used to
calculate the DEM for the region.
13
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
As illustrated by the DEM below, the project site is located at a mean elevation of approximately
1662m above sea level. The DEM shows that the area is relative flat and undulating and does not
comprise of relatively steep hills or ridges. As a result, there are no prominent topographical
manifestations in close proximity to the project site, from which the project site and proposed
activity is particularly visually exposed.
Figure 6: Digital Elevation Model illustrating the undulating nature of the area and the dominant view corridors in the
sub-region.
5.3
PHOTOGRAPHIC STUDY AS SUPPLEMENTARY COMPONENT
In order to quantify and assess the visibility and potential impact of the proposed activity and to
provide a basis for selecting appropriate observation points outside of the project site, a
photographic study and analysis was undertaken in the vicinity of the project site. The analysis
and ground-truthing identified several observation points with similar characteristics and
assessments outcomes.
A selection of Key Observation Points is therefore included under
Annexure 2.
14
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
6
July 2015
DIGITAL VIEWSHED ANALYSIS
The photographic study summarised above was supplemented with a digital viewshed analysis
based upon the Digital Elevation Model (refer to Figure 7). As stated previously, the purpose of
these two steps was to provide a basis for the identification and selection of appropriate
observation points outside the project site for the VIA.
The viewshed3 analysis was undertaken in accordance with the Guideline Document for involving
Visual Specialists in EIA Processes. Geographic Information Systems (GIS) technology was used to
analyse and map information in order to understand the relationships that exist between the
observer and the observed view. Key aspects of the viewshed are as follows:

It is based on a single viewpoint from the highest point of the project site.

It is calculated at an estimated 6m above the existing natural ground level to reflect the
highest point of the proposed activity.

It represents a ‘broad-brush’ designation, which implies that the zone of visual influence
may include portions that are located in a view of shadow and it is therefore not visible
from the project site and vice versa. This may be as a result of landscape features such as
vegetation, buildings and infrastructure not taken into consideration by the DEM.

The viewshed generated from each of the selected observation points referred to in
Annexure 2 is calculated at 1.7m above the natural ground level to reflect the average
height of person either walking or sitting in a vehicle.
As illustrated by the generated viewsheds (refer to Figure 8 below), the zone of visual influence4 is
located in defined clusters around the project site. Due to the flat terrain, the viewshed appears
almost uniform across the landscape with a few areas obscured from the site. The latter generally
coincide with the lower-laying natural drainage areas, dams and lakes.
The viewshed is
predominantly located within 10km from the project site while the majority of the viewshed is
found within 5km from the site. The viewshed coincide with the mentioned dominant view
corridors, residential neighbourhoods, institutional facilities, recreational areas and industrial
areas.
3
A viewshed is defined as ‘the outer boundary defining a view catchment area, usually along crests and
ridgelines. Similar to a watershed’. A Viewshed Analysis is therefore the study into the extent to which a
defined area is visible to its surroundings.
4
15
Zone of visual influence is defined as ‘An area subject to the direct visual influence of a particular project’.
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
The GIS-generated viewshed illustrates a theoretical zone of visual influence. This does not mean
that the proposed activity would be visible from all observation points in this area.
The distance radii indicating the various viewing distances from the project site are illustrated by
Figure 8. Also illustrated by the figure are the view corridors in the middle ground, namely the
N12, M44 and Putfontein Road.
Figure 7: Viewshed generated from the highest point of the project site.
6.1
KEY ASPECTS OF THE VIEWSHED
The distance between the observer and the observed activity is an important determinant of the
magnitude of the visual impact. This is due to the visual impact of an activity diminishing as the
distance between the viewer and the activity increases. Viewsheds are categorised into three
broad categories of significance, namely:
a)
Foreground: The foreground is defined as the area within 1km from the observer within
which details such as colour, texture, styles, forms and structure can be recognised.
16
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Objects in this zone are highly visible unless obscured by other landscape features, existing
structures or vegetation.
b)
Middle ground: The middle ground is the area between 1km and 3km from the observer
where the type of detail which is clearly visible in the foreground becomes
indistinguishable. Objects in the middle ground can be classified as visible to moderately
visible, unless obscured by other elements within the landscape.
c)
Background: the background stretches from approximately 3km onwards. Background
views are only distinguishable by colour and lines, while structures, textures, styles and
forms are often not visible (SRK Consulting, 2007).
7
VISUAL IMPACT ASSESSMENT
7.1
SELECTION OF OBSERVATION POINTS
A total of 20 Key Observation Points (KOPs) were provisionally identified and selected within the
defined viewshed for the visual assessment in accordance with the selection criteria stipulated in
the Visual Guidelines. These KOPs correspond with movement routes, residential areas and
general populated areas, commercial and institutional areas in the region. As a result of the
similarity in the assessment results of the KOPs, the description and assessment of only a selected
few KOPs are included in Annexure 2.
KOPs selected for the assessment are generally located at the intersection between the zone of
visual influence and the defined view corridors (refer to Section 5.1 above). The view corridors are
those areas that are accessible to the general observer.
7.2
ASSESSMENT PROCESS
The identified observation points were categorised and assessed as summarised in the table
below.
Table 3: VIA methodology and process.
KEY
DESCRIPTION
NUMBER
Each observation point was allocated a reference number.
CO-ORDINATES
The co-ordinates of each of the observation points are provided.
ALTITUDE
The altitude of the observation point was provided in meters above sea level.
DESCRIPTION
A brief description where the observation point is located is provided.
17
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
TYPE
July 2015
Each observation point is categorised according to its location and significance
rating. These criteria include the following:

