Infor mative gu i des on i n du s t r y bes t pr ac t ic e s Creating a Win-Win Scenario through Supplier Scheduling Tom Strohl – Oliver Wight Americas Inspiring Business Excellence It was Monday morning, and Doug sat at his desk staring blankly at his computer screen displaying today’s raw material shortage list or the “Hot List,” as it was called in his company. Of course, “Hot” was a relative term relating to who was screaming the loudest; so the list ultimately had to be separated into subcategories using descriptive phrases such as “red-hot,” “boiling hot,” and Doug’s least favorite, “thermonuclear-hot.” 2 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING Next to his terminal was a computer That, along with countless requests printout of past-due orders which to delay or cancel purchase orders were not needed and which nobody (PO) already released, was having a seemed to have any questions about. negative effect on his relationships He looked over at his inbox and saw with his suppliers. They were becom- that it was full again with new requisitions he had received from his planners the previous day. He still needed to approve and generate new purchase orders for them, but wondered quietly to himself which list “ Your suppliers already know your company is incompetent. Why continue to prove it to them? each one would ultimately land on after he placed the order. He could not escape the feeling that his title of Director of Purchasing should probably be changed to Chief Expediting and Paper Shuffling Officer. He was dreading the rest of his day as he dreaded most days; he knew what was coming. His morning would be filled with calls to suppliers requesting that they move out or cancel orders he had already placed and placing new orders for other materials that were needed immediately. The number of orders expedited inside the suppliers’ lead times has been increasing steadily for several months. CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 3 ” “ Creation of valid plans and the application of supplier scheduling techniques will change Doug’s life and significantly improve his company’s bottom line. ” ing less willing to meet his ever-changing needs. He knew his suppliers were now placating him by accepting his order and giving him a promise date that met his request, but for the past several months, they had been consistently delivering late. Their behavior was making his life miserable; the unmet expectations were destroying his credibility with his peers and with executive management. Later that day, he had been scheduled to meet with the production manager and the financial controller. He knew the production manager would ask why he didn’t have the materials he needed to support his production schedule. The controller would ask why raw material inventories were so high and what steps was he taking to reduce them. The irony of the conflicting interests of the two functional leaders was not lost on him. Unfortunately, Doug’s plight is all too familiar; it is repeated every day in far too many companies. Fortunately, there is a way out of this chaos. Creation of valid plans and the application of supplier scheduling techniques will change Doug’s life and significantly improve his company’s bottom line. If Doug’s situation seems similar to yours, these techniques will change your life, too. VALID PLANS Before you attempt to provide long-range plans to your suppliers, you’ll need to get your own house in order, namely, by creating valid plans and proving that you can actually execute those plans predictably. Communicating long-range plans to your suppliers in the absence of valid supply plans is ill-advised and will do more harm than good to your supplier relationships and material costs. Communication of raw material plans that turn out to be unreliable creates excessive disruptions throughout the end-to-end supply chain and undermines credibility with your suppliers. Suppliers often take the full brunt of supply chain disruptions, much like the unfortunate last person in a children’s game of “crack-the-whip.” In the heat of expediting to respond 4 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING to last-minute production schedule changes, too little regard is paid to the added costs and long-term damage done to supplier relationships. Those relationships soon become adversarial to the detriment of both parties. In valid plans “ For to exist, there must be alignment between aggregate and detailed plans. this context, a colleague of mine once summed it up nicely by saying, “Your suppliers already know your company is incompetent. Why continue to prove it to them?” ” Let’s start at the beginning. For valid plans to exist, there must be alignment between aggregate and detailed plans. That alignment is created through multiple levels of planning which are reviewed and updated with the latest view of the business each month (see Figure 1). At the top of the monthly planning cycle chart below, forward-looking, aggregate Figure 1. Planning and Scheduling Processes - Monthly Cycle Integrated Business Planning Product Management Review Demand