Squire Patton Boggs

The Construction (Design and
Management) Regulations 2015
Gary Lewis
20 October 2015
CDM 2015
 “The CDM Regs”
 2015 version came into force on 6 April 2015
squirepattonboggs.com
2
CDM 2015
Here we go again!
squirepattonboggs.com
3
CDM 2015
 A little bit of history:  CDM Regs
1994 (ACoP)
 CDM Regs
2007 (ACoP)
 CDM Regs
2015 (Guidance L153)
squirepattonboggs.com
4
CDM 2015
 Key principles:  PLANNING AND EXECUTION OF CONSTRUCTION PROJECT
• Design
• Co-operation
• Co-ordination
squirepattonboggs.com
5
CDM 2015
 The primary objective in summary:  “The right information for the right people at the right time”
 Sequential appointments are a clear attempt to rationalise this objective in practice
squirepattonboggs.com
6
CDM 2015
 Design aspect
 Evolution of role holders: • Planning Supervisor (CDM 1994)
• CDM Co-ordinator (CDM 2007)
• Principal Designer (CDM 2015)
squirepattonboggs.com
7
CDM 2015
 The key principles and objectives have remained constant
squirepattonboggs.com
8
CDM 2015
 What has changed?
 It was always envisaged that that client should have a pivotal role in terms of the
management of a project.
 This has not always come to pass not least because the regulations allowed the
client to delegate responsibility to other role holders.
 Why is the client important? “The client has a major influence over the way that a
project is procured and managed. Regardless of the size of the project, the client
has contractual control, appoints designers and contractors, and determines the
money, time and other resources available”.
 “CDM 2015 makes the client accountable for the impact their decisions and
approach have on the health, safety and welfare of the project”.
squirepattonboggs.com
9
CDM 2015
The client
 “Any person for whom a project is carried out”
 If more than one client – one or more of the clients may agree in writing to be
treated as the only client or clients.
 N.B. – Cannot delegate duty to co-operate or provide pre-construction
information
squirepattonboggs.com
10
CDM 2015
The client
 Must make sure suitable arrangements for managing the project, including
allocation of sufficient time and resource
 Must ensure arrangements are maintained and reviewed
 Must provide pre-construction information as soon as practicable to every
designer and contractor
 Where project is notifiable, the client must give notice in writing to the HSE
squirepattonboggs.com
11
CDM 2015
The client
 Must appoint in writing (where more than one contractor on project)
 A DESIGNER with control over pre-construction phase as PRINCIPAL DESIGNER
 A CONTRACTOR as PRINCIPAL CONTRACTOR
Before the construction phase begins
 N.B. – if the client does not appoint a PRINCIPAL DESIGNER and/or a
PRINCIPAL CONTRACTOR, the client is deemed to be fulfilling the duties
squirepattonboggs.com
12
CDM 2015
The client
 Must take reasonable steps to ensure that the PRINCIPAL DESIGNER
(Regs 11 & 12) and PRINCIPAL CONTRACTOR (Regs 12-14) comply with
their duties
 Must ensure that the PRINCIPAL CONTRACTOR has drawn up the
construction phase plan before the construction phase begins and keeps it
under review
 Must ensure that the PRINCIPAL DESIGNER prepares the health and safety
file for the project and keeps it under review
squirepattonboggs.com
13
CDM 2015
Notification
 Project is notifiable if the construction work is scheduled to: a) Last longer than 30 working days and have more than 20 workers working
simultaneously at any point in the project, or
b) Exceed 500 man days
 N.B. Notification does not give rise to additional duties as before.
squirepattonboggs.com
14
CDM 2015
Competence
 Moved away from the prescriptive formula for assessing competence
[designers and contractors]
to generic
 Skills, knowledge and experience
squirepattonboggs.com
15
CDM 2015
 The Principal Designer
 Must plan, manage, monitor and co-ordinate matters relating to health and safety
during the pre-construction phase, IN PARTICULAR in relation to design, technical
and organisational aspects
 Must take into account the general principles of prevention
 Must prepare the safety file and keep it under review
squirepattonboggs.com
16
CDM 2015
 The Principal Designer
 Must assist the client in the provision of pre-construction information
 Must provide pre-construction information within his control
 Must provide the Principal Contractor with all information relevant to the construction
phase plan
 Must liaise with the Principal Contractor during the construction phase
squirepattonboggs.com
17
CDM 2015
 The Principal Contractor
 Must draw up construction phase plan
 Must ensure that the construction phase plan is reviewed, updated and revised
 Must ensure co-operation and co-ordination as between contractors
 Monitor the construction activity
squirepattonboggs.com
18
CDM 2015
Overview
 More of the same:  Client is pivotal to management control of the project
 The design phase is important
 Sequential appointments should facilitate the timing of information
 Competence? One step forward, two steps back?
 Right information/ right people/ right time
squirepattonboggs.com
19
CDM 2015
Questions?
squirepattonboggs.com
20
Contact
Gary Lewis
Squire Patton Boggs (UK) LLP
Tel: 0161 830 5373
Mob: 07825 204 407
Email: [email protected]
squirepattonboggs.com
21
Global Coverage
Abu Dhabi
Manchester
Africa
Israel
Office locations
Beijing
Miami
Argentina
Mexico
Regional desks and strategic alliances
Berlin
Moscow
Brazil
Panamá
Birmingham
New York
Chile
Peru
Bratislava
Northern Virginia
Colombia
Turkey
Brussels
Palo Alto
Cuba
Venezuela
Budapest
Paris
India
Cincinnati
Perth
Cleveland
Phoenix
Columbus
Prague
Dallas
Riyadh
Denver
San Francisco
Doha
Santo Domingo
Dubai
Seoul
Frankfurt
Shanghai
Hong Kong
Singapore
Houston
Sydney
Kyiv
Tampa
Leeds
Tokyo
London
Warsaw
Los Angeles
Washington DC
Madrid
West Palm Beach
squirepattonboggs.com
22