PAPER NO. : EMC/RCP/92/2017/06 SUBJECT : RULES CHANGE PANEL WORK PLAN 2017/18 FOR : DISCUSSION AND DECISION PREPARED BY : LOH LUCIA SENIOR ECONOMIST REVIEWED BY : PAUL POH LEE KONG EVP, MARKET ADMINISTRATION DATE OF MEETING : 07 MARCH 2017 Executive Summary This paper presents the proposed update of the 2-year Rules Change Panel (RCP) work plan, incorporating feedback from 9 January 2017 to 15 February 2017. EMC recommends that the RCP discuss and agree on an updated work plan, and task EMC to monitor the progress of the approved work plan. The approved work plan is presented in Table 4 of section 6 of this paper. Page 1 of 23 EMC/RCP/92/2017/06 1. Introduction This paper takes stock of the progress made in the previous work plan approved in March 2016. It then presents the list of existing and new issues raised during the work plan consultation exercise, together with the corresponding rankings and comments made by various stakeholders. The proposed issues to be tackled over the next 2 years are then tabled for RCP’s discussion and approval. 2. RCP’s Achievements: April 2016 – March 2017 2.1 Overview At its 85th meeting in March 2016, the RCP agreed on the 2016/17 work plan and tasked EMC to monitor its progress. This work plan comprises 35 issues, with 12 to be addressed within the first 12 months (i.e. by March 2017). Of the 12 issues, the RCP has completed work on 8 of them, including: Removal of Market Assessment Unit (MAU)’s Obligation to Provide Information to the EMA under Section 4.3.10 of Chapter 3 of the Market Rules Price Assignment for Islanded Generation Facilities Enhancement to the existing process of releasing security limit advisories to market participants Enhancement to the existing process for releasing AGOP to market participants Update of Settlement Market Manual (Chapter 7 Market Rules) Publication of Half-Hourly Total Solar Export1 Provision of real-time estimates of HEUC Review of methodology for the recovery of EMC’s and PSO’s fees At the same time, significant progress has been made on 4 of the remaining issues: Combining Primary Reserve and Secondary Reserve into a single class of Reserve – The PSO had published a consultation paper in March 2015 on the “Enhancement to the Spinning Reserve Requirements for the Singapore Power System”, and was evaluating whether to direct a rule change, or to go through the RCP work plan process. On 20 April 2016, the PSO informed EMC to proceed with the latter. EMC then sent a draft paper to PSO for inputs. On 9 February 2017, the PSO informed EMC of the PSO’s intention to proceed with a directed rule change. Review of Automatic Financial Penalty Scheme (AFPS) – On 11 May 2016, EMC sought industry feedback on the additional issues to be addressed. EMC is currently analysing the issues received, which pertains to (i) expansion of exempted cases, (ii) minimum penalty value, and (iii) treatment of embedded generators’ must-run quantity. Review of Mechanisms to Mitigate Credit Default – This proposal was tabled at the 91st RCP meeting and the RCP supported the proposed amendment to the calculation of Estimated Average Daily Exposure of new market participants and the revision to the deadline for submission of bilateral contract quantities, and tasked EMC to draft the relevant rule modifications. EMC is drafting the rule modifications. Review of Market Participants’ Classification and Rules Change Panel’s Composition – This proposal was published for comments on 24 February 2017. In addition to the agreed work plan, during the financial year, the RCP also addressed the following rule change: Lead Time For Extension Of Commissioning Generation Facility's Registration 1 The issue culminated into RC340: Publication of Half-hourly Metered Generation by Facility Type. Page 2 of 23 EMC/RCP/92/2017/06 Further, the EMA also directed EMC under Section 46(2)(b) of the Electricity Act to undertake the following rule change in the past year: Rules Modification for EMA’s “Implementing Demand Response in the National Electricity Market of Singapore (NEMS)” – This rules modification which took effect on 28 April 2016 is to give effect to the EMA’s policy decision to allow loads to be able to submit energy bids for the purposes of providing load curtailment, and to correspondingly receive incentive payment if the curtailments were deemed to have lowered USEP. 3. RCP Work Plan Prioritisation Exercise 2017 3.1 List of Issues for Prioritisation Prior to the consultation meetings, EMC presented stakeholders with a list of 51 issues comprising 28 that were carried over from the previous work plan, 1 which was raised during the mid-year review, and 22 that were newly raised by stakeholders. The 23 new issues are summarised below: (1) Invalid load ramping constraints in the Rules Modification for EMA’s “Implementing Demand Response in the NEMS – Currently, in the market clearing engine’s model, the ramp rates of a load registered facility (LRF) constrain only the quantities in its energy bid, which represents the dispatchable portion of the LRF’s load. It is proposed, however, that the ramp rates constraint be applied to the entire load (i.e. aggregate of energy bid quantity and non-dispatchable load) of the LRF. (Proposed by: DNV GL and NTU) (2) Review of Net Metering Treatment for Embedded Intermittent Generation Sources (IGS) – Low tension consumers with embedded IGS pay grid charges on a net basis. This issue suggests changing the net metering treatment given to such consumers to avoid the under-recovery of grid charges or higher cost burden on remaining consumers. (Proposed by: Tuas Power Generation) (3) Reduction