Procuring complex projects using the competitive dialogue: Expected effects Mieke Hoezen Directorate-General for Public Works and Water Management Ministry of Infrastructure and Environment P.O. Box 20000 3502 LA Utrecht The Netherlands Tel +31 (0)6-50929130 Mail: [email protected] Hans Voordijk (corresponding author) Construction Management and Engineering Twente University P.O. Box 217 7500 AE Enschede The Netherlands Tel. +31 53-4894214 Fax. +31 53-4892511 Mail: [email protected] Submission date: December 15, 2010 Number of words: 3853 (article), 4304 (total). WG2. PPP performance in the Transport Sector Procuring complex projects using the competitive dialogue: Expected effects Abstract For the procurement of complex projects, the European Commission (EC) has developed the competitive dialogue (CD) procedure, a procurement system aimed at aligning the complex demands of principals with the possible solutions of contractors. The objective of this study is to uncover expert expectations of the effects of the CD procedure. The objectives of the European Commission in designing the CD procedure are put alongside expectations of 33 experts. Although in theory the procedure’s design should meet the EC’s objectives of dialogue, competition, innovation and trust, experts in the Dutch construction industry expect the following negative side-effects: large transaction costs, lack of clarity about when the procedure is allowed to be used, risk averseness and opportunistic behaviour of the parties involved, and a lack of openness. These side-effects could cause that the actual effects of the CD procedure are less positive than expected ahead. Keywords: Contractor selection, construction, procurement, side-effects, expectations 1. Introduction In the past decades, the procurement of large infrastructure projects has gone through three major developments. First, projects are becoming larger (Baccarini, 1996; Laufer et al., 1996); qualitative demands are increasing (for example in sustainability); time pressure is growing; demands to restrict congestion and nuisance are getting louder; public expenses are watched more closely and, due to new developments, it is increasingly difficult to foresee all possible solutions to a problem (Alderman et al, 2005; Walker, 2007, p.51). Second, the relation between the market and government changed through liberalisation, privatisation, and deregulation (Blanken, 2008; Pierre, 1997; Linder, 1999; Ter Bogt, 1997) The EC introduced rules meant to encourage strong competition in parts of the public sector. These rules resulted in the transfer of tasks from the public sector to private organisations. Third, in recent decades, the construction sector has been characterised by fragmentation, a lack of client-orientation, innovation, productivity, and transparency (Emmerson, 1962; Latham, 1994; Egan, 1998; National Audit Office, 2001). The combination of increased project complexity; changed role of the government; and the construction sector’s poor professional functioning form the context of the design of a new procurement procedure, the Competitive Dialogue (CD) procedure introduced by the European Commission in 2004. This procurement method consists of several discussion rounds between the principal and potential suppliers, during which all aspects of the tender can be discussed. The CD procedure assists contracting authorities to procure complex projects in which technical specifications and price levels can be defined during the dialogue rather than being predetermined. The CD procedure aims to align complex demands of principals with possible solutions that contractors have to offer (Hebly and Lorenzo van Rooij, 2006). According to the EC, the objective of the CD procedure is to provide “a flexible procedure […] which preserves not only competition between economic operators but also the need for the contracting authorities to discuss all aspects of the contract with each candidate” (2004/18/EC, recital 31). The Committee for Economic and Monetary affairs advised the European Parliament that “the content and limits of the negotiated procedure should be made transparent for both contracting authorities and contenders and, in the interests of both parties, should provide the basis for collaboration based on trust” (A5-0378/2001, p.100). Another suggested objective of the procedure was to give “the contracting authority the opportunity to appropriate the results of participants’ inventiveness and innovation” (CES0515/2001, par. 4.4.2)). The ideas on “collaboration based on trust”, the “innovation stimulus” and “appropriation” play an important role in the rhetoric and justification of the competitive dialogue and in its rolling out in practice. Thus, the CD procedure was meant to create more dialogue, competition, innovation and mutual trust in the procurement of complex construction projects. This study is an attempt to uncover expert expectations of the effects of the CD procedure. For this purpose, the following experts were interviewed: academic and legal experts, procuring agents, contractors and advisors. Main consideration was the idea that the design of the procedure would cause side-effects which might have taken into account too little by the policy makers. This paper answers the question which (side)-effects do experts and stakeholders in the Dutch construction industry expect from the design of the CD procedure. The outline of this study is as follows. After a short description of the study design (including the research method used, the participants selected and the analysis method), the results will be presented: the expected (side)-effects of the CD procedure. 