M1 Status G. Carboni for the Muon Group • material budget • cable layout • status & plans M1 status – TB 12.07.2007 1 Material budget: what is in the MC (T. Ruf) chambers with the Faraday cages and electronics, rest is uniform M1 status – TB 12.07.2007 2 Ingredients of X0 calculations Try to be as accurate as possible by including (hopefully) all importants elements Cross-check calculations with measurements (weight) In the final version local disuniformities will be included to some reasonable level of granularity Data used X0 cm g/cm2 Cu 1.43 12.86 Plastic 30 40 FR4 19.4 33 Al 8.9 24 HV 13.2 LVDS 11.2 ECS 11.2 cables M1 status – TB 12.07.2007 3 Average values: Services <t>/X0 Walls Al 3 mm 0.034 Balconies Al bars 0.011 Ground Braids (v) Cu 50 mm2 0.007 Gas pipes (h) Cu <L> =2 m 0.019 HV/LVDS/ECS cables (v) <L>=3m 0.028 LV Cables (h) <L>=2m 0.009 Total 0.108 (h) mostly horizontal (v) mostly vertical M1 status – TB 12.07.2007 4 Average values: chambers 03.07.07 M1 Chambers Material Budget AS - GC V2.1 <t/X0> M1R3 M1R4 Cathodes FR4 Cathodes Cu Bars H Bars V V mm3 236880 11844 157500 33300 M1R2 Cathodes FR4 Cathodes Cu Bars H Bars V V mm3 255379.2 6384.48 84900 33300 N M ch kg 6 2.416176 6 0.105412 4 1.071 4 0.22644 3.82 M ch kg 6 2.604868 6 0.056822 4 0.57732 4 0.22644 3.47 720 720 480 480 t/X0 <t> mm 6.886047 0.344302 3.052326 0.645349 72 72 48 48 <t> mm 0.742381 0.01856 0.164535 0.064535 N 0.035495 0.024077 0.015734 0.003327 0.078632 N 0.003827 0.001298 0.000848 0.000333 0.005125 TOTAL CHAMBERS 0.083757 FC + 0.06 GEM to be included for the detailed description. Do not play a role in the average M1 status – TB 12.07.2007 5 Average values: electronics cards FC CARDIAC FR4 Pins 5 layers CU Plastic Average SPB FR4 Pins 5 layers CU Plastic Average 0.06 V mm3 4832 3.43 90 11700 N 1000 82000 5000 1000 <t> mm 0.19509 0.011356 0.018169 0.472384 0.001006 0.0008 0.0013 0.0016 0.004645 V mm3 4832 3.43 90 8500 N 1000 82000 5000 1000 <t> mm 0.19509 0.011356 0.018169 0.343185 0.001006 0.0008 0.0013 0.0011 0.004214 LV Burkhard 0.0035 HV Burkhard 0.0011 Total electronics M1 status – TB 12.07.2007 0.0134 6 Summary t/X0 Services 0.108 Chambers (incl. FC) 0.144 Electronics 0.013 Total 0.265 A modest increase w.r.t. the present MC description M1 status – TB 12.07.2007 7 Cable layout Original layout unsatisfactory because of large disuniformities in material distribution M1 status – TB 12.07.2007 8 Old Layout M2-M5 A-side Big X0 jumps X C-side New layout proposed for M1 (Burkhard) to get a more uniform arrangement of cable material for a better EM Calo performance. But layout different from M2-M5 M1 status – TB 12.07.2007 9 Cable layout It was decided to stick to the old chamber layout but to devise new more uniform cabling scheme Emiliano Danè (last week meeting) • horizontal cables behind each chamber row (max 40 cables/row) • remaining part arranged in vertical chimneys (two front and two back) M1 status – TB 12.07.2007 10 Rows with only R4 chambers: rows from 26 to 32 (rows 2->8 mirrored). b c d a Sec. a Sec. b ECS Used 3 clamps; LV 12 places each; HV 36 places in total; For these rows we have: LVDS 18 gas pipes cables + 8 pipes = 26 places M1 status – TB 12.07.2007 11 Rows 22 and 20. (12 and 14) •68 cables in row 20. •So 14 cables of chamber 20A3 go to row 22. •See the Autocad file to better understand. F 1st wires plane Row 22 Row 20 a B Row 22 C 2nd wires plane D E G Row 20 M1 status – TB 12.07.2007 12 External chimney 252 cables Tray B chimney 126 cables Tray A3 chimney 126 cables Vertical routing M1 status – TB 12.07.2007 13 X0 budget due to cables A4 A3 A2 A1 D C B2 B1 32 0.0225 0.0169 0.0113 0.0113 0.0296 0.0296 0.0056 0.0056 30 0.0225 0.0169 0.0113 0.0113 0.0296 0.0296 0.0056 0.0056 28 0.0225 0.0169 0.0113 0.0113 0.0296 0.0296 0.0056 0.0056 26 0.0225 0.0169 0.0113 0.0113 0.0296 0.0296 0.0056 0.0056 24 0.0438 0.0381 0.0325 0.0325 0.0403 0.0403 