Strategic Alliance Agreement Framework PSP Early Conditional Appointment Volume 3 September 2013 Version 1.0 Document Structure Early Conditional Appointment Schedule 1 - ECA Details Schedule 2 - Pre-Construction Phase Services Schedule 3 - Partnering Timetable Schedule 4 - Risk Register Schedule 5 - Site Information Schedule 6 - Works Information Schedule 7 - Activity Schedule Schedule 8 - Form of Pre-Construction Agreement (NEC) Schedule 9 - Form of Commencement Agreement Schedule 10 - NEC Conditions Schedule 11 - Shared Savings Scheme The structure of the document set is as above. This document sets out the early conditional clauses which would be applicable to the NEC model form contract to deliver Construction Works and Services for either the National or Regional requirements. Scope This section details the draft terms and conditions applicable to the Pre-Commencement Phase Services. It should be read with the Requirements for other aspects of the Product and Service and particularly the NEC contract documents and Strategic Alliance within Volume 3. The structure of the tender documents is as indicated below. This is “The Strategic Alliancing Agreement” Volume 3 An outline of the Ministry of Justice its aims objectives and the challenges that face it and the role of its Estate Directorate. Describes the procurement strategy, its structure, objectives and implementation. Gives the basis for pricing tenders including the approach to profit, overheads and risk. Volume 5: Volume 1: Pricing document Introduction to the Ministry of Justice Volume 4: The RFP documents Model Project Brief Together these documents describe the Model Projects that form the basis for the tender and give the information upon which Proposals shall be based Volume 3: Strategic Alliancing Agreement Volume 2: Constructor Request for Proposals Provides the instructions for Bidding including restrictions, conditions and a statement of the Information to be returned Detailed content of the Strategic Alliancing Agreement PPC 2000 NEC 3 Model Form contract Special Terms Z Clauses Project Partnering Agreement Early Contractor Involvement Joining Agreement Joint Supply chain Provides a model copy of the agreement that will underpin the contractual basis of the procurement strategy. The Client retains the option for PPC2000 or NEC3 model terms. Amendments to both are included. The PPC 2000 two stage approach to building up to an Agreed Maximum Price is replicated in an Early Contractor Involvement for NEC3. Documents sitting outside the main constructors agreement. Joining agreement provides the terms under which other clients utilise the Strategic Alliance Agreement. Joint Supply Chain documentation provides terms should a joint supply chain be implemented. dated [ ] [Ministry of Justice] and [ ● Contractor ] [Based on the NEC3 Engineering and Construction Contract June 2005 Option A: Priced contract with activity schedule, subject to amendment as required if the Ministry of Justice or relevant Additional Client elects to use Option C: Target contract with activity schedule] Early Conditional Appointment for [ ● ] in relation to a Strategic Alliance Agreement concluded by the Ministry of Justice Early Conditional Appointment (ECA) An Early Conditional Appointment is made (as a deed) the [ ] day of [ IN RELATION TO [ ] (the Site) ] (the Works) at [ ] BETWEEN (1) Ministry of Justice of [ (2) [ ] (the Employer); and ] (registration number [ ]) whose registered office is at [ ] (the Contractor) WHO AGREE Working in mutual cooperation to fulfil their agreed roles and responsibilities and applied their agreed expertise in relation to the Works in accordance with and subject to the terms of this Early Conditional Appointment (ECA) and the other Contract Documents described in or created pursuant to this ECA and that subject to amendment in accordance with this ECA: 1 Definitions and interpretation 1.1 In this ECA defined words and expressions in the NEC Conditions shall have the same meanings unless otherwise stated in this clause 1 and the following words and expressions shall have the following meanings: Activity Schedule – the Activity Schedule set out in Schedule 7 subject to development in accordance with this ECA; Best Value – [ ]; Budget - the maximum Prices in relation to the Works forming the basis for the selection of the Contractor and the conclusion of this ECA and also known as the IPP; Business Case - a business case proposed by the Contractor pursuant to clause 7.2 of this ECA comprising prices and proposals seeking to justify Employer approval of a Direct Labour Package or a Preferred Specialist without market testing; Commencement Agreement – an agreement governing commencement of the Works on Site, signed pursuant to clause 11 and based on the form set out in Schedule 9; Consultation – such consultation as shall be reasonable without delaying the PreConstruction Services and without delaying any necessary action of any of the Employer, the Project Manager or Contractor for the benefit of the Works; Contract Documents – the Contract Documents forming part of this ECA and set out in the schedules to this ECA as amended and developed pursuant to this ECA; Error! Unknown document property name. 1Error! Unknown document property name..Error! Unknown document property Core Group – the individuals identified in this ECA as Core Group members, subject only in each case to replacement in accordance with the NEC Conditions, and so that references shall apply to each and all Core Group members; Defined Cost – the components of Defined Cost as set out in the Shorter Schedule of Cost Components forming part of the NEC Conditions; Direct Labour Package – any part of the Works undertaken by the Contractor using its own direct labour; ECA – this Early Conditional Appointment; Environment – all and any land, water and air including air within any natural or manmade structure above or below ground; Fee – the fee as stated in Schedule 1 payable to the Contractor in the event that the Works proceed in accordance with the Commencement Agreement ; NEC Conditions – the Core Clauses, W Clauses, X Clauses, Y Clauses, Z Clauses and Shorter Schedule of Cost Components forming part of the NEC3 Engineering and Construction Contract of June 2005, Option A Priced Contract with Activity Schedule amended as set out in Schedule 10; Open-book – involving the declaration of all price components including the Fee and Defined Cost and the costs of materials, goods, equipment, works and services, with all and any relevant books of account, correspondence, agreements, orders, invoices, receipts and other relevant documents available for inspection; Operation – use, occupation, operation, maintenance, repair, alteration and demolition; Partnering Adviser – any partnering adviser named in Schedule 1 subject only to replacement in accordance with the NEC Conditions; Partnering Timetable – the Partnering Timetable as set out in Schedule 4; Pre-Commencement Phase – all activities in relation to the Works up to and including the date of the Commencement Agreement; Pre-Commencement Phase Fee – the Pre-Commencement Phase Fee as stated in Schedule 1 payable to the Contractor for performance of the Pre-Commencement Phase Services ; Pre-Commencement Phase Services - the services required to be performed by the Contractor under this ECA as set out below in Schedule 2. Pre-Construction Activities – any activities, other than Pre-Commencement Phase Services, forming part of the Works and undertaken by the Contractor on or off Site prior to the date of the Commencement Agreement; Pre-Construction Agreement – any agreement governing Pre-Construction Activities signed pursuant to clause 9.6 of this ECA and based on the form set out in Schedule 8; Preferred Specialist – a Specialist proposed by the Contractor in a Business Case; Error! Unknown document property name. 2Error! Unknown document property name..Error! Unknown document property Prices – as defined and stated in the developed Activity Schedule forming part of the Commencement Agreement; Project Manager – the Project Manager identified in Schedule 1 subject to replacement in accordance with the NEC Conditions; Risk Management - a structured approach to ensure that risks are identified at the inception of the Works, that their potential impacts are allowed for and that where possible such risks or their impacts are minimised; Risk Register – the Risk Register set out in Schedule 4. Shared Savings Scheme – the Shared Savings Scheme set out in Schedule 11; Site – the Site as described in the Site Information; Site Information – the Site Information set out in Schedule 5 as developed in accordance with this ECA; Specialist – any party providing to the Contractor works or services or supplies of goods, materials or equipment forming part of the Works; Sustainability - measures intended to achieve reduced carbon emissions, reduced use of energy and of natural and manmade resources, improved waste management, improved employment and training opportunities, and any other measures intended to protect or improve the condition of the Environment or the wellbeing of people; Value Engineering - a structured system for the review of the design, supply and construction process to identify options and scope for improvement, including reduced capital and/or whole life costs, improved buildability and improved functionality; Value Management – a flexible but structured management approach aimed at achieving a solution that meets the Employer's needs while achieving best value; Working Day – Monday to Friday inclusive but not including any public holiday; Works – the Works as described in the Works Information; Works Information - the Works Information set out in Schedule 6 subject to development in accordance with this ECA; 2 Pre-Commencement Phase Services and Core Group 2.1 The Contractor shall carry out the Pre-Commencement Phase Services subject to and in accordance with this ECA and the NEC Conditions. 2.2 The Core Group, whose members are identified in Schedule 1, shall fulfil the functions stated in this ECA in accordance with the governance arrangements stated in the NEC Conditions. Error! Unknown document property name. 3Error! Unknown document property name..Error! Unknown document property 3 Project Manager and Partnering Adviser 3.1 The Project Manager shall fulfil its functions as described in this ECA and the other Contract Documents exercising any discretion fairly and constructively and shall facilitate and integrate the processes described in this ECA in accordance with the Contract Documents and with the support of the Employer and the Contractor as stated in the Contract Documents. 3.2 The Project Manager shall organise and monitor the contributions of the Employer and Contractor to Value Engineering, Value Management and Risk Management exercises in relation to the Works (to which the Employer and Contractor shall contribute if so requested), as stated in this ECA and as otherwise agreed by the Core Group, and the Contractor shall submit to the Employer and the Core Group proposals for approval based on the results of these exercises and in the best interests of the Works. 