Network Rail Possession Indicator Report Period 01 2017/18 Contents Purpose ................................................................................................................... 3 Executive Summary ................................................................................................ 5 Dashboard ............................................................................................................... 6 1. Possession Disruption Index – Passenger (National) ......................................... 7 2. Possession Disruption Index – Freight (National) ............................................. 12 3. Working Timetable Measure – Passenger ........................................................ 14 4. Working Timetable Measure – Freight .............................................................. 21 5. Weekend Working Timetable Compliance ........................................................ 29 6. Rail Replacement Bus Hours ............................................................................ 30 7. Number of Planned Disruption Mitigation Interventions .................................... 31 8. Possession Notification Discount Factor ........................................................... 32 9. Late Changes to Possessions........................................................................... 33 10. Delay Minutes Due to Possession Overrun per 100 Train Kilometre.............. 34 11. Cancellation Minutes Due to Possession Overrun Per 100 Train Kilometre... 35 12. Unplanned Temporary Speed Restrictions (TSR) .......................................... 36 APPENDIX – Terms used in this report ................................................................ 37 2 Purpose The Possession Indicator Report (PIR) presents Network Rail’s performance against the regulatory Network Availability outputs set by the Office of Rail Regulation (ORR) in the final determination for the Period covering 1 April 2014 to 31 March 2019 known as Control Period 5 (CP5). The PIR is published every four weeks and includes a series of other key disruption indicators. Structure of this report The PIR is structured under the headline measures shown in the Table below: Keeping passengers on trains Key Performance Indicators 3. Working timetable measure passenger (WTMP) WTM-P measures the number of unamended schedules (in the baseline timetable) and the relative passenger impact of amended schedule changes (from the baseline timetable) as a percentage of the schedules in the baseline timetable. 4. Working WTM-F measures the timetable measure - percentage of available suitable freight (WTM-F) capacity for freight flows against the maximum for a given freight flow (as defined in the Joint Network availability Plan (JNAP). It provides an indication of the level of planned working time table delivery for passenger operators as a proportion of the baseline timetable. 5. Weekend working timetable compliance The measure provides visibility of the levels of weekend timetable compliance with a view to delivering a 90% compliance aspirational target. Working Time Table compliance measures the percentage of train schedules that ran as scheduled or were disrupted (cancelled or replaced by buses vs. the permanent timetable) each weekend by franchised passenger train service operators. 6. Rail replacement Rail replacement bus hours bus hours measure the percentage of train (weekend) schedules that ran and were disrupted (cancelled or replaced by buses vs. the permanent timetable) per weekend, per TOC. The purpose of the metric is to measure the planned availability of the railway infrastructure to meet freight operators’ requirements to deliver to their customers (source to destination) in CP5 vis-à-vis engineering works taking place on the network. The Rail replacement bus hours measure provides an indication of the extent of bus substitution at weekends. 3 K ey Performance Indicators Disruption mitigation 7. Number of planned disruption mitigation interventions (SLW, BiDi, Simbids) Measures the number of adjacent line open interventions planned to minimise the impact of planned engineering work on rail users. The measure includes the number of possessions planned with either bidirectional signalling, single line working or Simplified Bi-Directional Signalling in operation to enable trains to run during engineering work / line blockages. 