Birch bay community park

BIRCH BAY
COMMUNITY PARK
Project Update - March 7, 2017
SITE LOCATION
PLANNING PROCESS
• Site Inventory and Analysis
– Design Survey
– Cultural Resources Analysis
– Site Analysis
• Community Outreach
– 3 Steering Committee Meetings
– 3 Community Workshops
• Development of Master Plan
– Design Alternatives
– Development of the Preferred Master Plan
– Cost Estimate & Phasing Plan
• Phase I - $3,530,000
– On-Site Parking
– Public Restroom
– Beach Access
•
Annual Maintenance
$91,000
• Phase II - $610,000
– Multi-purpose Pavilion
– Open Field Play
– Picnic Areas
•
Annual Maintenance
$108,000
• Phase III - $256,000
– Nature Play
– Additional
– Picnic Areas
•
Annual Maintenance
$110,000