RFPEG2013 PRE-BID MEETING RFPEG2013 – Pre-Bid meeting January 9, 2014 Presentation by Derek Davis – Public Utilities Commission Historic Demand and Energy Generation Planning Perspective - • Demand Growth 4.34% PA Demand & Energy 2002 to 2012 600.00 90.00 80.00 500.00 70.00 • Net Gen Growth 5.3% PA 60.00 50.00 300.00 MW GWhs 400.00 40.00 200.00 30.00 20.00 100.00 • LF Improved 67% to 73.5% 10.00 - 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Net Generation & Purchases 315.24 347.76 377.86 403.82 417.68 438.71 463.59 472.81 483.27 492.84 528.17 Total Sales 278.95 307.55 329.98 349.73 359.59 381.76 406.99 417.37 426.23 428.49 462.17 Maximum Demand 53.70 57.40 61.10 63.50 66.60 70.00 74.30 76.20 80.60 79.30 82.09 Year Net Generation & Purchases Total Sales Maximum Demand - • Losses Maintained approx. 12% Generation Planning Perspective - Sources of Generation 2012 • Observations SOURCES OF GENERATION (TOTAL 528 GWHS) • Low Hydrology Year – 15% below average Hydro 40% HFO & Diesel 3% Imported from Mexico 45% Other 55% Bagasse 12% • Generation From Bagasse also Low by 15% • Prices from Mexico Higher than expected by 30% at average US$ 0.18/KWh Demand and Energy Forecast done by SIEMENS 2009 LCEP Study Generation Planning Perspective - • SIEMENS Methodology • Forecast Period 2007 to 2028 • Regression with GDP and Population – Full system • Zone Forecast based on historical regression • Consideration of additional Special Customers Demand Forecast for Generation Planning PUC – (Growth:- Lo – 1.5% - Expected – 4% - Hi – 6.5%) Generation Planning Perspective - Year Units BEL System Maximum Demand 1.50% Low Forecast 4.00% Medium Forecast 6.50% Hi Forecast MW 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 82.09 82.09 83.32 84.57 85.84 87.13 88.43 89.76 91.10 92.47 93.86 95.27 96.70 82.09 85.37 88.79 92.34 96.03 99.87 103.87 108.02 112.34 116.84 121.51 126.37 82.09 87.42 93.11 99.16 105.60 112.47 119.78 127.56 135.86 144.69 154.09 164.11 Generation Planning Perspective - Planning Criteria • LOLP – Loss of Load Probability • The expected value of the number of days in a year in which the available generation cannot supply the system peak load. There are many ways to calculate this indicator, some more accurate than others. • Percent Reserve • The reserve Generation (positive or negative) as a percentage of annual peak demand • There is correlation between these 2 indicators for a particular Power System • For BEL’s Grid system - LOLP of 3 days/year equivalent to approximately 30% Reserve • LOLP usually gives medium to long term performance of Generation System. Short term usually different. • For BEL’s Grid System 2013 there were outages but no cases of outages due to lack of generation Generation Planning Perspective - Generation Requirements Firm Capacity Analysis BEL's Power Grid 2012 to 2023 Year Units 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Avaiable Firm Capacity From ALL Sources Cascade Hydro (Chal/Moll/VACA) BELCOGEN - Bagasse and 2 by 2 MW HFO Units Hydro Maya - Hydro BEL Gas Turbine - Diesel BAL/ BAPCOL - 2 by HFO Units JICA - Solar Facility - 480 KWp Mexico - CFE - Interconnection Firm Capacity Generation Additions RFP 2013 (projected) MW MW MW MW MW MW MW MW 17.66 7.00 20.00 50.00 - 17.66 7.00 20.00 15.00 50.00 - 17.66 7.00 20.00 15.00 50.00 - 17.66 11.00 20.00 15.00 50.00 - 17.66 11.00 20.00 15.00 50.00 25.00 17.66 13.50 20.00 15.00 50.00 25.00 17.66 13.50 20.00 15.00 50.00 25.00 17.66 13.50 20.00 15.00 50.00 40.00 17.66 13.50 20.00 15.00 50.00 40.00 17.66 13.50 20.00 15.00 50.00 40.00 17.66 13.50 20.00 15.00 50.00 60.00 17.66 13.50 20.00 15.00 50.00 60.00 Total Firm in Country Total Firm incl. CFE MW MW 44.66 94.66 59.66 109.66 59.66 109.66 63.66 113.66 88.66 138.66 91.16 141.16 91.16 141.16 106.16 156.16 106.16 156.16 106.16 156.16 126.16 176.16 126.16 176.16 BEL System Maximum Demand Low Forecast Medium Forecast Hi Forecast MW 82.09 82.09 82.09 82.09 83.32 85.37 87.42 84.57 88.79 93.11 85.84 92.34 99.16 87.13 96.03 105.60 88.43 99.87 112.47 89.76 103.87 119.78 91.10 108.02 127.56 92.47 112.34 135.86 93.86 116.84 144.69 95.27 121.51 154.09 96.70 126.37 164.11 Low Med Hi Percent Reserve - In Country % % % -46% -46% -46% -28% -30% -32% -29% -33% -36% -26% -31% -36% 2% -8% -16% 3% -9% -19% 2% -12% -24% 17% -2% -17% 15% -6% -22% 13% -9% -27% 32% 4% -18% 30% 0% -23% Low Med Hi Percent reserve Incl. CFE Mexico % % % 15% 15% 15% 32% 28% 25% 30% 24% 18% 32% 23% 15% 59% 44% 31% 60% 41% 26% 57% 36% 18% 71% 45% 22% 69% 39% 15% 66% 34% 8% 85% 45% 14% 82% 39% 7% 1.50% 4.00% 6.50% Generation Planning Perspective - Observations Median Forecast (4% per annum) used to determine Generation additions