8. Notification discount factor -% Possessions notified post TW-22 Timetable Possession Notification Discount Factor measures the percentage of disruptive passenger possessions notified in each of the three possession notification bands. The measure serves as an incentive to plan possessions as far in advance as possible. This helps passengers plan their journey's better as fewer changes are made to the published timetable. 9. Planned disruption - Late notice possession changes Measures the number of new, cancelled, curtailed or extended disruptive possessions that were agreed between the CPPP and the WON as approved by the Engineering Access Planning unit (EAP). It captures Network Rail driven changes which have an additional material impact that will be felt by the travelling public and/or freight customers (e.g. cancelled trains, retimings and diversions away from stations), compared to what was published in the Confirmed Period Possession Plan (CPPP). Key Performance Indicators Possession incidents 10. Delay minutes The indicator is the delay The measure aims to provide a view due to possession minutes per 100 train kilometre of the levels of passenger journeys overrun run due to possession overrun. disruption resulting from extended journey times due to overrunning planned engineering works. 11. Cancellation The number of equivalent delay minutes due to minutes per 100 train kilometre possession overrun run caused by cancellations due to possession overruns The measure aims to provide a view of the levels of passenger journeys disruption resulting from cancelled train services due to overrunning planned engineering works. 12. Unplanned temporary speed restrictions (TSR) The measure aims to provide a view of the disruptions to passenger journeys resulting from unplanned TSR The Unplanned TSRs measure provides an indication of the number of unplanned TSR’s in place. 4 Executive Summary The Possession Disruption Index for Passengers (PDI-P) for period 13 was 1.49, improving when compared to the same period in 2015/16 of 2.44. The moving annual average for period 13 was 1.25, declining when compared to the same period in 2015/16 of 1.10. Period 13 saw passenger services disrupted due to various planned improvement works including weekend renewals work at Thirsk, re-ballasting works taking place between King Edwards Bridge South Jn and Swalwell Jn, Overhead renewals work on the Hertford loop, Port Talbot resignalling & structures work, Cardiff East for intersection bridge work in connection with electrification, North Wales Coast resignalling, the Mersey Tunnel slab track project and continuation of the Eden Brow landslip resilience scheme. NOTE: Possession Disruption index for Passenger is reported a period in arears Executive Summary The Possession Disruption Index for Freight (PDI-F) for period 01 was 0.95, declining when compared to the same period in 2016/17 of 0.90. The moving annual average for period 01 was 1.05, again declining when compared to the same period in 2016/17 of 0.85. Period 01 included the Easter Bank Holiday and various planned engineering works throughout the period impacting freight services. These included a16 day possession at Bath Spa for track and civils works to enable new Intercity Express Programme trains to run. All Lines were blocked on weekends and Good Friday / Easter Monday, one line was blocked and one open with trains running in both directions on weekdays. The Working Timetable Measure for Passengers for period 01 was 98.14%, a slight decline compared to the same period in 2016/17 of 99.11%. The moving annual average for period 01 was 99.07%, a similar figure when compared to the same period in 2016/17 of 99.01%. The Working Timetable Measure for Freight for period 01 was 72.67%, declining when compared to the same period in 2016/17 of 74.11%. The moving annual average for period 01 was 68.37%, again declining when compared to the same period in 2016/17 of 69.20%. The Weekend Working Timetable for period 01 was 75.46%, deteriorating when compared to the same period in 2016/17 of 81.35%. The moving annual average for period 01 was 79.66%, again deteriorating when compared to the same period 2016/17 of 81.18%. Rail Replacement Bus Hours in period 01 were 18,583 hours, increasing adversely when compared to the same period in 2016/17 of 13,254 hours. The moving annual average for period 01 was 16,258 hours, deteriorating when compared to the same period in 2016/17 of 14,739 hours. Period 01 included the Easter Bank Holiday together with various planned engineering work requiring the necessity for rail