Design of a Cross Drainage Structure for D 20 Distributary in A Tadipudi Lift Irrigation Scheme Ch. Apparao,Rishu kumar,N.Sambasivarao College of Agricultural Engineering, Bapatla Acharya N.G. Ranga Agricultural University ABSTRACT The present study a methodology was developed for the Design of Well Syphon, a cross drainage structure for D 20 Distributary in A Tadipudi Lift Irrigation Scheme(TLIS) on the river Godavari under Jalayagnam project. The objectives of this study was to i) to develop methodology for the design of cross drainage work for canal to cross two drains and a highway ii) to design well siphon system as an appropriate cross drainage structure The maximum flood discharge for the drains was estimated by using Ryve’s formula. The maximum scour depth was estimated to be 2.22 m. The structural stability of well was estimated by considering two conditions (i) when the well was full, and (ii) when the well is empty (worst condition) with the help of Lame’s analogy. The maximum compressive stress developed in concrete structure was 15.526 t/m2 which was less than the maximum compressive strength of concrete. The maximum compressive stress developed in the foundation of well was 7.85 t/m2 which is less than the bearing capacity of soil. The maximum compressive stress developed in profile wall was estimated as 18.913 t/m2 which is less than the compressive stress of concrete. Key words: Well Syphon, lift irrigation, cross drainage structure 1.INTRODUCTION Investment in irrigation sector has led not only to a substantial increase in agricultural growth, income and development, but also to an increase in the gross National product. About 40% of the Andhra Pradesh state’s gross cropped area is irrigated, and irrigation contribution to State agricultural production is about 60%. The Government has, therefore, given highest priority for the completion of on-going irrigation projects. For this purpose, in the year 1996 Government has evolved a threefold strategy namely; (i) to achieve maximum irrigation by completing on-going irrigation projects; (ii) to rehabilitate and modernize existing irrigation schemes to bridge the gap ayacut in tail-end area; and (iii) to hand over the management and maintenance of all irrigation schemes in the State to farmers’ organizations to ensure reliable and timely supply of water. Twenty-six major and medium irrigation projects costing Rs. 46,000 crores (Revised to Rs. 67, 823 crores) are taken up for execution. Tadipudi Lift Irrigation Scheme (TLIS) on the river Godavari is an on-going project under Jalayagnam (Fig. 1) that has been planned to utilize 14.47 TMC s of Godavari river water to irrigate 2,06,572 acres. 80.45 KM TADIPUDI LIFT IRRIGATION SCHEME L1 KM 5 GODAVARI RIVER L2 KM 15.90 L3 KM 33.50 L4 KM 80 0.00 KM Lift Height Pumps each Discharge Agreement Date Present Stage Length of the canal Ayacut Power required Tender Amount 1st Pump House, Pressure Mains, Cistern : Progress 2nd Pump House, Pressure Mains : Progress Main Canal : Progress 2nd Lift Pumps, Pump Houses, Pres. Mains : Designs &Drawings Under Approval Utilisation : 14.40 TMC Ayacut : 2,06,600 Acres PUMP HOUSE DELIVERY CISTERN MAIN : 27.00 Mts : 6 Nos. of 4,000 HP : : : : : : : 700 Cusecs. 