ELECTRICAL SAFETY INSPECTION REPORT ABANTI COLOR TEX LTD. Shashongaon, Enayetnagar, Fatullah, Narayanganj-1400, Bangladesh. Factory List: 1. Abanti Color Tex Ltd. Inspected by: Pema Wangdi Report Generated by: Pema Wangdi Inspected on July 07, 2014 SUMMARY The Abanti Color Tex Ltd. factory is established in its own three different buildings. The buildings 1, 2 and 3 are eleven storied (G+10), 10- storied (G+9) and 10-storied (G+6) respectively. The Building 1 was initially approved for construction up to eleven stories; however, it was initially only constructed to 4th floor in 2000. Later in 2002 the extension work began and was completed till 11th floor in 2009. The factory first began production in 2001.The construction of Building 2 started in 2009 and was completed in 2012, Building 3 was started in 2010 and completed in 2013. During the time of inspection, the factory accommodated a total of about 6,420 workers on a regular basis. The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The purpose of the survey was to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial electrical safety inspection was limited to the review and identification of major electrical safety issues. The inspection did not include identification of minor deficiencies, which will be further addressed as part of follow-up inspections. Table below summarizes the major electrical safety issues identified during the inspection. Recommendations have been provided to address each issue. An implementation schedule shall be developed by the factory to remediate each of the findings. The specific timing of improvements, including any requested extensions due to design / installation constraints, shall be submitted to the Accord for approval. Abanti Color Tex Ltd. Page 2 of 13 FINDINGS AND RECOMMENDATION Finding No. E- 1 Category: TRANSFORMER Finding: Transformer guarded with wire mesh fencing. (Typical) Recommendation: Construct a separate room for the transformer by constructing barrier (brick) walls (fire rated wall) up to the ceiling; the minimum area of the transformer room should be 10-13 sq. m (according to BNBC 2006, Section-2.6.3). Remediation Timeframe: 3 Months The transformer in the electrical substation 1. (Typical) Finding No. E- 2 Category: CABLE & CABLE SUPPORTS Finding: Cables laid randomly in open (without cover) cable trench. Recommendation: Cables in trench must be supported on trays inside trench and should be protected with covers with ample strength and rigidity. The cable trench in the transformer room. Remediation Timeframe: 3 Months Abanti Color Tex Ltd. Page 3 of 13 Finding No. E- 3 Category: TRANSFORMER ROOM Finding: Excessive HT cable with acute bend not supported and protected; The HT and LT cables are laid in the same trench without separation. Recommendation: Install separate cable tray with protective cover for HT and LT cables; Latch the HT cable properly avoiding acute bend. Cables trench in the transformer room. Remediation Timeframe: 3 Months Finding No. E- 4 Category: TRANSFORMER ROOM Finding: Arching horn not installed at transformer HT side. Recommendation: Arching horn should be installed at the HT bushing (may consult the servicing/supplier company). Arching horn should be installed at the HT bushing (may consult the servicing/supplier company). Remediation Timeframe: 3 Months Finding No. The power transformer in substation 1. E- 5 Category: TRANSFORMER ROOM Finding: Silica gel in transformer breather, discolored. Oil cup below transformer breather is empty. (Typical) Recommendation: Replace silica gel and must include in routine maintenance to check and maintain. Breather oil cup must be filled with transformer oil to required level as instructed by the manufacturer. The power transformer breather. (Typical) Remediation Timeframe: 3 Months Abanti Color Tex Ltd. Page 4 of 13 Finding No. E- 6 Category: CABLE & CABLE SUPPORTS Finding: Cables/wires passing through floor are not protected /supported and remaining gaps around the cable/wiring are not sealed. (Typical) Recommendation: Cables/wirings passing through floor must be protected/supported installing covered cable tray/raceway/rigid pipes and remaining gaps must be sealed with fire resistant materials. Cable tray/raceway shall be installed for the support of the cable throughout its length. The service cables from the electrical room towards the upper production floors. (Typical) Remediation Timeframe: 3 Months Finding No. E- 7 Category: DISTRIBUTION & PANELS Finding: Openings in the panel base plate. (Typical) Recommendation: Make circular hole at the top plate of panels and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. The distribution panel. (Typical) Remediation Timeframe: 3 Months