Review Supply Review Integrated Reconciliation Management Business Review Senior Team Horizon = minimum of 24 months; Focus months 4+; Strategic Planning: Supply - Demand - Production Weekly Planning Review Weekly Planning Review Weekly Planning Review Weekly Planning Review Demand Planners, Supply Planners, Production Planners Horizon = 1-4 weeks & 2 months; Focus months 1-3; Tactical Scheduling Daily Planning Meeting Daily Planning Meeting Daily Planning Meeting Daily Planning Meeting Daily Planning Meeting Daily Planning Meeting Daily Planning Meeting Supervisors, Team Leaders, Operators, Suppliers Horizon = 3-4 days; Focus days; Here & now CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 5 supply plans, looking out a minimum the supply organization. The supply Review (MBR), the culmination of of a rolling 24 months, are devel- organization analyzes the uncon- the month-long Integrated Business oped as an output of Integrated Busi- strained request for product against Planning process. It is during that ness Planning (IBP). The Integrated rough-cut capacity and inventory to meeting that Product, Demand, Supply, Business Planning process is shown create an aggregate Supply Plan. and Financial Plans are approved, and in the top portion of Figure 2. Following financial analysis and recon- decisions are made to resolve issues ciliation of all three plans, analysis of and ensure alignment with strategic The output of the Product Manage- potential gaps to the business strategy, plans and business commitments. ment Review and Demand Review business commitments, and con- is a time-phased request for prod- sideration of any resulting issues, the Following approval of valid, aggre- uct expressed in unit volume for resulting plans and recommendations gate Demand and Supply Plans in the each agreed-upon product family or are brought to senior management MBR, the master supply scheduler subfamily that is communicated to during the Management Business begins the process of disaggregating Figure 2. Integrated Business Model Strategic Alignment Enabling Processes 6 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING Aggregate Planning Detail Planning the aggregate family and subfamily exceed 95 percent, the ERP system Production Plan into detailed SKU will be supportive of effective Master production schedules, normally over Scheduling, Material Planning, and a three- to six-month planning horizon, Capacity Planning processes. It is ensuring these detailed schedules are commonly understood that 70 to 80 aggregated to the family Production percent of ERP implementations fail Plan and are also valid; that is, the to deliver expected benefits. The root product is needed, and the neces- cause of those failures is quite often sary production resources are, or will invalid master data. be, available. This translation of the aggregate to detailed plan occurs at Effective Master Supply Planning and the SKU level and is presented in daily Scheduling is also enabled by daily (near-term horizon), weekly, and monthly and weekly production schedules (longer-term horizon) time buckets that provide detailed execution plans balanced against detailed capacity to the shop floor and to each work and inventory objectives. location. These plans are typically presented in daily buckets by Work Underpinning Master Supply Planning Location at the SKU level of detail and Scheduling within an Enterprise looking out one to three weeks. Vari- Resource Planning (ERP) system is ances to plan at the detailed level a vast array of planning master data are communicated back up to Supply that must be maintained and audited and Demand planners so that plans regularly to ensure accuracy. If they can be modified to ensure consistent are not accurate, no plan will be valid, alignment of all functional activities. and the company will be in a continuous state of chaos. These critical The Master Supply Schedule is “ex- planning elements within the ERP ploded” through Bills of Material and system encompass Item Masters, Routings to develop a view of materials Bills of Material, Routings, and Work and capacity requirements needed to Location files. support the Master Supply Schedule and, in turn, the aggregate Production When Planning Master Data and and Inventory Plans approved in the Inventory Record Accuracy regularly MBR. Given accurate Planning Master CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 7 Data, the ERP system will produce from the Master Supply Schedule recommended Material Requirement Plans (MRP) and Capacity Requirement Plans (CRP). The plans recommended by the system, particularly those within the cumulative lead time, are subject to review by a planner who accepts or rejects the system recommendations based upon their knowledge and experience and is accountable for these decisions. These plans define a time-phased projection of required materials and capacity (labor and equipment) over the full planning horizon. For now, let’s focus on material needs. Once the Master Supply Plan has “ Supplier Scheduling offers an opportunity to eliminate the waste of unnecessary paperwork and