23-1-2004 work in progress 80.45 Km. 2,06,572 Acres 28 MW Rs. 302.64 Cr. CANAL PSC PRESSURE MAINS (2 x 6 Nos.) L1 KM 5 L2 KM 15.90 L3 KM 33.50 L4 KM 80 PROGRESS 4 Nos. of 3,000 HP each For each pump house (2 Pump houses) 80.45 KM TADIPUDI (V) (WEST GODAVARI (DT)) 0.00 KM GODAVARI RIVER Fig. 1: Tadapudi Lift Irrigation Scheme 2. MATERIALS AND METHODS The study area (Fig.2) was located near national highway joining Tadepalligudem and Nallajerla . it was about 6 km from Tadepalligudem. Fig. 2 : Location of Cross drainage structure on D20 distributary 2.1 Collection of Hydraulic Data The following hydraulic data was collected for the study a. Canal 1. Full supply discharge 2. Bed width 3. Full supply depth 4. Bed level 5. Bed slope 6. Full supply level 7. Top of bank level 8. Cross section of canal 9. Nature of bed material and value of Manning’s coefficient (n) 10. Velocity in canal 11. Scour depth b. Drainage channel 1. Extent and nature of drainage area ( catchment area ) 2. Maximum flood level 3. Silt factor 4. Allowable afflux in view of water spread, upstream of the proposed work 5. Reported or observed scour depth for any nearby structure on the same drainage channel 6. Bearing capacity of the foundation strata c. Structural Data 1. Empty self-weight of the structure 2. Surcharge loads, if any 3. Full internal water pressure 4. Soil reaction and up-lift pressure 5. Earth loads on sides 2.2 Criteria for Selection of Particular Cross Drainage Work Table 1: .................................................. Particulars Bed level, m Water level, m Discharge, cumecs Drain 19.290 20.290 (HFL) 5.73 Canal 19.665 20.045 (FSL) 0.113 Since, HFL was at higher level than FSL as well as the discharge from canal was very less compare to drain. Therefore, the canal bed was depressed and syphoned. Since, canal was passing two drains and a national highway, therefore, well syphon was proposed. 2.3 Estimation of maximum flood discharge and High Flood Level(HFL) Maximum flood discharge (MFD) was estimated by using Rvye’s formula. 𝑄 = 𝐶₁𝐴₁2/3 ...(1) Where, Q = Maximum flood discharge in cusecs and A₁ is in square miles. 𝐶₁= 750 (Adopted from I & CAD Dept., Govt. of AP) 2.4 Design of drainage channel Drainage channel was designed based on Kennedy theory with Manning’s equation. The estimation of various parameters like drain area, hydraulic radius and wetted perimeter were given below. i. Calculation of area of drain Area, A= (B+ZD) D, ...(2) Where, A= Area (m2), B= Base width (m), D= Drain depth( m), Z= Side Slope ii. Calculation of Perimeter: Perimeter, P= B+ 2D√ (1+Z²) ...(3) Where, P= Perimeter (m), B= Base width (m), D= Drain depth (m), Z= Side Slope iii. Calculation of Hydraulic Radius: Hydraulic Radius, R=A/P ...(4) Where, R= Hydraulic radius (m), A= Area (m2), P= Perimeter in meter iv. Calculation of Velocity: Velocity, v= Q/A ...(5) Where, v= Velocity in m/s, Q= Discharge in cumec, A= Area in square meter v. Calculation of Bed Slope: Bed Slope, S= (nv/R⅔)² ...(6) Where, n= Manning’s constant, v= Velocity in m/s, R= Hydraulic radius in meter 2.5 Determination of scour depth Scour depth was estimated by using Lacey’s formula . 𝑄2 1⁄ 3 𝑑 = 1.34 ( 𝑓 ) ...