on behalf of the LHC Access Project Team

LHC Access System
LHC Access System – Status and Planning
August 2006
Elena Manola-Poggioli
Eva Sanchez-Corral
TS-CSE
on behalf of the LHC Access Project Team
August 2006
LHC Access System
LHC Access System
• LHC Access Control System – LACS
– Supports the physical equipment regulating the access to
the accelerator
– Allows operation of access equipment
• LHC Access Safety System – LASS
– Provides interlock between EIS-faisceau and EIS-acces
– Ensures the collective protection of personnel from the
radiation hazards
August 2006
LHC Access System
LHC Access Control
•
•
•
•
•
•
•
•
•
•
•
34 Access Points
95 controlled sector doors
65 interlocked end-of-zone doors
26 interlocked ‘portes crionolines + ventilation’
17 interlocked movable shielding walls
200 junction boxes
170 racks
110 surveillance cameras
200 controllers (PLCs, PCs)
Control system from CCC and experiments
Supervision system
August 2006
LHC Access System
LHC0: design validation
August 2006
LHC Access System
Installation Status: sector doors and junction boxes
• Sector doors:
– Point 8: 90%
– Point 7: 90%
– Point 1: 75%
August 2006
• Junction Boxes:
–
–
–
–
Point
Point
Point
Point
8:
7:
1:
6:
100%
100%
100%
90%
LHC Access System
August 2006
LHC Access System
Access points - Underground
• Installation of the access points in UX85, UJ83
and UJ87 in progress
• Complete test of the access point UX85,
including the IHM and control from the CCC,
supervision and maintenance procedures
-> mid September
• Circulation of personnel not affected
August 2006
LHC Access System
Installation Strategy – Underground Access Points
•
•
Not used for personnel passage before the definite closure of the area
(installation of the grids)
Configured for biometric recognition and RFID badge identification
August 2006
LHC Access System
August 2006
LHC Access System
Access for the Pits Head
•
Prerequisites:
•
Constraints: minimize the impact on the personnel flow during the LHC
installation period
•
Strategy:
–
–
–
Access points UX85, UJ83 and UJ87 integrated and validated
Access Help Desk manned and operational
User information:
• Posters, group secretariats, TCC, bulletin
–
Biometric recognition disabled
–
Use of the new CERN site access cards (equipped with MIFARE RFID chips) for the personal
identification – Under validation
• Current CERN site ACCESS magnetic cards is being progressively replaced by the new
RF cards (TS/CSE responsibility)
–
–
Dosimeters not required during the LHC installation
Before LHC start-up, users shall be requested to get a dosimeter equipped with the RFID
chips
August 2006
LHC Access System
• New CERN Site Access Cards:
August 2006
LHC Access System
•
Persons working on the Points 7 and 8 will be asked to
retrieve the new access cards at the Building 55 already in
September
•
Access to the LHC interlocked areas in the LHC operation
phase: personnel dosimeter equipped with the RFID chip and
biometric identification
August 2006
LHC Access System
• Short term objectives Points 7 and 8:
– PM85:
• Dismantling of the existing system: beginning October (1
week)
• Installation and integration of the new system (1 week)
• Presence of the security guardian required during
dismantling and installation
• Operational mid October
– PM76 operational end October
– PZ85 operational beginning November
August 2006
LHC Access System
Global Planning
•
Installation and Commissioning detail planning
–
–
Integrated within the LHC IC General plan (TS/IC)
• EDMS 769853
Machine and Experiments
•
Deployment:
•
Tests:
•
Follow-up with MTF
–
–
–
–
–
–
–
P8, P7, P4 -> 2006
P1: January 2007
P5: February 2007
P3: March 2007
P6: April 2007
P2: May 2006
Final installation (inter-site doors, biometric identification, dosimeters with RFIDs, grids)
June 2007
• Site functional tests per site at the end of the site installation; in coordination with
machine groups concerned
• Global and Final tests
– at the end of the installation during summer 2007
– special requirements (coordination with different groups concerned, access
restricted to personnel involved in tests)
August 2006
LHC Access System
Tests
• Tests strategy defined all along the I&C phases till
transfer to Operation and Maintenance
– EMDS 497865
– HW, SW Functional and Safety (INB requirements !)
• Tests Phases:
•
•
•
•
•
•
Local acceptance
Integration
Functional Site
Functional Inter-site
Global Tests and Final Tests
AB/DSO INB Tests
• Roles and Responsibilities being defined with different
groups concerned
– project team, contractors, HC, equipment groups, experiments, AB
August 2006
LHC Access System
LASS General Status
• Safety software under development
• Functional software (Man machine interfaces..)
under development
• Electrical design: power supplies, rack installation
drawings, LASS command interface (Pupitre), cable
loop – delays, but progressing well recently
• Goal: follow-up with the installation the pace of the
LACS installation in order to synchronize the testing
August 2006
LHC Access System
Conclusions
• Objectives:
– LASS and LACS operational in LHC7, LHC8, CCC by mid November
2006
• All pieces of the ‘LEGO’ are there or under production
• Planning relies on:
– No major technical issues during integration
– Contractors and subcontractors respect the deadlines
August 2006