of Gate Closure during Forced Outage Events – This proposal suggests allowing a GRF to offer within the 65-minute gate closure following the GRF’s forced outage, so as to increase the supply available in the system more promptly. (Proposed by: PacificLight Power) (4) Calculation Methodology for Probability of Failure – This proposal suggests reviewing the calculation methodology for the probability of failure (POF) to ensure fair and consistent treatment across both single shaft and multi shaft plants, given that a partial trip of a multi-shaft plant does not count towards that plant’s POF. (Proposed by: PacificLight Power) (5) Publication of high/low price scenarios in the short term schedule – This proposal suggests extending the high and low load scenarios of the pre-dispatch scenario and market outlook scenario to the short-term schedule as well. (Proposed by: PacificLight Power) (6) Review of Costs of Appeal under the Automatic Financial Penalty Scheme (AFPS) – This proposal suggests providing greater clarity on the costs that an MP would incur when they appeal to the Market Surveillance and Compliance Panel for a refund of penalty imposed under the AFPS, and that such costs should commensurate with the level of penalty in question. (Proposed by: Senoko Waste-to-Energy) (7) Review of the minimum penalty amount under the AFPS – This proposal suggests removing the minimum penalty of $5000 under the AFPS, as it could be overly punitive. (Proposed by: Senoko Waste-to-Energy) Page 3 of 23 EMC/RCP/92/2017/06 (8) Treatment of forced outages under the AFPS – This issue suggests extending the exemptions under the AFPS to include partial outages of GRFs. (Proposed by: Senoko Waste-to-Energy) (9) Compensation for generators adversely affected by Type 2 Price Revision – This proposal suggests re-examining the issue of providing compensation for gencos that received a lower market energy price as a result of ex-post price revision that is attributed to the MCE using erroneous input data. (Proposed by: Senoko Energy and Senoko Energy Supply) (10) Introduction of an inertia adjustment factor to reserve requirements for enhanced power system security with increased solar generation – This proposal suggests adjusting the primary reserve requirements for inertia, such that more primary reserve are scheduled when solar generation is high, so as to maintain power system security. (Proposed by: Diamond Energy Managers) (11) Alignment of market rules with transmission code in relation to reserves level – The Transmission Code stipulates the minimum reserve capability of GRFs. This proposal suggests that the MCE schedule primary and secondary reserves at levels which are at least the aggregate minimum reserve capability across all GRFs. (Proposed by: Diamond Energy Merchants) (12) Remove or amend conflicting methodology that is referred to in Chapter 6 sections 5.2.5B and 5.2.5C – Under Chapter 6 sections 5.2.5B and 5.2.5C, the metered withdrawal of embedded generation facilities’ (EGFs’) associated load in a given settlement interval is compared with the EGF’s declared quantity in its energy offers, which is given priority in dispatch by being priced at -$4750/MWh, for the corresponding dispatch period. If the EGF’s metered withdrawal is lower than its declared quantity less a 5MWh tolerance, the EMC will report the case to the MSCP for investigation. The proposal suggests removing the above check, given that Chapter 2 section 5.5.9 of the market rules separately requires that the associated load be at least half of that EGF’s generation. (Proposed by: Shell Eastern Petroleum) (13) Earlier release of delayed offer stack – This proposal suggests bringing forward the publication of the energy offer, which is currently published with a 28-day lag. (Proposed by: PacificLight Power) (14) Earlier release and higher level of granularity of delayed offer stacks – This proposal suggests bringing forward the publication of energy offer stacks from a 28-day lag to a 1day lag, and in a non-aggregated manner. (Proposed by: I Switch) (15) Improvement of real-time information flow regarding unplanned outages and return to service – This issue suggests improving the reporting of real-time generator availability, especially information on when generators have returned to service. (Proposed by: I Switch) (16) Streamline metering requirements for consumers with embedded intermittent generation sources (IGS) under 1MWac who wishes to sell excess electricity into the grid – This proposal suggests alternative metering arrangements for consumers with embedded IGS that are less than 1MWac and who wishes to be paid for their export of electricity into the grid, for the settlement of market charges, so as to avoid the need to install costly M1 meters. (Proposed by: LYS Genco Beta) (17) Streamline metering requirements for high tension and above consumers with embedded intermittent generation sources (IGS) – This proposal suggests alternative metering arrangements for consumers with embedded IGS that are connected at high Page 4 of 23 EMC/RCP/92/2017/06 tension and above, for the purposes of settling market and/or grid charges, so as to avoid the need to install costly M1 meters. (Proposed by: LYS Genco Beta) (18) Settlement of generation meters for IGS to NEMS – This proposal suggests allowing an MP which is a generation licensee to install, maintain and operate a generation meter, and to register that meter with EMC for settlement. (Proposed by: Sun Electric Power and Sun Electric Energy Assets) (19) Direct metering of generation services – This issue proposes that MPs be allowed to submit