Cost Risk

Pricing Arrangements: Choose Your
Contract Type Wisely & Reduce Your
Risks!
Breakout Session # 304
Jo Cunningham
April 7, 2009
2:30 PM
1
Selecting the contract pricing
arrangement is THE most
important decision you will
ever make!
AVOID
Cost Plus
Percentage
of Cost
2
What’s Really in it For Me?
Describe how
you saved us
$10 Million
AND reduced
our risks!
3
Contract Types
• Two Basic Pricing Arrangements:
– Fixed Price
• FFP, FFP/EPA, FP+AF, FP+I, FF Rate, CostShare
– Cost Reimbursement
• CNF, CPFF, CPIF, CPAW, Cost-Share
• T&M, LH
4
Failure is NOT an Option!
• Firm Fixed Price: Failure is not an option
• Time & Materials: We can’t fail as long
as we show up for work.
• Cost Reimbursable: We will give it our
best try, but failure may be an option
5
Statement of Work Is Crucial
• The SOW:
– First and most important basis for pricing
arrangement selection.
– The pricing arrangement must be
consistent with the SOW in its final form.
6
Cost Risk & Contract Type
Cost Risk:
High
>>>>>>>>>>>>>>>>>>>>>>>>
Low
Vague
>>>>>>>>>>>>>>>>>>>>>>>>>
Well Defined
Requirement
Definition
Production
Stages
Concept
Studies, &
Exploratory
Test/
Full scale
Full
Development
Demo
Development
Production
CPFF
CPIF,
CPIF, FPIF,
FFP, FPIF,
FPIF
or FFP
or FPEPA
Basic Research
Contract
Type
Varied
7
Comparison of Major Contract Types
• Fixed Price
– Principle Risks: None, Contractor assumes all cost risk.
– Use When: The requirement is well-defined.
Contractors are experienced in meeting the fixed price.
Market conditions are stable.
Financial risks are otherwise insignificant.
– Elements: A firm fixed-price for each line item or one or more
groupings of line items.
– Contractor is required to: Provide acceptable deliverable at
the time, place and price specified in the contract.
8
Comparison of Major Contract Types
• Fixed Price
– Contractor Incentive: Generally realizes an additional
dollar of profit for every dollar that costs are reduced
– Typical Application: Commercial supplies and services.
– Primary Limitations: Generally NOT appropriate for
R&D.
– Variants: Firm Fixed-price Level of Effort.
9
Comparison of Major Contract Types
• Fixed Price Economic Price Adjustment
- Principle Risks: Unstable market prices for labor or material
over life of contract.
- Use When: Market prices at risk are severable and significant.
Risks stem from industry-wide contingencies beyond contractor's
control. Dollars at risk outweigh administrative burdens of an FPEPA.
- Elements: Fixed-price, ceiling on upward adjustment, & a formula
for adjusting prices up or down based on established prices, actual
labor or material costs, labor or material indices.
- Contractor is required to: Provide acceptable deliverable at
the time and place specified in the contract at the adjusted price.
10
Comparison of Major Contract Types
• Fixed Price Economic Price Adjustment
– Contractor Incentive: Generally realizes an additional
dollar of profit for every dollar that costs are reduced.
– Typical Application: Long-term contracts for commercial
supplies during a period of high inflation.
– Primary Limitations: Must be justified.
– Variants: None.
11
Comparison of Major Contract Types
• Fixed Price Incentive Fee
– Principle Risks: Moderately uncertain contract labor or
material requirements.
– Use When: Ceiling price can be established that covers
most probable risks inherent in nature of work. Proposed
profit sharing formula would motivate contractor to control
costs to & meet other objectives.
– Elements: Ceiling price; Target cost; Target profit; Delivery,
quality, other performance targets; Profit sharing formula.
– Contractor is required to: Provide acceptable deliverable
at time & place specified in contract, at or below ceiling price.
12
Comparison of Major Contract Types
• Fixed Price Incentive Fee
– Contractor Incentive: Realizes a higher profit by
completing work below ceiling price and/or by meeting
objective performance targets.
– Typical Application: Production of a major system based
on a prototype.
– Primary Limitations: Must be justified. Must be
negotiated. Contractor must have an adequate
accounting system. Cost data must support targets.
– Variants: Successive Targets.
13
Comparison of Major Contract Types
• Fixed Price Award Fee
– Principle Risks: Risk that the user will not be fully satisfied
because of judgmental acceptance criteria.
– Use When: Judgmental standards can be fairly applied by
Award-fee panel. The potential fee is large enough to both: (1)
Provide meaningful incentive; (2) Justify related administrative
burdens.
– Elements: Firm fixed-price; Standards for evaluating
performance; Procedures for calculating fee based on performance
against standards.
– Contractor is required to: Perform at time, place, and price
fixed in contract.
14
Comparison of Major Contract Types
• Fixed Price Award Fee
– Contractor Incentive: Generally realizes an additional
dollar of profit for every dollar that costs are reduced; earns
an additional fee for satisfying performance standards.