2. Research design This study is an attempt to uncover expert expectations of the effects of the CD procedure. For this purpose, experts were interviewed from several of the fields involved: i.e. academic and legal experts, procuring agents, contractors and advisors. 2.1 Individual, semi-structured expert interviews The semi-structured interviews consisted of three main parts. Part A served to assess the general opinion of the experts about the CD procedure. Part B considered the positive and negative elements of the CD procedure’s design. Part C was included to determine how the experts envisaged the effects of the CD procedure in terms of both project control and the objectives of the CD procedure as formulated by the European Commission. This last part was added to part A and B for two reasons: first, the project control indicators of time, costs and quality are common effectiveness indicators in construction projects. Second, the objectives of the European Commission, as the instigator of the procedure, are the main objectives to be evaluated in an effectiveness analysis and should therefore be included. In each part, an open question was first asked to allow participants to express their basic ideas. The next step was to narrow the question so as to acquire results that would be easier to compare. 2.2 Experts To achieve a balanced and comprehensive overview, a range of Dutch experts with experience in the CD procedure were approached for this study. Using the PSIBouw network (a Dutch organisation for stimulating innovation in the construction industry), we selected between seven and ten prominent individuals from each of the key expert groups and invited them to participate in our study. Of the 35 selected experts, only two (a lawyer and an advisor) declined to take part. The interviewed persons were experts or stakeholders in a certain field and also representative of a specific group of experts/stakeholders. Table 1 gives an overview of the groups and the functions of the interview participants, who are referred to as experts. Table 1 Expert / stakeholder groups Main group A. Law / science Function 1 Professor in Dutch private law, contract law, construction and procurement law 2 Professor in Construction law, lawyer in construction and procurement law 3 Lawyer in e.g. construction, development, international arbitration, joint ventures, projects, public procurement 4 Attorney and lawyer in corporate law transactions, privatisations, large-‐scale contracting processes, PPP and project financing 5 Lawyer in environment and planning practice, including PPP 6 Chartered accountant and senior lecturer at the European Institute of Public Administration in PPP, public procurement and comparative public service delivery B. Procuring agencies 1 Infrastructure project manager Dutch Public Works and Water Management 2 Contract manager Dutch Public Works and Water Management 3 Project manager Dutch Public Works and Water Management 4 Project director Dutch Public Works and Water Management 5 Advisor PPP Dutch Public Works and Water Management 6 Senior Financial Advisor Dutch Public Works and Water Management 7 Senior advisor Market relations and procurement Dutch Public Works and Water Management 8 Purchasing manager Dutch Public Works and Water Management 9 Advisor to the Infrastructure Board of the Dutch Public Works and Water Management C. Industry (contractors) 1 Project and contract manager, large construction firm 2 Director Concessions, large construction firm 3 Director PPP, large construction firm 4 Project manager from a large infrastructure construction firm 5 Project manager for discipline and work exceeding projects, large construction firm 6 Director PPP Projects, large infrastructure firm 7 Project manager PPP, large construction firm 8 Project director, large construction firm 9 Project director, small construction firm 10 Director Integral Projects, large construction firm D. Advisors 1 Senior Consultant in Contract and Project Management, large engineering firm 2 Senior Consultant, large engineering firm 3 Senior advisor, association of Dutch construction and infrastructure firms 4 Consultant, project management firm 5 Consultant in Contract management and Procurement, consultancy firm 6 Management consultant, consultancy firm 7 Senior consultant, project management firm, Partner for infrastructural projects in the Dutch network of innovators in construction 8 International Procurement Policy Advisor at the Office of Government Commerce 2.3 Analysis The qualitative data analysis software QSR Nvivo was used in the analysis of the transcribed interviews. After transcription, codes (called ‘nodes’ in NVivo) were assigned to text fragments using a ‘top-down’ approach for Parts A and C of the interviews, and a ‘bottom-up’ approach for Part B. The top-down approach is based on an a priori coding scheme with tree nodes (See Table 2), whereas the bottom-up approach starts without any such strong prior assumptions. Table 2: Coding scheme for Parts A and C of the interviews Part A C Tree nodes Family node ADDED VALUE EXPECTATIONS Parent node FOR CONTRACTOR FOR CONTRACTING AUTHORITY FOR OTHERS PROJECT CONTROL EC OBJECTIVES OTHER Child node QUALITY TIME COSTS DIALOGUE COMPETITION INNOVATION TRUST 3. Results 3.1 Part A: Added value of the CD procedure The first question asked enabled the experts to explain the added value they expected from the new CD procedure compared to the already existing negotiated and restricted procedures. To start, all the experts mentioned the fact that, with the CD