the metered quantities for their generation facilities, instead of having meter reading done by the market support services licensee. (Proposed by: Sun Electric Power and Sun Electric Energy Assets) (20) Clarification on the determination of 1MWac threshold for IGS – This issue seeks clarification on how the capacity of IGS is to be determined. (Proposed by: LYS Genco Beta) (21) Raising the nameplate rating threshold of embedded IGS required to register in the market – This proposal suggests raising the current 1MWac threshold for embedded IGS that is required to hold a Wholesale (Generation) Licence and register as an MP with EMC to 5MWac or 10MWac. This would avoid downsizing of solar installations in order to avoid registration. (Proposed by: LYS Genco Beta) (22) Online meter data access by Demand Response and Interruptible Load providers, and electricity retailers – This proposal suggests that Demand Response and Interruptible Load providers and electricity retailers be given access to consumers’ realtime meter data online, to facilitate demand-side management and optimise the use of the existing metering infrastructure. (Proposed by: Red Dot Power) (23) Amending Connection Agreement Requirements – This proposal suggests allowing two separate connection agreements to be signed for EGFs whose load and generation are owned and operated by different entities. This is especially so for embedded IGS, where the solar facility could be owned and operated by a third party and the load facility owner may not want to be liable for that solar facility. (Proposed by: Sunseap Leasing) 3.2 Consultation Process Over a six-week period from 9 January 2017 to 15 February 2017, EMC met up with various market participants2 , the PSO, SP Services and SP PowerAssets to refine the scope of the issues, and rate each issue according to its importance and urgency. Stakeholders could also vote to remove issues from the list, and provide their qualitative comments. Section 4 below summarises stakeholders’ ranking. The following themes/messages emerged from the consultation process: a) While some of the issues raised are not within the purview of the RCP, and hence proposed to be removed, they reflect concerns and issues faced by the industry. EMC 2 A total of 39 market participants were involved, namely Air Liquide Singapore, Best Electricity Supply, Buri Energy, Charis Electric, CGNPC Solar-Biofuel Power (Singapore), Diamond Energy Managers, Diamond Energy Merchants, ECO Special Waste Management, Environmental Solutions (Asia), Exxonmobil Asia Pacific, Hyflux Energy, I Switch, Keppel Electric, Keppel Merlimau Cogen, Keppel Seghers Tuas Waste-To-Energy Plant, LYS Genco Beta, Nanyang Technological University, National Environment Agency, PacificLight Energy, PacificLight Power, Red Dot Power, Sembcorp Cogen, Sembcorp Power, Senoko Energy, Senoko Energy Supply, Senoko Waste-To-Energy, Seraya Energy, Shell Eastern Petroleum, Singapore District Cooling, Singapore LNG Corporation, Sun Electric Energy Assets, Sun Electric Power, Sunseap Energy, Sunseap Leasing, TP Utilities, Tuas Power Supply, Tuas Power Generation, Tuaspring and YTL PowerSeraya. Page 5 of 23 EMC/RCP/92/2017/06 proposes that the RCP refer these issues to the EMA for the EMA to deal with the issues with relevant inputs from SPPG/SP Services where required, and remove these issues from the RCP’s work plan. Such issues comprises: Table 1: Issues proposed to be referred to the EMA Relevant Agency Relevant Legislation Issue No. (Issue Title) EMA Electricity Act and Electricity (Electricity Generation Licence) (Exemption) (No. 2) Order Issue 18 (Waiver of registration for embedded generation facilities which would not produce more than 1MW, regardless of nameplate rating) Issue 37 (Clarification on the determination of 1 MW AC threshold for intermittent generation sources) Issue 38 (Raising the nameplate rating threshold of embedded IGS required to register in the market) EMA EMA’s Policy Decision Issue 28 (Review of Net Metering Treatment for Embedded IGS) EMA/ SP Services Metering Code Issue 24 (Enabling more than a single retailer for single off-take premise) EMA/ SP Services Metering Code Issue 33 (Streamline metering requirements for consumers with embedded IGS under 1MWac who wishes to sell excess electricity into the grid) Issue 34 (Streamline metering requirements for consumers with embedded IGS that are connected at High Tension (HT) and above) EMA/ SP Services Metering Code Issue 35 (Settlement of Generation meters for IGS to NEMS) Issue 36 (Direct metering of generation services) EMA/ SP Services MSS Code Issue 39 (Online meter data access by DR and IL providers and electricity retailers) EMA/ SPPG Transmission Code/ SPPG’s Connection Agreements Issue 40 (Amending requirements) connection agreement Note that the proposer requests for this issue to be removed as the change has been effected. Page 6 of 23 EMC/RCP/92/2017/06 b) Various issues can be meaningfully grouped together given their inherent synergies and similar topic. As such, EMC generally recommended combining these issues for ranking during the consultation process. Table 2 below indicates the list of similar issues that should be grouped together. An average of the average scores of issues under each topic is used for ranking3 (in Table 3). Table 2: Grouping of similar issues Issue No. / Topic Sub-issues Issue 11 11A) Differentiation in probability of failure computation for multi-shaft plants and single-shaft plants Probability of Failure Methodology Issue 17 Provisions regarding settlement bank and settlement account Issue 20 Proposed adjustments