NEG coating W30

ELENA – Vacuum chambers and
vacuum activities
IIC meeting
14-07-2016
G. Riddone
(contribution from A. Sapountzis, A. Sinturel)
1
Production by EN-MME
Fabrication completed
• LNR Dipole vacuum chambers
• LNI Y-vacuum chamber
• LNI quadrupole vacuum chambers
• LNI dipole vacuum chambers
• LNR inj-ejection vacuum chambers
• LNS: AD_VCPAB0001 - AD_VCPAC0001
Fabrication under way
• LNE50: following green light on 9 June, the production of the 4 LNE50
chambers have been launched at the main workshop: VCDCU/CX/CW/CV
2
Production by Trinos
2nd batch x8
AD_VCDCE0001 x1
AD_VCDCF0001 x1
AD_VCQAP0001 x2
AD_VCQBJ0001 x2
AD_VCDME0001 x1
AD_VCDBQ0001 x1
3rd batch x13
AD_VCDCI0001 x1
AD_VCDBU0001 x1
AD_VCDBV0001 x1
AD_VCDBW0001 x1
AD_VCDBY0001 x1
AD_VCDBZ0001 x1
AD_VCDCS0001 x1
AD_VCDDB0001 x1
AD_VCDBR0001 x1
AD_VCPAA0001 x1
AD_VCDBX0001 x1
AD_VCSPB0001 x1
AD_VCSPA0001 x1
•
last batch x6
VC upstream and
downstream
the fast valves, on the
way to CERN
NEG coating W30
•
•
Available for installation
1st batch x12
AD_VCDBS0001 x1
AD_VCDCG0001 x2
AD_VCPIB0001 x1
AD_VCXBA0001 x2
AD_VCLBA0001 x2
AD_VCPQA0001 x1
AD_VCXBB0001 x1
AD_VCXAA0001 x1
AD_VCQBK0001 x1
Available for installation
•
3
NEG coating
• LNR dipole vacuum chambers
– #1 to 5: completed
– #6 : NEG coating W28
• LNR chambers TRINOS
– Chambers for fast valves W30
• Y-chambers x3:
– completed
4
NEG coating/Acceptance tests
•
PU SCHOTTKY (Responsible: Jorge Sanchez Quesada)
– 4 chambers received (weight ~80 kilos each, very fragile): 2/4 need to be coated
– optical inspection of the 4 chambers have dust, projections, metallic shavings, oxidation,
scratches and white spots.
– ACTION:
•
•
•
•
method to remove the oxidation to be found by EN-MME,
then degreasing (to avoid the trapping of chemical residuals)
for the 2 with coating: techniques for removing the oxidation should be tested before the coating of
the real piece (coating, adhesion test, end of validation). Otherwise high risk for NEG peel-off
and finally NEG coating (week 29-30?)
BPM for Tune (Responsible: Joel Albertone)
– After the acceptance test there is peel-off (dust-like).
– ACTION: remove NEG dust, perform a 2nd acceptance test (week 26-27): results complying
with the specification and ready for installation. A second unit is under testing.
•
LNS: SEM acceptance test is completed, device available today. The result is good
after bake out.
5
Planning for next weeks
6