Next steps of ILC Detector/Physics Studies Sakue Yamada SiDWS@Eugege Nov15, 2010 2010/11/15 S.Yamada SiD WS@Eugene 1 Where we are • Fall 2007: Call for LOIs was made by ILCSC • Mar.2008: IDAG formed & 3 LOI groups known 2007 RDR 2008 • • • • • Mar.2009: 3 LOIs submitted Summer 2009: IDAG recommendation Oct 2009: Work plan of the validated groups Mar:2009: IDAG began monitoring the groups End 2010: Interim report to be produced 2009 2010 Now 2011 2012 • End 2012: DetailedS.Yamada Baseline Design Report SiD WS@Eugene 2010/11/15 2 Where we are (cont’ed) • SiD and ILD groups are in the middle of detector R&D, integration studies, and physics simulation, to complete Detailed Baseline Design of their concepts. You collaborate with ILD (through 5 common task groups), and with R&D collaborations and CLIC detector group. IDAG monitors the progress of SiD and ILD and the activity of the CTGs. 2010/11/15 S.Yamada SiD WS@Eugene 3 Purpose of the Detailed Baseline Designs In 2012, when GDE will complete the ILC design to propose the project, we need to present that detectors can be built and desired physics can be pursued at ILC. The detectors must have unprecedentedly high precision, e.g. for recoil mass or jet-jet mass measurement. High resolution and Fine granularity > advanced Component R&D Hermeticity, dead material (area) reduction > Integration studies • Realistic physics simulation to confirm performance 2010/11/15 S.Yamada SiD WS@Eugene 4 Work plan • 9 items to be fulfilled in preparing DBD: e.g. to finish R&D of critical components for feasibility proof, to define baseline design, to complete push-pull studies, etc. • The resource situation is hard and getting worse. This is happening in all regions. • During the LCWS09 last March, we decided to relax the level of accomplishment of each item seeing the available resources. e.g. Reduction of benchmark reactions • IDAG agreed with the measure. However, we have to keep the minimum line. 2010/11/15 S.Yamada SiD WS@Eugene 5 Component R&D • So far good progress has been made. Resource condition of each region Europe: the new budget (AIDA) was approved but reduced relative to the present EUDET (till end 2010). Asia: e.g. JSPS grant renewal is approaching (tough competition). US: university budget will end FY2012. The funding scheme is changing and may become harder. IDAG noted this problem through the interview of the detector R&D CTG during the last IDAG meeting. Both ILCSC and PAC are informed of the situation. 2010/11/15 S.Yamada SiD WS@Eugene 6 Integration Many items of integration are crucial • Detector components into a system Dead material/area deteriorates the performance and they tend to increase as study goes on. simulation with realistic configuration needed • Integration with the accelerator Here push-pull is a critical item to be studied. Vibration, relocation of the components (acc. & det.), switching period, etc. Through integration studies are required to be sure that the designed performance is realized. 2010/11/15 S.Yamada SiD WS@Eugene 7 Integration (continued) Issue: Engineering support is lacking or missing. This is common for the two detector groups. The reason is likely: • The importance of engineering in the R&D phase is not understood well. • ILC project has no “host” laboratory yet. Each supporting lab has its own urgent project. The request, which was made through ILCSC before the last PAC, is waiting for a response yet. Our lesson: We had to be quick to react to the offer for help in making a concrete request. The urgency was not shown. 2010/11/15 S.Yamada SiD WS@Eugene 8 Physics Simulation • New benchmarks were proposed by Physics CTG. • Being considered by the joint working group of ILD, SiD, Software and physics representatives based on the proposed list and the suggestion of IDAG. It will be finished soon. • Various software tools are being prepared by the software CTG. • A new working groups for event generation was set up. • Hope: when the detector baselines are made, simulation can be started with these tools. • There can be new contribution from the CLIC. 2010/11/15 S.Yamada SiD WS@Eugene 9 IDAG monitoring • IDAG meets twice a year now. • IDAG met during IWLC2010 in Geneva last October. 1. IDAG discussed with the management, and interviewed the detector groups, SiD and ILD, two CTGs, detector R&D CTG and Software CTG. 2. IDAG observed the status and issues of detector R&D made by the various R&D collaborations. 3. IDAG recognizes the importance of R&D beyond the TDR phase and expresses its concern about funding. 4. Report was made during the ECFA plenary (in Geneva) and to PAC (last week) by Michel. 2010/11/15 S.Yamada SiD WS@Eugene 10 Cooperation with CLIC and Mu-col • In Europe combined study for ILC+CLIC R&D is the recent way to obtain resources. • ILD and SiD were adapted also for CLIC detectors. And intensive cooperation with CLIC detector has been developed. • It mitigates some of the resource problem. • Besides joint funding, exchange of knowledge/info, and participation to CLIC-CDR preparation are going. The cooperation leads to a better understanding of the ILC detectors, too. 2010/11/15 S.Yamada SiD WS@Eugene 11 We need to note… • Under the present human resources, we still wish that necessary works be completed in time to prepare for DBD. • The cooperation may give effects on our plan (both +/-). • We hope good balance is reached in total, if not on everyday base, and the cooperation build a win-win relation. • In US, a similar move for cooperation or joint request for funding between ILC & Mu-C is under discussion. Effort for ILC may be defocused in such an environment. But we wish you do keep eyes on DBD (and the interim report, as well) and to accomplish desired milestones. (This SiD Work Shop IS very important.) 