to reserve requirements 11B) Calculation methodology for probability of failure 17A) Introduction of settlement account settlement bank diversification flexibility and 17B) Allowing MPs without embedded generators to have multiple settlement accounts 20A) Establishment of a new class of reserve to cater for intermittent generation 20B) Reserve requirements to reflect the largest contingency in the interconnected system 20C) Introduction of an inertia adjustment factor to reserve requirements for enhanced power system security with increased solar generation 20D) Alignment of market rules with transmission code in relation to reserves level Issue 21 Offer publication 21A) Publication of supply bidding behaviour (for reserve and regulation) 21B) Earlier release of delayed offer stack 21C) Earlier release and higher level of granularity of delayed offer stacks) Issue 25 Publication of different load scenarios 3 25A) Publication of price sensitivities to demand or requirement changes for the reserve, regulation and energy services) 25B) Publication of high and low price scenarios in the short term schedule Issue 30 30A) Review of the costs of appeal under the AFPS Automatic Financial Penalty Scheme (AFPS) Issues Raised in RC Prioritisation 2017 30B) Review of the Minimum Penalty Amount under the AFPS 30C) Treatment of forced outages under the AFPS 30D) Remove or amend conflicting methodology that is referred to in Chapter 6 sections 5.2.5B and 5.2.5C For example, the score of Issue 11 is the average of the average scores of Issues 11A and 11B. Page 7 of 23 EMC/RCP/92/2017/06 c) The RCP should consider removing issues that have remained on the list for several years but which has consistently not been ranked high enough for work to be carried out. This would keep the list of issues concise, and facilitate stakeholders’ prioritisation. 4. Ranking Methodology Adopted Two methods to determine the overall ranking of each issue are presented for the RCP’s consideration: (1) Simple Average Methodology: Averages scores for ‘importance’ and ‘urgency’ of each issue across all stakeholders. (2) Group-Weighted Methodology: Averages scores for ‘importance’ and urgency’ of each issue across each of the 4 groups of representatives/stakeholders (generation licensees, retail licensees, wholesale trader licensees and service providers). The average of these 4 scores is then calculated. Table 3 below summarises the ranking results under each of these methodologies, together with an indication of whether work has commenced and the number of stakeholders who proposed to remove the issue, with a detailed breakdown of the ranking results shown in Annex 1. As mentioned in section 3.2(b), issues pertaining to similar topics (as set out in Table 2) are grouped together, resulting in a total of 40 issues. Page 8 of 23 EMC/RCP/92/2017/06 Table 3: Work Plan Issues by Rank4 Issue No. 1 2 30 3 4 5 29 4 Issue Title Rank (Simple Average) Combining Primary Reserve and Secondary Reserve into a single class of Reserve Review of Automatic Financial Penalty Scheme (AFPS) Automatic Financial Penalty Scheme (AFPS) Issues - Raised in RC Prioritisation 2017 30A) Review of the costs of appeal under the AFPS 30B) Review of the Minimum Penalty Amount under the AFPS 30C) Treatment of forced outages under the AFPS 30D) Remove or amend conflicting methodology that is referred to in Chapter 6 sections 5.2.5B and 5.2.5C Review of methodology for recovery of EMC/PSO fees Review of Mechanisms to Mitigate Credit Default N.A. Review of Market Participants’ Classification and Rules Change Panel’s Composition Reduction of gate closure during forced outage events N.A. Rank Work Started? (GroupWeighted) On-going Issues N.A. Y (EMA will direct a rule change) N.A. Y Propose to Remove Summary of Reasons for Removal N.A. N.A. N.A. N.A. 9 14 Y 30A) 0 30B) 2 30C) 2 30D) 4 30B - Policy matter under EMA’s purview 30C - Consider with Issue No. 2 (Review of AFPS) 30D - Methodology is not conflicting EGs should not be required to participate in SWEM N.A. N.A. Y N.A. N.A. N.A. N.A. Y N.A. N.A. N.A. N.A. Y N.A. N.A. Other Issues 4 N 1 1 - A shorter gate closure could reduce reaction time and introduce greater dispatch uncertainty th Arising from the RCP’s decision at its 78 meeting, ongoing issues need not be ranked. The remaining issues where work has not started are arranged by their ranking based on the simple average method. Page 9 of 23 EMC/RCP/92/2017/06 Issue No. 31 28 Issue Title Compensation for generators adversely affected by Type 2 Price Revision Review of Net Metering Treatment for Embedded IGS Rank (Simple Average) 2 Rank (GroupWeighted) 3 Work Started? N Propose to Remove 1 3 2 N 12 Summary of Reasons for Removal - 21 12 25 6 32 7 Could result in market bearing additional costs Net metering is EMA’s directive; should refer issue to EMA instead Not under the purview of the market rules Support retaining the existing net metering treatment Offer publication 21A) Publication of supply bidding behaviour (for reserve and regulation) 21B) Earlier release of delayed offer stack 21C) Earlier release and higher level of granularity of delayed offer stacks Removal of redundant FSC settlement provisions 4 7 N 21A) 2 21B) 2 21C) 2 21A - Not so useful 21B/ 21C - 28 days’ delay is the EMA’s policy decision; should refer issue to EMA instead 5 1 N 2 Publication of different load scenarios 25A) Publication of price sensitivities to demand or requirement changes for the reserve, regulation and energy services) 25B) Publication of high and low price scenarios in the short term schedule Load restoration command from PSO to be in