(7) Where, d= normal depth of scour in meters below the flood level corresponding to the value of Q adopted Q= the discharge adopted for design, in cubic meter per second per meter width f= the silt factor for a representative sample of the bed material; =1.76√m where m is the mean diameter in millimetre = 1.0 for silty soils To calculate maximum scour depth, normal scour depth was calculated by using Lacey’s formula and was multiplied by a factor of safety 1.5. 2.6 Head loss through syphon barrel Head loss through barrel was calculated by using Unwin’s formula. 𝐿 𝑉2 𝑅 2𝑔 ℎ = (1 + 𝑓1 + 𝑓2 ) − 𝑉𝑎2 2𝑔 ...(8) Where, h= head loss through the syphon, in m L= length of barrel, in m R= hydraulic mean radius of the barrel, in m V= velocity of flow through the barrel, in m/s 𝑉𝑎 = velocity of approach, and is generally neglected 𝑓1= coefficient of head loss at entry = 0.505 for unshaped mouth= 0.08 for bell mouth 0.3𝑏 𝑓2 = 𝑎 (1 + ) = coefficient for the loss of head by the friction through the syphon barrel, 𝑅 a and b are constants. The constants 𝑎= 0.00316 and b = 0.1 were assumed. 2.7 Intensity of active earth pressure Intensity of active earth pressure was estimated by using Rankine’s formula. 𝑊𝐻 𝑃𝑎 = 2 1−sin ∅ 𝑥 1+sin ∅ where ...(9) Where, 𝑃𝑎 = Earth Pressure, t/m2, 𝑊= Unit Weight of Saturated Soil, t/m3,𝐻= Height of Backfill, m ∅= Angle of repose of the soil= 29˚ (Anonymous, 1998) 2.8 Design of inlet and outlet well: i. Thickness of well: The thickness of well was estimated by using anology of Lame’s theorem of thick cylinder. 𝑏 𝑃𝑥 = 𝑥2 −𝑎 ...(10) Where, 𝑃𝑥 = Intensity of Pressure at a distance x. a and b are arbitrary constants. 𝑏 𝜎𝑥 = 𝑥2 +𝑎 ...(11) Where, 𝜎𝑥 = Intensity of Hoop Stress induced ii. Stress developed in well The stress developed in well was computed by estimating loads acting of the structure, lever arm, eccentricity and maximum and minimum stress developed in concrete and foundation soil of well. a. Lever arm Lever arm was estimated by using the following formula. 𝑍= ∑𝑀 ...(12) ∑𝑉 Where, ∑𝑀= Total moment, ∑𝑉= Total load b. Eccentricity To calculate eccentricity the following formula is used. 𝑏 𝑒 =2−𝑍 ...(13) Where, b= Base width, Z= Lever arm c. Stress developed at base point To calculate maximum stress developed at base point the following formula is used. 𝜎= ∑V 𝑏 Where, (1 ± 6𝑒 𝑏 ) ...(14) 𝜎= Stress at base point, ∑𝑉= Total load b= Base width, 𝑒= Eccentricity 2.9 Design of head wall To design the head wall, we have to calculate stress developed in head wall. To calculate stress developed in head wall, we need to calculate lever arm, eccentricity and maximum and minimum stress developed in concrete and foundation soil of head wall by using above formulae. 3. RESULT AND DISCUSSIONS The hydraulic particulars of the canal are given in Table.2 Table 2. Hydraulic Particulars of Canal S. NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Description Ayacut Discharge Bed Width FSD Free Board Side Slope Bed Fall Value of n Velocity Top Width of Bank CBL FSL TBL GL Unit Ac Cumec m m m m/s m m m m m Particulars @ km 6.204 629.17 0.113 0.6 0.38 0.3 1.5:1 1:2300 0.025 0.309 1.5 19.665 20.045 20.345 19.290 3.1 Hydraulic Particulars of Drain 3.1.1 Drain @ 6.204 km Bed level of the drain= 19.290 m Maximum flood depth= 1.00 m Maximum flood