3.3 In all matters relating to the operation of this ECA the Employer, the Contractor and the Project Manager may together or individually utilise the advice and support of the Partnering Adviser subject to prior agreement of costs and the Partnering Adviser's duty of care including: 3.3.1 Team-building, review of the developed Contract Documents and review of Specialist Contracts for consistency with the Contract Documents; 3.3.2 Preparation Agreement; 3.3.3 Provision of fair and constructive advice as to processes, the development of relationships and the operation of the Contract; 3.3.4 Attendance at such meetings of the Core Group as its members consider appropriate; 3.3.5 Assistance in the solving of problems and the avoidance or resolution of disputes in accordance with the NEC Conditions. of any Pre-Construction Agreement and Commencement 4 Partnering Timetable and Accepted Programme/Key Dates 4.1 Subject to alteration in accordance with this ECA, the Contractor shall adhere to the dates set out in the Partnering Timetable in the performance of the Pre-Commencement Phase Services, and the Employer, the Project Manager and the Contractor shall undertake their other agreed activities in relation to the Works during the period prior to the date of the Commencement Agreement regularly and diligently in accordance with the Partnering Timetable. 4.2 The proposed programme, comprising the starting date(s), access date(s), Date(s) for Completion, Key Dates and other detailed arrangements as to timing for implementation of the Works with effect from the date of the Commencement Agreement, shall be submitted to the Project Manager by the Contractor with supporting method statements and procedures by the date or dates stated in the Partnering Timetable, shall be reviewed by the Core Group and shall be subject to approval by the Employer to create the Accepted Programme and Key Dates. Error! Unknown document property name. 4Error! Unknown document property name..Error! Unknown document property 5 NEC Conditions 5.1 The NEC Conditions shall apply to this ECA, but in the event of any conflict or discrepancy between the NEC Conditions and this ECA, then this ECA shall take precedence. 6 Design Development 6.1 Best Value The Contractor shall develop the designs of the Works, in accordance with this clause 6, with the objective of achieving Best Value for the Employer. 6.2 Design liability The Contractor shall be solely responsible for the design of the Works and shall undertake the development of an integrated design, supply and construction process for the Works in accordance with this ECA. 6.3 Design process Based on the drawings and specifications set out in the Works Information, the designs for the Works shall be developed as follows within the periods stated in the Partnering Timetable: 6.3.1 the Contractor shall prepare and submit to the Employer and the Core Group outline designs for the Works including such alternative solutions for the integrated design, supply and construction of the Works and any part of it as are required by the Works Information or as are otherwise appropriate; 6.3.2 the Contractor shall present for Core Group consideration and Employer approval the designs prepared in accordance with clause 6.3.1 and comparisons between any alternative solutions by reference to the Works Information; 6.3.3 following Employer approval, after Core Group Consultation, of outline designs and choice of any alternative solution or solutions pursuant to clause 6.3.1, the Contractor shall develop designs for the Works based on such outline designs and solution or solutions and shall submit these to the Employer and the Core Group, developed to the level of detail stated in the Partnering Timetable and sufficient to comprise the basis for an application for full planning permission for the Works; 6.3.4 the Contractor shall obtain the maximum input to design development under clauses 6.3.1 to 6.3.3 from Specialists as is required by the Works Information or as is otherwise appropriate during the course of or after their selection in accordance with clause 7 of this ECA; 6.3.5 following Employer approval, after Core Group Consultation, of designs developed pursuant to clause 6.3.3, the Contractor shall submit in the name of the Employer an application for full planning permission for the Works and shall further develop and submit to the Employer and Core Group designs for the Works, in the sequence and to the level of detail stated in the Partnering Error! Unknown document property name. 5Error! Unknown document property name..Error! Unknown document property Timetable, for Employer approval after Core Group Consultation and for the selection of Specialists, the development of the Prices and Activity Schedule and the satisfaction of any planning conditions and other pre-commencement regulatory approvals. 6.4 Site surveys and investigations The Contractor shall commission or undertake, and shall coordinate and monitor, any Site surveys and investigations stated in Schedule 1 and the Partnering Timetable. The Contractor shall review the results of such surveys and investigations and advise the Employer and the Core Group as to their effect on the integrated design, supply and construction of the Works, and shall amend designs as required as a consequence, for Employer approval after Core Group Consultation. 6.5 Regulatory approvals The Contractor shall apply for and diligently pursue, in accordance with the Partnering Timetable, all regulatory approvals stated in Schedule 1 and otherwise required for commencement of the Works on Site, and shall report to the Employer and the Core Group on progress and results with recommendations to overcome any problems. 6.6 Budget At each stage of design development the Contractor shall take into account the Budget and shall provide, with all design submissions, updated cost estimates reconciled with such Budget. 6.7 Value Engineering At each stage of design development the Contractor shall amend designs as necessary to adopt the results of Value Engineering exercises undertaken in accordance with clause 3.2, where such results are approved by the Employer after Core Group Consultation. 6.8 CDM Coordinator At each state of design development the Contractor shall provide to the CDM Co-ordinator copies of all designs submitted pursuant to this clause 6, together with related information in accordance with Regulation 11(6) of the CDM Regulations and the CDM Co-ordinator shall provide within five (5) Working Days from the date of provision of such copies (or within any other period stated in the Partnering Timetable) advice to the Employer and Project Manager as to the health and safety implications of such designs and related information. 6.9 CDM compliance The Employer and the Contractor shall fulfil their respective responsibilities under the CDM Regulations, including without limitation the preparation, collation and circulation of the Pre-Construction Information by the Employer or the CDM Co-ordinator as appropriate and the preparation of the Construction Phase Plan by the Contractor in compliance with the CDM Regulations as preconditions to implementation of the Works on Site. Error! Unknown document property name. 6Error! Unknown document property name..Error! Unknown document property 6.10 Design approvals No approval or comment by the Employer or the Project Manager in respect of any design submitted in relation to the Works shall in any way relieve or affect the responsibility for that design of the Contractor. 6.11 Designs and Works Information All designs approved by the Employer in accordance with this clause 6 shall become Works Information, and any subsequent proposed change to any such approved design shall be subject to change only in accordance with the NEC Conditions. 7 Specialists 7.1 Specialist relationships The Employer and the Contractor shall implement the procedures in this clause 7 in accordance with the Partnering Timetable in order to establish Specialist relationships in relation to all aspects of the Works that: 7.2 7.1.1 are Open-book to the maximum achievable extent; 7.1.2 clearly reflect the agreed requirements of the Employer, the interests of the Employer and the Contractor, and the needs of the Works; 7.1.3 secure the best available Specialist warranties and support and maximise the potential for Specialist innovation and other contributions to the Works; 7.1.4 establish and demonstrate Best Value to the Employer; 7.1.5 establish, wherever possible, relationships complementary to those described in this ECA and the NEC Conditions. Business Cases The Contractor shall submit to the Employer its Business Case for each and any part of the Works that it wishes to undertake either as a Direct Labour Package or through the appointment of any Preferred Specialist, and such Business Case shall be developed and presented on an Open-book basis by reference to the Works Information including relevant designs approved under clause 6 of this ECA. 7.3 Best Value The Employer and the Core Group shall be entitled to analyse each Business Case submitted pursuant to clause 7.2 of this ECA and to request reasonable further information from the Contractor, and in each Business Case it shall be the Contractor's responsibility to demonstrate Best Value to the Employer. 7.4 Market testing If the Employer, after Core Group Consultation, is not satisfied with any aspect of a Business Case submitted pursuant to clause 7.2 of this ECA, then it may reject that Business Case, and the Contractor shall test that Business Case against the prices and Error! Unknown document property name. 7Error! Unknown document property name..Error! Unknown document property proposals of comparable prospective Specialists on an Open-book basis in accordance with clauses 7.5 and 7.6 of this ECA. 7.5 Specialist tenders With the exception of each Direct Labour Package and Preferred Specialist in respect of which a Business Case submitted pursuant to clause 7.2 of this ECA is approved by the Employer, the Contractor shall invite tenders from prospective Specialists approved by the Employer and the Contractor, and shall select those Specialists who are approved by the Employer after Core Group Consultation on the basis of prices and other proposals which offer Best Value to the Employer in a manner consistent with this ECA and of benefit to the Works. 7.6 Selection documentation In the course of the development of the Business Case for a Direct Labour Package or a Preferred Specialist and in the course of tendering to other prospective Specialists, all documentation prepared and issued by or for the Contractor, all tender returns and proposals submitted by prospective Specialists and all related correspondence with prospective Specialists shall be copied by the Contractor to the Project Manager upon their issue or receipt by the Contractor. The Employer and the Contractor shall treat all such documentation as confidential. The Project Manager shall be invited and entitled to attend all interviews and other meetings organised by the Contractor with prospective Specialists. 7.7 Maximum Specialist contributions All documents relating to the selection of Specialists shall encourage their maximum contribution to and participation in an integrated design, supply and construction process for the Works. All designs prepared by Specialists and approved in accordance with clause 6 shall form part of the Works Information. 