Finding No. E- 8 Category: DISTRIBUTION & PANELS Finding: Phase barrier/separators between different phases are not installed. (Typical) Recommendation: Phase barriers between different phases supplied by the breaker manufacturer must be installed to avoid arc flashing. Remediation Timeframe: 1 Month Abanti Color Tex Ltd. Page 5 of 13 The distribution panel in the production floors. (Typical) Finding No. E- 9 Category: DISTRIBUTION & PANELS Finding: Openings in the top plate after the cable passage. (Typical) Recommendation: Make circular hole at the base plate/top plate of panels and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. Distribution panel in the production floor. (Typical) Remediation Timeframe: 3 Months Finding No. E- 10 Category: DISTRIBUTION & PANELS Finding: Panel base plates removed to allow cable entry. (Typical) Recommendation: Make circular hole at the base plate/top plate of panels and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. The main distribution board. (Typical) Remediation Timeframe: 3 Months Finding No. E- 11 Category: CABLE RACEWAY & DUCTS Finding: Exposed wires/cables in the production. The cables extended are not drawn in a rigid conduit. Recommendation: The extended cables, which are exposed, must be encased in a rigid conduit or a required size of cable duct/tray must be used. Remediation Timeframe: 3 Months Abanti Color Tex Ltd. Page 6 of 13 The wires/cables in the production floor. (Typical) Finding No. Category: E- 12 CABLE RACEWAY & DUCTS Finding: Power cables laid on concrete floor. Recommendation: Cables must be laid inside covered cable-tray installed on the floor or trench. The production floor in building 3. Remediation Timeframe: 3 Months Finding No. Category: E- 13 DISTRIBUTION & PANELS Finding: Multiple cables are terminated into single point of busbar. (Typical) Recommendation: Terminate each cable individually on the bus bar. Multiple cables shall not be terminated on same point of bus bar. Distribution board in the production floors. (typical) Remediation Timeframe: 3 Months Finding No. E- 14 Category: DISTRIBUTION & PANELS Finding: Cables connecting to MCCB inside panel without cable lugs. Recommendation: Cables shall be connected to terminals only by cable lugs according to cable size. Remediation Timeframe: 3 Months Abanti Color Tex Ltd. The service cable from the distribution pole. Page 7 of 13 Finding No. E- 15 Category: CABLE RACEWAY & DUCTS Finding: Cables running along the ladder are not securely fastened. Recommendation: The service cables which are not securely fastened to the ladder must be fastened at regular intervals using cable ties. Service cable for upper floors. (Building 3) Remediation Timeframe: 3 Months Finding No. E- 16 Category: CABLE RACEWAY & DUCTS Finding: Flexible PVC cable not supported. Recommendation: Replace the flexible pipe with PVC pipe to support and protect the cables. Ensure the industrial graded PVC pipe is properly clamped with saddle at a regular interval. The service cable for the main building. Remediation Timeframe: 3 Months Finding No. E- 17 Category: DISTRIBUTION & PANELS Finding: Cables entering or leaving distribution panel are not supported on tray/riser. Recommendation: Cables must be laid into a covered cable-ladder, installed on the wall to prevent any physical damages. Remediation Timeframe: 3 Months Abanti Color Tex Ltd. Cables terminated to the distribution board. (Typical) Page 8 of 13 Finding No. E- 18 Category: GENERATOR ROOM Finding: Generator panel base plates removed to allow cable entry. (Typical) Recommendation: Make circular hole at the base plate/top plate of panels and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. Generator panel. (Typical) Remediation Timeframe: 3 Months Finding No. E- 19 Category: CABLE RACEWAY & DUCTS Finding: Cables encased in flexible PVC pipe carried from one floor to another through floor not protected. Recommendation: Install covered cable tray or rigid pipe for passing cables and it should be prevailed throughout the permanent wall to protect cables insulation from damage and the remaining gaps must be sealed with fire resistant materials. Sservice line for building 3 Remediation Timeframe: 3 Months Finding No. E- 20 Category: CABLE RACEWAY & DUCTS Finding: Cables or wiring drawn in flexible PVC conduits, extended from the BBT are not supported. (Typical) Recommendation: Cables extended from BBT in flexible PVC conduit must be supported in covered cable trays. Remediation Timeframe: 3 Months Abanti Color Tex Ltd. Cables in flexible PVC conduits not supported (Typical) Page 9 of 13 Finding No. E- 21 Category: CABLE RACEWAY & DUCTS Finding: Cables from Bus Bar Trunking (BBT) in electrical shaft, extended to different levels (floors) are not supported. (Typical). Recommendation: Cables extended from BBT breaker to distribution boards at various floors must be supported on trays/risers or rigid pipes may be used for passing through the slab. Flexible conduit must not be used for passing through slab & long point wiring (except for special wirings). Cable terminated from the BBT towards the distribution panels.