level of the drain= 20.290 Drain bed width= 5.00 m Estimated catchment area of the drain= 0.363 km² = 0.1399 miles² a. Estimation of maximum flood discharge C= 750 M= 0.1399 miles² From Ryves’ formula Q= 202.1187 cusecs = 5.73 cumec b. Estimation of scour depth q= 5.73/5= 1.146 cumecs/m f= Silt factor = 1.00 Therefore, 1.1462 𝑅 = 1.34( 1 )1/3= 1.467m c. Maximum Scour Depth, Rmax= 1.5R= 1.5 x 1.467= 2.21m 3.1.2 Drain @ 6.256 km Bed level of the drain= 19.345 m Maximum flood depth= 0.700 m Maximum flood level of the drain= 20.045 m Drain bed width= 0.900 m Estimated catchment area of the drain= 0.026 km² = 0.0100 miles² a.Estimation Maximum flood discharge: 0.988 cumecs Normal Scour depth (𝑅) : 1.426m Maximum Scour Depth (Rmax): 2.139m Particulars@ km 6.256 629.17 0.113 0.6 0.38 0.3 1.5:1 1:2300 0.025 0.309 1.5 19.642 20.022 20.322 19.345 b.Decision on foundation depth Scour depth for canal: 0.43 Maximum Scour Depth (Rmax):0.659 m Estimated scour depths for drain @ 6.204 km= 2.21 m Estimated scour depths for drain @ 6.204 km= 2.139 m The maximum of above three calculated scour depth is considered as the depth of foundation. Hence, the top level of the foundation should be at least 2.21m below the ground level. 3.2 Design of Syphon Barrel Discharge in Canal, Q₁ = 0.113 m³/s Velocity allowed in the Barrel, v₁= 0.6 m/s (assume, double the velocity in the channel) Cross-sectional area of Barrel, A₁= Q₁/v₁= 0.113/0.6=0.1883 m/s If d is the diameter of barrel, then (∏/4)d² = 0.1883 Or, d= 0.4898m Considering a diameter of pipe about 0.450m or 450mm. Therefore, Actual cross-sectional area of barrel, A₁´ = (∏/4) d²= (∏/4) x (0.450)²= 0.1589m² Actual velocity through barrel, v₁´= Q₁/A₁´= 0.113/0.1589= 0.711m/s Since, the velocity in barrel is almost twice the velocity in the canal. Hence, its OK. Hence, NP3 class hume pipes 450 mm ø conforming to BIS 458/2003, was selected as barrel. 3.3 Details of NP3 class hume pipe Diameter= 450 mm, Thickness= 75 mm, Length= 2.5 m, Proposed length of the barrel= 25m Hence, 10 numbers of NP3 hume pipes should be provided. 3.4 Collar dimensions Caulking space= 19mm, Minimum thickness= 35 mm, Minimum length= 200 mm 3.5 Details of the craddle bedding As per IS: 783-1985, minimum thickness of the bedding is 1/4th of pipe internal diameter. Thickness of the bedding= 0.3m, Minimum earth cushion over pipes= 0.5m Offset on either sides of pipe= 0.15m, Spacing between pipes= 0.3m 3.6 Profile wall Provide profile wall of wide= 300 mm on U/S and D/S. 3.7 Head loss through syphon L= Length of barrel= 25m V= Velocity in barrel= 0.711m/s Vₐ= Velocity of approach (velocity of approach was considered as zero) R= Hydraulic mean radius= d/4= 0.450/4= 0.1125m 𝑓1= 0.505 for unshaped mouth 0.3𝑏 𝑓2 = 𝑎 (1 + 𝑅 )= 0.00403 (where 𝑎=0.00316, 𝑏=0.1) From UNWIN’s formula: h= 0.062m≈0.1m Therefore, the water level in the U/S well would head=20.022+ 0.1= 20.122m 3.8 Hydraulics of Inlet and Outlet Well a. Check for thickness of the well for safety against hoop tension W= 2.10T/m³, H= 3.05m, ∅= 29˚ From Rankine’s active earth pressure, 𝑃𝑎 = (2.10x3.05/2) x ((1-sin29˚)/ (1+sin29˚)) = 1.111 T/m² External radial pressure on the outer periphery of the well wall can be estimated by Lame’s theory of thick