Tourist-related corridors, including linear geographical areas visible to
users of a route or vantage points.
PHOTOGRAPH

Residential areas.

Institutional areas.

Commercial areas.

Recreational area.
A photograph was taken from each observation point in the direction of the
project site to verify the digitally-generated viewshed.
PROPERTY LOCATION
The location of the property was described a foreground, middle ground or
background.
PROXIMITY
The distance between the observation point and the project site was provided
in kilometres.
VISUAL SENSITIVITY OF The visual impact considered acceptable is dependent on the type of
RECEPTORS
receptors. A high (i.e. residential areas, nature reserves and scenic routes or
trails), moderate (e.g. sporting or recreational areas, or places or work), or low
sensitivity (e.g. industrial, mining or degraded areas) was awarded to each
observation point.
VISUAL EXPOSURE
Exposure or visual impact tends to diminish exponentially with distance. A
high (dominant or clearly visible), moderate (recognisable to the viewer) or low
exposure (not particularly visible to the viewer) rating was allocated to each
observation point.
VISUAL
ABSORPTION The potential of the landscape to conceal the proposed activity was assessed.
CAPACITY (VAC)
A rating of high (effective screening by topography and vegetation), moderate
(partial screening) and low (little screening) was allocated to each observation
point.
VISUAL INTRUSION
The potential of the activity to fit into the surrounding environment was
determined. The visual intrusion relates to the context of the proposed
activity while maintaining the integrity of the landscape. A rating of high
(noticeable change), moderate (partially fits into the surroundings) or low
(blends in well with the surroundings) was allocated.
DURATION
With regard to roads, the distance (in kilometres) and duration (in seconds) for
which the property will be visible to the road user, were calculated for each
observation point.
18
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
7.3
July 2015
SUMMARY OF ASSESSMENT
Based on the viewshed analysis and the preceding sections, the envisaged visual impact of the
proposed activity was assessed in accordance with the criteria for visual impact assessments
(DEA&DP, 2005). The findings of the assessment from selected observation points are included
under Annexure 2.
7.3.1 Assessment Criteria
It is stated in the DEA&DP’s Visual Guidelines that to aid decision-making, the assessment and
reporting of possible impacts requires consistency in the interpretation of impact assessment
criteria. The criteria that specifically relate to VIAs were therefore described in Table 3 and
Annexure 2.
The potential visual impact of the proposed activity was assessed against these criteria, with
reference to the summary of criteria in Box 12 of the Visual Guidelines. Table 4 provides a
description of the summary criteria used to determine the impact significance.
Table 4: Summary of criteria used to assess the potential impacts of the proposed activity.
CRITERIA
NATURE
DESCRIPTION
OF
IMPACT
THE The nature of the impact refers to the visual effect the proposed activity would
have on the receiving environment. The nature of the development proposals
are described in the preceding sections.
EXTENT (Scale)
This category deals with the spatial or geographic area of influence and refers
to the following levels:

Site-related (extending only as far as the activity),

Local (limited to the immediate surroundings),

Regional (affecting a larger metropolitan or regional area),

National (affecting large parts of the country),

International (affecting areas across international boundaries).
A value between 1 and 5 is assigned as appropriate (with 1 being low and 5
being high).
DURATION
Duration refers to the expected life-span of the visual impact. A rating of
immediate (assigned score of 1), short term (0-5 years) (assigned score of 2),
medium term (5-15 years) (assigned score of 3), long term (ceases at the end of
operation) (assigned score of 4), or permanent (where time will not mitigate
19
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
the visual impact) (assigned score of 5) were applied.
MAGNITUDE
Magnitude refers to the magnitude of the impact on views, scenic or cultural
resources. The following ratings were allocated to determine the intensity of
the impact:

No effect (assigned score of 0),

Low (visual and scenic resources not affected) (score of 2),

Minor (will not result in impact on processes) (score of 4),

Medium (affected to a limited scale) (assigned score of 6),

High (scenic and cultural resources are significantly affected) (assigned
score of 8),

PROBABILITY
Very high (result in complete destruction of patterns) (score of 10).
This category refers to the degree of possibility of the visual impact occurring.
A rating of none (probably will not happen) (assigned score of 0), improbable
(very low possibility of the impact occurring) (assigned score of 1), low
probability (assigned score of 2), medium probability (distinct possibility that
the impact will occur) (assigned score of 3), highly probability (most likely)
(assigned score of 4), or definite (impact will occur regardless of any
preventative measures) (assigned score of 5) were applied.
STATUS
Status will be described as positive, negative or neutral.
REVERSIBILITY
Degree to which the activity can be reversed. The following rating were
allocated:
SIGNIFICANCE

Reversible (assigned score of 1),

Recoverable (assigned score of 3), or

Irreversible (assigned score of 5).
The significance is calculated by combining the criteria in the following
formula:
S = (E+D+M)P
S = Significance
E = Extent
D = Duration
M = Magnitude
P = Probability
The significance ratings for each potential impact are as follows:

Low (where it will not have an influence on the decision) (<30 points),

Medium (where it should have an influence on the decision unless it is
mitigated) (30-60 points), or
20
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM

July 2015
High (where it would influence the decision regardless of any possible
mitigation) (>60 points).
7.4
ASSESSMENT OF IMPACTS
7.4.1 Assessment of Impact on the Landscape Character
Sense of place and landscape character is closely related to one another. Sense of place refers to
a unique experience of an environment by a user, based on his or her cognitive experience of the
place.
Visual criteria and specifically the landscape character of an area (informed by a
combination of aspects, such as topography, level of development, vegetation, noteworthy
features, cultural/historical features, etc.) play a significant role (MetroGIS, 2012).
A visual impact on the sense of place is one that alters the visual landscape to such an extent that
the user experiences the environment differently, and more specifically, in a less appealing or less
positive light (MetroGIS, 2012).
The sensitivity of the landscape character is an indication of ‘the degree to which a particular
landscape can accommodate change from a particular development, without detrimental effects
on its character’ (GLVIA, 2002). A landscape with a high sensitivity would be one that is greatly
valued for its aesthetic attractiveness and/or have ecological, cultural or social importance
through which it contributes to the inherent character of the visual resource (Axis Landscape
Architect, 2014).
A landscape sensitivity rating was adapted from GOSW (2006) and applied in the classification of
the study area into different sensitivity zones.
Table 5: Landscape character sensitivity rating (adapted from GOSW, 2006).
DESCRIPTION
These landscapes are likely to:
Low Sensitivity
Moderate sensitivity
21

Have distinct landforms;

Have a strong sense of enclosure that reduces visual sensitivity;

Have been affected by man-made features;

Have reduced tranquillity;

Have little inter-visibility with adjacent landscapes; and

Exhibit a low density of sensitive landscape features.
These landscapes are likely to:
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM

July 2015
Have moderately prominent landforms that provide some form of
enclosure;

Have been affected by some man-made features;

Have little inter-visibility with adjacent landscapes; and

Exhibit a moderate density of sensitive landscape features.
These landscapes are likely to:
High sensitivity

Have poorly defined landforms;

Be open or exposed with a remote character and an absence of man-made
features;

Be highly visible from adjacent landscapes; and

Exhibit a high density of sensitive landscape features.
As a result of existing semi-rural nature of the smallholdings area and the passive land uses on site,
the sense of place of the project site has to a large degree remained intact. As a result, the sense
of place of the area is commonly associated with semi-rural residential as well as infrastructure
development strongly associated with the adjacent existing Vlakfontein reservoir. The landscape
character of the project site is therefore considered to be of moderate to low sensitivity.
The table below attempts to summarise the significance of the activities in relation to the
landscape character.
Table 6: Impact table summarising the significance of visual impact on the landscape character.
NATURE:
Potential visual impact on the landscape character and sense of place.
Without Mitigation
Score
With Mitigation
Score
EXTENT
Site-related
1
Site-related
1
DURATION
Long term
4
Medium term
2
MAGNITUDE
Low
1
Low
1
PROBABILITY
Improbable
2
Improbable
2
SIGNIFICANCE
Low
12
Low
8
STATUS
Neutral
IRREPLACEABLE LOSS OF No
Neutral
No
RESOURCE?
CAN
IMPACTS
BE Partially
MITIGATED?
MITIGATION:

Keep disturbed areas to a minimum.

Determine the extent of the construction site in collaboration with the
appointed specialists.

22
No clearing of land to take place outside the demarcated footprint.
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM

July 2015
Institute low-scale landscaping along the perimeter of the project site to
soften the visually prominent concrete fence and to minimise direct
views onto the proposed activity.

Also consider planting shrubs and plant species with a shallow root
system on the banks of the reservoir.

Only indigenous plant species to be introduced and planted. Consult
with the appointed botanical specialist for suitable plant species.

All infrastructure must be set as low down as possible on their respective
footprints to reduce impacts on skylines.
CUMULATIVE IMPACTS:
It is expected that the cumulative effect of the proposed activity would be
indirect as the property would no longer be used for the storage of large
pipes and associated infrastructure. The cumulative effect would also be
synergistic (e.g. the incremental increase in size of the proposed activity).
RESIDUAL IMPACTS:
It is argued that the proposed activity would have a neutral effect in terms of
the status quo as one passive activity is replaced by another, with possibly
positive effects.
7.4.2 Assessment of Impact of Construction Activities
As a result of the nature of the proposed activity, very little impacts could be attributed to
activities taking place during the operational phase. Hence, most impacts will occur during the
construction phase.
The primary impact of the construction phase would be associated with dust that may be
generated from turned-up soils. Other impacts may include noise caused by heavy vehicles,
littering by labourers and increased levels of crime. Just to name a few.
Dust, however, has a visual impact, especially where dust clouds extend above tree canopies and
landscaping features. The causes of such dust plumes are commonly associated with construction
vehicles being driven on unsealed roads, rock crushing operations, drilling operations and wind
blowing over disturbed areas.
It is difficult to model the visual impact since the degree of visibility will differ depending on
climatic conditions (especially wind and temperature conditions), the nature of operations, and
proximity to the activity.
23
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Table 7: Impact table summarising the significance of visual impact of construction activities.
NATURE:
Potential visual impact of construction activities.
Without Mitigation
Score
With Mitigation
Score
EXTENT
Regional
3
Site-related
1
DURATION
Short term
1
Short term
1
MAGNITUDE
Medium
6
Minor
4
PROBABILITY
Probable
3
Probable
3
SIGNIFICANCE
Medium
30
Low
18
STATUS
Negative
IRREPLACEABLE LOSS OF No
Negative
No
RESOURCE?
CAN
IMPACTS
BE Yes
MITIGATED?
MITIGATION:

Reduce and control dust through the use of approved dust suspension
techniques as and when required.

Rehabilitate any exposed soils as soon as construction has been
completed to stabilise loose soils.