(Typical) Remediation Timeframe: 3 Months Finding No. E- 22 Category: GENERATOR ROOM Finding: Termination of body earthing is not properly done. Recommendation: Generator must be connected to earth securely at least at two points. Ensure the earthing cable size is not less than 35sq.mm. The termination must be done using cable lugs. The generator frame earth. Remediation Timeframe: 1 Month Finding No. E- 23 Category: GENERATOR ROOM Finding: Storage in generator room. Recommendation: Remove all the combustible materials stored inside the Generator room. Inside the gas generator room. Remediation Timeframe: Immediately Abanti Color Tex Ltd. Page 10 of 13 Finding No. E- 24 Category: BOILER & COMPRESSOR ROOM Finding: Power cables of compressor are carried through flexible PVC pipe and it is not supported. (Typical). Recommendation: The compressor power cables must be supported in cable tray/riser or the flexible PVC duct must be replaced with a rigid conduit to prevent cables from physical damage. Remediation Timeframe: 3 Months Finding No. The unsupported compressor power cables. (Typical) E- 25 Category: DISTRIBUTION & PANELS Finding: Multiple cables inserted into a single lug. (Typical) Recommendation: Use proper sized cable lugs for each single cable and punches them by proper hand puncher or hydraulic puncher to avoid loose connection. Enlarge the earth bus-bar size according to the capacity of the panel and make more holes. Use single point (hole) of bus bar to terminate each single cable (lugs). The distribution panel in the production floor Remediation Timeframe: 1 Months Finding No. E- 26 Category: CABLE RACEWAY & DUCTS Finding: Electrical room used as maintenance room. Recommendation: The maintenance room must be relocated. The electrical room must not be used as maintenance room. The distribution board in a production floor. Remediation Timeframe: 1 Month Abanti Color Tex Ltd. Page 11 of 13 Finding No. E- 27 Category: DISTRIBUTION & PANELS Finding: Gland holes in cable base plates left open. (Typical) Recommendation: Provide cable gland same as the cable size at the cable entry and exit so that the cables are not stressed on the sharp edges of the entry and exit hole of the panel board. Unused gland holes in base plates cover must be sealed with proper way. Panels in the production floor (Typical) Remediation Timeframe: 1 Month Finding No. E- 28 Category: DISTRIBUTION & PANELS Finding: Panel doors not connected with earth bond. (Typical) Recommendation: Provide earth connection for body and doors of metallic distribution boards using green cables preferably braid so that the metallic door remains at zero potential all the time. Panels in the production floor (Typical) Remediation Timeframe: 1 Month Finding No. E- 29 Category: EQUIPEMENT & MACHINE Finding: Large exhaust fans in production floors are directly controlled by the MCB. (Typical) Recommendation: Large exhaust fans must be connected through control device such that it will not restart automatically when power is restored. Remediation Timeframe: 1 Month Abanti Color Tex Ltd. The exhaust fan in the production floors. Page 12 of 13 Finding No. E- 30 Category: WIRING Finding: Cable ducts covered by the flexible PVC duct. Recommendation: Disconnect the electric supply to the duct and provide cover made of non-combustible material preferably metal on the duct to prevent ingression of dust and debris. The cable trays in the production floor. Remediation Timeframe: 3 Months Finding No. E- 31 Category: CABLE RACEWAY & DUCTS Finding: The flexible PVC conduit is supported against the overfilled aluminum duct. (Typical). Recommendation: The cable within the flexible PVC conduit may be laid in the aluminum cable duct. If the aluminum duct do not accommodate all the cables it may be replaced by a bigger cable duct. The flexible PVC conduit in the production floor. Remediation Timeframe: 3 Months Finding No. E- 32 Category: DISTRIBUTION & PANELS Finding: Multiple cables terminating to MCCB in panel. (Typical) Recommendation: Multiple cables connecting at a MCCB terminal must be removed. Individual circuit breaker must be used for each load according to the respective cable-size. Remediation Timeframe: 1 Month Abanti Color Tex Ltd. The distribution board in the production floor. Page 13 of 13
© Copyright 2026 Paperzz