7.8 Specialist Contracts Each proposed form of Specialist Contract shall be prepared by the Contractor and approved by the Employer prior to its issue to any Specialist and shall not conflict with this ECA or the NEC Conditions. 7.9 Responsibility for Specialists The Contractor shall be responsible for all aspects of the performance by each Specialist of its responsibilities in relation to the Works and no approval or other involvement by the Employer or the Project Manager in the selection of any Specialist shall in any way affect that responsibility. 7.10 Termination of Specialist Contracts The Contractor shall not terminate any Specialist Contract without prior Consultation with the Employer. If any Specialist Contract is so terminated, the Contractor shall replace that Specialist with any alternative Specialist of comparable expertise subject to compliance with this clause 7 and subject to approval by the Employer after Core Group Consultation. Error! Unknown document property name. 8Error! Unknown document property name..Error! Unknown document property 7.11 Instructions to Specialists Only the Contractor shall have authority to issue instructions to any Specialist. 8 Prices 8.1 In respect of the Pre-Commencement Phase Services performed during the period prior to the date of the Commencement Agreement, the Employer shall pay the Contractor the Pre-Commencement Phase Fee set out in Schedule 1 in accordance with the payment provisions set out in the NEC Conditions. 8.2 In respect of Pre-Construction Activities under any Pre-Construction Agreement entered into pursuant to clause 9.3, the Employer shall pay the Contractor those amounts stated in such Pre-Construction Agreement . 8.3 Prices for all aspects of the Works shall be developed and agreed in accordance with this clause 8 by reference to the Budget and the information supporting the Budget, by reference to the Activity Schedule and the other Contract Documents, to establish Prices within the Budget and otherwise as low as is achievable consistent with Best Value and in compliance with the Contract Documents. 8.4 The Fee shall be fixed at the agreed amount set out in the Schedule 1 subject only to such variations as the Employer and the Contractor may agree. 8.5 Those Prices attributable to each of the Contractor's proposed Direct Labour Packages and Preferred Specialists shall be developed by the Contractor, in conjunction with each relevant Preferred Specialist, and shall form part of each Business Case submitted pursuant to clause 7.2. 8.6 If the Employer approves the Prices proposed by the Contractor as part of the Business Case for any proposed Direct Labour Package or Preferred Specialist, then those Prices shall be incorporated in the Activity Schedule. 8.7 Where a Specialist is selected by tender in accordance with clause 7.5, then the Prices of the selected Specialist shall be incorporated in the Activity Schedule. 8.8 No discounts or other benefits shall be payable by any Specialist to the Contractor for prompt payment or otherwise unless agreed pursuant to this clause 8.8 or clause 9.2 of this ECA. 8.9 All and any proposed risk contingencies shall be notified by the Contractor to the Employer, but shall only be incorporated in the Activity Schedule and form part of the Prices if and to the extent that any such risk contingency has been approved by the Employer after the Contractor has first reviewed each relevant risk in accordance with clause 12 and has submitted proposals for Core Group review and Employer approval as to how the relevant risk should or could be eliminated, reduced, insured, shared or apportioned and as to the extent to which the risk contingency can be removed or reduced and subject to such Employer approval have taken appropriate actions including those stated in the Risk Register. Error! Unknown document property name. 9Error! Unknown document property name..Error! Unknown document property 8.10 The Core Group shall investigate the potential for cost savings against the Budget and Prices and for added value in the design, supply, construction and Operation of the Works, and shall make recommendations for approval by the Employer, 9 Incentives and Pre-Construction Activities 9.1 The Employer, the Project Manager and the Contractor shall operate the Shared Savings Scheme set out in Schedule 11. 9.2 The Contractor shall notify the Employer of any payment or benefit offered or received by it in relation to the Works other than pursuant to the Contract and any such payment or benefit shall be subject to the Employer's prior approval. 9.3 The Employer and the Contractor may agree that the Contractor shall undertake and be paid for Pre-Construction Activities forming part of the Works in accordance with the terms of a Pre-Construction Agreement based on the form set out in Schedule 8 which the Project Manager shall [arrange for the Partnering Adviser to] prepare and which shall be signed by the Employer and the Contractor. 9.4 In relation to all Pre-Construction Activities (except only as stated in the Pre-Construction Agreement): 9.4.1 Intellectual Property Rights, insurance obligations, risk, responsibility and ownership shall be governed by the NEC Conditions; 9.4.2 Timing shall be governed by the Partnering Timetable; 9.4.3 The only payment shall be the amount or amounts stated in the PreConstruction Agreement payable under the payment provisions set out in the NEC Conditions; 9.4.4 Problem-solving and avoidance or resolution of disputes shall be governed by the NEC Conditions; 9.4.5 The Pre-Construction Agreement shall not create any other obligations on any party; 9.4.6 All Pre-Construction Activities shall form part of the Works; 9.4.7 The Contractor shall cease all Pre-Construction Activities and vacate the Site if and so requested by the Project Manager. 10 Pre-Conditions to Start on Site 10.1 Implementation of the Works on Site shall commence subject to satisfaction of the following pre-conditions, either completely or to such lesser extent as is agreed by the Employer, the Project Manager and the Contractor: 10.1.1 agreement of the Accepted Programme and Key Dates in accordance with clause 4.2 of this ECA; 10.1.2 completion and distribution of the Pre-Construction Information and the Construction Phase Plan in accordance with clause 6.9 of this ECA and Error! Unknown document property name. 10Error! Unknown document property name..Error! Unknown document propert confirmation that the Employer is satisfied that the requirements of Regulation 22(1)(c) of the CDM Regulations have been met; 10.1.3 completion of pre-commencement Site accordance with clause 6.4 of this ECA; surveys and investigations in 10.1.4 grant of planning permission satisfactory to the Employer and of other precommencement regulatory approvals in accordance with clause 6.5 of this ECA; 10.1.5 development on an integrated design, supply and construction process in accordance with clause 6 of this ECA; 10.1.6 selection and full involvement of Specialists in accordance with clause 7 of this ECA; 10.1.7 finalisation of the Price(s) supported by the Activity Schedule in accordance with clause 8 of this ECA; 10.1.8 evidence of all insurances required in accordance with the NEC Conditions; 10.1.9 satisfactory progress against KPIs and Targets in accordance with the NEC Conditions; 10.1.10 completion by the Employer of any required Site acquisition or funding and satisfaction of any other pre-conditions stated in the Works Information; 10.1.11 signature by the Employer and the Contractor of the Commencement Agreement; 10.1.12 agreement to all remaining Works details for inclusion in the Contract Data – Part 1, Contract Data – Part 2, Site Information, Works Information and Activity Schedule forming part of the Commencement Agreement. 10.2 The Employer and the Contractor shall use reasonable skill and care appropriate to their agreed roles, expertise and responsibilities as stated in this ECA to pursue diligently and satisfy the pre-conditions described in clause 10.1 of this ECA, and shall notify each other as soon as they are aware that such pre-conditions have been satisfied. 11 Works on Site As soon as the pre-conditions described in clause 10 have been satisfied, the Project Manager shall [arrange for the Partnering Adviser to] prepare a Commencement Agreement, based on the form set out in Schedule 9, completed as to all agreed Works details and developed Contract Documents listed in the Commencement Agreement, and shall provide copies to the Employer and the Contractor allowing not less than ten (10) Working Days for their comments. Subject to its amendment after Consultation to reflect such comments as are necessary for compliance with this ECA and the NEC Conditions, the Employer and the Contractor shall sign the Commencement Agreement. Error! Unknown document property name. 11Error! Unknown document property name..Error! Unknown document propert 12 Risk Management 12.1 The Employer and the Contractor recognise the risks involved in the design, supply and construction of the Works, and the costs associated with those risks. The Employer and the Contractor shall work together and individually, through Risk Management exercises in accordance with this ECA, including through the actions described in the Risk Register within the periods and/or deadlines stated in such Risk Register and in the Partnering Timetable, to analyse and manage risks in the most effective ways including: 13 12.1.1 identifying risks and their likely costs; 12.1.2 eliminating or reducing risks and their costs; 12.1.3 insuring risks wherever affordable and appropriate; 12.1.4 sharing or apportioning risks according to which one or more of the Employer and the Contractor are most able to manage such risks. Termination The Employer may terminate the appointment of the Contractor if, due to non-achievement of any of the pre-conditions set out in clause 10 of this ECA or for any other reason not reasonably foreseeable by the Employer arising at any time prior to the date of the Commencement Agreement, it no longer wishes to proceed with the Works. In such circumstances the Employer shall give the Contractor not less than twenty (20) Working Days prior notice terminating its appointment under this ECA, within which period the Contractor shall cease all activities under this ECA in an orderly manner. Upon expiry of that period the Project Manager shall issue a valuation to the Contractor pursuant to the payment provisions set out in the NEC Conditions. The Employer shall pay in accordance with the NEC Conditions the amounts stated in such valuation and notices, but shall not be liable to pay any other amount. No notice may be given under this clause 13 after the date of the Commencement Agreement. Error! Unknown document property name. 12Error! Unknown document property name..Error! Unknown document propert Schedule 1 ECA Details Core Group members (clause 2.2) For the Employer:[ ] For the Contractor: [ ] For the Project Manager: [ ] For the Supervisor: [ ] For the Cost Consultant: [ ] For the CDM Co-ordinator: [ [For the Technical Assessor: [ ] acting by [ ] ] acting by [ ] Partnering Adviser (clause 3.3) The Partnering Advisor is [ ]] Project Manager (clause 3.1) The Project Manager is [ ] Required surveys and investigations (clause 6.4) [As set out in the relevant Mini-invitation or (in the context of direct award) specified