the cost of reactive scheduling for your suppliers. ” stabilized and performance consistently exceeds 95 percent, material requirements are now viewed as credible plans that are aligned, updated, and formally reviewed each month. Confidence in the reliability and predictability of long-range material requirements conveyed to suppliers increases and becomes the foundation for Supplier Schedules. With increased credibility comes improved on-time delivery performance, reduction of quality issues, and improved supplier relationships. SUPPLIER SCHEDULING Companies often use cumbersome purchase requisitions and purchase orders to release raw material orders. Planners identify the need for a raw material and fill out a purchase requisition for that material order. The requisition is passed to the buyer for approval. That buyer then creates a purchase order defining the terms, conditions, quantities, and timing for procurement of that material. These purchase orders are contracts obligating each party and are created for each material order. These requisitions and purchase orders must be modified each time the schedule is changed. This resulting mountain of paperwork and bureaucracy is costly, inefficient, non-value added, and not even required by external accounting audit firms. Worse yet, this approach to material acquisition provides suppliers absolutely no forward visibility and, thereby, ensures they will continue to operate reactively 8 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING and inefficiently—read that as providing you with unnecessarily high-cost materials. Why are purchased requisitions and purchase orders needed? When you consider that the business strategy has been approved by senior management; the annual operating plan (or budget) based upon documented demand, supply, and financial plans has been approved; and the updated Integrated Business Planning process has enabled the leadership team to formally review and approve updated sales, production, inventory, and financial plans covering at least a rolling 24 months by family each month over a 24-month horizon, there requisitions and “ These purchase orders must be modified each time the schedule is changed. ” is simply no need to create purchase requisitions and purchase orders that simply support what has already been approved. Issuing a Supplier Schedule is a far better approach that will better serve you and your suppliers. Supplier Scheduling offers an opportunity to eliminate the waste of unnecessary paperwork and the cost of reactive scheduling for your suppliers. Long-term contracts or agreements, defining the terms and conditions around which the two companies will do business, are negotiated by the procurement organization with the supplier. The contracts, or agreements, are based upon the aggregate volumes agreed to by the Leadership Team in the MBR and the detailed, time-phased requirements as recommended by the ERP system and approved by the master supply schedulers and material planners. CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 9 Table 1.* Example of Supplier Schedule Jones Company supplier schedule for: Smith, Inc. - Week of 02/01/xx Supplier Scheduler: AB Buyer: CD Firm Zone: first 4 weeks Material Zone: next 6 weeks Requirements F Item # Description 13579 Plate 24680 4257 77543 Panel Tube Frame 1-Feb F 2-Feb F 3-Feb F 4-Feb F F 5-Feb 8-Feb F 9-Feb Qty: 100 PO#: B1146 F F F F F F F F F F F F F M M M Next Next 10-Feb 11-Feb 12-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb Wk 3/1 Wk 3/8 4 Wks 12 Wks Qty: 20 20 20 20 PO#: B1122 B1146 B1180 B1203 20 Qty: 300 200 PO#: B1122 B1203 Qty: 40 PO#: B1180 100 100 300 20 80 340 1100 3500 40 *Adapted from Purchasing in the 21st Century, Second Edition, John E. Schorr Under those terms and conditions, This approach reduces or eliminates tive when your own house is in order schedules are issued each week by much of the clerical paperwork as- and your plans are reliable (see Table 1). the supplier scheduler providing time- sociated with the purchase requisition/ phased quantities, by item, with re- purchase order management and frees The Supplier Schedule depicted in quired due dates. Because MRP and up significant time for the buyer to fo- Table 1 is for all four material items the resulting Supplier Schedules are cus on the more value-added activities being acquired from one supplier, now based upon valid data, the sys- of sourcing strategies, quality improve- Smith, Inc. The specific materials tem output for material requirements ments, and collaboration efforts with addressed by the Supplier Schedule is simply the result of a mathematical suppliers for gaining cost, product, are listed in the first column on the left. calculation within the ERP system. and competitive advantages. Time-phased volume requirements for This virtually eliminates the need for each item are shown by time period. redundant purchase requisition and The format and content of a supplier purchase order review and approval. schedule is fairly simple but very effec- 10 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING In this example, the