– Typical Application: Performance-based service
contracts.
– Primary Limitations: Must be negotiated.
– Variants: None.
15
Comparison of Major Contract Types
• Fixed Price Prospective Redetermination
– Principle Risks: Costs of performance after the first year
because they cannot be estimated with confidence.
– Use When: Buyer needs a firm commitment from contractor to
deliver supplies /services during subsequent years. Dollars at risk
outweigh administrative burdens of FPRP.
– Elements: Fixed price for first period; Proposed subsequent
periods (12 months apart); Timetable for pricing next period(s).
– Contractor is required to: Provide acceptable deliverables at
time & place specified in contract at price established for each
period.
16
Comparison of Major Contract Types
• Fixed Price Prospective Redetermination
– Contractor Incentive: For the period of performance,
realizes an additional dollar of profit for every dollar that costs
are reduced.
– Typical Application: Long-term production of spare parts
for a major system.
– Primary Limitations: MUST be negotiated. Contractor
must have an adequate accounting system that supports the
pricing periods. Prompt redeterminations.
– Variants: Retroactive Redetermination
17
Comparison of Major Contract Types
• Cost Plus Incentive Fee
– Principle Risks: Highly uncertain & speculative labor hours, labor
mix, material requirements (and other things) necessary to perform
contract. Buyer assumes risks; benefiting if actual cost is lower than
expected cost; losing if work can’t be completed within expected cost of
performance.
– Use When: Objective relationship can be established between fee &
such measures of performance as actual costs, delivery dates,
performance benchmarks, etc.
– Elements: Target cost; Performance targets; Minimum, maximum &
target fee; Formula for adjusting fee based on actual costs and/or
performance.
– Contractor is required to: Make good faith effort to meet Buyer's
needs within estimated cost in the Schedule.
18
Comparison of Major Contract Types
• Cost Plus Incentive Fee
– Contractor Incentive: Realizes a higher fee by completing work
at lower cost and/or by meeting other objective performance targets.
– Typical Application: Research and development of prototype for
major system.
– Primary Limitations: Contractor must have adequate accounting
system. Buyer must exercise surveillance during performance to
ensure use of efficient methods & cost controls. Must be negotiated.
Must be justified. Statutory & regulatory limits on fees that may be
negotiated. Must include applicable Limitation of Cost clause at
FAR 52.232-20 through 23.
– Variants: None.
19
Comparison of Major Contract Types
• Cost Plus Award Fee
– Principle Risks: Highly uncertain & speculative labor hours, labor
mix, material requirements (and other things) necessary to perform
contract. Buyer assumes risks inherent in contract; benefiting if actual
cost is lower than expected cost; losing if work cannot be completed
within expected cost of performance.
– Use When: Objective incentive targets are not feasible for critical
aspects of performance. Judgmental standards can be fairly applied.
Potential fee would provide a meaningful incentive.
– Elements: Target cost; Standards for evaluating performance; Base
& maximum fee; Procedures for adjusting fee, based on performance
against standards.
– Contractor is required to: Make good faith effort to meet Buyer's
needs within estimated cost in the Schedule.
20
Comparison of Major Contract Types
• Cost Plus Award Fee
– Contractor Incentive: Realizes a higher fee by meeting
judgmental performance standards.
– Typical Application: Large scale research study.
– Primary Limitations: Contractor must have adequate
accounting system. Buyer must exercise surveillance during
performance to ensure use of efficient methods & cost controls.
Must be negotiated. Must be justified. Statutory & regulatory limits
on fees that may be negotiated. Must include applicable Limitation
of Cost clause at FAR 52.232-20 through 23.
– Variants: None.
21
Comparison of Major Contract Types
• Cost Plus Fixed Fee
– Principle Risks: Highly uncertain & speculative labor hours,
labor mix, material requirements (and other things) necessary to
perform contract. Buyer assumes risks inherent in contract;
benefiting if actual cost is lower than expected cost; losing if work
cannot be completed within expected cost of performance.
– Use When: Relating fee to performance (e.g., to actual costs)
would be unworkable or of marginal utility.
– Elements: Target cost; Fixed fee.
– Contractor is required to: Make good faith effort to meet
Buyer's needs within estimated cost in the Schedule.
22
Comparison of Major Contract Types
• Cost Plus Fixed Fee
– Contractor Incentive: Realizes a higher rate of return (i.e., fee
divided by total cost) as total cost decreases.
– Typical Application: Research study.
– Primary Limitations: Contractor must have adequate
accounting system. Buyer must exercise surveillance during
performance to ensure use of efficient methods & cost controls.
Must be negotiated. Must be justified. Statutory & regulatory limits
on fees that may be negotiated. Must include applicable Limitation
of Cost clause at FAR 52.232-20 through 23.
– Variants: Completion or term contract.
23
Comparison of Major Contract Types
• Cost-Sharing
– Principle Risks: Highly uncertain & speculative labor hours,
labor mix, material requirements (and other things) necessary to
perform contract. Buyer assumes risks inherent in contract;
benefiting if actual cost is lower than expected cost; losing if work
cannot be completed within expected cost of performance.
