NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA Alignment of the Infrastructure Delivery Cycle with the Budget Cycle and Strategic Planning Cycle Prepared by the Infrastructure Delivery Improvement Programme (IDIP) 1 NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA The Infrastructure Delivery Improvement Programme (IDIP) • IDIP is a continuous improvement programme which guides & capacitates to improve infrastructure delivery • IDIP is coordinated by National Treasury in partnership with DBSA, DPW & CIDB • IDIP provides flexible tools that can be adapted to the province & sector • IDIP is a key strategy of government to address inadequate capacity and skills in the infrastructure sector 2 State of the Nation Address 2005 NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA “Certainly it is a reflection of weaknesses in the governance system that the plans to build school infrastructure are unfolding at a much slower pace than envisaged.” “We need massively to improve the management, organisational, technical and other capacities of government so that it meets its objectives.” President Thabo Mbeki – State of the Nation Address 2005 3 State of the Nation Address 2006 NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA “We cannot allow that government departments become an obstacle to the achievement of the goal of a better life for all because of insufficient attention to the critical issue of effective and speedy delivery of services.” “Integration of planning and implementation across the government spheres is therefore one of the prime areas of focus in our programme…” President Thabo Mbeki – State of the Nation Address 2006 4 Problem Statement NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA • Continuing under expenditure of infrastructure budgets. • Inappropriate expenditure patterns characterized by the 4th Quarter expenditure spike. • Currently there appears to be very little alignment between the Infrastructure Delivery Cycle and either the Budget Cycle or the Strategic Planning Cycle. • Currently the budget for large multi-year projects is committed to 1 financial year instead apportioning the budget across the MTEF. 5 Overview of Presentation NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA • This presentation covers the following topics: – – – – – – The Strategic Planning Cycle The Budget Cycle The current Infrastructure Delivery Cycle The improvements to the Infrastructure Delivery Cycle The alignment and interdependence between these 3 cycles An overview of the Infrastructure Plan, Infrastructure Programme Management Plan (IPMP), & Infrastructure Programme Implementation Plan (IPIP) – Budget allocation for Infrastructure Delivery Programmes – Managing cashflows across years to ensure 100% effective expenditure – Benefits & Challenges 6 Fiscal Years 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Election Electoral Cycle Election 5 Year Election Mandate Election 5 Year Election Mandate 5 Year Electio Planning & Budgeting • Five-year Strategic and Performance Plans • Annual Performance Plans and Budgets (with 3 Year MTEF) LEGEND: 5 year Strategic & Performance Plan detailing Targets & priorities 5 year Strategic & Performance Plan detailing Targets & priorities 5 year Strat Plan detailing MTEF (3 years)(3 years) MTEF MTEF (3 years)(3 years) MTEF MTEF (3MTEF years)(3 years) MTEF (3 years) MTEF (3MTEF years)(3 years) Year 1 Year 2 Year 3 MTEF (3 years)(3 years Year 1 Year 2 Year 3 MTEF Year 1 Year 2 Year 3 Budget Budget Budget MTEF Year 1 Year 2 Year 3 Budget Budget Budget Budget Budget Budget APP APP APP APP APP APP APP APP For For For APP For For For For For Year 1 Year 2 Year 3 For3 Year 1 Year 2 Year Year 1 Year 2 Year 1 APP – Annual Performance Plan Year 1 Year 2 Year 3 Budget Year 1 Year 2 Budget Budget Year 1 Budget Budget Budget Budget Budget Budget APP APP APP APP APP APP For APP APP For For APP For For For Year 3 For3 For Year 2 Year For Year 1 Year 2 Year 3 Year 1 Year 2 Year 1 Year 3 Year 2 Year 1 Budget Budget Budget Year 3 Year 2 Year 3 Year 1 Year 2 Budget Year 1 Budget Budget Budget Budget Budget APP APP APP APP APP APP For APP APP For For APP For 3 For For Year For For Year 2 Year 3 For Year 1 Year 2 Year 3 Year 1 Year 2 Year 1 Year 3 Year 2 Year 1 Budget Budget Budget Year 3 Year 2 Year 1 Budget Budget Budget APP APP APP APP APP For APP For For For For Year 3 For 3 Year 2 Year Year 1 Year 2 Year 1 7 3 Year MTEF Period MTEF Budget Cycle 31 Aug Year 0 17 Feb Mid Dec 31 Mar Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Draft Update Final Budget Budget Budget LEGEND: Final APP Budget Day (15 Feb) Budget