7 November 2016 F-Factor Incentive Scheme RIS Powerline Bushfire Safety Program GPO Box 2392 MELBOURNE VIC 3001 Jemena Electricity Networks (Vic) Ltd ABN 82 064 651 083 Level 16, 567 Collins Street Melbourne, VIC 3000 PO Box 16182 Melbourne, VIC 3000 T +61 3 9173 7000 F +61 3 9173 7516 www.jemena.com.au cc: [email protected] F-Factor Incentive Scheme RIS Thank you for allowing Jemena Electricity Networks (Vic) Ltd (JEN) the opportunity to respond to this RIS. JEN’s submission is set out in the following paragraphs. For ease of understanding, we have categorised our submission into the following three sections: commentary on the background information presented as part of the RIS, commentary on the RIS itself, and JEN’s response to the RIS recommendations/conclusion. Comments on RIS background information The background discussion provided in the RIS clearly targets fire prevention in the areas of country Victoria susceptible to bushfires with potential extreme consequences; of which none overlap the JEN area. The background discussion also appears to have an underlying focus on the systems, plans and fire prevention strategies developed for those areas. As such, some of the background discussion, presented in general terms, does not correlate with JEN’s current policies and practices. These inconsistencies, however, do not influence JEN’s acceptance of the fundamental principles of the proposed new f-factor scheme (i.e. JEN’s comments are provided to complete the background discussion, not to correct the message or justification for change). JEN’s detailed comments on the RIS background information are: a) Section 1.3.4. “Use of Discretionary Capital” JEN disagrees with the message that JEN’s discretionary capital is not spent in the high bushfire risk area (HBRA), as provided for in JEN Bushfire Mitigation Plan (BMP). By way of example, JEN has replaced all high voltage (HV) and subtransmission (ST) wood crossarms with steel crossarms; designed to significantly reduce the incidence of pole top fires. This program—started in the late 1990s—has also resulted in the insulators and conductor ties being replaced with the crossarms. Examples of other dedicated, “discretionary capital” projects, are the replacement of neutral screened services and the installation of an Arc Suppression Coil (ASC) at the Sydenham zone substation. All of this work is over and above the routine replacement required to address defects identified with reference to condition criteria set out in the JEN’s Asset Inspection Manual (AIM). The “discretionary capital” projects were identified as prudent and efficient through risk assessment workshops and the analysis of relevant Asset Class Strategies; all in adherence to the JEN BMP. b) Section 1.3.1. Exogenous variables JEN agrees with the statement “Legislation cannot eliminate this risk” - however suggests that legislation could be strengthened in respect to greater clearance spaces and mandated removal of hazardous trees which would further reduce the risk (since a fire needs an ignition source and fuel). The f-factor scheme is legislation targeting the ignition source from utility assets and the Electric Line Clearance Regulations is legislation aimed at fuel component of a fire. JEN suggests that in geographies categorised as Severe or Extreme the fuel reduction component could be increased along with relevant increase in funding. c) Section 1.3.2. Prohibitive costs of network fire elimination In JEN’s experience, undergrounding the network significantly reduces the risk of fire ignition, but it does not “eliminate” fire starts. All “underground” electricity networks have components above ground - for example, connections in pits or pillars, substations, switching stations and cable connections to the overhead network. In very rare cases the buried cables could fault, resulting in an above ground fire, under favourable conditions. Overall, JEN accepts the reasoning to introduce an incentive scheme for the justification of projects on the basis of likelihood to reduce sources of fire ignition from JEN electricity assets. The Incentive There is a discrepancy in the average annual ignition risk unit (IRU) between JEN’s calculation and that quoted in the RIS. JEN’s calculation of the average cumulative annual IRU over the 2012 to 2015 period (inclusive) is 9.37, compared with the 9.7 quoted in the RIS. JEN uses the RIS value of 9.7 as the foundation for providing further information in this submission. For clarification purposes JEN does not have any areas within its distribution area categorised as “Extreme” as defined under this scheme. For JEN, as with the original version of the f-factor scheme, the incentive value is not material when compared with the expenditure required for even the smallest of projects. As an example, rusty steel conductor replacement cost: $250k for assessment and $660k to replace 30km totals value $910k. If the base line IRU were to be used as an incentive, the result is 9.7 x $15k = $145.5k. If the “worst case scenario” were to be used as an incentive the result is 4.6 (Geography Weight) x 5.0 (Time Weight) x $15k (IRU Incentive Rate) = $345k penalty or “incentive” for a single fire ignition event. For JEN a “cost neutral” f-factor incentive scheme (with reference to section 3.5.2. Symmetric Method in the RIS), based on the analysis in the RIS would see $145.5k spent on fire prevention from electrical assets across the whole distribution area, i.e. not just the HBRA, compared with the $1,652.5k incentive of the existing scheme (calculated from a target of 66.1 and fire start rate of $25k / event). In JEN’s recorded fire start history, there have been no “worst case scenario” events, negating the justification of using a single $345k incentive. The proposed IRU base line value of 9.7 also hides the true cost of fire prevention for JEN. Over the past 2 decades JEN has invested significant effort and cost in fire prevention. It is not possible to extract a single value which exclusively represents fire prevention, as all our operational and capital expenditure programs are designed to cover multiple drivers, such as fire mitigation, public safety, supply quality and supply reliability. The biggest cost incentive continues to be the threat of loss of life, property loss / damage and flow on consequences including the potential for legal actions (e.g. class action) against JEN to arise. For JEN, the proposed f-factor incentive is not sufficient to change the fire prevention risk tolerance. JEN’s response to fire risk will continue to be managed under existing asset management tools at its disposal in the prevention of fire starts. JEN, through its review of the new f-factor incentive scheme, expects immaterial reward against the baseline for 9 out of 10 years, however could suffer material penalties under the proposed scheme for the 1 in 10 year extreme fire event— especially if the fire occurred in the Coolaroo zone substation region (the only area of Jemena that attracts a ‘severe’ geographical risk factor). That is, if a “worst case scenario” fire started in the Coolaroo area on an Extreme fire rated day the penalty for a single event is $345k. Recommendations/conclusion JEN welcomes this legislation, which aims to minimise electricity as an ignition source and, limit the amount of fuel (i.e. trees) available to carry a fire, however, requests the following changes to the scheme or legislation to support the scheme: 1. The scheme should distinguish between fire types. The scheme was designed with the intent of focusing on bushfires, not smouldering pole-tops or scorched possums and so JEN proposes the scheme be amended to exclude all fires contained to a pole top and ground fires that result in less than 1m2 of burnt land. 2. The scheme should apply a capped penalty if a ‘1 in 10 year event’ (i.e. an event similar to Black Saturday) occurs. The penalty could be capped to equate to any benefits achieved in the preceding 5 years. This proposal supports the DELWP principle that the scheme be revenue neutral over time. 3. The scheme should depart from applying fixed weightings for each of the Victorian DNSPs for the time and geography based risk factors. 4. Strengthened fuel reduction legislation (and associated funding) in geographies categorised as Severe or Extreme. The Electric Line Clearance Regulations could, for example, add another level of clearing requirement for Severe and Extreme areas which is above that currently required for areas designated HBRA. If you have any queries in relation to this submission, please contact Matthew Serpell on telephone (03) 9173 8231 or email [email protected]. Yours sincerely [Signed] CAMERON HERBERT General Manager Regulation (Acting)
© Copyright 2026 Paperzz