Institute low-scale landscaping along the perimeter of the property to
act as bio-filters.
CUMULATIVE IMPACTS:
The proposed activity and the introduction of construction vehicles will
contribute to the cumulative effect of dust in the area.
It is expected that the cumulative effect of dust caused by the proposed
activity would be direct and additive.
RESIDUAL IMPACTS:
It is argued that the proposed activity would have a neutral effect in terms of
the status quo as one passive activity is replaced by another, with possibly
positive effects.
7.4.3 Assessment of Impact on Sensitive Receptors
Specific viewers (visual receptors) experience different views of the visual resource and value it
differently. They will be affected because of alterations to their views due to the proposed
activity. The visual receptors are grouped according to their location and significance.
Differentiation is made between:
a)
Tourist-related and areas of cultural significance.
b)
Motorists along roads.
24
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
c)
Residential Areas and Farmstead.
d)
Recreational areas.
July 2015
Tourists are regarded as visual receptors of exceptional high sensitivity. Their attention is focused
towards the landscape which they essentially utilise for enjoyment purposes and appreciation of
the quality of the landscape.
Residents of the affected environment are classified as visual receptors of high sensitivity owing to
their sustained visual exposure to the proposed development as well as their attentive interest
towards their living environment.
Motorists are generally classified as visual receptors of low sensitivity due to their momentary
view and experience of the proposed development.
As a motorist’s speed increases, the
sharpness of lateral vision declines and the motorist tends to focus on the line of travel (USDOT,
1981). This adds weight to the assumption that under normal conditions, motorists will show low
levels of sensitivity as their attention is focused on the road and their exposure to roadside objects
is brief.
Motorists on scenic routes will present a higher sensitivity. Their reason for being in the landscape
is similar to that of the tourists and they will therefore be categorised as part of the tourist viewer
group (Axis Landscape Architects, 2014).
Table 8: Impact table summarising the significance of visual impact on sensitive receptors.
NATURE:
Potential visual impact on sensitive receptors.
Without Mitigation
Score
With Mitigation
Score
EXTENT
Regional
3
Local
2
DURATION
Permanent
5
Permanent
5
MAGNITUDE
Low
2
No
0
PROBABILITY
Probable
3
Probable
3
SIGNIFICANCE
Medium
30
Low
21
STATUS
Negative
IRREPLACEABLE LOSS OF No
Negative
No
RESOURCE?
CAN
IMPACTS
BE Partially
MITIGATED?
MITIGATION:
25

Keep disturbed areas to a minimum.

Determine the extent of the construction site in collaboration with the
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
appointed specialists.

No clearing of land to take place outside the demarcated footprint.

Institute low-scale landscaping along the perimeter of the project site to
soften the visually prominent concrete fence and to minimise direct
views onto the proposed activity.

Also consider planting shrubs and plant species with a shallow root
system on the banks of the reservoir.

Only indigenous plant species to be introduced and planted. Consult
with the appointed botanical specialist for suitable plant species.

