2-DAY NATIONAL WORKSHOP ON ESSENTIALS OF BUILDING AND ENGINEERING CONTRACT DOCUMENTATION AND ADMINISTRATION Date: 22nd – 23rd MARCH, 2017 VENUE: KOLA NUT EVENT CENTRE, BARRACK ROAD, CALABAR TOPIC: COMPARATIVE EVALUATION OF DIFFERENT FORRMS OF CONTRACT & DISCHARGE OF CONTRACTS By EKKANEM, SCHOLASTICA FIDELIS (MNIQS, RQS) Department of Quantity Surveying School of Environmental Studies, Akwa Ibom State Polytechnic, Ikot Osurua, Ikot Ekpene, Akwa Ibom State COMMON FEATURES IN ALL THE FORMS OF CONTRACT QUALITY CONTROL VARIATION TIME AND MONEY PRACTICAL COMPLETION AND SNAGING COST SCRUTINY THE PROGRAMME PROVISION SUMS PAYMENT MATURITY AND CASE PRECEDENCE ADMINISTRATIVE REQUIREMENT EXTENSION OF TIME/ LOSS AND EXPENSE TERMINOLOGY CLAUSES NATURE PRICING OPTIONS DISPUTE RESOLUTION RISK MANAGEMENT CONTRACT ADMINISTRATION COMPARISON EVALUATION – (FIDIC, NEC3 AND JCT 2011) JCT Contract NEC Project Manager FIDIC Engineer Administrator Quality Control Issues timely Acts as gatekeeper to contractor’s Issues instructions, modified drawings information relating to design and programme (conditions as necessary for the execution of the set out any other pre21.23), works and the remedying of any defects agreed information as Replies within the period for reply (clause 3.3) and when required to any communication submitted to it by the contractor May attend management meetings with Issues certificates to the employer the contractor and contractor JCT Contract NEC Project Manager FIDIC Engineer Administrator Variations Issues instruction to Issues instruction relating to Issues instructions to deal with overcome discrepancies changes in scope and instances of delay and and/or changes in scope completion date disruption, remedying of defects of works and instructing any variation. Issues notices in respect Actively monitors by means of Requests measurement of the of remedying any early warning mechanism works, if required (clause 2.1) discrepancies between for any change to scope in contract documents price, timings or impairment of Issues variations (clause 13.1) (clauses 2, 13-2.18) performance and payment certificates (clauses 14.6, 14.11 and 14.13) JCT Contract Administrator Time and Money Certifies sum due Issues extensions of time which it considers fair and reasonable and reaches a decision as soon as reasonably practical (clause 2,28.2) Considers with the QS, if employed, all interim valuations, claims for variations and loss/expense resulting and issue payment certificates as appropriate NEC Project Manager FIDIC Engineer Certifies sums due Certifies sums due Decides the date of completion and certifying completion (condition 30) Notifies the contractor of the outcome for any claim and requests quotations for any proposed instruction or changed decision Agrees to commencement date, and ensure the programme for the works is adhered to (clause 8.1), Considers compensation events, their value and instructing their implementation (conditions 6065) Approved variations for payment after scrutiny (clause 13.1). determine extension of time for the contractor (clause 8.4), JCT Contract Administrator NEC Project Manager FIDIC Engineer Practical completion and snagging Determines when practical completion Determines when practical achieved and issues notices of noncompletion achieved completion, defects and can allow early possession. Issues practical completion certificate Assesses defects and their or sectional completion certificates value (conditions 40-45) (clause 2.30-2.32) or a non-completion certificate (clause 2.31) Responsible for the ‘taking over’ process for completion of the works or sections of it. Assesses the time for, and issues a taking over certificate upon application from the contractor (clause 10.1) JCT Contract Administrator Cost Scrutiny In JCT contract there may be some cost scrutiny via the contract sum analysis and tender negotiations The Programme The JCT contract does not have a programme as a contractual document. Peripheral importance NEC Project Manager FIDIC Engineer NEC contract has an open book In FIDIC contract there may be some procedure with the key concepts of cost scrutiny via the contract sum defined cost and disallowed cost analysis and tender negotiations The programme is at the heart of the NEC ethos. It is a contractual document and to be regularly updated. Key to the function of contract mechanisms The FIDIC contract does not have a programme as a contractual document. Peripheral importance JCT Contract NEC Project Manager FIDIC Engineer Administrator Provisional Sums The JCT Contract NEC contract does not FIDIC Contract contains contains Provisional Provisional sums sums Payment In relation to payment, In relation to NEC In relation to FIDIC the JCT contract contract, it is located in 3 contract, contract price and payment section is clear, different location in payment is in one section is all in one section clause 5, Y(UK) and (clause 14). (clause 4) and easy to contract Data part 1 follow JCT Contract Administrator NEC Project Manager Maturity & Case Precedence FIDIC Engineer Very matured, over 80 years Over 20 years in use, Very matured, over 100 with many precedence cases limited cases precedence years with many in law in law precedence cases in law Administrative Requirement Minimum High, requires parties to Minimum document extensive amount of written communication JCT Contract Administrator Extension of Time/loss and expense • the JCT contract has relevant matters and time and money are dealt with as separate concepts (Clauses 2.29 and 4.24) NEC Project Manager FIDIC Engineer The NEC contract has the compensation event and it deals with both time and money. Driven: The compensation events also have a condition procedure nature, and failure to notify the compensation event within the 8 weeks period can have dire consequences