by the Ministry of Justice] Pre-Commencement Phase Fees (clause 8.1) [As set out in the relevant Mini-invitation or (in the context of direct award) specified by the Ministry of Justice] Fee (clause 8.4) [As set out in the relevant Mini-invitation or (in the context of direct award) specified by the Ministry of Justice] [direct fee percentage] [subcontracted fee percentage] Error! Unknown document property name. 13Error! Unknown document property name..Error! Unknown document propert Schedule 2 Pre-Construction Phase Services (clause 2.1) Error! Unknown document property name. 14Error! Unknown document property name..Error! Unknown document propert Schedule 3 Partnering Timetable (clause 4.1) Description of Activity/Requirement Clause of ECA Error! Unknown document property name. name. Party Responsible for Activity Period/Deadline for Activity Additional Comments 15Error! Unknown document property name..Error! Unknown document property name..Error! Unknown document property Schedule 4 Risk Register (clause 12.1) Risk Likelihood of Risk Error! Unknown document property name. name. Impact of Risk on Project Party responsible for Risk Management Risk Management Action Action Period/Deadline 16Error! Unknown document property name..Error! Unknown document property name..Error! Unknown document property Schedule 5 Site Information Error! Unknown document property name. 22Error! Unknown document property name..Error! Unknown document propert Schedule 6 Works Information Error! Unknown document property name. 23Error! Unknown document property name..Error! Unknown document propert Schedule 7 Activity Schedule [Breakdown and components of Budget/IPP by reference to Defined Cost] Error! Unknown document property name. 24Error! Unknown document property name..Error! Unknown document propert Schedule 8 Form of Pre-Construction Agreement (NEC) The Employer and the Contractor in accordance with and subject to the terms of an Early Conditional Appointment dated [ ] (the "ECA") entered into between them in relation to: Project: [ ] Site: [ ] Agree under this Pre-Construction Agreement that: 1 Words and expressions used in this Pre-Construction Agreement shall have the same meanings as in the ECA. 2 The Contractor shall undertake the following Pre-Construction Activities: 3 The dates for completion of such Pre-Construction Activities are: 4 The Employer shall pay the Contractor the following amounts for such Pre-Construction Activities: 5 [Other terms as required] Signed for and on behalf of [ by [ ] (the Employer) ……………………………………………. Dated Signed for and on behalf of [ by [ …………………………………………… ] ] (the Contractor) ……………………………………………. ] Dated Error! Unknown document property name. ……………………………………………. 25Error! Unknown document property name..Error! Unknown document propert Schedule 9 Form of Commencement Agreement The Employer and the Contractor in accordance with and subject to the terms of an Early Conditional Appointment dated [ ] (the "ECA") entered into between them in relation to: Project: [ ] Site: [ ] Agree under this Commencement Agreement that: 1 Words and expressions used in this Commencement Agreement shall have the same meanings as in the ECA. 2 To the best of their knowledge the Works are ready to commence on Site. 3 The parties to the Commencement Agreement shall be bound by the terms of the Contract Documents subject to and in accordance with this Commencement Agreement. 4 The following detail shall apply by reference to the listed clauses of the NEC Conditions: Contract Data Part 1 – Data provided by the Employer. Contract Data Part 2 – Data provided by the Contractor: Site Information: Works Information: Prices: Activity Schedule: Z clauses (if any) additional to those set out in or attached to the NEC Conditions: Signed for and on behalf of [ by [ ] (the Employer) ……………………………………………. Dated Signed for and on behalf of [ by [ …………………………………………… ] ] (the Contractor) ……………………………………………. ] Dated Error! Unknown document property name. ……………………………………………. 26Error! Unknown document property name..Error! Unknown document propert Schedule 10 NEC Conditions Please note that these Z clauses have been produced before NEC has published amendments to reflect the changes made to the Housing Grants Construction and Regeneration Act 1996 by the Local Democracy, Economic Development and Construction Act 1996. Accordingly, the MoJ reserves the right to update these amendments to reflect the approach taken by NEC. Z.1 Identified and defined terms (31) Confidential Information means the Client's Confidential Information and/or the Contractor's Confidential Information as further defined in clause Z.5. (32) Contractor's Personnel means all employees, Subcontractors/sub-consultants of the Contractor. (33) Crown means the Government of the United Kingdom (including the Northern Ireland Executive Committee and the Northern Ireland Departments, the Scottish Executive and the National Assembly for Wales) including but not limited to government ministers, government departments, government in particular bodies and government agencies; (34) Employer Data means: (a) agents, consultants and the Data, text, drawings, diagrams, images or sounds (together with any database made up of any of these) which are embodied in any electronic, magnetic, optical or tangible media, and which are: (i) supplied to the Contractor by or on behalf of the Employer; or (ii) which the Contractor is required to generate, process, store or transmit pursuant to the Contract; or (b) any Personal Data for which the Employer is the Data Controller. (35) Final Account means the account produced by the Project Manager for agreement pursuant to clause 50.7 showing the final balance of the amount due between the Employer and the Contractor. (36) Fraud means/is any offence under the law creating offences in respect of fraudulent acts or at common law in respect of fraudulent acts in relation to the Crown or defrauding or attempting to defraud or conspiring to defraud the Crown. (37) Intellectual Property Rights means: (a) copyright, rights related to or affording protection similar to copyright, rights in databases, patents and rights in inventions, semi-conductor topography rights, trade marks, rights in Internet domain names and website addresses and other rights in trade names, designs including BIM, know-how, trade secrets and other rights in Confidential Information; (b) applications for registration, and the right to apply for registration, for any of the rights listed at (a) that are capable of being registered in any country or Error! Unknown document property name. 27Error! Unknown document property name..Error! Unknown document propert jurisdiction; and (c) all other rights having equivalent or similar effect in any country or jurisdiction (38) Know-how means all ideas, concepts, schemes, information, knowledge, techniques, methodology, and anything else in the nature of know how relating to the Services but excluding know how already in the possession of the Employer or Contractor before the date of this Contract; (39) Personnel means all employees, agents, consultants and subcontractors of either party. (40) Strategic Alliancing Agreement means the Strategic Alliancing Agreement between the Employer, the Contractor and others Z.2 Health and Safety Amend clause 27 (Other responsibilities) as follows: 27.4 The Contractor promptly notifies the Employer of any Health and Safety hazards which may arise in connection with the performance of the Contract. The Employer promptly notifies the Contractor of any Health and Safety hazards which may exist or arise at the Site and which may affect the Contractor in the performance of the Contract. Supplement clause 27 as follows: 27.5 While on the Site, the Contractor complies with any Health and Safety measures implemented by the Employer in respect of Contractor's Personnel and other persons working on the Site. 27.6 The Contractor notifies the Employer immediately in the event of any incident occurring in the performance of the Contract on the Site where that incident causes any personal injury or damage to property which could give rise to personal injury. 27.7 The Contractor ensures that its Health and Safety policy statement (as required by the Health and Safety at Work etc. Act 1974) is made available to the Employer on request. Z.3 Security and Vetting In this clause Z.3: Contractor's Personnel Vetting Procedure means the Employer's procedures for the vetting of Contractor's Personnel, as advised to the Contractor by the Employer. Employer's Personnel means all employees, agents, consultants and subcontractors of the Employer. Independent Safeguarding Authority is a non-departmental public body sponsored by the Home Office set up under the provisions of the Safeguarding Vulnerable Groups Act 2006 and which is responsible for the decision-making and maintenance of two lists covering the children's and vulnerable adults' sectors. Relevant Conviction means a conviction that is relevant to the provision of the works or as listed by Error! Unknown document property name. 28Error! Unknown document property name..Error! Unknown document propert the Employer and/or relevant work of the Employer. The Vetting and Barring Scheme means the scheme set up under the provisions of the Safeguarding Vulnerable Groups Act 2006. Z.3.1 Where the Contractor's Personnel are required to have a pass for admission to the Site the Employer, subject to satisfactory completion of approval procedures, arranges for passed to be issued. Contractor's Personnel who cannot produce a proper pass when required to do so by any of the Employer's Personnel, or who contravene any conditions on the basis of which a pass was issued, may be refused admission to the Site or required to leave the Site if already there. Z.3.2 The Contractor promptly returns any pass if at any time the Employer so requires or if the person to whom the pass was issued ceases to be involved in the performance of the Contract. The Contractor promptly returns all passes on completion or earlier termination of the Contract. Z.3.3 Contractor's Personnel attending the Site may be subject to a search at any time. Strip searches are only conducted on the specific authority of the Employer under the same rules and conditions applying to the Employer's Personnel. The Contractor is referred to the Prison Rules 1999 Part III and the Prison (Amendment) Rules 2005 and the Young Offender Institute Rules 2000 Part III and the Young Offender Institute (Amendment) Rules 2008. Z.3.4 The Employer, whose decision is final and conclusive, reserves the right under the Contract to refuse to admit to, or to withdraw permission to remain on, the Site or any premises occupied by or on behalf of the Employer: ● any member of the Contractor's Personnel or ● any person employed or engaged by a Sub-contractor, agent or servant of the Contractor whose admission or continued presence is, in the opinion of the Employer, undesirable. Z.3.5 If and when directed by the Employer, the Contractor provides a list of the names and addresses, National Insurance numbers, periods of employment, immigration status and tax exemption certificates of all persons who it is expected may require admission in connection with the Contract to the Site or any premises occupied by or on behalf of the Employer, specifying the capacities in which