All infrastructure must be set as low down as possible on their respective
footprints to reduce impacts on skylines.
CUMULATIVE IMPACTS:
It is expected that the cumulative impact of the proposed activity would be
indirect as the project site would no longer be used for storage purposes.
The cumulative effect would also be synergistic (e.g. the incremental
increase in size of the proposed activity).
RESIDUAL IMPACTS:
It is argued that the proposed activity could possibly result in an
improvement of the status quo and that any residual impacts would be that
of the current site, in which case, the proposed activity (with the suggested
mitigation measures) could be an improvement on the status quo.
It is submitted that many sensitive receptors are located in the foreground of the project site.
These sensitive receptors represent mostly residential properties and tourist-related areas within
the Van Ryn Smallholdings area. As illustrated by Figure 8 above and the results of the assessment
included under Annexure 2, only those receptors immediately adjacent to the project site will be
visually impacted upon by the proposed activity. Receptors situated further away tend not to be
impacted by the proposed activity due to the visual absorption capacity of the landscape within
which the project site is located.
7.4.4 Assessment of Impact of Artificial Lighting
The occurrence of light sources in the vicinity of the project site is predominantly associated with
the individual residential dwellings in the smallholdings area. The extent of these light sources is
26
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
relatively minimal, however, the sky glow5 effect created by the more densely populated
surrounding areas is clearly visible.
Structures and ground surfaces that are highly illuminated can be clearly visible for long distances,
especially on clear nights. A primary cause of light pollution is unshielded outdoor illumination
fixtures. These fixtures produce large amounts of upward and horizontal spill. Light that shines
upward is a direct waste and is the primary cause of light pollution. Horizontal light produces
glare which might cause a degree of annoyance for viewers, especially at close proximity
(MetroGIS, 2009).
Even though no specifications with regard to supporting infrastructure (such as plant buildings)
were provided, it is expected that, should such facilities be present on site, these might include a
range of light sources.
Table 9: Impact table summarising the visual impact of artificial lighting.
NATURE:
Potential visual impact of artificial lighting as a result of the activity.
Without Mitigation
Score
With Mitigation
Score
EXTENT
Regional
3
Local
2
DURATION
Long term
4
Long term
4
MAGNITUDE
Medium
6
Minor
4
PROBABILITY
Improbable
1
Improbable
1
SIGNIFICANCE
Low
13
Low
10
STATUS
Negative
IRRIPLACEABLE LOSS OF No
Negative
No
RESOURCE?
CAN
IMPACTS
BE Yes
MITIGATED?
MITIGATION:

Outdoor lighting must be strictly controlled so as to prevent light
pollution.

All lighting must be installed at downward angles.

Sources of light must as far as possible be shielded by physical barriers
such as a planted trees and shrubs or built structures.

