ATLAS upgrade activities for SLHC - Indico

- Alignment
- Manipulation InGrid chips
- Field cage single chip module
Fred Hartjes
NIKHEF
Nikhef/Bonn LepCol meeting
April 10, 2017
Alignment tooling mostly completed
Fred Hartjes
Nikhef/Bonn LepCol meeting. Nikhef. February 27, 2017
2
Vacuum system in
preparation
One channel operational
Waiting for vacuum buffers
Leakage problems due to design errors with
alignment block
Cannot be easily cured
New pickup block has to be made
Fred Hartjes
Nikhef/Bonn LepCol meeting. Nikhef. February 27, 2017
3
Picking chips with InGrid from the box
Manual picking hard
Some rubbing of the vacuum tool on the InGrid surface cannot be avoided
=> damage of the InGrid surface
Tool using small XYZ stage in preparation
Fred Hartjes
Nikhef/Bonn LepCol meeting. Nikhef. February 27, 2017
4
Previous field cage for single chip detector
Made from Semitron ESD 490 HR
Gives field deformations due to inhomogeneity of the material
Fred Hartjes
Nikhef/Bonn LepCol meeting. Nikhef. February 27, 2017
5
New field cage for
single chip detector
Field shaping foil with metal strips to
be placed inside
Strip pitch 1 mm
Network from 17 resistors 470 MΩ
=> ~50 nA leakage current @ 200
V/cm
To be mounted in existing Semitron
field cage
May be verified with N2 laser
Fred Hartjes
Nikhef/Bonn LepCol meeting. Nikhef. February 27, 2017
6