– Use When: The contractor expects substantial compensating
benefits for absorbing part of the costs and/or foregoing fee.
– Elements: Target cost; Agreement on Buyer’s share of cost.
– Contractor is required to: Make good faith effort to meet
Buyer's needs within estimated cost in the Schedule.
24
Comparison of Major Contract Types
• Cost-Sharing
– Contractor Incentive: Shares in the cost of providing a
deliverable of mutual benefit.
– Typical Application: Joint research where Contractor expects to
derive long term benefits to his company.
– Primary Limitations: Contractor must have adequate
accounting system. Buyer must exercise surveillance during
performance to ensure use of efficient methods & cost controls.
Must be negotiated. Must be justified. Must include applicable
Limitation of Cost clause at FAR 52.232-20 through 23.
– Variants: Firm fixed price, where Contractor pays all costs over
contract price.
25
Comparison of Major Contract Types
• Cost No Fee
– Principle Risks: Highly uncertain & speculative labor hours,
labor mix, material requirements (and other things) necessary to
perform contract. Buyer assumes risks inherent in contract;
benefiting if actual cost is lower than expected cost; losing if work
cannot be completed within expected cost of performance.
– Use When: The supplier is a not-for-profit entity.
– Elements: Target cost; No fee.
– Contractor is required to: Make good faith effort to meet
Buyer's needs within estimated cost in the Schedule.
26
Comparison of Major Contract Types
• Cost-No-Fee
– Contractor Incentive: Providing a deliverable with benefits to
both parties; Contractor expects to derive long term benefits to his
firm; Enhanced reputation.
– Typical Application: Joint research with an educational
institutions or other not-for-profit entities.
– Primary Limitations: Contractor must have adequate
accounting system. Buyer must exercise surveillance during
performance to ensure use of efficient methods & cost controls.
Must be negotiated. Must be justified. Statutory & regulatory limits
on fees that may be negotiated. Must include applicable Limitation
of Cost clause at FAR 52.232-20 through 23.
– Variants: None.
27
Comparison of Major Contract Types
• Time and Materials
– Principle Risks: Highly uncertain & speculative labor hours,
labor mix, material requirements (and other things) necessary to
perform contract. Buyer assumes risks inherent in contract;
benefiting if actual cost is lower than expected cost; losing if work
cannot be completed within expected cost of performance.
– Use When: No other type of contract is suitable (e.g., because
costs are too low to justify an audit of the contractor's indirect
expenses).
– Elements: Ceiling price; Per-hour labor rate includes overhead &
profit; Provisions for reimbursing direct material costs.
– Contractor is required to: Make good faith effort to meet
Buyer's needs within ceiling price.
28
Comparison of Major Contract Types
• Time and Materials
– Contractor Incentive: None.
– Typical Application: Emergency repairs to heating plants
and aircraft engines; Contractor support for field exercises.
– Primary Limitations: Labor rates must be negotiated.
MUST be justified. The Buyer MUST exercise appropriate
surveillance to ensure efficient performance.
– Variants: Labor Hour (LH)
29
Steps to Selecting Contract Type
1. Customers Requirements – Talk with them!
– Need What? By When??!!??
– Project Management Requirements?
– Funding Availability? Limitations of Obligation?
Phases?
– Complexities and Possible Complications?
– Risks? Who should carry the burden of risks?
30
Steps to Selecting Contract Type
2. Contractor Selection Influences Choices
– Not for Profit?
– Educational Institution?
– Small Businesses? Unsophisticated accounting
system?
– Does the contractor have a job-cost accounting
system?
31
Steps to Selecting Contract Type
3. Consider revising the SOW to reduce risks
4. Request your Audit Department to perform
and accounting survey if you are considering
a Cost-type or T&M contract, where the
contractor has no history of performing such
contracts for you.
5. Select the most appropriate pricing
arrangement for your contract.
32
The Logic Tree!
33
Three Statements of Work –
What Pricing Type Shall We Choose?
• Fish & Bad-Boy Finders LLC
• Desert Rat Communications, Inc.
• Z-Pinchie Consolidated
34
Summary
• Initial steps to remember:
• Discuss requirements with the customer & compare to the SOW,
revising as necessary
• Review the pricing types, and consider the pros & cons of each.
• Pitfalls:
• Avoid cost-type and T&M/LH if contractor has unsophisticated
accounting system.
• Avoid setting up Contractor for failure.
(using FFP when not appropriate)
• Award / Incentive Fees = High Admin costs
• Remember: Choosing Wisely Reduces Risks
and may save you potentially significant costs!
35
Summary
• Practical approaches are in the briefing on the website,
including the Logic Tree, and the Comparison of Major
Contract Types (a.k.a. Eye Chart), courtesy of Defense
Procurement & Acquisition Policy-Contract Pricing
Reference Guide.
• Questions?
36