C7844 Rise and Fall Summary - Department of Transport and Main

Rise and Fall Summary
C7884
Contract Number:
Payment Certificate
Final Certificate
Certificate number
Schedule works completed this payment period.
Pn (this period) – Pn-1 (last period) = (†1) (P)
$
Value of Directed Variations of Schedule Items (Amount from Form C7887A) (Q1)
$
Value of Work Carried Out After the Date for Practical Completion for this period (T)
$
Value of bitumen for this period in accordance with Annexure B, Commercial
Framework, Clause 5, (A x B) (U2)
$
Certified Amount for Payment (Unadjusted for Rise and Fall) P + Q1 – T – U2 = E
The value of the Road and Bridge Construction Index for the quarter prior to the
month tenders were required to be lodged (†2) (F)
The value of the Road and Bridge Construction Index for the quarter prior to the
month during which the work is performed (†2) (G)
Adjustment for Rise and Fall This Certificate
0.85 x (G - F) x E
F
(H)
$
(†1) From Form C7883
(†2) The Road and Bridge Construction Index (RBCI) is as stated in Table 17 of
ABS Catalogue Number 6427.0 (Producer Price Indexes, Australia).
Compiled by
Administrator for the Contract
Name
Signature
Date
The Department of Transport and Main Roads collects personal information on this form so that you may compile and certify
the Rise and Fall Summary. The information on this form is accessible by authorised departmental officers and external
personnel who are engaged to administer the Contract who will not disclose your personal details to a third party without your
consent unless required to do so by law.
Transport Infrastructure Contract, Transport and Main Roads, April 2015
1 of 1