replacement bus services to operate. These included the continuation of Crossrail, Great Western and Wales Electrification, slab relaying work taking place on the Wirral lines and Bath Spa Major Project work. Planned Disruption Mitigation Interventions in period 01 were 147, improving when compared to the same period in 2016/17 of 135. The moving annual average for period 01 was 134, declining when compared to the same period in 2016/17 of 165. Possession Notification Discount Factor in period 13 for possessions post TW-22 was 7.74%, improving when compared to the same period in 2015/16 of 11.42%. The moving annual average for period 13 was 6.86%, improving when compared to the same period in 2015/16 of 9.49%. Period 13 has seen an increase in the actual figure when compared to the previous three periods. This is mainly due to a large number of late notice possessions around Paddington (mainly in connection with Crossrail works) and also ongoing Over Head Line work around Dalmeny Jn impacting ScotRail services throughout the period. NOTE: Possession Notification Discount Factor is reported a period in arears. Late Change to Possessions for period 01 was 229, a significant increase when compared to the same period in 2016/17 of 87. The moving annual average for period 01 was 122, again deteriorating when compared to the same period in 2016/17 of 95. The increase seen this period is mainly due to the level of change on Western Route being higher than the norm due to a volume of change associated with the Crossrail commissioning which was delayed last period from week 49 to week 52. There has been an ongoing reaction to this in order that the infrastructure is ready for the May 2017 WTT. There is also change to electrification access due to Rules / Standard changes which are technically disruptive, but don’t affect booked traffic. And at Paddington for Crossrail construction works where services can be dealt with in alternative platforms no or minor effects on timing. Delay Minutes Due to Possession Overrun per 100 Train Kilometres in period 01 was 0.015, improving when compared to the same period in 2016/17 of 0.029. The moving annual average for period 01 was 0.037, declining when compared to the same period in 2016/17 of 0.032. Cancellation Minutes Due to Possession Overrun per 100 Train Kilometres in period 01 was 0.007, improving when compared to the same period in 2016/17 of 0.020. The moving annual average for period 01 was 0.019, declining when compared to the same period in 2016/17 of 0.013. Unplanned Temporary Speed Restrictions for period 01 were 224, improving when compared to the same period in 2016/17 of 256 and the lowest seen during this year. The moving annual average in period 01 was 245, deteriorating when compared to the 5 same period in 2016/17 of 214. Dashboard Regulatory metrics Dashboard P01_17/18 MAA P01_16/17 MAA 13 period trend (MAA) Control period (MAA): CP5 Min Av. Max ** Possession Disruption Index for Passenger 1.25 1.10 0.70 0.93 1.34 Possession Disruption Index for Freight 1.05 0.85 0.85 0.90 1.05 Keeping passengers on trains P01_17/18 MAA P01_16/17 MAA 13 period trend (MAA) Control period (MAA): CP5 Min Av. Max Working Timetable Measure - Passenger 99.07% 99.01% 99.01% 99.14% 99.27% Working Timetable Measure - Freight 68.37% 69.20% 67.01% 70.33% 73.62% Weekend Working Timetable Compliance 79.66% 81.18% 79.66% 82.32% 84.33% Rail Replacement Bus Hours 16259 14739 12133 13874 16324 Disruption mitigation Number of Planned Disruption Mitigation Interventions (SLW, BiDi, Simbids) P01_17/18 MAA P01_16/17 MAA 13 period trend (MAA) Control period (MAA): CP5 Min Av. Max 134 165 133 157 172 ** Notification Discount Factor -% Possessions Notified Post TW-22 Timetable 6.86% 9.49% 6.00% 8.13% 10.61% Planned Disruption - Late Notice Possession Changes 1.53% 1.19% 0.93% 1.15% 1.53% Possession incidents P01_17/18 MAA P01_16/17 MAA 13 period trend (MAA) Control period (MAA): CP5 Min Av. Max Delay Minutes Due to Possession Overrun 0.037 0.032 0.031 0.040 0.052 Cancellation Minutes Due to Possession Overrun 0.019 0.013 0.012 0.021 0.031 245 214 154 197 255 Unplanned Temporary Speed Restrictions ** metric reported a period in arrears 6 1. Possession Disruption Index – passenger Possession Disruption Index – Passenger(National) (National) The Possession Disruption Index for Passengers (PDI-P) for period 13 was 1.49, improving when compared to the same period in 2015/16 of 2.44. The moving annual average for period 13 was 1.25, declining