sync with the periods for which loads offered to provide reserve Improvement of real-time information flow regarding unplanned outages and return to service Period-based minimum demand forecast by day types 6 10 N 25A) 0 25B) 0 7 5 N 4 - Proposal may pose system security risk Panel removed this item in 2015 8 13 N 5 - Already considered under CP67 at the st 91 RCP meeting 10 6 N 3 - Should be addressed operationally or by improving accuracy of data submitted by Issue resulted from EMA’s directive; should refer issue to EMA instead - Money might be spent for removal N.A. - Page 10 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Rank (Simple Average) Rank (GroupWeighted) Work Started? Propose to Remove Summary of Reasons for Removal PSO Proposal may make it difficult to ascertain accuracy of demand forecast used in the MCE N.A. - 15 39 13 33 11 37 20 Review of sections 9.1.2.2 and 9.1.3 of Chapter 5 Online meter data access by DR and IL providers and electricity retailers Proposed Amendment to Sample Bankers’ Guarantee Format 11 11 N 0 12 15 N 12 13 18 N 5 - Streamline metering requirements for consumers with embedded IGS under 1MWac who wishes to sell excess electricity into the grid Probability of failure methodology 11A) Differentiation in probability of failure computation for multi-shaft plants and single-shaft plants 11B) Calculation methodology for probability of failure Clarification on the determination of 1 MW AC threshold for intermittent generation sources Proposed Adjustments to Reserve Requirements 20A) Establishment of a new class of reserve to cater for intermittent generation 20B) Reserve requirements to reflect the largest contingency in the interconnected system 20C) Introduction of an inertia adjustment factor to reserve requirements for enhanced power 14 16 N 14 - 15 24 N 11A) 4 11B) 5 - Rules on forced outages and the impact on GRFs’ probability of failure are already in place 16 19 N 16 - Policy matter under EMA’s purview, not that of the market rules 17 21 N 20A) 10 20B) 8 20C) 0 20D) 5 Not under purview of the market rules Should be referred to the EMA/ SPS MPs may need to request re-issuance of bankers’ guarantee Proposal has been on the list since 2013 Policy matter under EMA’s purview, not that of the market rules 20A - Policy matter under EMA’s purview. The EMA has stated that current reserve arrangements are sufficient for IGS up to 600MW - Proposal not necessary given Issue 1 suggests combining reserve classes instead 20B - Not possible to know Malaysia’s schedule Page 11 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Rank (Simple Average) Rank (GroupWeighted) Work Started? Propose to Remove system security with increased solar generation 20D) Alignment of market rules with transmission code in relation to reserves level 8 14 16 34 9 23 19 38 40 Review CVP associated with violation of Type 2 Artificial Lines Review of the timeline for meter data investigation and adjustments after notice of dissent has been raised Review composition of the market surveillance and compliance panel (MSCP) Streamline metering requirements for consumers with embedded IGS that are connected at High Tension (HT) and above Regulation Effectiveness Factor Removal of the first-approach of Constraint Violation Penalties (CVP) rerun Removal of price warning advisory notices Raising the nameplate rating threshold of embedded IGS required to register in the market Amending connection agreement requirements Summary of Reasons for Removal - 18 17 N 2 Proposal will lead to over-procurement of reserve. Interconnection agreement already requires respective parties to provide sufficient reserve within the respective power systems. 20D - Capability of machine is different from reserve requirements - Not of substantial importance at present 19 8 N 2 - Do not think proposal is required 20 20 N 9 - MSCP do not have jurisdiction over futures market 21 25 N 16 - Policy matter under EMA’s/Metering Code purview, not that of the market rules 22 23 12 30 N N 0 2 N.A. - Current process works well 24 22 N 4 - 25 23 N 18 - 26 28 N 19 - 18 Waiver of registration for embedded generation facilities which would not 27 26 N 20 - Prefer retaining price warning advisory notices Policy/licensing matter under EMA’s purview, not that of the market rules The proposer suggests removing this issue as the change had been effected. Policy matter under EMA’s/SP’s purview, not that of the market rules Policy/licensing matter under EMA’s purview, not that of the market rules Page 12 of 23 EMC/RCP/92/2017/06 Issue No. 10 35 26 17 22 36 Issue Title produce more than 1MW, regardless of nameplate rating Adjustment for regulation charges and price neutralisation after final settlement Settlement of Generation meters for IGS to NEMS Removal of Singapore Government Treasury bills as acceptable credit support Provisions regarding settlement bank and settlement account 17A) Introduction of settlement account flexibility and settlement bank diversification 17B) Allowing MPs without embedded generators to have multiple settlement accounts Modelling of on-site ambient temperature into the MCE such that GTs/CCPs’ maximum capacity are adjusted dynamically Direct metering of generation services Rank (Simple Average) Rank (GroupWeighted) Work Started? Propose to Remove Summary of Reasons for Removal - Expected output is subjective, unlike name-plate rating Should be discussed between EMA and SPS Policy matter under EMA’s purview 28 9 N 1 - 29 29 N 17 - 30 33 N 6 - 31 32 N 17A) 2 17B) 4 32 27 N 4 - Proposal has not been prioritised high enough for too long 32 31 N 17 - Policy/Metering Code matter