Initial period shows generation reserves as inadequate <30% Earliest addition possible assumed to be in 2016 Consideration of in-country sources very important Percent reserve of -10% to be maintained This allows System Generation + Self-Generation of customers to meet demand Generation Planning Perspective - Candidate Units Firm Power – RFPEG2013 • Firm Power – Least Cost Expansion Plan to be developed (Dispatch Simulation Exercise) • 60 MW over the period from 2013 to 2023 • Eligible Bids/Proposals under RFPEG2013 become candidate Units Hydro With storage and effective Firm capacity Located on the Macal River – Challilo Dam provides storage Located on other Rivers – Needs Storage Thermal Diesel/HFO Natural Gas Coal/LPG??? Dedicated contracts with plants in Mexico - Wheeling Generation Planning Perspective - Other Candidate Units – RFPEG2013 Bio-mass bagasse Cohune Nuts Other Sources – Grass etc. Energy Efficiency – Not a part of RFPEG2013 – GOB initiative Lighting/Roadway Lighting Air-conditioning Water Heating Generation Planning Perspective - Evaluation Firm Power under RFPEG2013 • Firm Power Bids Received to be analyzed to ensure responsiveness and feasible and ranked based on evaluation criteria • Then used in a 15 Year planning dispatch simulation exercise to satisfy Grid Generation Reserve Requirements and minimize the Cost of Power (Total Capacity plus Energy Costs for the 15 Year period) • Existing Power Supply contracts must be taken into account • The flexibility of Dispatch and price of proposals shall ultimately determine the success of proposals • Negotiations to be held with bidders whose proposals are a part of the 15 Year Least cost generation plan Generation Planning Perspective - Candidate Units Intermittent Power – RFPEG2013 • Consideration of non-firm RE sources after Firm Power Analysis - Solar/Wind/Run-of-River Hydro/Etc. • Grid Power System variable cost to be considered displaced when RE dispatched • Identification of opportunities to further lower Generation Cost by addition of RE intermittent sources • Commitment to add 15 MW over the period 2013 to 2023 at lowest possible cost Solar with/without Mexico Intermittent – phased in System problems if too much > 15% of peak demand. CFE ? Wind – with/without Mexico Intermittent – phased in System problems if too much > 15% of peak demand. CFE ? Tracking/No Tracking JICA experience for CF – 16% Source/Methodology to determine Wind speed characteristics to be declared Generation Planning Perspective - Evaluation Intermittent Power under RFPEG2013 • Non-Firm Power Bids Received to be analyzed to ensure responsiveness and feasible and ranked based on evaluation criteria • Then used in a 15 Year planning dispatch simulation exercise assuming the displacement of generation variable costs • Existing Supply contracts must be taken into account • The set of non-firm projects totaling 15 MW over the period 2013 to 2023 with LOWEST COST shall be considered for negotiations Generation Planning Perspective - Grid Interconnection Costs & Transmission Strengthening • Grid Interconnection will be required for ALL Projects • BEL to provide Estimates to be added to proposal costs • Transmission System Reinforcement • If needed the BEL to cost for addition to proposal cost • In some cases Transmission reinforcement is only accelerated • In the case of acceleration only accelerated cost will be added to proposal Generation Planning Perspective - Potential additional opportunities outside the country of Belize • For such projects developer to identify market • Developer responsible to get PPA with external parties • Developer to negotiate wheeling with BEL/PUC if feasible • GOB may assist • PUC/BEL not responsible market prices or failure • No price transfer shall occur under any circumstances to Belize Electricity customers Generation Planning Perspective - CFE Mexico Dispatch 2013 to 2023 – The way we see it Projection CFE Purchases Energy/% of Net generation 350.00 60.00% 300.00 50.00% 250.00 40.00% GWhs 200.00 30.00% 150.00 20.00% 100.00 10.00% 50.00 - 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Mexico - CFE Purchases 265.65 295.11 326.12 148.10 182.49 218.69 138.56 178.71 220.98 107.81 154.67 CFE Purchases % of Net generation 47.77% 50.39% 52.89% 22.81% 26.69% 30.38% 18.28% 22.39% 26.29% 12.18% 16.60% Year 0.00% Generation Planning Perspective - Belize/Mexico – Long Term Relationship CFE Mexico will remain important to the Belize Power System Spinning Reserve Service Absorb VARs during Light Load periods Static VAR Compensator – Voltage Control Frequency Control/System Black Start/Emergency Energy sales/Low cost energy sometimes
© Copyright 2026 Paperzz