procedure, one had a procurement procedure in which it is possible to ‘have a real conversation’, ‘communicate’, ‘be given much more information than is possible in writing’ or ‘go into detail’. The value of this lies, according to all the experts, in the fact that this makes possible ‘a proper alignment of problems and solutions’, ‘explanations when something is unclear’ and ‘better mutual understanding’. However, in reacting to the statement that all features of the CD procedure are already incorporated in the existing negotiated and restricted procedures, opinions differed. The legal/academic expert group tended to think that strictly speaking, both the negotiated procedure and the restricted procedure did offer the possibility of conversations between procuring agencies and contractors. Within the negotiated procedure this possibility is more obvious than in the restricted procedure, and since none of the experts in this group actually knew of an example of a ‘real’ conversation within a restricted procedure, one cannot be sure that this interpretation of the law (that this kind of conversation is allowed in a restricted procedure) is correct. Nevertheless, four of the six legal experts were convinced of the technical possibility. Except for two members of the advisors’ group and one from the group of procuring agencies, this opinion was not shared by other experts. The other experts were convinced that a conversation similar to the dialogue in the CD procedure was not possible, or allowed for, in the restricted procedure. An additional advantage of the CD procedure is the fact that both the contractor and the contracting agency are able to become comfortable about the bid at an early stage. The contracting agency is allowed to ask contractors to submit elements of their bid (except for the bid price) during the dialogue stage of the CD procedure, and they are allowed to comment on these parts. These comments make the contractors feel more comfortable that their bid matches the expectations of the contracting agency. On the other hand, the contracting agencies feel better able to prevent contractors making invalid bids than was possible with the negotiated procedure. In the negotiated procedure it was not uncommon to have invalid bids (bids that did not meet the selection criteria), ending in frustration on both sides: the bidders wasted their efforts, and the contracting authorities might have no valid bids to choose from. This first part of the interview shows that the experts agree that the biggest added value of the CD procedure, compared to existing procedures, is the fact that it offers the ability to have a structured, officially sanctioned conversation between the procuring agency and contractors, during which a fit between problems and solutions can be sought. The expected effect of this is that complexity will be decreased, while cooperation, competition and dialogue will be stimulated, and division of tasks and risks will become more balanced. 3.2 Part B: Positive and negative elements of the CD procedure’s design Positive elements Generally, three elements were mentioned as the most positive within the CD procedure. The first element covers the interests of the contractors. The experts all think that the Directive secures those interests well, since cherry-picking is explicitly forbidden. Although the Directive insists contracting authorities to act transparently, it also makes clear that confidential information may not be shared with others than the contractor concerned, unless they agree with sharing. The way in which the CD procedure is shaped in projects of the Dutch Public Works and Water Agency creates an even stronger base to build on. The system of general and special clarifications is clear to all experts, and assessed positively. The second element covers flexibility in demand specifications. When contractors come up with solutions which are, for example, more efficient or cheaper, but do not exactly fit the initial demand specifications, the contracting authority is allowed to make adaptations to its initial specifications. As one would expect, the contracting agency experts were positive about this element but the group of contractor experts and advisors were also positive. The group of legal/academic experts had more reservations than the other groups (see the negative elements, below), but also mentioned this element. The third positive element is the possibility to focus on the content instead of on the price. With the CD procedure, the bid price only enters the procedure at the moment of final bidding. Until then, the conversation during the CD procedure can focus on the quality elements of the bid. The constant returning to the bid price, as was the case in the negotiated procedure where it was continuously the subject of the negotiations, should not occur with the CD procedure. Especially the group of advisors mentioned this as a positive element of the CD procedure. This part of the interview indicated that the experts agree that three other elements are important alongside the possibility of interaction, which is the most positive element of the CD procedure. These are the security of the contractors’ interests, the possible flexibility in demand specifications, and the fact that bid price does not come into play until the end. All lead to the expectation that the conversation will focus on the content of the bid rather than its price. These three elements together are expected to positively affect trust, competition, dialogue and innovation. Negative elements All experts mentioned the transaction costs of the CD