On MEGA projects and evaluation of their economic and other impacts Heikki A. Loikkanen Professor (emeritus) of urban economics, University of Helsinki Lecture at Aalto University, Dept. of Architecture, September 28, 2016, Espoo TOPICS TO BE COVERED WHAT TYPES OF MEGA PROJECTS - PERSONAL, PRIVATE BUSINESS, PUBLIC, MIXED - SHORT AND LONG: REVERSIBLE OR IRREVERSIBLE COST BENEFIT ANAYLYSIS OF PRIVATE & PUBLIC PROJECTS (in this file) HELSINKI EASTERN METROLINE CASE Seppo Laakso’s dissertaion has a chapter on this ON SPORTS AND CULTURAL MEGA EVENTS WC2005 IN HELSINKI (Summary report in English available) EUROVISION SONG CONTEST 2007 IN HELSINKI (Summary of a Finnish report available) UNFORTUNATELY, I CANNOT DELIVER ALL PRESENTATIONS 2 Mega Project and Cost-Benefit Analysis (CBA) 1. Introduction • CBA can be applied to evaluate investment projects, which typically have a long lasting cost and benefit structure • Business investment (a special case of CBA) • Railway, highway, power plant • School, opera, environmental project • Labour market reform (viewed as investment) Heikki Loikkanen, NAPA 2016 Cost and revenue structure of a typical investment project over time Revenue 0 Time Costs Heikki Loikkanen, NAPA 2016 How to evaluate and choose which project is best, and should it be realized? - Assume that building takes 5 years, and then investment brings revenue until year 20. PROPOSAL • if the sum of benefits B1+ ... +B20 , is greater than the sum of costs C1+...+C20, then project is worth realizing? • WHAT IS WRONG WITH THIS CRITERION? Heikki Loikkanen, NAPA 2016 2. Three investment criteria Two projects x and z. PRESENT VALUE (PV) CRITERION PVi = B0i-C0i + (B1i-C1i)/(1+r) + ... + (BTi-CTi)/(1+r)T , i = x, z. where r is the market interest rate. Decision rule: what is it? Heikki Loikkanen, NAPA 2016 CBA continues Internal rate of return (ij )method B0j-C0j + (B1j-C1j)/(1+ ij) + ... + (BTj-CTj)/(1+ ij)T = 0 , j = x, z. Solve ij Decision rule: what is it? Heikki Loikkanen, NAPA 2016 Numerical example The annual net benefits (revenue-costs) of projects x and z during three years are: • project x: (-100, 0, 120) • project z: (-100, 115, 0) • In Figure 1 the present value function of project x intersects the r-axis at value r= 9.5 %, and the PV function of z at value r= 11,5 %. If the market rate of interest exceeds 9,5 % project x is unprofitable. Project z becomes unprofitable if interest rate exceeds 11,5 %. In our numerical example r* is the intersection point of two projects’PV functions and it happens at interest rate level of 4,4 %. DECISION RULE: When the market rate of interest is below 4.4 % choose project x. When the market rate of interest is above 4.4 % choose project z, but if the interest rate exceeds 11,5 reject also project z and don’t realiza either project. Heikki Loikkanen, NAPA 2016 Figure 1 Investment criteria (NPV and Internal Rate of Return) Heikki Loikkanen, NAPA 2016 CBA continues Benefit-cost ratio B/C B= B0i + (B1i)/(1+r) + ... + (BTi)/(1+r)T , i = x,z C = C0i + C1i/(1+r) + ... + CTi/(1+r)T , i = x, z Decision rule: what is it? Which of the three rules should be applied? Always or depending on case? Heikki Loikkanen, NAPA 2016 3. Evaluating public projects with CBA Differences with private projects Three baskets: • items which have market prices (like in private projects), • items which have to be assessed, • items which cannot even be assessed but are worth mentioning and evaluating in some way Risks: how should they be taken into account? Why applications of CBA are more art than science, and what could be done to improve the use of CBA? Heikki Loikkanen, NAPA 2016 Thank you Heikki Loikkanen, NAPA 2016
© Copyright 2026 Paperzz