LIU PT 05.11.2015 M. Vretenar and C. Rossi From the 2015 CMAC Report (Cost Review of LIU & HL-LHC): «the large operating cost of the LHC could justify the acquisition of a spare RFQ to address this single-point failure item» • • • • • • • Four-vane structure 3 m length three modules of 1 m each RF frequency 352.2 MHz Energy 45 keV – 3 MeV Between LEBT (2 m) and MEBT 4 years for detailed design, construction and commissioning 1. Essential for operation. 2. Sensitive: small variations to geometry or voltage (coming from deformations or contaminations) critically reduce beam transmission. 3. Exposed to load from ion source (hydrogen, unmatched particles, caesium). 4. Monobloc brazed structure: the 3 modules cannot be opened for repair or modifications. Machining of new modules takes years. 5. Long experience of problems: at CERN (oil pollution, 1989), at JPARC (oil pollution), at SNS (detuning). Laboratories that have foreseen a spare: CERN (Linac2, 1992), JPARC (2010), SNS (ongoing), ISIS. Methodology: Mini-workshop (17.06.2015) with participation of CERN experts in RFQ and in the surrounding systems, with the goal of: a) list all possible failure scenarios; b) collectively evaluate the probability and impact of these failures; c) collectively elaborate mitigations that if applied would reduce probability and/or impact. Participants: C. Rossi (BE/RF), M. Vretenar (DG/DI), A. Lombardi (BE/ABP), S. Mathot (EN/MME), R. Scrivens (BE/ABP), J. Lettry (BE/ABP), J. Hansen (TE/VSC). The team identified and analysed 8 failure modes (risks): 1 2 3 4 5 6 7 8 Risk Electrode damage (sputtering of copper) due to beam loss at the RFQ entrance Electrode contamination due to Cs deposition / normal caesiation. Electrode contamination due to Cs deposition / caesiation accident. Damage of the RF power coupler (mechanical deformation or surface effects) Vacuum degradation due to a cooling circuit water leak (e.g. from erosion of the brazed joints of the water circuit caps). Mechanical deformation of the RFQ. Vacuum contamination of the RFQ from hydrocarbons. Flanges for RF tuner or RF pick-up broken because of mechanical stress. LEVEL DEFINITION LIKELIHOOD 1 Marginal Once in >50 years 2 Low Once in 30-50 years 3 Medium Once in 10-30 years 4 High Once in 5-10 years 5 Very high Once in 1-5 years PROBABILITY LEVEL DEFINITION Total beam loss Reduction of high intensity (Isolde) 1 Negligible Beam stop < 1 hour Reduction < 1 day 2 Marginal 1 hour < Beam stop < 1 day 1 day < Reduction < 1 week 3 Medium 1 day < Beam stop < 1 week 1 week < Reduction < 2 months 4 Critical 1 week < Beam stop < 2 months 2 months < Reduction < 1 year 5 Catastrophic Beam stop > 2 month Reduction > 1 year IMPACT Risk Analysis P I S 1 Certainly occurring, effect is Electrode damage (sputtering of limited because of the low duty copper) due to beam loss at the RFQ 5 1 5 cycle of Linac4 (0.08%) and of entrance the presence of a pre-chopper 2 Certainly occurring, effect is Electrode contamination due to Cs limited because Cs penetrating 5 1 5 deposition / normal caesiation. in the RFQ immediately oxidises (oxide is not e emitter) 3 Electrode contamination due to Cs deposition / caesiation accident. 4 5 6 7 8 Damage of the RF power coupler (mechanical deformation or surface effects) Vacuum degradation due to a cooling circuit water leak (e.g. from erosion of the brazed joints of the water circuit caps). Might happen (ISIS); in the worst case, would require a cleaning of the RFQ Already well protected mechanically, surface problems quite unlikely The caps on the cooling circuits are brazed over a long distance, if happens differential pumping can be applied No stresses present on the Mechanical deformation of the RFQ. cavity, field can be corrected Vacuum contamination of the RFQ Pumps are dry, oil quantity is from hydrocarbons. minimal, voltage is not too high Weldings and brazes are strong, Flanges for RF tuner or RF pick-up are if happens repair or differential broken because of mechanical stress. pumping can be applied 2 4 8 1 4 4 1 2 2 Mitigation Mitigation measures already present: a) surveillance on beam transmission; b) pre-chopper cutting unused beam. Additional measure: a mask in the LEBT to scrape beam out of RFQ acceptance (to be installed when beam is stable). Implement a hard-wired interlock on top of existing procedure to assure that the amount of Cs that can enter the RFQ is always a controlled quantity. Implement a hard-wired interlock on top of existing procedure to assure that the amount of Cs that can enter the RFQ is always a controlled quantity. A "box" around the coupler is already implemented. Additional mitigation would be to build a spare Ridge 1 P' I' S' 3 1 3 3 1 3 1 4 4 1 2 2 No mitigation measure can be envisaged; 2 the risk is evaluated as low. 1 2 3 6 2 4 3 6 Build 12 additional tuners or variable 2 tuners. Accept reduced beam transmission 2 3 6 2 during re-conditioning. 2 4 8 4 2 8 Install a protection on critical elements. 2 Overall cost of the proposed mitigations: about 90 kCHF Conclusion: after applying mitigations (total cost about 100 kCHF), all risks have an impact medium (1 week LHC beam stop) or lower; the medium impact corresponds to risks with marginal probability (every 50 years). The experts look confident that the Linac4 RFQ is quite safe and that problems could be repaired in a time comparable to what needed to install the spare. This is a consequence of the solid design (different from JPARC and SNS) and of the relaxed operating conditions as compared to other RFQs (low duty cycle, conservative field level, relatively long LEBT). Is RFQ technology reaching maturity? BUT: Is our list of risks exhaustive? Are there other unforeseen events that could happen? The error bars in this type of exercises are large, in particular when evaluating events with high impact and low probability. A careful approach should be recommended. We could exploit the fact that CERN is the only laboratory equipped with workshops that can rapidly produce RFQ modules and that some of the failures considered in the risk analysis have a long time constant (from first appearance to impact on operation). (on top of the mitigations identified in the risk analysis) *: full construction at CERN, cost estimated by EN/MME; alternatively, one could build the RFQ outside of CERN
© Copyright 2026 Paperzz