under EMA’s purview Any party with a MSSL Licence can perform the role Not operationally feasible Outcome can be resolved via financial arrangements Suggest simplifying the DR penalty scheme instead Proposal has not been prioritised high enough for too long T-bill can remain as an option 17A - Would more costs be incurred by EMC? 17B - May complicate settlement 24 Enabling more than a single retailer for single off-take premise 34 34 N 17 - 27 Invalid load ramping constraints in the Rules Modification for EMA’s “Implementing Demand Response in the National Electricity Market of Singapore” 35 35 N 1 - Page 13 of 23 EMC/RCP/92/2017/06 5. Approach to Prioritisation EMC recommends that the RCP consider the following in its prioritisation process: Ranking received from stakeholders – The ranking by stakeholders indicates which issues are likely to provide the most impact in enhancing the performance of the market. On-going issues – As considerable amount of effort were already invested in the ongoing issues, it would be sensible to continue with these work streams. Issues to be referred to the EMA – Issues listed in Table 1 (also shaded in purple in Table 3) are not under the purview of the RCP and should be referred to the EMA. Stakeholders had proposed that certain issues be removed from the work plan, along with their reasons. It would be useful for the RCP to deliberate if these issues should be removed from the work plan. EMC proposes that 12 issues be addressed in the next 12 months (i.e. from April 2017 to March 2018). 6. Conclusions and Decisions at the 92nd RCP Meeting The Panel, having considered the 395 issues and EMC’s recommendations, made the following decisions: (i) Issues to be referred to the EMA (Table 1) The Panel unanimously agreed to refer the issues set out in Table 1 to the EMA, for the EMA to deal with the issues with relevant inputs from SPPG and/or SP Services, since those issues are not within the RCP’s purview. In addition, the Panel also tasked EMC to write to the proposers to inform them that their respective proposals have been referred to the EMA. (ii) Issues to be combined (Table 2) The Panel generally agreed with the proposed grouping of similar issues set out in Table 2. In addition, Issue 30 (AFPS Issues – Raised in RC Prioritisation 2017) will be combined with Issue 2 (Review of AFPS) as a single issue given the similar scope of both issues. (iii) Updated Work Plan 2017/18 Since the EMA/PSO intends to issue a directed rule change for Issue 1 (Combining Primary Reserve and Secondary Reserve into a single class of Reserve), it will be removed from the work plan. Mr. Dallon Kay suggested including Issue 20 (Proposed Adjustments to Reserve Requirements) in the list of issues for commencement within the first 12 months. Mr. Soh Yap Choon, on the other hand, felt that Issues 20B, 20C and 20D should be removed for the following reasons: 5 While a total of 40 issues (after combining) were presented in Table 3, 1 of the issues (i.e. Issue 3: Review of nd Methodology for the Recovery of EMC’s and PSO’s fees) was tabled and completed by the RCP at its 92 meeting, prior to the work plan discussion. Page 14 of 23 EMC/RCP/92/2017/06 Issue 20B (Reserve requirements to reflect the largest contingency in the interconnected system) – The interconnection agreement specifically requires the respective interconnected systems to provide sufficient reserve for the largest unit operating in the respective power systems. Issue 20C (Introduction of an inertia adjustment factor to reserve requirements for enhanced power system security with increased solar generation) – Already work in progress for the PSO. PSO is monitoring the effect of solar PV on reserve requirement and plans to update the reserve requirement formulation in the SOM accordingly. PSO will consult the industry when changes to the SOM are made. Issue 20D (Alignment of market rules with transmission code in relation to reserves level) – The Transmission Code stipulates the reserve capability of a generating unit, which is different from reserve requirement. The Panel decided to monitor and consider whether Issue 20 should be removed at the Panel’s mid year review of the work plan. The RCP generally agreed with EMC’s recommendation to place the top 12 issues that remained on the updated work plan for commencement within the next 12 months, with subsequent issues slated for commencement within 13-24 months. However, since the analytical effort required by EMC should be minimal for Issue 12 (Removal of redundant FSC settlement provisions), one more issue was agreed to be included for commencement within the next 12 months, bringing the total number of issues slated for commencement by March 2018 to 13 issues. Given the above resolutions, the RCP agreed on the updated work plan in Table 4 below, and tasked EMC to monitor the progress of this work plan: Table 4: Updated Rules Change Work Plan from April 2017 to March 2019 Expected Commencement/ Completion Within next 12 months (i.e. by March 2018) Issue No. Issue Title 2, 30 Review of Automatic Financial Penalty Scheme (AFPS) & Automatic Financial Penalty Scheme (AFPS) Issues - Raised in RC Prioritisation 2017 30A) Review of the costs of appeal under the AFPS 30B) Review of the Minimum Penalty Amount under the AFPS 30C) Treatment of forced outages under the AFPS 30D) Remove or amend conflicting methodology that is referred to in Chapter 6 sections 5.2.5B and 5.2.5C Review of Mechanisms to Mitigate Credit Default Review of Market Participants’ Classification and Rules Change Panel’s Composition Reduction of gate closure during forced