they are concerned with the Contract and giving such other particulars as the Employer may reasonably desire. Z.3.6 The Contractor's Personnel, engaged within the boundaries of a Government establishment, comply with rules, regulations and requirements (including those relating to security arrangements) as may be in force from time to time for the conduct of Contractor's Personnel when at that establishment and when outside that establishment. Z.3.7 If the Contractor fails to comply with Z.3.2 and Z.3.5 the Employer, (whose decision is final and conclusive) may decide that such failure is prejudicial to the interests of the Crown; and if the Contractor does not comply with the Employer's reasonable requests within 2 months of the date of a written notice from the Employer so to do, then the Employer may terminate the Contract, provided that such termination does not prejudice or affect any Error! Unknown document property name. 29Error! Unknown document property name..Error! Unknown document propert right of action or remedy which has accrued or thereafter accrues to the Employer. Z.3.8 The Contractor bears the cost of complying with the requirements notices, instructions or decisions received from the Employer in relation to the Contractor's obligations in respect of information relating to individuals. Z.3.9 The Contractor does not employ any person where the Contractor knows, or by reason of the circumstances which might reasonably be expected to know, that the person concerned is involved in any unlawful procurement of Social Security benefits or tax exemptions in connection with his employment by the Contractor. The Contractor does not make, facilitate or participate in the procurement of any unlawful payments to any person employed by the Contractor, whether in the nature of Social Security fraud, evasion of tax or otherwise. Z.3.10 The Contractor complies with the Employer's procedures for the vetting of Contractor's Personnel in respect of all persons to be employed or engaged to Provide the Works. The Contractor confirms that all persons employed or engaged by the Contractor or that will be employed or engaged by the Contractor in relation to this Contract are vetted and recruited on a basis that is equivalent to and no less strict than the Contractor's Personnel Vetting Procedures. Z.3.11 The Employer may require the Contractor to ensure that any person employed to Provide the Works has undertaken a Criminal Records Bureau check as per the Contractor's Personnel Vetting Procedures or any other security check as may be required by the Employer from time to time. The Contractor ensures that no person who discloses that he/she has a Relevant Conviction, or is found by the Contractor to have a Relevant Conviction (whether as a result of a police check or through the Criminal Records Bureau check or otherwise), is employed or engaged to Provide the Works. Z.3.12 Individuals, including those held in lawful custody or on probation are regarded as vulnerable persons under the Safeguarding Vulnerable Groups Act 2006. Where the Employer deems it necessary, the Contractor provides a list of Personnel who Provide the Works that are vetted by the Independent Safeguarding Authority. The Employer may in its sole discretion refuse access to the Site by any member of the Contractor's Personnel who do not successfully complete the vetting procedures under the Vetting and Barring Scheme. Z.3.13 Whilst on the Site the Contractor's Personnel comply with all security measures implemented by the Employer in respect of staff and other persons attending the Site. The Employer provides copies of its written security procedure to the Contractor on request. The Contractor and all members of the Contractor's Personnel are prohibited from taking any photographs on the Site unless the Employer has given prior written consent and an Employer representative is present so as to have full control over the subject matter of each photograph to be taken. Z.3.14 The Contractor takes measures needed to prevent its Personnel from taking, publishing or otherwise circulating such photographs. Z.3.15 The Employer has the fight to carry out any search of Contractor's Personnel or of vehicles used by the Contractor at the Site. Z.3.16 The Contractor co-operates with any investigation relating to security which is carried out Error! Unknown document property name. 30Error! Unknown document property name..Error! Unknown document propert by the Employer or by any person who is responsible to the Employer for security matters, and when required by the Employer: Z.4 ● takes all reasonable measures to make any Contractor's Personnel identified by the Employer available to be interviewed by the Employer, or by a person who is responsible to the Employer for security matters, for the purposes of the investigation. Contractor's Personnel have the right to be accompanied by and to be advised or represented to the other person whose attendance at the interview is acceptable to the Employer; and ● subject to any legal restriction on their disclosure, provides all documents, records or other material of any kind which may reasonable be required by the Employer or by a person who is responsible to the Employer for security matters, for the purposes of the investigation, so long as the provision of that material does not prevent the Contractor from performing the Contract. The Employer has the right to retain any such material for use in connection with the investigation and, so far as possible, provides the Contractor with a copy of any material retained. Information Security [Using additional defined terms as they appear in the Strategic Alliancing Agreement:] Z.4.1 The Contractor: ● identifies, keeps and discloses to the Employer upon request a record of those members of the Contractor's Personnel and any Sub-contractors with access to or who are involved in handling Employer Data (users) and ● provides to the Employer details of its policy for reporting, managing and recovering from information risk incidents, including losses of protected Personal Data and ICT security incidents and its procedures for reducing risk and raising awareness; and ● immediately reports information security incidents to the Employer. Significant actual or potential losses of Personal Data may be shared with the Information Commissioner and the Cabinet Office by the Employer. Z.4.2 The Contractor protects Employer Data whose release or loss could cause harm or distress to individuals. The Contractor handles all such Employer Data as if it were confidential while it is processed or stored by the Contractor or its Sub-contractors, applying the measures set out in clauses Z.4.1 to Z.4.9 (inclusive). Z.4.3 When Employer Data is held on paper it is kept secure at all times, locked away when not in use or the premises on which it is held secured. If Employer Data held on paper is transferred it must be by an approved secure form of transfer with confirmation of receipt. When Employer Data is held and accessed on ICT systems on secure premises, the Contractor applies the minimum protections for information set out in the Works Information, or equivalent measures, as well as any additional protections as needed as a result of the Employer's risk assessment. Where in exceptional circumstances equivalent measures are adopted by the Contractor obtains the Employer's prior approval in writing. Z.4.4 Wherever possible, Employer Data should be held and accessed on paper or ICT systems Error! Unknown document property name. 31Error! Unknown document property name..Error! Unknown document propert on secure premises protected as above. The Contractor does not use removable media (including laptops, removable discs, CD-ROMs, USB memory sticks, PDAs and media card formats) for storage or access to such Data where possible. Where the Employer agrees that this is not possible, the Contractor works to the following hierarchy, recording the reasons for a particular approach not being adopted in a particular case or a particular business area: Z.4.5 ● best option; hold and access data on ICT systems on secure premises; ● second best option:; secure remote access, so that Data can be viewed or amended without being permanently stored on the remote computer. This is possible for Employer Data over the internet using products meeting the FIPS 1402 standard or equivalent, unless otherwise agreed with the Employer; and ● third best option: secured transfer of Employer Data to a remote computer on a secure site on which it will be permanently stored. Both the Employer Data at rest and the link should be protected at least to the FIPS 140-2 standard or equivalent. Protectively marked Employer Data must not be stored on privately owned computers unless they are protected in this way; ● in all cases the remote computer should be password protected, configured so that its functionality is minimised to its intended business use only, and have up to date software patches and anti-virus software. Where the Employer agrees that it is not possible to avoid the use of removable media, the Contractor applies all of the following conditions: ● the Employer Data transferred to the removal media should be the minimum necessary to achieve the business purposes, both in terms of the numbers of people covered by the Employer Data and the Works Information of Employer Data held. Where possible only anonymised Employer Data should be held; ● the removal media should be encrypted to a standard of at least FPIS 140-2 or equivalent in addition to being protected by an authentication mechanism, such as a password; ● user rights to transfer Employer Data to removable media should be carefully considered and strictly limited to ensure that this is only provided where absolutely necessary for business purposes and subject to monitoring by the Contractor and the Employer; and ● the individual responsible for the removable media should handle it – themselves, or if they entrust it to others – as if it were the equivalent of a large amount of their own cash. Z.4.6 Where the Employer agrees that the second condition of encryption cannot be applied due to business continuity and disaster recovery considerations, such unprotected Employer Data should only be recorded, moved, stored and monitored with strong controls. Z.4.7 All material that has been used for confidential Employer Data should be subject to controlled disposal. The Contractor must: Error! Unknown document property name. 32Error! Unknown document property name..Error! Unknown document propert ● destroy paper records containing protected Personal Data by incineration, pulping or shredding so that reconstruction is unlikely and ● dispose of electronic media that has been used for protected Personal Data through secure destruction, overwriting, erasure or degaussing for re-use. Z.4.8 The Contractor has appropriate mechanisms in place in order to comply with the Employer's requirements as set out in this clause including adequate training in handling confidential Data for the Contractor's Personnel. Z.4.9 The Contractor: ● puts in place arrangements to log activity of Data users in respect of electronically held protected personal information and for managers to check the arrangements are being properly conducted, with a particular focus on those working remotely and those with