AECOM Minutes of Meeting.dot

5757 Woodway Drive
Suite 101 West
Houston, Texas 77057
713 780 4100 tel
713 267 3296 fax
Minutes of Meeting
Date of Meeting
Nov 12, 2012
Project Name
US 59 Schematic and EA
Location
TxDOT Beaumont District Office
Regarding
Project Kick-off Meeting
Attendees
Distribution
Start Time 3:00 PM
Scott Ayers – TxDOT
Leanna Sheppard – TxDOT
Paul Smith – TxDOT
Phillip Lujan – TxDOT
Tucker Ferguson – TxDOT
Roger Beall – TxDOT (via phone)
Doug Booher – TxDOT (via phone)
Lindsey Kimmitt – TxDOT (via phone)
Sandra Chipley - TxDOT (via phone)
Project Number 60278496
Joe Shalkowski – Atkins (via phone)
Lori Cole – Atkins (via phone)
Steven Lindsey – Atkins (via phone)
Mashhood Shah – AECOM
Jorge Villalta – AECOM
Kelly Krenz - AECOM
All attendees
Minutes Prepared By Jorge Villalta
Below is a brief record of my understanding and notes from the above mentioned meeting. If a
discrepancy is found upon your review of these minutes, please send clarification to me at your
earliest convenience. Action items have been shown in Italic font for ease of locating.
1.
Mr. Ayers, the TxDOT project manager (PM) called the meeting and requested AECOM to
describe the project.
2.
AECOM provided the project background and described the scope of work.
3.
TxDOT provided a brief history of the project and the I-69 Program. This project will deliver
the first environmental document for I-69 Program and the Beaumont District will set
precedence for other segments of I-69 Program.
4.
TxDOT recommended to keep Need and Purpose simple (Bring the US 59 highway to
interstate standards).
5.
TxDOT recommended eliminating TSM/TDM improvements as well as Transit.
6.
TxDOT recommended addressing pedestrian and bicycling needs by providing these facilities
along frontage roads only.
7.
For Planning and Programming purposes, TxDOT recommended traffic analysis to be
performed for Year 2015 (PS&E completion year, not the letting) plus 20 years.
Page 2
Minutes of Meeting
09-10-2012
8.
It was agreed upon that the schematic design would be for 6-mainlanes, which could be
constructed in phases.
9.
The current TIP contains schematic and environmental document for a 4-lane facility and
needs to be revised to include 6-lanes.
10.
TxDOT recommended including a No-Build and a Build alternative consisting of widening to
the west side because of the railroad constraints on the east side. A brief description of
alternatives to be included in the environmental document.
11.
US 59 schematic to be designed based on interstate design standards (follow AASHTO
standards). No design exceptions will be accepted. AECOM will update the design criteria
based on AASHTO guidelines.
12.
AECOM stated that field surveying to be completed in March, 2013.
13.
AECOM requested traffic data for the traffic analysis. TxDOT requested AECOM to provide a
line diagram. AECOM to provide line diagram exhibit for traffic.
14.
It was agreed upon that Kelly Krenz would coordinate with Leanna Sheppard regarding
environmental document preparation and will copy Scott Ayers.