Consider the application of motion detectors to allow the application of
lighting only where and when it is required.
5
Sky glow refers to the illumination of the night sky or parts thereof. The most common cause of sky glow is
artificial light that emits light pollution, which accumulates into a fast glow that can be seen from kilometers
away.
27
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
CUMULATIVE IMPACTS:
July 2015
The proposed activity may contribute to the cumulative lighting effect of the
area.
Should the activity be lit, it is expected that the cumulative impact of
artificial lighting caused by the proposed activity would be direct and
additive.
RESIDUAL IMPACTS:
Sources of light could be controlled and, hence, removed once the activity is
decommissioned. As a result, the visual impact would also be removed.
8
POLICY CONTEXT
8.1
STRATEGIC PLANNING DOCUMENTS
The Ekurhuleni Metropolitan Spatial Development Framework (MSDF) is based on the National
Spatial Development Perspective and is informed by its comparative economic advantages as well
as its competitive advantages. The comparative advantage is the provision of efficient production
and service delivery. In particular, the comparative advantage of the municipality is its industrial
and manufacturing base. Several of the spatial objectives and strategies contained in the MSDF
are therefore geared towards strengthening this comparative advantage.
In addition, the spatial objectives and concept is based on the Core Development Triangle, Activity
Nodes, Development Corridors, Municipal Open Space and the Urban Edge. These elements aim
to provide guidance to officials, consultants and the general public, alike, as to the future
development concept and growth direction of the municipality.
As for the water infrastructure, the Provincial Growth and Development Strategy (PGDS) (EMM,
2007) recognises certain sections of the Municipality is characterised by old infrastructure, which
needs continuous maintenance and upgrading.
The PGDS continue and states that well-maintained trading services will attract investment and
development to the EMM, and the municipality will therefore ensure that it allocates adequate
resources for maintenance and to prevent degradation of existing trading services.
28
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
As far as the upgrading of services is concerned, the PGDS states that the focus will be on ensuring
equity – the township areas and informal settlements will receive the bulk of the capital budget
until this goal has been achieved.
Access to engineering services for the high potential economic developmental zones, will also be
promoted in a responsible and proactive manner to ensure that proper direction and support are
provided for these high economic core zones.
9
IMPACT STATEMENT
The on-site verification from the selected Key Observation Points and the viewsheds generated
from the latter points indicated that the proposed activity will only be visible from receptors
situated in the foreground of the project site. To this end, the results of the viewshed analysis
from defined Key Observation Points, together with photographs indicating the actual view has
been included under Annexure 2.
The results of the Visual Impact Assessment for the proposed additional Vlakfontein Reservoir
consequently found that the overall visual impact is summarised as being of a neutral significance.
The primary informants of this assessment are as follows:
a)
The activity will take place within the boundaries of a site that is currently utilised for
passive storage of infrastructure relating to the primary activity.
b)
The proposed activity would result in a decrease of traffic (at least during operation).
c)
The proposed activity would take place on a site which is already cordoned-off by a
concrete fence.
d)
The height of the proposed activity would be no greater than the surrounding built forms.
In fact, many of the houses in the area are higher than the proposed activity.
e)
All that would be visible of the activity (through the fence) would effectively be a
landscaped berm, which, when mitigated as proposed, could add to the visual quality of
the area.
f)
All forwards planning documents reference the importance of services infrastructure to
supply in the needs of the greater community.
g)
Despite its size, the project site is only visible from observation points in the foreground.
More than that, due to the complex urban pattern and mature vegetation of the sub-area,
it has been verified that the project site is actually only visible from approximately 100m
from the site itself.
29
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
It is therefore concluded that the sense of place, and most other expected impacts of the
proposed activity, will not alter to such an extent where users might experience the visual
landscape in a less appealing or less positive light. In it furthermore conceivable that user
experiences of the visual landscape at the end of life of the activity might be preferred above the
status quo, especially should the proposed mitigation measures be implemented.
10
ENVIRONMENTAL MANAGEMENT PROGRAMME
The management plan tables aim to summarise the key findings of the visual impact report and to
suggest possible management actions in order to mitigate the potential visual impacts.
Table 10: Environmental Management Programme – Planning Phase
OBJECTIVE: To establish a facility that would have the least intrusive impact on the landscape and not
create a detrimental visual impact.
Project component/s
The creation of a low-scale water reservoir.
Potential Impact
Potential visual intrusion and impact on the skyline.
Activity/risk source
Potential impact on sensitive receptors within the foreground.
Mitigation:
Diligent planning of the proposed facility to minimise the expected visual
Target/Objective
impact.
Mitigation: Action/control
Responsibility
Timeframe
Prepare an environmental constraints plan Rand Water / planners In the planning phase
for the wider area to establish the / landscape architect
environmental sensitive areas and those
areas upon which the activity (pipelines)
may impact.
Plan vegetated and landscaped areas along Rand Water / planners In the planning phase