Allocation Letter (Nov) Draft 2 APP MTEC Hearings (Sept) Draft APP AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR AR Q4 PR Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Final APP Financial Reports (Section 32 PFMA) & Non-Financial Data Reporting AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR AR Q4 PR Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Final APP AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Planning Processes AR Q4 PR Implementation Processes Closure Processes APP – Annual Performance Plan AFS – Annual Financial Statements AR – Annual Report PR – Performance Report Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Final APP Imple Q1 Q Rep R 8 Q P 3 Year MTEF Period MTEF Budget Cycle Year 0 Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J These J A S Oare N DallJ the F M A M J J concurrent budget AFS Draft Update Final Implement Budget AR activities that need to be Budget Budget Budget undertaken in any 1 year Final APP Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Q4 PR Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Budget Day Budget Allocation Letter Draft 2 APP MTEC Hearings Draft APP Final APP Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR AR Q4 PR Draft Update Final Budget Budget Budget Draft APP LEGEND: AFS Implement Budget Draft 2 APP Final APP AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Planning Processes AR Q4 PR Implementation Processes Closure Processes APP – Annual Performance Plan AFS – Annual Financial Statements AR – Annual Report PR – Performance Report Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Final APP Imple Q1 Q Rep R 9 Q P 3 Year MTEF Periodinformation is used as input to The following MTEF Budget Cycle Year 0 prepare the budget: Draft Budget due 31 August •Annual Financial Statements from last year due 31 May mid July Year 4 Year 1 Year •1st2Quarter Report from thisYear year 3due A M J J A S O N D J F M A M J J A S O N D J F M A M J J A SUpdated O N D J Budget F M A M J mid J A December S O N D J F M A M J J due •2nd Quarter Report from this year due mid October Draft Update Final Budget Budget Budget Final APP Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Budget Day Draft 2 APP Final APP Final Budget due 17 February •Budget Allocation Letter •3rd Quarter Report from this year due mid January Q4 PR Draft Update Final Budget Budget Budget Draft APP AR AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Draft Update Final Budget Draft Budget Update Budget Final Draft Draft 2 Budget Final Budget Budget APP APP APP AR Q4 PR Implementation Processes Closure Processes APP – Annual Performance Plan AFS – Annual Financial Statements AR – Annual Report PR – Performance Report AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Q1 PR Q2 PR Q3 PR Planning Processes Budget Allocation Letter LEGEND: Budget Allocation Letter Draft 2 APP MTEC Hearings Draft APP AFS Q4 PR Draft Update Final Budget Budget Budget Draft APP Draft 2 APP Final APP AR Imple Q1 Q Rep R 10 Q P Fiscal Years 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Election Electoral Cycle Election 5 Year Election Mandate 5 Year Election Mandate Planning & Budgeting • Five-year Strategic and Performance Plans • Annual Performance Plans and Budgets (with 3 Year MTEF) LEGEND: 5 year Strategic & Performance Plan detailing Targets & priorities 5 year Strategic & Performance Plan detailing Targets & priorities MTEF (3 years)(3 years) MTEF MTEF (3 years)(3 years) MTEF MTEF (3MTEF years)(3 years) MTEF (3 years) MTEF (3 years) Year 1 Year 2 Year 3 Year 1 Year 2 Year 1 Budget Budget Budget Budget Budget Budget Year 3 Year 2 Year 1 Budget Budget Budget Year 3 Year 2 Year 1 Budget Budget Budget Year 3 Year 2 Year 3 Year 1 Year 2 Budget Year 1 Budget Budget Budget Budget APP APP APP Budget APP APP APP APP APP APP For For For APP APP APP For For For APP APP APP For3 For For Year 1 Year 2 Year APP APP For3 For For Year 1 Year 2 Year APP For For For Year 1 Year 2 Year 3 For3 For Year 1 Year 2 Year For Year 1 Year 2 Year 3 Year 1 Year 2 Year 1 Year 3 Year 2 Year 1 Budget Budget Budget Year 3 Year 2 Year 3 Budget Budget Budget APP APP APP APP APP APP For For For For 3 For For Year Year 2 Year 3 Year 1 Year 2 Year 3 Infrastructure Plan Update (10 Year Plan) Infrastructure Plan Update (10 Year Plan) Infrastructure Plan Update (10 Year Plan Infrastructure Plan Update (10 Year Plan) Infrastructure Plan Update (10 Year Plan) Infrastructure Plan Update (10 Year Plan) APP – Annual Performance Plan 11 Etc, etc, etc Infrastructure Delivery Cycle Year 0 3 Year MTEF Period Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current