evonshires solicitors CONSTRUCTION LAW UPDATE: A Moder n Approach to Penalty Clauses You should read this Update if: • You use or have considered using liquidated damages clauses in your construction contracts; • If you are challenging such a clause; or • You are defending against a claim that a liquidated damages clause in your construction contract amounts to a penalty. Makdessi v Cavendish Square Holdings BV [2013] 1 All E.R. (Comm) 787 and Talal El Makdessi v Cavendish Square Holdings BV [2013] EWCA Civ 1539 ‘goodwill’ payments and that he was obliged to sell his shares at the reduced price. The defendant questioned the validity of the relevant clauses on the grounds that they were penalties. Summary This case involved both a first instance judgement and successful appeal in the Court of Appeal (CoA). It is not directly a liquidated damages case, but clarifies the evolving ‘modern approach’ to the law on penalties. This is relevant to all construction contracts containing liquidated damages clauses. The First Instance Decision The Facts Burton J considered that the law has moved beyond this simple dichotomy. That is to say, if there is some other commercial justification for the clause it may be valid even if it is not a ‘genuine pre-estimate of loss.’ The case concerned a share sale agreement which provided for ‘goodwill’ payments to the seller and restrictive covenants on the seller competing with the company concerned. In the event that the seller breached those restrictions, the contract required he forfeit the goodwill payments and entitled the purchaser to purchase the seller’s remaining shares at a reduced price. Subsequent to the agreement the seller/ defendant breached his fiduciary duties to the company (which he admitted). The company/ claimant brought a claim for a declaration that the defendant was not entitled to the Burton J reviewed the authorities on penalties. In his view the law had previously drawn a simple dichotomy between ‘genuine pre-estimates of loss’ (i.e. liquidated damages) and penalties (i.e. clauses intended to deter breach). Accordingly the only relevant question was: is the clause a genuine pre-estimate of loss? He went on say that the modern approach is to consider whether: 1. There is a commercial justification for the clause; 2. The clause is extravagant or oppressive; 3. Its main purpose is to deter breach; and 4. If relevant, it was negotiated on a level playing field. He found that, although the clause in question was not a genuine pre-estimate of loss, it was valid. It served a twofold commercial purpose namely: to adjust consideration between the parties and to decouple them, in the event of a breach. The clause was not oppressive and had not been intended simply to deter breach. The Decision on Appeal The CoA overturned this judgement. Whilst agreeing with the approach adopted by Burton J, they found that the clause in question was extravagant to such an extent that it was not commercially justified. The CoA agreed that “the fact that payment on breach may not really be a pre-estimate of loss does The fact that payment on breach may not be a pre-estimate of loss doesn’t mean it must be penal. not mean that it must be penal.” It also agreed that the four considerations outlined by Burton J were the relevant ones. However it provided clarification on how these considerations would interrelate, and consequently came to a different decision. According to the CoA, the first question is whether the clause is a genuine pre-estimate of loss, if so it is valid. If not, this need not be fatal. The next question is whether it is extravagant or oppressive. This will largely turn on the facts of the case, however the main consideration will be whether the amount to be paid/ lost by the defaulting party is “out of all proportion to the loss attributable to the breach.” If so it is most likely to function as a deterrent and unlikely to serve a justifiable commercial purpose. This decision brings the ‘modern approach’ more closely in line with the ‘pre-estimate of loss’ approach by limiting the circumstances in which clauses which are not pre-estimates of loss can be held ‘commercially justifiable.’ Implications The main implication of these decisions is that assessments of whether liquidated damages clauses are valid are likely to become more fact sensitive. In a sense this will increase the certainty of such provisions as courts will be less likely to overturn them even if they do not amount to pre-estimates of loss. Consequently, however, in cases where clauses are not genuine pre-estimates of loss it will be far harder to determine whether or not they are valid, each case turning on its own particular facts. Some Practical Advice Liquidated damages clauses should still be drafted to cover genuine pre-estimates of loss; such clauses will remain valid and enforceable. Effort should be made to evidence the calculations/ assessments on which such pre-estimates are based. This may prove useful in the event such clauses are challenged. The ‘commercial justification test’ should only be resorted to where a clause has failed the ‘preestimate of loss test.’ Finally it is worth considering whether clauses that appear penal can be reformulated. If clauses that specify obligations to make payments/ forfeit sums following a breach can instead be expressed so as to make certain payments conditional on performance, the question of whether they are penal will not arise as their operation will not be dependent on any breach. Contact us This is one of a series of regular updates from the construction engineering department. For advice on any of the above issues, or if you have any suggestions for topics you’d like us to cover next, please do email us at construction@devonshires. co.uk. This is a new initiative so please share this article among your colleagues and contacts and encourage them to subscribe via the same address. The tiny print No action should be taken on the matters covered by this leaflet without taking specific legal advice. Find out more This is one of a series of regular updates from the Construction & Engineering Department. For advice on any of the above issues, or if you have any suggestions for topics you’d like us to cover next, please do email us at construction@ devonshires.co.uk. This is a new initiative so please share this article among your colleagues and contacts and encourage them to subscribe via the same address.
© Copyright 2026 Paperzz