outage events Compensation for generators adversely affected by Type 2 Price Revision Offer publication 21A) Publication of supply bidding behaviour (for reserve and regulation) 21B) Earlier release of delayed offer stack 21C) Earlier release and higher level of granularity of delayed offer stacks Removal of redundant FSC settlement provisions Publication of different load scenarios 25A) Publication of price sensitivities to demand or requirement changes for the reserve, regulation and energy services) 4 5 29 31 21 12 25 Page 15 of 23 EMC/RCP/92/2017/06 Expected Commencement/ Completion Issue No. 6 32 Within 13-24 months (i.e. by March 2019) 7 15 13 11 20 8 14 16 9 23 19 10 26 17 22 27 Issue Title 25B) Publication of high and low price scenarios in the short term schedule Load restoration command from PSO to be in sync with the periods for which loads offered to provide reserve Improvement of real-time information flow regarding unplanned outages and return to service Period-based minimum demand forecast by day types Review of sections 9.1.2.2 and 9.1.3 of Chapter 5 Proposed Amendment to Sample Bankers’ Guarantee Format Probability of failure methodology 11A) Differentiation in probability of failure computation for multishaft plants and single-shaft plants 11B) Calculation methodology for probability of failure Proposed Adjustments to Reserve Requirements 20A) Establishment of a new class of reserve to cater for intermittent generation 20B) Reserve requirements to reflect the largest contingency in the interconnected system 20C) Introduction of an inertia adjustment factor to reserve requirements for enhanced power system security with increased solar generation 20D) Alignment of market rules with transmission code in relation to reserves level Review CVP associated with violation of Type 2 Artificial Lines Review of the timeline for meter data investigation and adjustments after notice of dissent has been raised Review composition of the market surveillance and compliance panel (MSCP) Regulation Effectiveness Factor Removal of the first-approach of Constraint Violation Penalties (CVP) rerun Removal of price warning advisory notices Adjustment for regulation charges and price neutralisation after final settlement Removal of Singapore Government Treasury bills as acceptable credit support Provisions regarding settlement bank and settlement account 17A) Introduction of settlement account flexibility and settlement bank diversification 17B) Allowing MPs without embedded generators to have multiple settlement accounts Modelling of on-site ambient temperature into the MCE such that GTs/CCPs’ maximum capacity are adjusted dynamically Invalid load ramping constraints in the Rules Modification for EMA’s “Implementing Demand Response in the National Electricity Market of Singapore” Page 16 of 23 EMC/RCP/92/2017/06 Annex 1: Ranking Results by Key Stakeholders Each stakeholder was asked for his view on the importance and urgency of each of the issues where work has not started. A score of 3 corresponds to “High”, 2 corresponds to “Medium”, and 1 corresponds to “Low”. In the Grand Total column, the number in front of the bracket shows the ranking score and the number in the bracket gives the number of stakeholders providing that ranking score. For example, 1(7) means 7 stakeholders have ranked this item as 1 or “Low”. The overall average score6 arising from each method is represented in the last 2 columns of Table 5. Table 5: Scoring of issues by stakeholders Issue No. Issue Title Grand Total Overall Score (Simple Average) 6 Load restoration command from PSO to be in sync with the periods for which loads offered to provide reserve Importance Urgency 7 Period-based minimum forecast by day types 1.611 1.667 1(20), 2(11), 3(4) 1(22), 2(12), 3(1) 1.471 1.468 1(23), 2(9), 3(5) 1(29), 2(4), 3(4) 1.419 1.544 1.363 1.565 1.485 1.375 Regulation Effectiveness Factor Adjustment for regulation charges and price neutralisation after final settlement Importance Urgency 11A 1(17), 2(14), 3(5) 1(20), 2(12), 3(4) Review CVP associated with violation of Type 2 Artificial Lines Importance Urgency 10 1.702 demand Importance Urgency 9 1.694 1(19), 2(6), 3(11) 1(21), 2(8), 3(7) Importance Urgency 8 Overall Score (Group-weighted Average) 1(27), 2(9), 3(4) 1(31), 2(6), 3(3) Differentiation in probability of failure computation for multi-shaft plants and single-shaft plants Importance 1(20), 2(7), 3(6) 6 To simplify representation, the “Average Total” column for the group-weighted method is not represented in the table. Page 17 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) Urgency 11B 1(25), 2(3), 3(5) Calculation methodology probability of failure (POF) for Importance Urgency 12 Proposed Amendment to Bankers’ Guarantee Format 1.786 1(18), 2(10), 3(4) 1(19), 2(9), 3(4) 1.547 1.446 1.467 1.588 1.574 1.558 1.457 1.411 1.363 1.273 1.284 1.251 1(20), 2(6), 3(4) 1(20), 2(6), 3(4) 1(16), 2(13), 3(5) 1(23), 2(6), 3(5) 1(23), 2(7), 3(5) 1(23), 2(9), 3(3) Introduction of settlement account flexibility and settlement bank diversification Importance Urgency 17B 1.730 Review composition of the market surveillance and compliance panel (MSCP) Importance Urgency 17A 1(19), 2(8), 3(10) 1(19), 2(10), 3(8) Review of sections 9.1.2.2 and 9.1.3 of Chapter 5 Importance Urgency 16 1.410 Review of the timeline for meter data investigation and adjustments after notice of dissent has been raised Importance Urgency 15 1.507 Sample Importance Urgency 14 1(19), 2(7), 3(6) 1(23), 2(3), 3(5) Removal of redundant FSC settlement provisions Importance Urgency 13 Overall Score (Group-weighted Average) 1(30), 2(3), 