when compared to the same period in 2015/16 of 1.10. Period 13 saw passenger services disrupted due to various planned improvement works including weekend renewals work at Thirsk, re-ballasting works taking place between King Edwards Bridge South Jn and Swalwell Jn, Overhead renewals work on the Hertford loop, Port Talbot resignalling & structures work, Cardiff East for intersection bridge work in connection with electrification, North Wales Coast resignalling, the Mersey Tunnel slab track project and continuation of the Eden Brow landslip resilience scheme. NOTE: Possession Disruption index for Passenger is reported a period in arears 7 Possession Disruption Index – Passenger Operators (1 of 4) Period 13 saw the moving annual average for c2c improve when compared to the same period in 2015/16. The moving annual average for Arriva Trains Wales, Chiltern Railways, CrossCountry, East Midlands Trains and Govia Thameslink Railway all declined when compared to the same period in 2015/16. 8 Possession Disruption Index – Passenger Operators (2 of 4) Period 13 saw the moving annual average for Great Western Railways, Heathrow Connect and London Midland all improve when compared to the same period in 2015/16. The moving annual average for Greater Anglia, London Overground and Merseyrail all declined when compared to the same period in 2015/16. 9 Possession Disruption Index – Passenger Operators (3of 4) Period 13 saw the moving annual average for Northern, Southeastern, TfL Rail and Transpennine Express all improve when compared to the same period in 2015/16. The moving annual average for ScotRail and South West Trains both declined when compared to the same period in 2015/16. 10 Possession Disruption Index – Passenger Operators (4 of 4) Period 13 saw the moving annual average for Virgin Trains East Coast and Virgin Trains West Coast both improve when compared to the same period in 2015/16. 11 2. Possession Disruption – Freight (National) On Disruption Index Index – freight (National) The Possession Disruption Index for Freight (PDI-F) for period 01 was 0.95, declining when compared to the same period in 2016/17 of 0.90. The moving annual average for period 01 was 1.05, again declining when compared to the same period in 2016/17 of 0.85. Period 01 included the Easter Bank Holiday and various planned engineering works throughout the period impacting freight services. These included a16 day possession at Bath Spa for track and civils works to enable new Intercity Express Programme trains to run. All Lines were blocked on weekends and Good Friday / Easter Monday, one line was blocked and one open with trains running in both directions on weekdays. 12 Possession Disruption Index - Freight Operators Period 01 saw an improvement in the moving annual average for Direct Rail Services when compared to the same period in 2016/17. The moving annual average for Freightliner, GB Railfreight and DB Cargo all declined when compared to the same period in 2016/17. 13 3. Working Timetable Measure – Passenger (National) . Working timetable measure – passenger The Working Timetable Measure for Passengers for period 01 was 98.14%, a slight decline compared to the same period in 2016/17 of 99.11%. The moving annual average for period 01 was 99.07%, a similar figure when compared to the same period in 2016/17 of 99.01%. 14 Working Timetable Measure – Passenger Summary Working timetable measure – passenger (Summary) Working Timetable Measure – Passenger (1 of 5) Working timetable measure – passenger 1 of 5 Working Timetable – Passenger Working timetableMeasure msure – passenger 2 of 4(2 of 5) 17 Working Timetable Measure – Passenger (3 of 5) Working timetable measure – passenger) 3 of 4 18 Working Timetable Measure – Passenger (4 of 5) Working timetable measure – passenger 4 of 5 19 Working Timetable Measure – Passenger (5 of 5) Working timetable measure – passger 5 of 20 4. Working Timetable Measure – Freight 4. Working timetable measure – fright The Working Timetable Measure for Freight for period 01 was 72.67%, declining when compared to the same period in 2016/17 of 74.11%. The moving annual average for period 01 was 68.37%, again declining when compared to the same period in 2016/17 of 69.20%. 