Infrastructure Delivery Cycle Infr. Plan update Project Design Project Tender Project Implementation Rolled Over Unspent Budget 100% Cumulative Cashflow Budget Rollover Time With the current Infrastructure Delivery Cycle, expenditure during the 1st half of the year is virtually impossible since most projects are still in the tender phase. The result is the 4th quarter expenditure spike and overall under-expenditure. Better supervision of infrastructure projects undertaken by government will be introduced, to ensure that capital budgets are spent without roll-overs - President Thabo Mbeki - State of the Nation Address 2006 12 Infrastructure Delivery Cycle 3 Year MTEF Period Year 0 Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current Infrastructure Delivery Cycle Infr. Plan update Project Design Project Tender Infr. Plan update Project Implementation Project Design Rolled Over Unspent Budget Project Tender Each Infrastructure Delivery Cycle is characterized by under-expenditure and rolled over unspent budgets Project Implementation Infr. Plan update Project Design Rolled Over Unspent Budget Project Tender Project Implementation Rolled Unspent Improved Infrastructure Delivery Cycle IPMP IPIP O&S Plan O&S O&S Budget Speech Infr. Plan update LEGEND: O&S Plan – Organisation & Support Plan IPMP – Infrastructure Programme Management Plan IPIP – Infrastructure Programme Implementation Plan 13 Infrastructure Programme Management & Implementation Plans (IPMP & IPIP) Client Department (CD) FUNCTIONS OF CD: 1. Planning 2. Procurement 3. Programme Management 4. Monitoring & Reporting Infrastructure Plan Update IPMP Update IPMP issued to IAs Implementing Agent IA 1 1. 2. 3. IPIP for IA 1 IPIPs respond to IPMP IPIP for IA 2 Implementing Agent IA 2 FUNCTIONS of IAs: Programme Management 4. Project Implementation Project Initiation 5. Project Completion Procurement 6. Monitoring & Reporting 14 Infrastructure Delivery Cycle 3 Year MTEF Period Year 0 Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current Infrastructure Delivery Cycle Infr. Plan update Project Design Project Tender Infr. Plan update Project Implementation Project Design Rolled Over Unspent Budget Project Tender Project Implementation Infr. Plan update Project Design Rolled Over Unspent Budget Project Tender Project Implementation Rolled Unspent Improved Infrastructure Delivery Cycle IPMP IPIP O&S Plan O&SPlan O&SPlan Project Design Project Tender Project Implementation Planned Multi-year Commitments Monitoring & Evaluation Budget Speech Infr. Plan update LEGEND: O&S Plan – Organisation & Support Plan IPMP – Infrastructure Programme Management Plan IPIP – Infrastructure Programme Implementation Plan 15 3 Year MTEF Period Year 0 Year 1 Year 2 Year 3 Year 4 AM J J A S O N D J F M AM J J A S O N D J F M AM J J A S O N D J F M AM J J A S O N D J F M AM J J Current Project Budgeting Infr. Plan update Project Design Project Tender Cumulative Cashflow Budget 100% Project Implementation Implementation of Roll-Over Whole project budget is committed to Yr 1 Rollover Implementation of Roll-Over Retention Period Rollover Time Best Practice Project Budgeting Infr. Plan update IPMP IPIP Project Design Project Tender Project Implementation Monthly Projected Cashflow Budget Commit from Yr 2 Commit from Yr 1 Commit from Yr 3 Retention Period Commit from Yr 4 Cumulative Cashflow Budget 100% 16 Example of a Programme Budget to commit the entire Annual Budget Department's Annual Budget = ( ,000) PROJECT TOTAL PROJECT BUDGET R 50,000 BUDGET FOR YEAR 1 R 60,000 BUDGET FOR YEAR 2 R 70,000 BUDGET FOR YEAR 3 Project 1 R 30,000 R 10,000 R 10,000 R 10,000 Project 2 R 20,000 R 5,000 R 10,000 R 5,000 Project 3 R 25,000 R 7,000 R 8,000 R 10,000 Project 4 R 15,000 R 12,000 R 3,000 R0 Project 5 R 10,000 R 5,000 R 5,000 R0 Project 6 R 20,000 R 11,000 R 4,000 R 5,000 R 120,000 R 50,000 R 40,000 R 30,000 R0 R 20,000 17 R 40,000 Amount Committed Amount remaining for new projects ( = Annual Budget less Amount Committed) Infrastructure Delivery Cycle 3 Year MTEF Period Year 0 Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current Infrastructure Delivery Cycle Infr. Plan update Project Design Project Tender Infr. Plan update Project Implementation Project Design These are all the concurrent infrastructure delivery activities that need to be undertaken in any 1 year Rolled Over Unspent Budget Project Tender Project Implementation Infr. Plan update Rolled Over Unspent Budget Departments therefore need to have the capacity Project Project Rolled Tenderto undertake Implementation Unspent all these concurrent activities. Project