Firm and Material Zones are clearly identified twice lows the supplier to track requirements on the Supplier Schedule; first, in over time as they begin to move into the header and also above each of the Material and Firm Zones. Forward the time periods, with ‘F’ defining the visibility and increased plan stability Firm Zone and ‘M’ defining the Material allow the supplier to optimize its pro- Zone. The Firm Zone is generally con- duction schedule, thus significantly sistent with the length of the supplier’s reducing overall supplier lead time cycle for producing its finished prod- and production costs. ucts. The Material Zone is generally consistent with the supplier’s lead time Companies operating at best practice to acquire the materials needed to performance levels modify less than produce each product. These zones five percent of its supplier orders are agreed upon between the buyer inside the Firm Zone. This level of and supplier during contract nego- schedule stability enables the supplier tiations. to optimize its operating costs, and it also enables the supplier to respond In the example above, the Firm more effectively when the rare change Zone is defined as 4 weeks and is is required inside the Firm Zone. presented in daily requirements for each material. The Material Zone is The level of commitment to the plan defined as the subsequent 6 weeks. is also negotiated and agreed upon Requirements over the next 12 weeks, in contract negotiations. Within the often referred to as the Open Zone, are firm zone, authorization is given to provided for information purposes only the supplier to produce the finished to allow the supplier to see anticipated, product. The company is making long-range material requirements. a commitment to the supplier to The length of the Open Zone should purchase that item, and the supplier also be agreed in contract negotiations is making a commitment to deliver it and could cover a much longer time on time. horizon if desired by the supplier. While there is no longer a need for As stated previously, the Supplier written purchase orders, internal Schedule is updated weekly and al- company procedure may still require CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 11 “ In preparation to implement Supplier Schedules, it is important to educate your suppliers on the new process, but not until you have demonstrated stability in your own master supply schedules and material plans. ” a PO number be assigned to each release to properly track the material. Note that PO numbers are assigned for each requirement in the Firm Zone. This number is typically assigned automatically by the ERP system and requires no action by the material planners or supplier schedulers other than releasing that order to the supplier. Generally, within the Material Zone, no POs are assigned by the system. However, because the requirement appears in the Material Zone of the supplier schedule, the company has authorized the supplier to secure the raw materials necessary to make the scheduled item. It is not uncommon for a company to negotiate agreement to pay for any long lead-time component used in no other product produced by the supplier even when, due to product design or market changes, that material is no longer required. There is no financial commitment to anticipated requirements appearing in the Open Zone. These requirements are provided for the supplier’s long-range volume and capacity planning. In preparation to implement Supplier Schedules, it is important to educate your suppliers on the new process, but not until you have demonstrated stability in your own master supply schedules and material plans. Best practice is to bring in small groups of key suppliers (follow the 80/20 rule) and formally educate them on the details of the process, your commitment to plan stability, and your expectations of the suppliers. This is often done off site to minimize disruptions. The sessions should be kicked off by the general manager of the business unit or production facility. This formal launch provides the supplier’s representatives assurance that the change is important and that the process has the full support and commitment of senior management. 12 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING Table 2.* Key Performance Measures Performance Measurements: Target: Master Data File Accuracy > 95% Item Masters > 95% Bills of Material > 98% Routing Files > 95% Work Locations > 95% Inventory Record Accuracy < 5% Master Schedule Changes in the Firm Zone < 5% Orders Released with Less-Than-Planned Lead Time < 5% Supplier Delivery Performance > 95% Supplier Quality Performance > 95% Recall, as in Doug’s situation, your relationships with key suppliers have likely been strained, and your credibility has been damaged. Despite that, suppliers, by their very nature, want to support their customers to the best of their ability. Like you, they cannot afford to lose a customer. The formal launch session affords an opportunity to acknowledge your sins of the past and start anew on a fresh path of collaboration and partnership. This is also a good time to start the