15MWac UTILITY SCALE SOLAR FARM Municipal Association of Victoria 12th July 2016 THE PROJECT • Sunshine Coast Council 100% Financing a 15MWac PV build – Located within SCC boundary – Grid connected – Initially provide 30GWh power annually • • • • Exhaustive 4 year process Reached Financial Close EOI/Tender process for D&C and O&M Construction is underway THE PLAN THE DRIVERS • Renewable Policy – – – – Climate Change & Peak Oil Strategy 2010-2020 Energy Transition Plan 2010-2020 Rural Futures Strategy Regional Economic Development Strategy 2013-2033 • Is Policy at all Cost? • ‘Traditional’ Renewable Project delivery not financially viable – PPAs, commercial providers, Green Power etc • Renewables Policy created an ‘Investment Problem’ FRAMING THE BACKDROP Electricity Cost Category Energy Usage Carbon Charges Electricity Network Charges Streetlight Service & Maintenance Other Charges Total 30 year Net Present Cost Forecast ($millions) $(78.7) m $(132.8) m $(98.5) m $(9.4) m $(319.2) m FRAMING THE BACKDROP Electricity Cost Category Energy Usage Carbon Charges Electricity Network Charges Streetlight Service & Maintenance Other Charges Total 30 year Net Present Cost Forecast ($millions) $(78.7) m $(132.8) m $(98.5) m $(9.4) m $(319.2) m Can enough be saved on energy usage to justify Investment? THE ALTERNATIVE Electricity Cost Category 30 year Business as Usual 30 year Solar Farm ($millions) Saving / (Cost) Energy Charges ($78.7)m ($35.4)m $43.3m Total Energy Usage Cost ($78.7)m ($35.4)m $43.3m Capital and financing costs - ($50.4)m ($50.4)m Operating cost - ($10.6)m ($10.6)m Large scale generation certificate income - $22.6m $22.6m Electricity Export - $12.8m $12.8m Solar farm terminal Value - $4.4m $4.4m ($78.7)m ($56.6)m $22.1m Total costs THE ALTERNATIVE Electricity Cost Category 30 year Business as Usual 30 year Solar Farm ($millions) Saving / (Cost) Energy Charges ($78.7)m ($35.4)m $43.3m Total Energy Usage Cost ($78.7)m ($35.4)m $43.3m Capital and financing costs - ($50.4)m ($50.4)m Operating cost - ($10.6)m ($10.6)m Large scale generation certificate income - $22.6m $22.6m Electricity Export - $12.8m $12.8m Solar farm terminal Value - $4.4m $4.4m ($78.7)m ($56.6)m $22.1m Total costs THE ALTERNATIVE Electricity Cost Category 30 year Business as Usual 30 year Solar Farm ($millions) Saving / (Cost) Energy Charges ($78.7)m ($35.4)m $43.3m Total Energy Usage Cost ($78.7)m ($35.4)m $43.3m Capital and financing costs - ($50.4)m ($50.4)m Operating cost - ($10.6)m ($10.6)m Large scale generation certificate income - $22.6m $22.6m Electricity Export - $12.8m $12.8m Solar farm terminal Value - $4.4m $4.4m ($78.7)m ($56.6)m $22.1m Total costs LGAs – THE IDEAL RENWABLE INVESTOR • Council is its own customer – Removes margin and credit risk making it cheaper • Not a selective use of capital – One way or another electricity usage is going to cost ~$80million • • • • Low financing costs Council is not looking for excess returns Longer-term view Economic and Social benefits – No value to a commercial player THE CHALLENGES • Community concerns – Visual Amenity – Property Value Impact – “How can Council do this if a commercial player cannot’ • Site location is a critical constraint – Grid connection is key & cheap land comes with it’s own issues • Grant Funding • General scepticism • Managing the internal decision process THE BENEFITS • Exceeding Community endorsed Policy aims (with Savings!) • SCC - 100% green power (~30GWh annually) • Reinforcing Sustainable Regional Credentials – Drives local investment and growth • Leverage natural Social & Environmental benefits – Budget for a learning/R&D centre with Education programs, school visits • Near term/follow on Economic investment – Cleantech sector investment encouraged • Strengthen Academic ties CONTACT Gary Kelly Director – Resource Analytics Mobile: 0429 441 834 Email: [email protected]
© Copyright 2026 Paperzz