higher levels of functionality. Summary records of managers' activity must be shared with the Employer and be available for inspection by the Information Commissioner's office on request; ● minimises the number of users with access to the Employer Data. Z.5 Confidentiality Z.5 In this clause Z.5: Z.5.1 ● Commercially Sensitive Information means the information listed in Appendix 1 (Commercially Sensitive Information). ● Contractor's Confidential Information means any information, however it is conveyed, that relates to the business affairs, developments, trade secrets, knowhow, Contractor's Personnel and suppliers of the Contractor, including Intellectual Property Rights, together with all information derived from the above and any other information clearly designated as being confidential (whether or not it is marked as "confidential") or which ought reasonably to be considered to be confidential including the Commercially Sensitive Information. ● Employer's Confidential Information means all Personal Data and any information, however it is conveyed, that relates to the business affairs, developments, trade secrets, know-how, personnel and suppliers of the Employer, including all Intellectual Property Rights, together with all information derived from any of the above and any other information clearly designated as being confidential (whether or not it is marked "confidential") or which ought reasonably to be considered to be confidential. Except where disclosure is expressly permitted elsewhere in this Contract, each Party: ● treats the other Party's Confidential Information as confidential and safeguard it accordingly and ● does not disclose to the other Party's Confidential Information to any other person without the owner's prior written consent. Error! Unknown document property name. 33Error! Unknown document property name..Error! Unknown document propert Z.5.2 The Parties' obligations in relation to Confidential Information do not apply to the extent that: ● the disclosure is a requirement of Law placed upon the Party making the disclosure, including any requirements for disclosure under the Freedom of Information Act, Code of Practice on Access to Government Information or the Environmental Information Regulations; ● the information was in the possession of the Party making the disclosure without obligation of confidentiality prior to its disclosure by the information owner; ● the information was obtained from a third party without obligation of confidentiality; ● the information was already in the public domain at the time of disclosure otherwise than by a breach of the Contract; or ● it is independently developed without access to the other Party's Confidential Information. Z.5.3 The Contractor only discloses the Employer's Confidential Information to the Contractor's Personnel who are directly involved in the provision of the works any of the Employer's Confidential Information and need to know, and ensures that the Contractor's Personnel are aware of and comply with their obligations in respect of Confidential Information. Z.5.4 The Contractor does not, and procures that the Contractor's Personnel do not, use of any of the Employer's Confidential Information received otherwise than for the purposes of the Contract. Z.5.5 At the written request of the Employer, the Contractor procures that members of the Contractor's Personnel identified in the Employer's notice sign a confidentiality undertaking on similar terms to the Contract prior to commencing any work in accordance with the Contract. Z.5.6 Nothing in the Contract prevents the Employer from disclosing the Contractor's Confidential Information: Z.5.7 ● to any Crown body or any other Contracting Authority on the understanding that they are entitled to further disclose the Confidential Information to other Crown bodies or other Contracting Authorities on the basis that the information is confidential and is not to be disclosed to a third party which is not part of any Crown body or any Contracting Authority; ● to any contractor, consultant or other person engaged by the Employer or any person conducting an Office of Government Commerce gateway review; ● for the purpose of the examination and certification of the Employer's accounts, or ● for any examination pursuant to Section 6(1) of the National Audit Act 1983 of the economy, efficiency and effectiveness with which the Employer has used its resources. The Employer uses its reasonable endeavours to ensure that any government department, Error! Unknown document property name. 34Error! Unknown document property name..Error! Unknown document propert Contracting Authority, employee, third party or Sub-contractor to whom the Contractor's Confidential Information is disclosed is made aware of the Employer's obligations of confidentiality. Z.5.8 Nothing prevents either Party from using any techniques, ideas or know-how gained during the performance of the Contract in the course of its normal business to the extent that this use does not result in a disclosure of the other Party's Confidential Information or an infringement of IPR. Z.5.9 The parties acknowledge that, subject to the foregoing provisions regarding the Contractor's confidential information, the content of this contract is not Confidential Information. Notwithstanding any other term of this Contract, the Contractor hereby gives consent for the Employer to publish the Contract in its entirety, including from time to time agreed changes to the contract, to the general public. Prior to the publication the Employer may, at his sole discretion, in whole or in part, redact information for one or more of the following grounds: (a) (b) (c) (e) (f) (g) national security; personal data; information protected by intellectual property law; (d) information which is not in the public interest to disclose (under a Freedom of Information Act analysis); third party confidential information; IT security; or prevention of fraud. Z.6 Fraud and Prevention of Corruption Z.6.1 The Contractor takes all reasonable steps to prevent Fraud. Z.6.2 Z.7 The Contractor notifies the Employer immediately if it has reason to suspect that any Fraud has occurred or is occurring or is likely to occur. CDM Regulations and SWMP Regulations Z.7.1 The Principal Contractor for the purposes of both the Construction (Design and Management) Regulations 2007 (the CDM Regulations) and the Site Waste Management Plans Regulations 2008 (the SWMP Regulations) is the Contractor or, if he ceases to be the Principal Contractor, such other contractor as the Employer will appoint pursuant to regulation 14(2) of the CDM Regulations and regulation 4(1) of the SWMP Regulations. Z.7.2 The CDM Co-ordinator for the purposes of the CDM Regulations is the Project Manager or, if he ceases to be the CDM Co-ordinator, such other person as the Employer will appoint pursuant to regulation 14(1) of the CDM Regulations. Z.8 Employment and Skills Z.8.1 The following new definitions shall be added to Core Clause 11: "11.20 The Employment and Skills Strategy is the Employer's Employment and Skills Strategy forming part of the Works Information; Error! Unknown document property name. 35Error! Unknown document property name..Error! Unknown document propert 11.21 The ESP is the works-specific Employment and Skills Plan produced by the Contractor and forming part of the Works Information to be complied with and implemented by the Contractor in order to execute the Employment and Skills Strategy; 11.22 The Method Statement is the works-specific method statement produced by the Contractor and forming part of the Works Information which sets out in detail how the Contractor shall implement the ESP;". Z.8.2 The Contractor complies with and implements the ESP and Method Statement in accordance with the Employment and Skills Strategy. Z.8.3 The Contractor nominates an individual to liaise with the Project Manager and provides the Project Manager with information as required to demonstrate the Contractor's compliance with the ESP and Method Statement. Z.8.4 The Project Manager provides to the Contractor information it has available to enable the Contractor to comply with and implement the ESP and Method Statement, including the details listed in the Employment and Skills Strategy. Z.8.5 The Contractor provides to the Project Manager on a monthly basis, in accordance with the relevant Key Dates, a report outlining the achievements during the previous month against the ESP and Method Statement and the employment and skills Key Performance Indicator contained in the [Schedule of Partners][Incentive Schedule], and provides details of the various employment and skills activities delivered in the month. The Project Manager is responsible for monitoring the Contractor's compliance with and implementation of the ESP and Method Statement, and such monitoring forms part of the Employer's assessment of the employment and skills Key Performance Indicator. Z.8.6 The Contractor and the Project Manager attend a meeting (convened by the Project Manager) after Completion to review the completed works and the Contractor's performance against the Key Performance Indicators (including performance against the employment and skills Key Performance Indicator), and its compliance with and implementation of the ESP and Method Statement, and to consider the scope for further improvement on future projects. Z.8.7 Any and all costs relating to compliance with and implementation of the ESP and Method Statement by the Contractor are included in the Activity Schedule. Z.7.8 Where a compensation event set out in clause 60.1 and agreed or established in accordance with clauses 60 to 65 substantially increases or decreases the Price, the Contractor may propose a corresponding and proportionate amendment to the employment and skills output figures contained in the ESP, the Method Statement and any relevant Key Performance Indicators. The Employer and the Project Manager consider any such proposal made by the Contractor and seek to agree any amendments with the Contractor. Z.9 Z.9.1 Priority Clause The Contract Documents shall be treated as complementary and it is the duty of the Contractor to warn the Employer and the Project Manager of any error, omission or discrepancy of which it becomes aware and (within the scope of its agreed role, expertise Error! Unknown document property name. 36Error! Unknown document property name..Error! Unknown document propert and responsibilities) to put forward proposals to resolve any such error, omission or discrepancy fairly and constructively without adversely affecting the agreed cost or time for completion or quality of the Works. Any proposal pursuant to this clause Z.9.1 is subject to prior approval by the Employer after Core Group consultation. Z.9.2 Z.10 In the event that any discrepancy cannot be resolved in accordance with clause Z.9.1 and except where a different priority is agreed by the Employer, the Project Manager and the Contractor, the priority between the Contract Documents shall be as follows in descending order: i The Commencement Agreement; ii The Early Conditional Appointment; iii The NEC Conditions; iv The Accepted Programme; v The Partnering Timetable; vi Those parts of the Works Information and Site Information provided by the Employer; vii Those parts of the Works Information and Site Information provided by the Contractor; viii The Activity Schedule; ix Any Risk Register; x Any other Contract Documents. Payment Delete clauses 50 and 51 and replace with the following: 50 Assessing the amount due 50.1 The first assessment date is decided by the Contractor to suit the procedures of the Parties and is not later than the assessment interval after the starting date. Later assessment dates occur (i) at the end of each assessment interval until four weeks after the Supervisor issues the Defects Certificate (ii) at Completion of the whole of the works. 