5 th Street Bridge Replacement Project Contract

5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
June 1, 2017
Presented By:
Kevin Bradford/Yuba City Public Works
Matt Griggs/Dokken Engineering
Mehrdad Varzandeh/The Hanna Group
1
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Agenda
• Introductions
• City Website
• Designer’s Presentation
–
–
–
–
–
–
–
–
–
History and Description of Project
Staging
Bridge Construction
Levee Work
Trestle
Environmental
Utilities
Cost/Time
Miscellaneous
• Questions
–
–
–
Save questions until the end
Meeting is being recorded – ask questions using microphone
PLEASE FILL OUT THE SIGN-IN SHEET OUT FRONT!
2
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Introductions
•
•
•
•
•
•
•
Kevin Bradford – City Project Manager, Yuba City Public Works
Matt Griggs – Design Firm Project Manager, Dokken Engineering
Mehrdad Varzandeh – CM Firm Project Manager, The Hanna Group
Rosa Griggs – Senior Engineer, Dokken Engineering
Tim Chamberlain – Senior Environmental Planner, Dokken Engineering
Scarlett Harris – Administrative Assistant, Yuba City Public Works
Heather Rush – Office Engineer, The Hanna Group
PLEASE FILL OUT THE SIGN-IN SHEET OUT FRONT!
3
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
City Website
• Refer to City website for information regarding the bid process
– http://www.yubacity.net/publicworksbids
• Website contains the following information:
–
–
–
–
–
–
–
Notice to Bidders
Construction Bid Resources (Information Handout)
Bid Opening Date and Time
Engineer’s Estimate
Spec Books and Plans (full size and half size)
Plan Holder List
Will also contain the Pre-Bid Presentation, Questions/Responses, and any
Addenda
• Refer to http://www.yubacity.net/bridge for other information
regarding the project.
4
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Staging
• VECP available to modify construction staging and traffic handling
• Intersection of 5th and J St will need to be completed in 120 days,
but waterline can't be installed before September 2018.
• Demo contract underway and tank removal to follow
5
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Bridge Construction
• Survey required before and after construction to ensure material is
not left in the floodplain
• Option to remove sidewalk on bridge to place final shaft
• Falsework for frame 2 can stay over winter
• Reinforcing for median barrier cannot be placed after the pour
• Temporary and permanent casings and construction methods
included in the cost of the shafts
• Backfill after bridge removal (included in the cost of removal)
• Limit of 3 precast girders on site, 56 hours before installation
• Bubble curtain requirements - needed for vibratory or impact
hammers, monitoring requirements apply
6
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Levee Work
• All material in levee must be levee fill material
• Work window is April 15 to November 1
• No pile driving in levee
• Levees must be rebuilt with RSP in place by November 1
7
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Trestle
• Critical for the schedule - submit at pre-con. Meeting
• Permitted for approximately 273 pipe piles - 22" dia. (H-piles are an
option)
• Trestle elevation
• Bubble curtain requirements - monitoring requirements only
8
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Utilities
• Relocations Underway
9
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Cost/Time
• Pilasters are included in the linear cost of barrier
• Shoring is lump sum for 5th Street Bridge, 2nd Street UC and road
staging
• No winter suspension
• Time related overhead intentionally omitted from Bid items - no bid
item
• Price Index Fluctuation removed
10
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Miscellaneous
• No access from the north on Biz Johnson Drive
• Use of the construction staging areas in the park/soccer complex
are limited to one season (August thru November). No staging area
outside of the bridge area can be utilized for more than 6 months
total in the park.
• Railroad flagging required by railroad when using equipment near
railroad bridge in Marysville.
• Parking lot and road repairs upon completion of work
• Concrete pavement between the approach slab is structural
concrete (approach slab)
11
5th Street Bridge Replacement Project
Contract No. 17-01
Pre-bid Meeting
Questions and Answers
• All questions and answers will be posted on City website
Yuba City appreciates your interest in this project and your investment in responding
to our bid advertisement!
12