Design Improved Infrastructure Delivery Cycle IPMP IPIP O&S Plan O&SPlan O&SPlan Budget Speech Infr. Plan update Project Design Project Tender Project Implementation Planned Multi-year Commitments Monitoring & Evaluation Infr. Plan update IPMP O&S Plan O&S IPIP Project Design Project Tender Project Implementation Planned Comm Monitoring & Evaluation O&S Infr. Plan update IPMP O&S Plan O&S LEGEND: O&S Plan – Organisation & Support Plan IPMP – Infrastructure Programme Management Plan IPIP – Infrastructure Programme Implementation Plan IPIP Project Design Project Tender Projec Monitorin O&S Infr. Plan update IPMP O&S Plan O&S IPIP O&S 18 Proje Desig Year 0 Year 1 Year 2 Yearall3 the concurrent Year 4 These are A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M activities J J A S Othat N Dneed J F MtoAbe M J J undertaken in any 1 year by a department AFS Draft Update Final Implement Budget AR MTEF Budget cycle Budget Budget Budget Final Draft Draft 2 APP APP APP Q1 Q2 Q3 Q4 Rep Rep Rep Rep Draft Update Final Budget Budget Budget Final Draft Draft 2 APP APP APP LEGEND: AFS Implement Budget Q1 Q2 Q3 Q4 Rep Rep Rep Rep Draft Update Final Budget Budget Budget APP – Annual Performance Plan Draft APP AFS – Annual Financial Statements Draft 2 APP Final APP AR – Annual Report IPIP Project Design Q1 Q2 Q3 Q4 Rep Rep Rep Rep Draft APP Infrastructure Delivery Cycle IPMP AFS Implement Budget AR Draft Update Final Budget Budget Budget PR – Performance Report Infr. Plan update AR Project Tender Project Implementation Final APP Draft 2 APP Imple Q1 Q Rep R Planned Multi-year Commitments Monitoring & Evaluation O&S Plan Infr. Plan update IPMP IPIP Project Design Project Tender Project Implementation Planned Comm Monitoring & Evaluation O&S Plan Infr. Plan update IPMP IPIP Project Design Project Tender Monitoring O&S Plan LEGEND: O&S Plan – Organisation & Support Plan IPMP – Infrastructure Programme Management Plan IPIP – Infrastructure Programme Implementation Plan Projec Infr. Plan update IPMP IPIP 19 Projec Design Alignment of the Infrastructure Delivery Cycle & the Budget Cycle Year -2 Year -1 Year 0 Year 1 Year 2 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J The improved Infrastructure Delivery Cycle now facilitates the alignment of the Infrastructure Delivery Cycle with the Budget Cycle. MTEF Budget Cycle Budget Preparation Process Draft APP The budget preparation process can now be strengthened by actual projects identified during Infrastructure Planning. Implement Budget Closure Processes Currently Infrastructure Planning is undertaken too late to facilitate effective alignment of the Infrastructure Delivery Cycle with the Budget Cycle. Current Infrastructure Delivery Cycle Infrastructure Planning And the final budget submission is further informed by accurate cashflows prepared during the Project Design Phase. Project Design Project Tender Project Implementation Rolled O Unspent B And the project tendering & implementation feed into the implementation of the budget, quarterly reporting & budget closure processes. Improved Infrastructure Delivery Cycle Infrastructure Planning IPMP The Draft APP in turn becomes an input into the current year’s infrastructure planning & IPMP update. IPIP Project Design Infr. Plan update Project Tender IPMP IPIP Planned Comm Project Implementation Project Design Project Tender 20 Project Monitoring 3 Year MTEF Period Year 0 Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current year’s infrastructure delivery activities Planned Multi-year Commitments Monitoring & Evaluation Project Implementation Monitoring & Evaluation Project Design Project Tender Monitoring & Evaluation Infr. Plan update IPMP IPIP Budget Speech O&S Plan The Infrastructure Plan sets out the infrastructure priorities for the next 10 years. It is updated annually on the basis of the: • Targets and priorities set out in the Strategic Plan & Annual Performance Plan • The anticipated MTEF Budget, and • The progress of the current projects. 