cylinder. For that we need to calculate a and b which are constant and can be calculated by considering two different situations. i. External earth pressure due to soil ii. Internal pressure due to water Let, r₁= internal radius of well= 900mm= 0.900m Fig.3.1. Radial Earth Pressure working on wall periphery r₂= outer radius of well= (1800+2x177)/2 mm= 1077mm = 1.077m Case1: External earth pressure due to soil: 𝜎𝑥 = 1.111 T/m², x = r₂= 1.077m Then by Lame’s theory 1.111= (b/ (1.077)²) + a………………….. (i) Case 2: Internal pressure due to water: The worst condition will be when there is no water in the well. Hence, 𝜎𝑥 =0 and x= r₁= 0.900m 0= (b/ (0.900)²) + a……………………… (ii) Solving equations (i) and (ii), we will get: b= -2.98, a= 3.679 Therefore, Hoop compression at the outer periphery: 𝑏 𝑃𝑥 = 𝑎 − 𝑥 2 = 3.679 – (- 2.98/1.077²)= 6.248 T/m² Hoop compression at the inner periphery: 𝑏 𝑃𝑥 = 𝑎 − 𝑥 2 = 3.679 – (-2.98/0.90²)= 7.358 T/m² This showed that no tension was developing in the well wall and the maximum compressive stress was within the permissible limits of masonry. Hence section assumed was quite safe. 3.9 Stability calculation of well Assumptions: Unit weight of soil= 2.10 T/m³ Unit weight of concrete= 2.40 T/m³ Unit weight of water= 1.00 T/m³ Unit weight of saturated soil= 2.20 T/m³ Horizontal coefficient of soil= 0.134 Vertical coefficient of soil= 0.0384 Height of surcharge on top of the abutment= 0m Equivalent height of surcharge= 0/2.40 =0m Total height of soil on foundation= 3.750m Stability of well checked for two conditions i. When well is full ii. When well is empty Well is made of RCC hume pipe of diameter 1800mm and thickness of 177mm. a. Stress developed in concrete (taking moment about A): Case I: When well is full Fig 3.2. Forces acting on the wall Table: Stress developed in concrete of Well (Taking moment about A) Lever arm= (∑M/∑V) = (26.390/20.126)= 1.311m Eccentricity= │ (d/2 – LA) │= │ (2.15/2) – 1.311│= 0.236m Allowable limit= 0.358 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = 𝑏 (1 + 𝑏 ) = 15.526 T/m² ∑V 6𝑒 Minimum stress developed, 𝜎𝑚𝑖𝑛 = 𝑏 (1 − 𝑏 ) = 3.19 T/m² Case I: When well is empty: Lever arm= (∑M/∑V) = (19.121/13.376)= 1.43 m Eccentricity= │ (d/2 – LA) │= │ (2.15/2) – 1.43│= 0.355m Allowable limit= 0.358 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = (1 + ) = 12.356/m² 𝑏 𝑏 ∑V 6𝑒 (1 − ) 𝑏 𝑏 Minimum stress developed, 𝜎𝑚𝑖𝑛 = = 0.057 T/m² b. Stress developed in soil (taking moment about B): Case I: When well is full: Lever arm= (∑M/∑V) = (65.819/26.926)= 2.444 m Eccentricity = │ (d/2 – LA) │= │ (4.45/2) – 2.444) │= 0.219 m Allowable limit = 0.742 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = 𝑏 (1 + 𝑏 ) = 7.85 T/m² S. No. Force Description Minimum stress developed, 𝜎𝑚𝑖𝑛 = Density ∑V 6𝑒 (1 − 𝑏 ) 𝑏 When well is full Weight L.A. T M = 4.26 T/m² Table3................................................................................ Moment T.m When Well is empty Weight L.A. Moment T m T.m 1 W1 2 W2 3 W3 4 W4 ½ 5 W5 ½ 6 Pv 0.0384 Total load, ∑V= 7 Ph 0.134 total moment, ∑M= x x x( 0.18 1.8 0.18 1.15 1.15 3.75 x x x x x ²) -( 3.75 3.75 3.75 3.75 3.75 0 x( 3.75 ²) -( 0 X X X X X ²)x 2.4 1 2.4 2.1 2.1 2.1 ²)x 2.1 1.593 6.750 1.593 4.528 4.528 1.134 20.126 3.957 0.089 1.077 2.066 2.537 -0.383 0.141 7.270 3.290 11.489 -1.736 0 1.5 5.936 26.390 1.593 0.000 1.593 4.528 4.528 1.134 13.376 3.957 0.089 0.000 2.066 2.537 -0.383 0.141 0.000 3.290 11.489 -1.736 0.000 1.500 5.936 19.121 Table 4. Stress developed in soil (taking moment about B) Force Description S. No. 0.18 1 W1 1.8 2 W2 0.18 3 W3 1/2 X 1.15 4 W4 1/2 X 1.15 5 W5 0.6 6 W6 0.0384 x ( 4.35 7 Pv Total load, ∑V= 8 Ph 0.134 x ( 4.35 total moment, ∑M= Density x x x x x x ²) -( 3.75 3.75 3.75 3.75 3.75 4.45 0 x x x x x x ²)x 2.4 1 2.4 2.1 2.1 2.4 2.1 ²) -( 0 ²)x 2.1 When well is full Weight L.A. Moment T m T.m 1.593 1.239 1.973 6.750 2.227 15.032 1.593 3.216 5.122 4.528 3.687 16.697 4.528 0.767 3.472 6.408 2.225 14.258 1.526 0.000 26.926 5.325 1.740 9.265 65.819 When Well is empty Weight L.A. Moment T m T.m 1.593 1.239 1.973 0.000 0.000 0.000 1.593 3.216 5.122 4.528 3.687 16.697 4.528 0.767 3.472 6.408 2.225 14.258 1.526 0.000 20.176 5.325 1.740 9.265 50.786 Case II: When well is empty: Lever arm= (∑M/∑V) = (50.786/20.176) = 2.52 m Eccentricity = │ (d/2 – LA) │= │ (4.45/2) – 2.52 │= 0.295m Allowable limit = 0.742 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = 𝑏 (1 + 𝑏 ) = 6.33 T/m² Minimum stress developed, 𝜎𝑚𝑖𝑛 = ∑V 6𝑒 (1 − 𝑏 ) 𝑏 = 2.73 T/m² Table5. Stress table Concrete Soil When well is full Maximum Stress, T/m² Minimum Stress, T/m² When well is empty Maximum Stress, T/m² Minimum Stress, T/m² 15.526 7.85 3.19 4.26 12.356 6.33 0.057 2.73 3.10 Structural Design of U/S & D/S Head Wall: Assumptions: Unit weight of soil= 2.10 T/m³ Unit weight of concrete= 2.40 T/m³ Unit weight of water= 1.00 T/m³ Unit weight of saturated soil= 2.20 T/m³ Horizontal coefficient of soil= 0.158 Vertical coefficient of soil= 0.0397 Height of surcharge on top of the abutment= 0m Equivalent height of surcharge= 0/2.40 =0m Total height of soil on foundation= 3.750m a. Stress developed in concrete (taking moments about A) Lever arm= (∑M/∑V) = (33.317/24.628)= 1.353M Eccentricity = │ (d/2 – LA) │= │ (2.20/2) – 1.353) │= 0.253m Allowable limit = 0.367 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = (1 + ) = 18.91 T/m² Minimum stress developed, 𝜎𝑚𝑖𝑛 = S. No 1 2 3 4 5 6 7 Force Description W1 W2 1/2 W3 1/2 W4 W5 Pv 0.0397 Total load, ∑V= Ph 0.1584 total moment, ∑M= 𝑏 𝑏 ∑V 6𝑒 (1 − 𝑏 ) 𝑏 = 3.47 T/m² x( 0.3 1.9 1.9 0.3 0.3 3.75 x x x x x ²) - ( 3.75 3.75 3.75 3.75 3.75 0 x x x x x ²) x Density 2.4 2.4 2.1 2.1 2.1 2.1 x( 3.75 ²) -( 0 ²) x 2.1 X X Weight 2.700 8.550 7.481 2.363 2.363 1.172 24.629 4.678 L.A. 2.050 1.267 0.633 -0.150 2.350 Moment 5.535 10.830 4.738 -0.354 5.552 0.000 1.500 7.017 33.317 Fig 3.3. Forces acting on the Head wall Table: Stress developed in concrete of Head wall (Taking moment about A) b. Table 6.Stress developed in soil (taking moments about B): Table7. Stress developed in soil (Taking moment about B) S. No 1 2 3 4 5 6 7 Force W1 W2 W3 W4 W5 W6 Pv Description 1/2 1/2 x x 0.0397 x( 0.3 1.9 1.9 0.3 0.3 0.6 4.35 X X X X X X ²) - ( 3.75 3.75 3.75 3.75 3.75 2.8 0 x x x x x x ²) x Density 2.4 2.4 2.1 2.1 2.1 2.4 2.1 Weight, T 2.700 8.550 7.481 2.363 2.363 4.032 1.578 L.A., m 2.350 1.567 0.933 0.150 2.650 1.400 Moment, T.m 6.345 13.395 6.983 0.354 6.261 5.645 0.000 8 Total load, ∑V= Ph 0.158 