3(7) 1(32), 2(4), 3(4) Allowing MPs without embedded generators to have multiple settlement accounts Importance Urgency 1(28), 2(6), 3(3) 1(30), 2(5), 3(2) Page 18 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) 18 Waiver of registration for embedded generation facilities which would not produce more than 1MW, regardless of nameplate rating Importance Urgency 19 1(26), 2(11), 3(2) 1(24), 2(13), 3(2) Establishment of a new class of reserve to cater for intermittent generation Introduction of an inertia adjustment factor to reserve requirements for enhanced power system with increased solar generation 1.410 1.292 1.263 1.656 1.542 Alignment of market transmission code in reserves level 1.483 1.417 1.417 1.379 2.069 1.876 1(12), 2(15), 3(5) 1(17), 2(13), 3(2) rules with relation to 1(17), 2(8), 3(4) 1(19), 2(8), 3(2) Publication of supply bidding behaviour (for reserve and regulation) Importance Urgency 21B 1.461 . 1(24), 2(9), 3(3) 1(33), 2(0), 3(3) Importance Urgency 21A 1.404 Reserve requirements to reflect the largest contingency in the interconnected system Importance Urgency 20D 1.410 1(23), 2(11), 3(4) 1(26), 2(8), 3(4) Importance Urgency 20C 1.369 Removal of price warning advisory notices Importance Urgency 20B 1.386 1(27), 2(2), 3(6) 1(28), 2(1), 3(6) Importance Urgency 20A Overall Score (Group-weighted Average) 1(22), 2(7), 3(7) 1(30), 2(3), 3(3) Earlier release of delayed offer stack Importance 1(11), 2(7), 3(18) Page 19 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) Urgency 21C 1.417 1.309 1.257 1.203 1.568 1.460 1.833 1.657 1.333 1.229 1.200 1.186 1(17), 2(12), 3(1) 1(19), 2(11), 3(0) 1(30), 2(3), 3(4) 1(31), 2(4), 3(2) 1(19), 2(12), 3(6) 1(22), 2(12), 3(3) 1(11), 2(16), 3(9) 1(16), 2(14), 3(6) Removal of Singapore Government Treasury bills as acceptable credit support Importance Urgency 27 1.359 Publication of high/low price scenarios in the Short Term Schedule (STS) Importance Urgency 26 1.294 1(23), 2(10), 3(1) 1(27), 2(6), 3(1) Publication of Price Sensitivities to Demand/ Requirement Changes for the Reserve, Regulation, and Energy Services Importance Urgency 25B 1.652 Enabling more than a single retailer for single off-take premise Importance Urgency 25A 1.743 Removal of the first-approach of Constraint Violation Penalties (CVP) rerun Importance Urgency 24 1(18), 2(5), 3(12) 1(19), 2(9), 3(7) Modelling of on-site ambient temperature into the MCE such that GTs/CCPs’ maximum capacity are adjusted dynamically Importance Urgency 23 1(14), 2(10), 3(12) Earlier release and higher level of granularity of delayed offer stacks Importance Urgency 22 Overall Score (Group-weighted Average) Invalid load ramping constraints in the Rules Modification for EMA’s 1(26), 2(3), 3(4) 1(26), 2(3), 3(4) Page 20 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) Overall Score (Group-weighted Average) “Implementing Demand Response in the National Electricity Market of Singapore” Importance Urgency 28 1(23), 2(7), 3(0) 1(25), 2(5), 3(0) Review of Net Metering Treatment for Embedded IGS Importance Urgency 29 Reduction of gate closure forced outage events 1.728 1.694 1.510 1.964 1.753 1.519 1.406 1.313 1.233 1.889 1.737 1(15), 2(11), 3(5) 1(15), 2(10), 3(6) 1(11), 2(6), 3(11) 1(11), 2(8), 3(9) 1(18), 2(3), 3(6) 1(18), 2(5), 3(4) Remove or amend conflicting methodology that is referred to in Chapter 6 sections 5.2.5B and 5.2.5C Importance Urgency 31 1.959 Treatment of Forced Outages under the Automatic Financial Penalty Scheme (AFPS) Importance Urgency 30D 1(11), 2(13), 3(13) 1(16), 2(10), 3(11) Review of the Minimum Penalty Amount under the Automatic Financial Penalty Scheme (AFPS) Importance Urgency 30C 1.767 Review of the Costs of Appeal under the Automatic Financial Penalty Scheme (AFPS) Importance Urgency 30B 1.758 during Importance Urgency 30A 1(18), 2(3), 3(12) 1(20), 2(3), 3(10) 1(24), 2(6), 3(2) 1(24), 2(6), 3(2) Compensation for generators adversely affected by Type 2 Price Revision Importance Urgency 1(15), 2(9), 3(12) 1(16), 2(9), 3(11) Page 21 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) 32 Improvement of real-time information flow regarding unplanned outages and return to service Importance Urgency 33 35 1.386 1.353 1.333 1.294 1.293 1.484 1.427 1.406 1.396 1.561 1.471 1(23), 2(6), 3(4) 1(23), 2(6), 3(4) 1(26), 2(4), 3(4) 1(26), 2(4), 3(4) 1(27), 2(4), 3(3) 1(27), 2(4), 3(3) 1(23), 2(2), 3(7) 1(24), 2(1), 3(7) Raising the nameplate rating threshold of embedded IGS required to register in the market Importance Urgency 39 1.424 Clarification on the determination of 1 MW AC threshold for intermittent generation sources Importance Urgency 38 1.470 Direct metering of generation services Importance Urgency 37 1.541 Settlement of Generation meters for IGS to NEMS Importance Urgency 36 1.500 1(24), 2(6), 3(7) 1(24), 2(6), 3(7) Streamline metering requirements for consumers with embedded IGS that are connected at High Tension (HT) and above Importance Urgency 1.643 1(20), 2(6), 3(9) 1(21), 2(7), 3(7) Streamline metering requirements for consumers with embedded IGS under 1MWac who wishes to sell excess electricity into the grid Importance Urgency 34 Overall Score (Group-weighted Average) Online meter data access by DR and IL providers and electricity retailers 1(25), 2(1), 3(6) 1(25), 2(1), 3(6) Page 22 of 23 EMC/RCP/92/2017/06 Issue No. Issue Title Grand Total Overall Score (Simple Average) Importance Urgency 40 Amending connection requirements Importance Urgency Overall Score (Group-weighted Average) 1(22), 2(3), 3(8) 1(22), 2(4), 3(7) agreement 1(21), 2(9), 3(3) 1(23), 2(10), 3(1) 1.404 1.355 Page 23 of 23
© Copyright 2026 Paperzz