50.2 The date on which a payment becomes due is seven days after the assessment date. 50.3 The amount due is (i) the price for Work Done to Date, (ii) plus other amounts to be paid to the Contractor, Error! Unknown document property name. 37Error! Unknown document property name..Error! Unknown document propert (iii) less amounts to be paid by or retained from the Contractor. Any tax which the law requires the Employer to pay to the Contractor is included in the amount due. 50.5 In assessing the amount due, the Project Manager considers any application for payment the Contractor has submitted on or before the payment due date. 50.5 If no programme is identified in the Contract Data, one quarter of the Price for Work Done to Date is retained in assessments of the amount due until the Contractor has submitted a first programme to the Project Manager for acceptance showing the information which this contract requires. 50.6 The Project Manager corrects any wrongly assessed amounts due in a later payment certificate. 50.7 The following procedures shall apply in relation to the Final Account: (i) The Project Manager prepares and issues to the Employer and the Contractor a Final Account (calculated in accordance with clauses 50.3 – 50.6 taking into account any adjustment provided for in accordance with this contract (including without limitation any adjustment required under clause 45) and reflecting amounts previously paid under this contract) within twenty (20) Working Days following issue by the Supervisor of the Defects Certificate under clause 43.3. (ii) The Employer or the Contractor (as the case may be) makes an application for payment stating the sum the Employer or the Contractor considers to be due to it and the basis on which that sum is calculated in reference to the Final Account and which shall be supported by such further information as the other party may reasonably require. The application is made on or after forty (40) Working Days from the issue by the Supervisor of the Defects Certificate under clause 43.3 (or any revised period agreed between the Employer and the Contractor). The due date for payment in respect of the application is the date of receipt by the payer of such application. (iii) The payer or the Project Manager issues to the payee a payment notice setting out the sum the payer considers to have been due on the due date for payment and the basis on which that sum is calculated within five (5) days from the due date for payment. The final date for payment is the later of twenty (20) Working Days from the due date for payment and fifteen (15) Working Days from the date of receipt by the payer of any required VAT invoice in the same sum as the payment notice. (iv) (v) If a payment notice is not issued in accordance with clause 50.7(iii) the application for payment pursuant to clause 50.7(ii) shall be treated as the payment notice. Subject to any notice issued in accordance with clause 51.4 the payer pays the sum stated as due in the payment notice or the application for payment by the final date for payment calculated in accordance with clause 51.5. The Final Account, when agreed, shall be conclusive evidence as to the balance of the amount due between the Employer and the Contractor. Error! Unknown document property name. 38Error! Unknown document property name..Error! Unknown document propert 51 Payment 51.1 The Project Manager certifies payment by issuing a payment notice within five days of the payment due date which sets out the sum the Project Manager considers to be due on the payment due date and the basis on which that sum is calculated. The first payment is the amount due. Other payments are the change in the amount due since the last payment certificate. A payment is made by the Contractor to the Employer if the change reduces the amount due. Other payments are made by the Employer to the Contractor. Payments are in the currency of this contract unless otherwise stated in this contract. 51.2 If the Project Manager fails to issue the Project Manager's certificate correctly or on time (i) long due (ii) the Contractor's application for payment (if any) is the notice of payment as as it specifies the sum the Contractor considers to be due on the payment date and the basis on which that sum is calculated, or the Contractor issues a payment notice specifying the sum the Contractor considers to have been due on the payment due date and the basis on which that sum is calculated. 51.3 The notified sum in the Project Manager's certificate or the Contractor's application for payment or payment notice (as the case may be) must be paid by the final date for payment, unless a Party has notified his intention to pay less as required by this Contract. 51.4 If either Party intends to pay less than the amount stated in the Project Manager's certificate or the Contractor's payment notice, he notifies the other Party not later than seven days before the final date for payment by stating the sum that Party considers to be due on the date the notice is served and the basis on which that sum is calculated. For the avoidance of doubt, the Project Manager may serve a pay less notice on behalf of the Employer. 51.5 The final date for payment for each payment is (i) 14 days from the payment due date or, (ii) if a different period is stated in the Contract Data, within the period stated. If the Contractor issues a Contractor payment notice, then the final date for payment will be postponed by the same number of days after the date that the Project Manager's payment notice should have been served in accordance with clause 51.1. If a certified payment is late interest is paid on the late payment. Interest is assessed from the date by which the late payment should have been made until the date when the late payment is made, and is included in the first assessment after the late payment is made. This clause does not exclude the Contractor's rights following non-payment set out in other clauses of this Contract or at law. 51.6 If an amount due is corrected in a later certificate either (i) by the Project Manager in relation to a mistake or a compensation event or Error! Unknown document property name. 39Error! Unknown document property name..Error! Unknown document propert (ii) following a decision of the Adjudicator or the tribunal, interest on the correcting amount is paid. Interest is assessed from the date when the incorrect amount was certified until the date when the correcting amount is certified and is included in the assessment which includes the correcting amount. 51.7 Z.11 Interest is calculated on a daily basis at the interest rate and is compounded annually. Termination Amend clauses as follows: Insert clause 90.1A (termination at any time) 90.1A.1 Notwithstanding any other provision of this Contract, the Employer may terminate this Contract at any time. In such circumstances the Employer gives the Contractor not less than twenty (20) Working Days prior notice, within which period the Contractor ceases all activities under the Contract in an orderly manner. 90.1A.2 Upon expiry of that period the Project Manager complies with the provisions of clause 50 (payment) and clauses 92 and 93.1 (procedure on termination, payment on termination). Amend clause 93.1 by inserting at the end of the clause: "provided that the Employer need not pay this sum and/or any sum that has already become due insofar as the Employer has given or gives a pay less notice in accordance with this Contract" Amend clause 93 by inserting new sub clause as follows: "93.3 Z.12 No sum is payable in respect of any sum due under this Contract, if the Contractor suffers an event of insolvency as defined in section 113(2) to (5) of the Housing Grants Construction and Regeneration Act 1996 (as amended) after the date on which the pay less notice is due in accordance with clause 51.4." Core Group Insert new clause 16A as follows: 16A.1 Core Group and members The Employer, Contractor and Project Manager establish a Core Group which meets regularly to review and stimulate the progress of the Works and to fulfil their other functions as described in this Contract. Members of the Core Group shall comprise the individuals listed in the Early Conditional Appointment subject to replacement only with the prior consent of the current Core Group members. The Employer ensures that the Project Manager's appointment contains terms providing that the Project Manager is a member of the Core Group and equivalent terms to this Z clause 16A. 16A.2 Responsibility for Core Group members Each of the Employer, Contractor and Project Manager ensures that any of its employees who are Core Group members attend Core Group meetings and fulfil the agreed functions Error! Unknown document property name. 40Error! Unknown document property name..Error! Unknown document propert of a Core Group member in accordance with the contract. 16A.3 Core Group meetings A meeting of the Core Group members is convened by the Project Manager at the request of any Core Group member and otherwise as required by the Contract, at not less than five (5) Working Days notice unless all Core Group members agree a shorted period, to all Core Group members (copied to all who are entitled to attend) stating its agenda. Each such meeting is chaired by an individual to be agreed at that meeting and deals only with the matters listed in its agenda (unless all Core Group members agree otherwise). 16A.4 Core Group decisions Decisions of the Core Group are by consensus (unanimous agreement following reasoned discussion) of all Core Group members present at that meeting. The Employer, Contractor and Project Manager comply with any decision of the Core Group made within the scope of its agreed functions. Z.13 Partnering Adviser Insert new Core Clause 16B as follows: 16.B.1 Partnering Adviser In all matters relating to the Contract relationships and the operation of the Contract, the Employer, Contractor, Project Manager and Supervisor may together or individually utilise the advice and support of the Partnering Adviser identified in the Early Conditional Appointment, subject to prior agreement of costs and the Partnering Adviser's duty of care, including: (i) team-building, review of the Contract Documents and review of Sub-Contracts and Professional Services Contracts for consistency with the Contract ; (ii) preparation of the Contract Documents; (iii) provision of fair and constructive advice as to the Contract processes and the operation of the Contract; (v) attendance at such meetings of the Core Group as their members consider appropriate; (vi) assistance in the solving of problems and the avoidance or resolution of dispute in accordance with clause W.1. 