procedure as its most negative element. Although this is not a direct element in the design of the procedure, it is closely related to the fact that intensive conversations are held with several contractors. Whereas, in the negotiated procedure, the contracting agency negotiated with just one contractor, in the CD procedure the agency conducts dialogues with often three to five contractors. This means that more contractors have to work out more details for a potential project. Thus, the costs of taking part in a CDprocured tender are high. This does not just affect contractors; contracting authorities make large transaction costs as well. All the products of the various contractors should be assessed, all clarification requests should be answered, and not just for one contractor but for maybe five of them. Further, the contracting authorities usually pay a design fee to potential contractors to cover part of the costs incurred, to stimulate them to take part and be innovative. The second negative element mentioned is the effect of adaptations to the design specifications, made in response to innovative ideas which did not meet the initial demand specifications. First, there is the fact that when the demand specifications are changed, this change applies to the demand specifications for all contractors, not just the one who suggested an innovation. Given that confidential information should not be communicated directly or indirectly to other contractors, changes made to demand specifications should not reveal the innovative ideas that led to the changes. Further, only small changes in the demand specifications are allowed since the contracting authority must assure a ‘level playing field’. That is, the interests of not only the competing contractors, but also those of other parties have to be taken into account. Summarising, this part of the interview process revealed two major negative elements in the CD procedure’s design: its effect on the transaction costs of both contracting authorities and contractors, and the requirement of a level playing field resulting in fewer openings for innovation. 3.3 Part C: Other expectations Project control With regard to the quality of projects, all the experts agreed with the statement that they expected the quality of the projects to increase as a result of the CD procedure. As to their reason for thinking that, they all mentioned the possibility of matching problem issues with possible solutions. By having a conversation about the real issue (the background to the demand specifications) a better fitting solution could be sought. Alongside this, the fact that all elements could be open for discussion meant that not only the technical, but also the financial and legal optimum conditions could be designed. This was expected to improve the quality of projects. In terms of reducing the time overrun of projects, the experts also expected a major contribution from the CD procedure. Although the procurement time was expected to be longer when the CD procedure was used, the experts thought that the conversations between contracting authorities and contractors would also focus on the risks of the project. By considering the risks, contractors should be better able to predict the time needed for project construction, and to assess the risks that could influence the delivery time. This is, however, to an extent dependent on the incentive agreements, whether the contractors will see time overrun as their problem, or that of the contracting authority. Experts found it difficult to respond to the statement that cost overruns would decrease as a result of the CD procedure. Their answers generally involved three elements: transaction costs, risk and the fit between problem and solution. All the experts emphasised that the costs for the tender phase of CD procured projects will be higher than for other projects. Nevertheless, 31 of them also expected that, due to the improved fit between the problem and possible solutions, there would be efficiency gains, and thus lower prices, which would compensate for the higher transaction costs. Alongside this, 12 of the experts added that, by talking about the risks, contractors would be better able to predict construction costs by being able to estimate the potential costs of risks that could affect the project. Overall, the experts’ expectations in terms of project control were positive. The general opinion was that, as a result of talking over risks as part of the dialogue, the CD procedure would contribute to the quality of projects as well as to a decrease in time and cost overruns. EC objectives Experts held high expectations of the dialogue. As such, it is not surprising that they unanimously agreed with the statement that the CD procedure is expected to facilitate a conversation between the contracting agencies and contractors. The intended meaning of the statement on competition “I expect that there will be greater competition in CD-procured tenders than was possible with the negotiated procedure” was unclear to the experts. Although some of the legal/academic experts understood the idea behind the statement, most of the experts needed further explanation. When the researchers explained the idea was that having dialogue with more than one contractor would offer greater competition than with only one, most experts tended to agree, but without being able to add further justifications to those offered by the researcher. All the experts expected innovation to be stimulated through CD procurement. By focusing on the problems of the contracting authority, rather than on a predetermined