21 Infrastructure Programme Management Plan (IPMP) Year 0 3 Year MTEF Period Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Current year’s infrastructure delivery activities The IPMP sets out in detail the work for the next 3 years. It is based on the updated Infrastructure Plan as well as the Draft Annual Performance Plan (APP). Planned Multi-year Commitments In Year 1 Monitoring & Evaluation (Very detailed) Project Implementation Planned Multi-year Commitments In Year 2 Monitoring & Evaluation Monitoring & Evaluation (Less detailed) Project Design Project Tender Monitoring & Evaluation IPMP IPIP O&S Plan O&S O&S Budget Speech Infr. Plan update Project Implementation Planned Multi-year Commitments Monitoring & Evaluation Monitoring & Evaluation Project Design Project Tender Monitoring & Evaluation Infr. Plan update IPMP IPIP O&S Plan O&S O&S In Year 3 (even less detailed) Project Implementation Planned Multi-year Commitments Monitoring & Evaluation Monitoring & Evaluation Project Design Project Tender Monitoring & Evaluation Infr. Plan update IPMP IPIP O&S Plan O&S O&S Project Implementation Monitoring & Evaluation Project Design Project Tender Monitoring & Evaluation Infr. Plan update IPMP NB: The total value of the work in each year must O&Sequal Plan theO&S Annual Budget for each year IPIP 22 Infrastructure Budget Allocation Year 0 3 Year MTEF Period Year 1 Year 2 Year 3 Year 4 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J Project Implementation Budget = TOTAL INFRASTRUCTURE BUDGET – Planned Multi-year Commitments – Project Design & Tender (10%) – Infrastructure Planning (1%) Planned Multi-year Commitments – Funding of O&S Plan Project Implementation Project Design Project Tender IPMP IPIP O&S Plan O&S O&S Budget Speech Infr. Plan update Planned Multi-year Commitments Project Implementation Project Design Project Tender Infr. Plan update IPMP IPIP O&S Plan O&S O&S Planned Multi-year Commitments Project Implementation Project Design Project Tender Infr. Plan update IPMP IPIP O&S Plan O&S O&S Planned Multi-year Commitments Project Implementation Project Design Project Tender Infr. Plan update IPMP O&S Plan O&S IPIP 23 Managing Cashflows Across Years In reality the neat chunks of work shown Some projectsYear or clusters of projects Year 0 Year 1 2 on the earlier slides are actually individual in the D J projects F M or A clusters M J ofJ projects A S with O N D J F M A M Jcurrent J A year S O can N be D delayed J F M causing potential under expenditure different start & end dates plementation gn & Tender Planned Multi-year Commitments Project Implementation Planned Multi-year Commitments Project Design & Tender Project Implementation IPIP But here we have clusters of Infr. been Plan update projects that have designed and are ready to go to tender IPMP IPIP NB: The total value of the work in this year equals the Annual Budget for this year 24 Managing Cashflows Across Years Year 0 D J Year 1 F M A M J plementation gn & Tender J A S O N D J Year 2 F M A M J J A S O N D J F M Planned Multi-year Commitments Project Implementation Planned Multi-year Commitments Project Design & Tender Project Implementation IPIP We need to tender these projects earlier Infr. Plan update IPMP and start implementation in Year 1 to offset the potential under expenditure caused by the delayed projects IPIP 25 Identified Benefits NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA • Better linkage with Strategic Planning is achieved • Better alignment of the budget with the targets set out in the Strategic Plan • Project planning & design is properly done resulting in achievable & realistic cashflows • Multi-Year commitments are planned and budgeted for thereby reducing rollovers • Improved clarity of roles & responsibilities between client departments and implementing agents 26 Possible Challenges NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA • Programme Manager with required skills is required – Planning for built environment – Quality Control – Contract Procurement • Commitment by political heads to only implement what is on the Infrastructure Plan • Understanding that if a project is entered as a new priority onto an Infrastructure Plan in Year 0 it must follow due process before implementation can begin Year 0 Year 1 Year 2 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M Infr. Plan update IPMP IPIP Project Design Project Tender Project Implementation 27 Recommendations accepted & approved by Joint DoE/DPW MINMEC NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA 1. That the Infrastructure Delivery Cycle be amended to include the Infrastructure Programme Management Plan (IPMP), the Infrastructure Programme Implementation Plan (IPIP), and the Service Delivery Agreement (SDA), and that these plans be made mandatory for all departments. 2. That the timeframes of the Infrastructure Delivery Cycle be amended to allow for the alignment of the Infrastructure Delivery Cycle with the Budget Cycle so that departmental budgets are informed by actual projects. 3. That best practice budgeting processes be adopted so that budgets for large projects are appropriately committed across the duration of the project. 28 NATIONAL TREASURY REPUBLIC OF SOUTH AFRICA Thank You 29
© Copyright 2026 Paperzz