total moment, ∑M= x( 4.35 ²) -( 0 ²) x 29.066 6.278 2.1 1.740 Lever arm= (∑M/∑V) = (49.907/29.068)= 1.717 M Eccentricity = │ (d/2 – LA) │= │ (2.80/2) – 1.717) │= 0.317 m Allowable limit =0.467 ∑V 6𝑒 Maximum stress developed, 𝜎𝑚𝑎𝑥 = 𝑏 (1 + 𝑏 ) = 17.433T/m² Minimum stress developed, 𝜎𝑚𝑖𝑛 = Table8. Stress table: Concrete Soil ∑V 6𝑒 (1 − ) 𝑏 𝑏 Maximum Stress, T/m² 18.913 17.433 = 3.329 T/m² Minimum Stress, T/m² 3.47 3.329 Fig. 3.4 Design of well- Siphin(Side view) 10.925 49.907 ` Fig 3.5. Plan of Well- siphon (Top View) 4CONCLUSION 1. The maximum pressure exerted on the foundation soil within the bearing capacity of the soil 2. No tension developed anywhere in the structure 3. The structure was safe against sliding and overturning. 5 REFERENCES Suresh, R. 2009. Soil and Water Conservation Engineering. Standard Publishers Distributors. New Delhi. 587-591. Garg, S.K. 2002. Irrigation Engineering and Hydraulic Structure. Khanna Publishers. New Delhi. 99 : 424-428 : 699-703 : 751-753 : 1138. Murthy, V.V.N. 2006. Land and Water Management. Kalayani Publishers. New Delhi. 525-526. Sushil, K. 1987. Treasure of RCC Design. Standard Book House. New Delhi. 490-495. Khurmi, R.S. 2010. Strength of Materials. S. Chand & Company Ltd. New Delhi. 755-756 : 422- 425. Kothyari, U. C. 2007. Indian practices on estimation of scour around bridge piers- A comment, Sadhana. 32(3):187-197. Rahman, Md. M. and Haque, Md.A. 2003. Local scour estimation at bridge site: Modification and application of Lacey formulae, International Journal of Sediment Research. 18(4):333-339. Khurmi, R.S. 2007. A text book of hydraulics, fluid mechanics and hydraulics machines. S. Chand & Company Ltd. New Delhi. 118. Bansal, R.K. 2005. A Text Book of Fluid Mechanics and Hydraulics Machines .Laxmi Publications (P) Ltd. 460. Punmia, B.C., Jain, A.K., and Jain, A.K. 2005. Soil Mechanics and Foundations. Laxmi Publication Pvt Ltd. New Delhi. 504 : 522. Murty, S.N.C. 2002. Water Resources Engineering. New Age International (P) Limited, Publishers. New Delhi. 12 : 72-74. Punmia B.C. and Pande B. B. L. 2001. Irrigation and Water Power Engineering. Laxmi Publication Pvt Ltd. New Delhi. 124-126 : 791- 796 : 798- 799 : 805-806. Association of Engineers I&CAD Department.1998. Civil Engineering Hand Book. Government of Andhra Pradesh. Hyderabad. 2-41: 2-57 – 2-61. Indian standard. Design of cross drainage works –Code of practice Part 1, General features. IS7784 (Part 1): 1993. Indian Standard. Design of Cross Drainage Works –Code of Practice Part 2, Specific Requirements, section 1. IS 7784 (Part 2/Sec 1): 1995. Indian standard. Recommendations for Estimation of Flow of Liquids in Closed Conducts: Part 1 Head Loss in Straight Pipes due to Friction Resistance. IS 2951 (Part 1): 1965. Indian standard. Recommendations for Estimation of Flow of Liquids in Closed Conducts: Part 2 Head Loss in Pipes and Fittings. IS 2951 (Part 2): 1965. Pickering, J., and Eggleton, R. 2007. Hydraulic module note. 43. Subramanya, k. 2008. Engineering Hydrology. Tata McGraw-Hill Publishing Company Limited. New Delhi. 238-239. Buckley, R. B. 1920. Irrigation Pocket Book- or, Facts, Figures, and Formulae, for Irrigation Engineer. E & F. N. Spon Ltd. 295-300.
© Copyright 2026 Paperzz