solution, the creativity of the contractors would be stimulated. A contracting authority should therefore design qualitative MEAT criteria (Most Economically Advantageous Tender), accept a fair allocation of risks and be willing to adjust the demand specifications if necessary. Although three of the experts pointed out the possible problems with the level playing field requirement, most of them simply expected innovation to be stimulated by the CD procedure. In concluding each interview, a final statement was posed: “I expect the CD procedure to contribute to a trust-based relationship between the contracting authority and the contractor”. Here, a large number of the experts linked this statement directly to the possibility of having a conversation. Essentially, talking to others over a longer period of time is seen as generally creating some kind of mutual understanding. However, two of the experts stated that, for trust to grow, both parties would have to open up to it. If that is not the case “then no CD procedure will contribute to trust anywhere”. The last element of the interview shows that experts do not have many expectations concerning the element of competition within the CD procedure. However, the expectations on other aspects (dialogue, innovation and trust) were mainly positive. In terms of innovation, the experts emphasised that it was up to the contracting authorities to create conditions in which innovation could flourish. 4. Conclusions and further research Experts from the four groupings (law/science; contracting agencies; contractors and advisors) all share the opinion that the CD procedure adds value compared to existing procedures in that it offers the possibility to have structured, officially allowed conversations between procuring agency and potential contractors, during which a fit between problems and solutions can be sought. The general expectation is that the CD procedure will contribute to the quality of the projects as well as to a drop in time and cost overruns. Most of the perceived positive aspects of the CD procedure, alongside these interactions, are related to the security of the contractors’ interests, the possible flexibility in demand specifications and the focus on the content of the bid rather than its price. Most of negative aspects mentioned relate to the high transaction costs and the requirement to maintain a level playing field which is seen as limiting potential innovation. In terms of boosting competition, one of the objectives of the CD procedure, experts seem to have few expectations. However, the views on the other expectations, concerning dialogue, innovation and trust, were mainly positive. It can be concluded that experts expect that, despite some counteracting elements and mechanisms, the objectives of the CD procedure will be met through its use. Since the experts’ expectations discussed above were not based on experience with the procedure, practice might show that some predicted effects did occur, whilst others did not. The use of the CD procedure could lead to unforeseen effects. Further research on these mechanisms is necessary Literature Alderman, N., Ivory, C., McLoughlin, I. and Vaughan, R. (2005) Sense-making as a process within complex serviceled projects. International Journal of Project Management, 23(5), 380– 385. Baccarini, D. (1996) The concept of project complexity – a review. International Journal of Project Management, 14(4), 201-204. Blanken, Anneloes (2008) Flexibility against efficiency? An international study on value for money in hospital concessions. Enschede, University of Twente. Bogt, H.J. ter (1999) Financial and Economic Management in Autonomized Dutch Public Organizations. Financial Accountability & Management, 15(3–4), 329–51. 2004/18/EC (2004) DIRECTIVE 2004/18/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts. Brussels, 31 March 2004. A5-0378/2001 (2001) ***I REPORT on the proposal for a directive of the European Parliament and of the Council on the coordination of procedures for the award of public supply contracts, public service contracts and public works contracts (By the Committee on Legal Affairs and the Internal Market of the European Parliament). Brussels, 29 October 2001. CES0515/2001 (2001) OPINION of the Economic and Social Committee on the Proposal for a Directive of the European Parliament and of the Council on the coordination of procedures for the award of public supply contracts, public service contracts and public works contracts. Brussels, 26 April 2001 Egan, J., 1998. Rethinking Construction. HMSO, London. Emmerson, Sir Harold (1962) Survey of Problems Before the Construction Industries. Report prepared for the Minister of Weoks. HMSO, London. Hebly, J.M. and Lorenzo van Rooij, N. (2006) European Public Procurement: Legislative History of the ‘Classic’ Directive 2004/18/EC, Kluwer Law International, Alphen aan den Rijn. Latham, M. (1994) Constructing the Team. HMSO, London. Laufer, A., Denker, G.R., and Shanhar, A.J. (1996) Simultaneous management: the key to excellence in capital projects. International Journal of Project Management, 14(4), 189-199. Linder, S. (1999) Coming to Terms with the Public-Private Partnership. A Grammar of Multiple Meanings. The American Behavioral Scientist, 43(1), 35-51. National Audit Office (2007) Improving the PFI process. National Audit Office, London. Pierre, D. (1997) Conditionality as an Instrument of Borrower Credibility. International Monetary Fund Paper on Policy Analysis and Assessment 2. Walker, A. (2007) Project Management in Construction. 5th ed. Blackwell Science: Oxford.
© Copyright 2026 Paperzz