2010/11/15 S.Yamada SiD WS@Eugene 12 Upcoming works/programs • Interim report • Update of planning taking realistic resources into account (This will be asked by IDAG at the coming meeting in Eugene.) • Participation to BAW2 at SLAC in January and preparation for it. • a common costing method for DBD (IDAG’s suggestion) (a joint WG is being formed.) • Participation in the CPDG discussions for after 2012 2010/11/15 S.Yamada SiD WS@Eugene 13 Interim Report • We plan to make an interim report by spring next year. • It will be a report to ILCSC, but will be circulated to the community and beyond, too. • It describes physics overview, overview of the LOI process, activities of R&D and integration, simulation and the activity of the common task groups and the working groups. • In a sense it makes an update of the RDR and will be useful for us, too. • It will be rather short and easy to read with a help of the communicators. The style will be similar with the interim report of GDE. 2010/11/15 S.Yamada SiD WS@Eugene 14 What will happen to DBDs ? • The question = ‘ How ILC will be pushed forward after the TDR phase ?’ • We need a clear view about how the ILC project will be brought forward toward realization. • We are all waiting good news from LHC. • But cannot simply wait putting the completed DBD on a bookshelf. Together with GDE’s TDR, our DBD must be fully effective in the project implementation effort. There should be a mechanism for this. • There are more R&D to continue, remaining physics studies to be refined. There should be also a mechanism to strengthen these efforts. 2010/11/15 S.Yamada SiD WS@Eugene 15 What comes next (cont’ed) • GDE studies the governance and project implementation issues and we participate. It is a role of ILCSC and/or ICFA to lay down a program after the TDR phase, regarding to propose the project to the governments and to seek ways for discussions. 2010/11/15 S.Yamada SiD WS@Eugene 16 ILCSC took a new move • In the last ILCSC meeting, siting sub-group of ILCSC (J. Mnich, P. Oddone, A. Suzuki) proposed a possible scheme for the next steps. • The idea is outlined in a white paper on Comprehensive Project Design Guideline, in which there are propositions on the site selection method, governance cases and an intermediate step to take. • The document is open for comments now. • This is indeed a guideline and details are left open. It makes a starting point for discussions in the community. 2010/11/15 S.Yamada SiD WS@Eugene 17 We welcome this proposition • Details are for everybody to read the paper and comment. • CPDG proposes a transient scheme which conducts the project after the TDR phase to prepare the final form. • The transient scheme can be regarded as similar to the present GDE & Detector Management scheme, but can be made more solid or strengthened in order to work both for continuation of R&D and for realization of the project. • To realize the new system and to make it effective, we have to bring our inputs for the discussion. We have experiences and know difficulties to be improved. 2010/11/15 S.Yamada SiD WS@Eugene 18 The White Paper is open for comments • The LC community should join this initiative of ILCSC. • We wish to participate in the discussions to design the details of the coming scheme. • I believe the voice of the community is the strongest force to move it. • During this WS, you can discuss what features are needed for the new scheme. 2010/11/15 S.Yamada SiD WS@Eugene 19 Summary • We are in the middle of the way to complete detailed baseline design. • We understand resources are limited and getting less for R&D works, integration works and simulation studies. • Cooperation with CLIC detector is going widely. We hope this ends up with win-win relation. And similar one with Mu-col may start in the US. • Under this circumstance we have to complete DBD as intended. Update of planning is needed seeing resources. • For the next step after 2012, ILCSC published CPDG. We wish to study it and comment to create a desirable scheme to come to project realization. 2010/11/15 S.Yamada SiD WS@Eugene 20 Back up 2010/11/15 S.Yamada SiD WS@Eugene 21 Items for the planning of the detector groups 1. Continue R&D on critical components to demonstrate proof of principle 2. Define a feasible baseline design (Options may also be considered.) 3. Complete basic mechanical integration of the baseline design accounting for insensitive zones 4. Develop a realistic simulation model of the baseline design, including faults and limitations 5. Develop a push-pull mechanism working with relevant groups 6. Develop a realistic concept of integration with the accelerator including the IR design 2010/11/15 S.Yamada SiD WS@Eugene 22 Plan of the detector groups (cont’ed) 7. Simulate and analyze benchmark reactions, which can be updated 8. Simulate and analyze some reactions at 1 TeV, including realistic higher energy backgrounds demonstrating the detector performance. 9. Develop an improved cost estimate. 2010/11/15 S.Yamada SiD WS@Eugene 23
© Copyright 2026 Paperzz