conversation about working collaboratively on cost reduction initiatives and on sharing in the future financial benefits realized through improved forward visibility and schedule stability, defining a win-win scenario to benefit both parties. “ Gaining control and deploying valid plans provide a solid foundation from which to deploy Supplier Schedules, improve supplier relationships, and reduce costs. ” Lastly, it is important to support the process with robust performance measures. CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 13 Having the ability to understand how both parties are performing helps drive continuous improvement of organization behaviors and results. Table 2 above identifies a list of essential measures and minimum performance levels needed to ensure success. SUMMARY Common symptoms begin to emerge when plans are invalid. Inventories increase even while customer service decreases. Inventories are of the wrong items while items that are needed are in short supply and often are at the wrong place. The unneeded items begin to age and become obsolete, severely damaging the bottom line, often causing financial surprises at the end of the quarter or end of the year. Buyers find that they are overwhelmed with past-due orders for items not needed and are required to expedite items that are needed tomorrow. As buyers routinely place orders with less-than-agreed-to lead times, the supplier is faced with a choice of whether to disrupt its own production schedule or to simply miss the delivery date and allow the backorder to occur. That disruptive influence ripples across the entire extended end-to-end supply chain causing chaos and deepening adversarial relationships. 14 CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING Supplier Scheduling can change everything. The benefits of implementing Supplier Scheduling include: • Reduced/eliminated past-due orders and hot lists “ • Increased customer service • Improved supplier delivery performance • Reduced supplier lead times • Improved supplier relations • Lowered inventories • Lower material costs • Minimized expediting costs • Reduced paperwork and non-value added activities • Improved teamwork in joint supply chain cost reduction projects • Improved quality of work life throughout the entire organization Gaining control and deploying valid plans provide a solid foundation The ability to provide suppliers with forward visibility of material needs as well as improved schedule stability creates a win-win scenario for both the company and the supplier. ” from which to deploy Supplier Schedules, improve supplier relationships, and reduce costs. The ability to provide suppliers with forward visibility of material needs as well as improved schedule stability creates a win-win scenario for both the company and the supplier. CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 15 REFERENCES BOOKS Purchasing in the 21st Century, A Guide to State-of-the-Art Techniques and Strategies; John Schorr Master Scheduling, A Practical Guide to Competitive Manufacturing; John Proud The Transition from Sales and Operations Planning to Integrated Business Planning – Moving from Fundamental Demand and Supply Balancing to Strategic Management; George Palmatier with Colleen Crum WHITE PAPERS Integrated Business Planning/Sales & Operations Planning – An Executive-Level Synopsis; George Palmatier Integrated Planning and Control – The Lost Art of Managing the Supply Chain; Jim Correll Managing the Extended Supply Chain – An Introduction; Ron Ireland Visit the Oliver Wight Americas' website https://www.oliverwight-americas.com/ to buy any of these books or to read any of these white papers. CREATING A WIN-WIN SCENARIO THROUGH SUPPLIER SCHEDULING 16 Infor mative gu i des on i n du s t r y bes t pr ac t ic e s ABOUT THE AUTHOR Tom Strohl, an Oliver Wight Americas principal, is a consultant, coach, and educator providing companies with guidance in Operations Planning and Control and Integrated Business Planning. In a career spanning more than 30 years, Tom has developed an acute awareness of the need to bring formality and process to both the business systems and the human capital needed to run those systems. He views the readiness of employees to embrace fundamental change in any business process as a critical success factor for sustained excellence. CONTRIBUTORS The author gratefully acknowledges the feedback and insights of Dennis Groves and Eric Deutsch shared for this article. Oliver Wight - leading business improvement specialists who educate, coach, and mentor people to lead and sustain change on the journey to business excellence and outstanding business perfomance. Oliver Wight Americas, Inc Asia/Pacific PO Box 368, 292 Main Street New London, New Hampshire 03257, USA 131 Martin Street Brighton, VIC 3186, Australia Telephone: 1.800.258.3862 1.603.526.5800 Europe, Africa & Middle East Facsimile: 1.603.526.5809 The Willows The Steadings Business Centre Maisemore, Gloucester GL2 8EY, UK [email protected] www.oliverwight-americas.com © Oliver Wight International Inspiring Business Excellence
© Copyright 2026 Paperzz