adjoining roads to minimise visual impacts / landscape architect
onto the site.
Performance Indicator
Well maintained activity that has no larger impact that the status quo. All
actions to be measured against the Operational Phase Environmental
Management Plan.
Monitoring
N/A
Table 11: Environmental Management Programme – Construction Phase
OBJECTIVE: Mitigate the potential visual impact associated with the construction phase.
Project component/s
Construction site
Potential Impact
Visual impact of general construction activities and associated impacts.
Activity/risk source
Potential impact on sensitive receptors within the foreground.
30
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Mitigation:
Minimal visual intrusion by construction activities and general acceptance and
Target/Objective
compliance with Environmental Specifications.
Mitigation: Action/control
Responsibility
Timeframe
An Environmental Control Officer (ECO) must be Rand Water
Pre-construction
appointed to oversee the construction process and
ensure compliance with conditions of approval.
Contractor to sign and undertake to comply with Contractor
Pre-construction
Environmental Specifications.
Demarcate sensitive areas and no-go areas with Rand Water / contractor Pre-construction
danger
tape
to
prevent
disturbance
during
construction.
Keep disturbed areas to a minimum.
Rand Water / contractor Throughout
construction
Identify suitable areas within the construction site for Rand Water / contractor Pre-construction
administrative offices, storage, workshops, eating
areas, ablution facilities and washing areas.
Institute a solid waste management programme to Rand Water / contractor Throughout
minimise waste generated on the construction site,
construction
and recycle where possible.
Reduce and control dust through the use of approved Rand Water / contractor Throughout
dust suspension techniques as and when required.
construction
Institute a planting regime in collaboration with the Rand Water / contractor Construction
appointed botanical specialist.
Performance
Construction site is confined to the demarcated areas identified on a Development
Indicator
Plan. No transgression of the Environmental Specifications visible and natural
processes occurring freely outside boundaries of the construction site.
Monitoring
Monitoring to be undertaken by an appointed Environmental Control Officer who
will enforce compliance with the Environmental Specifications.
Table 12: Environmental Management Programme – Operational Phase
OBJECTIVE: Mitigate the possible visual impact associated with the operational phase.
Project component/s
Low scale water reservoir.
Potential Impact
Potential visual intrusion and impact on the skyline.
Activity/risk source
Potential impact on sensitive receptors within the foreground.
Mitigation:
An activity that results in the least visual impact on all receptors.
Target/Objective
Mitigation: Action/control
Responsibility
Maintain the general appearance of the Rand
facility as a whole.
31
Water
Timeframe
/ Throughout operational phase
contractor
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Monitor the area along the pipelines and
surrounding the project site for water
leakage
and
disturbance
of
natural
processes.
Maintain surrounding roads to prevent
scouring and erosion, especially after rains.
Performance Indicator
Well maintained activity that has little or no impact on the environment.
All actions to be measured against the Operational Phase Environmental
Management Plan.
Monitoring
ECO to undertake monitoring functions for a year after the activity has
reached the end of life to ensure compliance with mitigation measures.
Management thereafter to be undertaken by the responsible entity.
11
REFERENCES
Axis Landscape Architects (CC). (2014). Proposed establishment of the Rustenburg strengthening
phase 2, Marang B 400/132kV and ±2km, 400 kV power line from the existing Bighorn-Marang or
Medupimarang or Midas-Marang or Marang-Midas 400kV power lines. Visual impact assessment
Chief Director of Surveys and Mapping, varying dates. 1:50 000 Topo-cadastral Maps and Data.
City of Ekurhuleni (2010).
Ekurhuleni Metropolitan Municipality. Development Guide.
Directorate: Communications and Marketing.
City of Ekurhuleni (2011). Ekurhuleni Metropolitan Spatial Development Framework Review 2011.
Report 2 – SDF Report. City Development Department, Spatial Planning Directorate.
City of Ekurhuleni (2013).
Ekurhuleni Metropolitan Municipality IDP, Budget and SDBIP.
Integrated Development Plan 2013/2014.
Crystal Park. 26°08’35.05’’ S and 28°22’09.70’’E. Google Earth. 10 June 2015
Dennis Moss Partnership (2010). Visual Impact Assessment for portions of the Farm Hartenbosch
No. 217.
Ekurhuleni Metropolitan Municipality (2005). Ekurhuleni Growth and Development Strategy
2025. Directorate: Communications and Marketing.
32
© Zone Land Solutions
Visual Impact Assessment
Proposed additional Vlakfontein Reservoir, Mapleton System, EMM
July 2015
Ekurhuleni Metropolitan Municipality (2009). Waste Management Services: Landfill – Annual
Report 2009/2010.
Environomics (2007). Environmental Management Framework for Ekurhuleni.
Government Office of the South West – England. (2006). Using landscape sensitivity for renewable
energy. Revision 2010 – Empowering the region.
Landscape Institute and the Institute of Environmental Assessment and Management. (2002).
Guidelines for Landscape and Visual Impact Assessment (GLVIA). Second Edition, E & FN Spon
Press.
MetroGIS (Pty) Ltd. (2009). Visual Impact Assessment for the proposed VeleColiery.
Mucina and Rutherford (2009). The vegetation map of South Africa, Lesotho and Swaziland.
SANBI, Pretoria.
Oberholzer, B. (2005). Guideline for involving visual and aesthetic specialists in EIA processes:
Edition 1.
Rolston, H. (1994). Conserving natural value: Perspectives in biological diversity series. New York:
Columbia University Press.
Setplan (2008). Ekurhuleni Metropolitan Municipality Densification Framework. Status Quo:
Analysis and Findings Document.
SRK Consulting. (2007). Visual Impact Assessment Report for the Proposed Sibaya Precinct
Development. Report Prepared for Moreland (Pty) Ltd.
ZONE LAND SOLUTIONS
19 JUNE 2015
33
© Zone Land Solutions