FIDIC contract has relevant matters and time and money are dealt with as separate concepts. (Clauses 8.4 and 20.1) JCT Contract Administrator Terminology Legal Clauses Nature Adversarial NEC Project Manager FIDIC Engineer Simple wording Legal collaborative Adversarial Pricing Options Limited to traditional norms 6 options, can be used together Limited to traditional norms Dispute resolution Arbitration Adjudication Dispute adjudication boards High awareness of risk, requires parties to register risks officially Limited Risk Management Limited SUMMARY NEC has probably may advantage our FIDIC and JCT particularly in clarity, flexibility, explicit project management procedures, partnering and teamwork, risk management, objective measurements of weather and ground condition risks and variations. Key NEC drafty features centre on flexibility, clarity and simplicity; and a stimulus to good management; no such aims exist within FIDIC and JCT. DISCHARGE OF CONTRACTS A contract may be discharged by the following methods: Performance, Agreement, Breach Frustration PRFORMANCE • The normal method of discharge mean that the performance of his obligations by a contracting party discharges that party from his obligations under the contract. Modification of the General Rule under performance discharges (a) Divisible Contracts: A contract may be entire, where the agreement provides that complete performance by one party is a condition precedent to contractual liability on the part of the other party; or, partial, where the contract provides for performance by instalments, with separate payment for each of them. (b) Acceptance of Partial Performance Where the party to whom the promise of performance was made, B, accepts partial performance of the contract by A, he must pay A for the goods he has accepted or the benefit of which he has received. However, B must have voluntarily accepted A’s partial performance (example the case of Sumpter v Hedges [1898] 1 QB 673, where the owner of halfbuilt stables was held not to have had any choice but to finish the building work). (C)Completion of Performance Prevented by the Promisee Where full and complete performance of the contract is prevented through the other party’s actions, the party unable to complete performance may claim for partial or substantial performance. In a case of Planché v Colburn (1831) 8 Bing 14, an author succeeded in recovering half his commission on a book he had half completed, after the publisher prematurely terminated the contract. AGREEMENT Where a contract is formed by agreement, it may also be discharged or terminated through agreement, subject to the conditions of the contract. • The agreement to extinguish or terminate the contract itself becomes a binding contract if supported by consideration or made under seal. Contract by agreement can be discharges through the following ways: Bilateral Discharge The contract will be mutually discharged where the parties agree to release one another from any further obligations existing from the original contract. Also the contract is discharged despite the parties failing to fully or partially discharge all their obligations. Accord and Satisfaction Accord and satisfaction occurs where one party accords the release of another party, who is in breach of the original agreement, from its obligations in return for the satisfaction for the performance of another obligation. Unilateral Discharge Unilateral discharge occurs where one party has completed its part of the bargain and agrees to release the other party from its outstanding obligations under the contract. The agreement is only binding if supported by consideration or made under seal. DISCHARGE BY BREACH • Discharge By Breach: Any breach of contract entitles the injured party to claim damages. The degree of breach and the consequences vary according to the type and nature of the term concerned. There are two types of breach: actual and anticipatory. Actual Breach One party may breach one or more of the terms of the contract in such a way that it amounts to a breach of the contract. Anticipatory Breach An anticipatory breach occurs where a contracting party indicates by express words or by implication through conduct before performance that he will not honour his contractual obligations. FRUSTRATION • FRUSTRATION : A contract is said to be frustrated where the conditions of the contract can no longer be performed, due to a change in circumstances not provided for in the contract, which occurs after the contract was concluded, and which was beyond the fault of the parties to the contract. • EXAMPLE ARE: Destruction of the Specific Object Essential for Performance of the Contract. Personal Incapacity to Perform a Contract of Personal Service. The Non-occurrence of a Specified Event. Interruption which Prevents Performance of the Contract in the form Intended by the Parties. FORCE MAJEURE • FORCE MAJEURE:“Force majeure” is a concept that originated in French, not English, law, and is not a doctrine under common law. However, force majeure does have legal effect where provided for in English law-governed contracts (and no effect without the existence of such a clause in the contract). “Force majeure” literally translates as “superior forces” and refers to the arising of unforeseen conditions or events beyond the control of both parties, which unavoidably disrupts performance of the contract. • Force majeure clauses are used in contracts due to the limited application of the doctrine of frustration. CONCLUSION Discharge of contract depend on the forms of contract of your choice and the documentation format, therefore having known various forms of contract and methods of documentation it is therefore proper to choose the one that fit your contract for effective delivering. THANK YOU
© Copyright 2026 Paperzz