21 WorkingTimetable timetable measure – Freight freight (Summary) Working Measure – (Summary) Working Timetable Freight (16)of 6) Working timeable Measure measure ––freight (1 of Working timetable measure–– Freight freight (2 of(2 6)of 6) Working Timetable Measure Working Measure – Freight orkingTimetable timetable measure – freight (3 of(3 6) of 6) 25 Working Timetable Freight (4 6) of 6) Working timetable Measure measure ––freight (4 of 26 Working Timetable Measure – Freight (5 of 6) Working timetable measure – freight (5 of 6) Working Timetable Measure – Freight Working timetable measure – freight (6 of 6)(6 of 6) 28 5. Weekend Working Timetable Compliance 6. Weekend working timetable compliance The Weekend Working Timetable for period 01 was 75.46%, deteriorating when compared to the same period in 2016/17 of 81.35%. The moving annual average for period 01 was 79.66%, again deteriorating when compared to the same period 2016/17 of 81.18%. 29 6. Rail Replacement Bus Hours 6. Rail replacement b Rail Replacement Bus Hours in period 01 were 18,583 hours, increasing adversely when compared to the same period in 2016/17 of 13,254 hours. The moving annual average for period 01 was 16,258 hours, deteriorating when compared to the same period in 2016/17 of 14,739 hours. Period 01 included the Easter Bank Holiday and saw various planned engineering works requiring bus replacement services to operate, these included-Arriva Trains Wales required bus replacement services due to planned engineering including Penarth-Cardiff Central, Cogan-Cardiff Central, Chester-Llandudno Jn, Barry Island-Cardiff, Codsall-Albrighton, Penarth-Cardiff Central, ShrewsburyChester, and Wolverhampton-Shrewsbury, -CrossCountry required bus replacement services to run due to engineering Coldham Lane Jn to Ely Dock Jn/Ely North Jn to Crescent Jn, Tollerton to Longlands Jn, Redbridge Jn to Bournemouth, Ely North Jn to Kings Dyke, Cambuslang to Eglington St Jn, Motherwell to Rutherglen West Jn and Leamington Spa Jn to Gibbet Hill Jn. -Govia Thameslink required bus replacement services due to planned engineering London Bridge-Norwood Jn, Tulse HillSutton & Wimbledon, Brighton-Preston Park & Lewis, Three Bridges-Billinghurst, West Croydon-Epsom Downs, Victoria-East Croydon, Arundel Jn-Chichester & Bognor, Balham-Beckenham Jn, Three Bridges-Horsham, Keymer Jn-Seaford & Holgate. -Greater Anglia required bus replacement services due to planned engineering works between Witham/Wickford and Newbury Park, Cambridge and Ely, Dullingham and Cambridge, Ipswich and Felixstowe, Ingatestone/Billericay and Newbury Park, Witham/Southend Victoria and Newbury Park, Broxbourne and Audley End/Stansted Airport, Ipswich and Lowestoft, Norwich and Cromer/Sheringham, and Stowmarket and Norwich. -Great Western Railway required bus replacement services due to Crossrail, Great Western and Wales Electrification, Bath Spa Major Works and Castle Cary Tamping Work. -London Overground required bus replacement services to operate due to planned engineering works between Romford/ Upminster, Camden Road and Stratford, and South Tottenham and Barking. -Merseyrail required bus replacement services due to continued slab track work on the Wirral lines. -Northern required bus replacement services to run due to planned engineering Hall Royd Jn-Greetland Jn, Preston Fylde JnBlackpool, Neville Hill West Jn-Gascoigne Wood, and Micklefield-Church Fenton. -ScotRail required bus replacement services to run due to engineering work Helensburgh Upper and Ardlui, Lanark Jn/Law Jn and Shieldmuir, Logans Road LC and Newton East Jn, Mossend West Jn and Uddingston Jn, Drumgelloch and Helensburgh Central, Craigendoran Jn and Crianlarich and Cambuslang and Eglington St Jn. -Southeastern had various planned engineering work which required bus replacement services to operate between Rainham to Faversham, Sittingbourne to Sheerness, Sevenoaks to Maidstone East, Tonbridge to Wadhurst, Herne Hill to Beckenham jn, Lewisham to Dartford via Sidcup, Rochester to Rainham, Ashford to Dover Priory and Strood to Paddock Wood. -South West trains had various planned engineering work which required bus replacement services to Operate AldershotGuildford, Alton-Aldershot, Ascot- Hounslow, Clapham Jn-Kingston, Eastleigh-Southampton Central, Haslemere-Woking, Hounslow-Reading, Reading-Staines, Romsey-Salisbury, Southampton Central-Bournemouth, Staines-Ascot, TemplecombeAxminster, Waterloo-Twickenham, Weybridge-Staines and Woking-Southampton Central. -Transpennine Express had various planned engineering works including Carlisle and Glasgow/Edinburgh, Leeds and Micklefield, Manchester Victoria, Oxenholme and Glasgow/Edinburgh and North of York blocked lines at Thirsk which necessitated bus replacement services to operate. -TfL required rail replacement bus services to operate from Ingatestone/ Billericay and Newbury Park and Newbury Park and Southend Victoria, Brentwood and Shenfield and no train services due to ongoing Crossrail work at Shenfield. -Virgin Trains had various planned engineering works including between Carlisle and Glasgow and Preston and Carlisle 30 which required bus replacement services to operate. 