0.0163 0.0163 22 0.0438 0.0381 0.0325 0.0325 0.0403 0.0403 0.0163 0.0163 20 0.0425 0.0369 0.0350 0.0775 0.0815 0.0528 0.0288 0.0288 18 0.0350 0.0294 0.0390 0.0603 0.0818 0.0993 0.0463 0.0463 16 0.0350 0.0181 0.0668 0.0718 0.1028 0.1203 0.0463 14 0.0425 0.0369 0.0780 0.1205 0.1525 0.1238 0.0288 0.0288 12 0.0438 0.0381 0.0955 0.0955 0.1033 0.1033 0.0163 0.0163 10 0.0438 0.0381 0.0955 0.0955 0.1033 0.1033 0.0163 0.0163 8 0.0225 0.0169 0.0743 0.0743 0.0926 0.0926 0.0056 0.0056 6 0.0225 0.0169 0.0743 0.0743 0.0926 0.0926 0.0056 0.0056 4 0.0225 0.0169 0.0743 0.0743 0.0926 0.0926 0.0056 0.0056 2 0.0225 0.0169 0.0743 0.0743 0.0926 0.0926 0.0056 0.0056 Average 0.039 0.037=0.028+0.009 of estimate on slide 4 M1 status – TB 12.07.2007 14 gas pipes contributions in detail M1 Gas Pipes X0 0.032 0.022 0.011 0.043 0.033 0.022 0.046 0.036 0.025 0.043 0.033 0.022 0.032 0.022 0.011 0.000 Average 1.9% M1 status – TB 12.07.2007 15 Work in progress • Software (Alessia) introduce the detailed description in the MC M1 status – TB 12.07.2007 16 Construction status M1 status – TB 12.07.2007 17 Since our last meeting (LHCb week): • the work on M1 beam started 3 weeks ago... • ...and it stopped due to late (and not announced) delivery of panels due to a broken machinery at the company New delivery date July 20 (was June 22) • a lot of effort done on implementing a - as minimal and uniform as possible - distribution of cables inside the active area and on top of this, a lot of engineering work by Alessandro In the meantime production centers are dressing M1 chambers: • GEM’s here at CERN by the end of July • ½ M1R4 here at CERN by early September (then M1R3) • CERN M1R2 under preparation M1 status – TB 12.07.2007 18 Design & Drawings • All the structural elements have been defined and drawn: – Walls >>> done – Carriages >>> done – Handling System >>> done – Cable Chains (order >>> done) • We have to prepare the executive drawings of the Bottom Rail • We are working on the chambers fixation (Balconies) M1 status – TB 12.07.2007 19 Design: structural elements • • The walls will arrive the Cern at the end of July (20 th). The carriages will arrive the Cern next week M1 status – TB 12.07.2007 20 Mechanics Rearranged Schedule Still to define Manpower shifts 11-giu-07 18-giu-07 25-giu-07 02-lug-07 09-lug-07 16-lug-07 23-lug-07 30-lug-07 06-ago-07 13-ago-07 20-ago-07 27-ago-07 03-set-07 10-set-07 17-set-07 24-set-07 01-ott-07 08-ott-07 15-ott-07 22-ott-07 29-ott-07 05-nov-07 12-nov-07 19-nov-07 26-nov-07 03-dic-07 10-dic-07 07-gen-08 14-gen-08 21-gen-08 28-gen-08 04-feb-08 11-feb-08 Mechanics Gas LV cables Cables Cables Chambers M1 beam M1C M1A Balconies C M1C Brackets Balconies A Rails/Chain C M1A Rails/Chain A M1C M1C M1A M1C M1A M1A M1A 21 Effects of new schedule: • start of LV/Gas cabling not earlier than Sept 15 • start of HV/ECS/Signal cabling not earlier than Oct 15 • start of chamber mounting not earlier than Nov 15 • probably some parallelism on cabling A/C side needed (otherwise too tight schedule) • cabling in the big chain still to be understood (and the interferences with the other operations) The Muon group is willing to have a complete muon system by March 2008 M1 status – TB 12.07.2007 22 SPARES M1 status – TB 12.07.2007 23 effects of the new M1 layout on TRIGGER In the standard layout, all 5 chambers belonging to a projective tower have the same ΔZ w.r.t. nominal position (so they have the same size). With the new layout for M1only, we would have a horizontal row as in the standard layout (Z = 3 4 3 4 in M1 and in M2-M5) alternate to a row with a sequence 1-2-1-2 in M2-M5 and 2-1-2-1 in M1 M3 M2 Towers with Z=1111 in M2-M5 see a “smaller” M1 chamber Z=2 M1 1 3 3 Y 3 IP 1 2 2 2 Towers with Z=2222 in M2-M5 see a “larger” M1 chamber Z=1 M1 status – TB 12.07.2007 1 1 24 TOP VIEW ROW 18 ACCESS SIDE B A3 A2 A1 IP M1 status – TB 12.07.2007 25
© Copyright 2026 Paperzz