16B.2 Replacement Partnering Adviser The Partnering Adviser may be replaced at any time by a decision of the Core Group. Z.14 Early Warning Insert new Core Clause 16.5 to read: 16.5 Without limitation to the remainder of this clause 16, the Employer, Contractor, Project Manager and Supervisor each notifies the others as soon as it is aware of any matter Error! Unknown document property name. 41Error! Unknown document property name..Error! Unknown document propert adversely affecting or threatening the Works or their performance under the contract or their Professional Services Contract as the case may be, and (within the scope of its agreed role, expertise and responsibilities) includes in such notification proposals for avoiding or remedying such matter. The Project Manager convenes a meeting of the Core Group within five (5) Working Days from the date of any such notification to agree an appropriate course of action unless all Core Group members agree such course of action without a meeting. Z.15 Risk Management Insert as new 16.6: The Employer, Contractor, Project Manager, Supervisor and appointed Consultants recognise the risks involved in the design, supply and construction of the Works, and the costs associated with those risks. The Employer, Contractor, Project Manager, Supervisor and appointed Consultants work together and individually, through Risk Management exercises in accordance with this clause 16, and otherwise in accordance with the Contract, including through the actions described in any Risk Register within the periods and/or deadlines stated in such Risk Register, to analyse and manage risks in the most effective ways including: (i) identifying risks and their likely costs; (ii) eliminating or reducing risks and their costs; (iii) insuring risks wherever affordable and appropriate; (iv) Z.16 sharing or apportioning risks according to which one or more Partnering Team members are most able to manage such risks. Insurance and security Professional Indemnity Insurance Insert new Core Clause 85.5 Professional indemnity insurance and/or product liability insurance is taken out by the Contractor as stated in the Insurance Table and is maintained for a period expiring no early than 12 years after the date of Completion and notwithstanding termination for any reason of the Contractor's engagement under the contract unless such cover is no longer generally available in the market-place on reasonable terms and at reasonable premiums. Amend the Insurance Table to add as follows: INSURANCE TABLE Insurance against Minimum amount of cover or minimum level of indemnity Professional indemnity insurance The amount stated in the Contract Data for any one event [which amount shall not in any event be less than [£xm]] Error! Unknown document property name. 42Error! Unknown document property name..Error! Unknown document propert Z.17 Limitations Insert new Core Clause 12.5 Notwithstanding the method of executing the Contract, the limitation period for all and any claims and proceedings arising under or out of or in connection with the Contract or the Works is twelve (12) years from the Completion Date. This limitation period shall not prevent claims and proceedings prior to the Completion Date or the conclusion of proceedings commenced prior to the expiry of such limitation period Z.18 Possession All parts of the Site are in the exclusive possession of the Contractor until the period immediately prior to the Completion Date when the Employer may need access to agreed areas of the Site in order to commence installation of agreed fixtures and fittings. The arrangements for any period of non-exclusive possession will be set out in the Contract. Z.19 Asbestos Notwithstanding any other provisions of the Contract, the risk of loss or damage to the Works and the Site occasioned by asbestos remains with the Employer provided always that, in the event that the Contractor discovers any asbestos the Contractor takes all steps that would be expected of a reasonable Contractor and, if the asbestos is to be removed, appoints and adequately supervises any subcontractors involved in the removal of the same. Z.20 Employees Delete Core Clause 24.2 and insert as follows: “The Employer is entitled to require any of the Contractor's employees to be replaced if in the reasonable opinion of the Employer that person’s performance is unsatisfactory and/or that person has breached the Security Requirements of the Employer set out in the Works Information. Such person is replaced with a person of at least the same experience and expertise at the expense of the Contractor and subject to the Employer’s approval (such approval not to be unreasonably withheld or delayed).” Z.21 Intellectual Property Rights Insert new Core Clause 22.2: The Intellectual Property Rights in all designs and other documents prepared by or on behalf of the Contractor in relation to the Works and the work executed from them are the property of and vested in the Employer who reserves the right to replace such designs and/or documents or to execute or to have executed works in accordance with such designs and/or documents as may be required by the Employer and the Intellectual Property Rights extends to any and all future projects implemented by the Employer. The Employer grants to the Contractor an irrevocable non-exclusive, royalty free licence (carrying the right to grant sub-licences) to use for the duration of the Works only and only for purposes directly relating to completion of the Works any Intellectual Property Rights relating to the works which are or become vested in or are licensed to the Employer. Error! Unknown document property name. 43Error! Unknown document property name..Error! Unknown document propert Z.22 Z.23 Inspection of financial records (1) The Contractor allows the Project Manager (or other representative of the Employer) to visit its offices and to inspect its financial records in relation to the Works at any time subject to reasonable prior notice; (2) The Contractor uses reasonable endeavours to ensure that a clause Is inserted into any Subcontracts specifically stating that the Project Manager (or other representative of the Employer) is entitled to visit the Subcontractor’s offices and to inspect its financial records in relation to the Works at any time subject to reasonable prior notice. Exclusion of Fee from Compensation Events Notwithstanding any other provision of this Contract, any quotation and payment for Compensation Events other than a Compensation Event under Core Clause 60.1(1), shall exclude any claim for an increased or additional Fee. Z.24 Problem Solving and Dispute Avoidance or Resolution: Option W1 Delete Option W1 and replace as follows: W1.1 Notice of difference or dispute As soon as it aware of any difference or dispute arising under or out of or in connection with the Contract or the Works (a "difference or dispute"), the Contractor or the Employer as the case may be gives notice to the other copied to the Project Manager. W1.2 Problem-Solving Hierarchy Upon receipt of notice in accordance with clause W1.1 the parties involved in a difference or dispute, guided as necessary by the Partnering Adviser, apply the Problem-Solving Hierarchy set out in Appendix [ ] and use reasonable skill and care to ensure that their employees named in the Problem-Solving Hierarchy express their views and propose their solutions within its stated timetable in seeking to achieve an agreed solution to the notified difference or dispute. W1.3 Core Group review Where application of the Problem-Solving Hierarchy does not achieve, within its stated timetable, a solution acceptable to all the Parties involved in a difference or dispute, then the Project Manager convenes a meeting of the Core Group at no more ten (10) Working Days' notice, notifying them of all available information regarding the difference or dispute and inviting all involved and the Partnering Adviser, who attends the meeting and makes constructive proposals in seeking to achieve an agreed solution to the notified difference or dispute. W1.4 Conciliation, mediation or other alternative dispute resolution If any difference or dispute is not resolved in accordance with clauses W1.2 and W1.3, and provided that no Party has by reason of that difference or dispute exercised a right of termination, then any Party involved in such difference or dispute may refer it to conciliation in accordance with the procedure referred to in Appendix [ ], or to mediation Error! Unknown document property name. 44Error! Unknown document property name..Error! Unknown document propert or any other form of alternative dispute resolution recommended by the Partnering Adviser in accordance with such procedure as the Partnering Adviser may recommend or organise and as the Parties involved in such different or dispute may agree. W1.5 Adjudication The procedures under clauses W1.1, W1.2, W1.3 and W1.4 are without prejudice to the rights of the Parties involved in a difference or dispute to refer it to adjudication, and any such reference shall be in accordance with the procedure referred to in Appendix [ ]. W1.6 Litigation Any difference or dispute that is not resolved by adjudication in accordance with clause W1.5 may be referred by any Party involved in such difference or dispute either to the courts of England and Wales. Z.25 Dispute resolution (Option W2) Delete clause W2.3(12) and insert: "The Adjudicator may correct his decision so as to remove a clerical or typographical error arising by accident or omission within five days of communicating his decision to the Parties." Insert new clause W2.5 as follows: "References to the Housing Grants, Construction and Regeneration Act 1996 in this schedule are to that Act (as amended)." Z.26 The Housing Grants, Construction and Regeneration Act 1996 (Option Y(UK) 2) Delete this clause and insert "Not used." Z.27 Compensation events Amend clause 60.1 by including new sub clause as follows: "(20) Z.28 The Contractor exercising its right to suspend any or all of his obligations under this Contract pursuant to the Housing Grants Construction and Regeneration Act 1996 (as amended);" Collateral warranties Insert a new core clause 26.4: 26.4 The Contractor procures the following collateral warranties: (i) in favour of the Employer from any Subcontractor with material design responsibility within ten (10) Working Days of the Project Manager's request or ten (10) Working Days of that Subcontractor's appointment in connection with the Works in the form set out at Appendix 1 to this contract; and (ii) in favour of the Employer from the any sub-contractor or sub-consultant of a Subcontractor with material design responsibility within fourteen days of the Project Manager's request or ten (10) Working Days of that sub-contractor or sub-consultant's appointment in connection with the Works in the form set out at Appendix 2 to this contract. Error! Unknown document property name. 45Error! Unknown document property name..Error! Unknown document propert Appendix 1 Error! Unknown document property name. 46Error! Unknown document property name..Error! Unknown document propert Appendix 2 Error! Unknown document property name. 47Error! Unknown document property name..Error! Unknown document propert Schedule 11 Shared Savings Scheme (clause 9.1) Error! Unknown document property name. 48Error! Unknown document property name..Error! Unknown document propert
© Copyright 2026 Paperzz