7. Number of Planned Disruption 7. Number of planned disruption mitigation interventions Mitigation Interventions Planned Disruption Mitigation Interventions in period 01 were 147, improving when compared to the same period in 2016/17 of 135. The moving annual average for period 01 was 134, declining when compared to the same period in 2016/17 of 165. 31 8. Possession Notification Discount Factor 8. Possession notification discount factor Possession Notification Discount Factor in period 13 for possessions post TW-22 was 7.74%, improving when compared to the same period in 2015/16 of 11.42%. The moving annual average for period 13 was 6.86%, improving when compared to the same period in 2015/16 of 9.49%. Period 13 has seen an increase in the actual figure when compared to the previous three periods. This is mainly due to a large number of late notice possessions around Paddington (mainly in connection with Crossrail works) and also ongoing Over Head Line work around Dalmeny Jn impacting ScotRail services throughout the period. NOTE: Possession Notification Discount Factor is reported a period in arears. 32 9. Late Late Changes changes to Possessions possessions 9. Late Change to Possessions for period 01 was 229, a significant increase when compared to the same period in 2016/17 of 87. The moving annual average for period 01 was 122, again deteriorating when compared to the same period in 2016/17 of 95. The increase seen this period is mainly due to the level of change on Western Route being higher than the norm due to a volume of change associated with the Crossrail commissioning which was delayed last period from week 49 to week 52. There has been an ongoing reaction to this in order that the infrastructure is ready for the May 2017 WTT. There is also change to electrification access due to Rules / Standard changes which are technically disruptive, but don’t affect booked traffic. And at Paddington for Crossrail construction works where services can be dealt with in alternative platforms no or minor effects on timing. 33 10.Delay Delayminutes Minutesdue Duetotopossession Possessionoverrun Overrunper per100 100train Train 10. Kilometre kilometre Delay Minutes Due to Possession Overrun per 100 Train Kilometres in period 01 was 0.015, improving when compared to the same period in 2016/17 of 0.029. The moving annual average for period 01 was 0.037, declining when compared to the same period in 2016/17 of 0.032. 34 11. 11. Cancellation Minutes Duedue to Possession Overrun perper 100100 train Cancellation minutes to possession overrun Kilometre train kilometre Cancellation Minutes Due to Possession Overrun per 100 Train Kilometres in period 01 was 0.007, improving when compared to the same period in 2016/17 of 0.020. The moving annual average for period 01 was 0.019, declining when compared to the same period in 2016/17 of 0.013. 35 12. Unplanned Unplanned temporary Temporaryspeed Speedrestrictions Restrictions (TSR) 12. (TSR) Unplanned Temporary Speed Restrictions for period 01 were 224, improving when compared to the same period in 2016/17 of 256 and the lowest seen during this year. The moving annual average in period 01 was 245, deteriorating when compared to the same period in 2016/17 of 214. 36 APPENDIX – Terms used in this report Note: Possession Disruption Index for Passengers (PDI-P) (Reported one month in arears) During a project to fix the Network Availability Reporting System (NARS) an error was detected in the calculation of PDI-P. This calculation error has existed since the PDI-P measure was created and has been reported consistently on this basis for Control Period 4 (2009-2014) and Control Period 5 (20142019) to date. However the error is not considered to be material as it impacts the target and actual reported number in equal measure. On this basis, we will continue to report against the existing target for the remainder of Control Period 5. If this measure continues to be reported in Control Period 6 (20192024) we intend to correct the calculation error for both target setting and future reporting. 37
© Copyright 2026 Paperzz