SafeTrack: Surge 1 June 4‐16: Ballston to East Falls Church Track 1, Continuous Single Tracking Final report: Data as of 06/22/16 The focus of Surge 1 is to repair/replace track and other rail infrastructure elements to provide a system that is free from safety defects, improves service reliability by eliminating speed restrictions and improves ride quality. Surge 1 finished on June 16, 2016, with almost all tasks completed. As a result, this section of track 1 from Ballston to East Falls Church was brought into a state of good repair. Overall Progress (% Planned Work Complete) Actual Work Complete All 0% 20% 40% 60% 0% 20% 40% 60% 40% 60% 20% 40% 60% 20% 40% 60% Track Structures 0% Automatic Train Control System 0% 20% Traction Power 0% | | | 80% 100% | | | | 80% 100% | | | | 80% 100% | | | 80% 100% | | *Rescheduled Work | 80% 100% During the surge, priority was given to addressing potential safety defects and repairing or replacing critical rail infrastructure that affects train speeds and ride quality. Additional regular and preventive maintenance activities were fit in as time permitted. These maintenance activities are and will continue to be conducted on a regular basis during non‐revenue hours to keep the infrastructure in a state of good repair. Critical tasks accomplished during the surge include: + Replacement of over 1,800 crossties + Renewal of over 540 insulators + Renewal of over 3,100 linear feet of spot rail + Inspection and repair of 30 power cables and 24 expansion cables In some cases, work crews were able to accomplish more than originally planned, such as renewing about 500 additional fasteners and inspecting and repairing about 70 additional Intrustion Detection Warning (IDW) systems. *Rescheduled work: one task remains for traction power +Two junction boxes will be inspected and repaired when crews return to this area during surge 5 at the end of July *Surge #1 results are preliminary and subject to quality control processes which will remain continuous throughout the duration of SafeTrack. Any remediation work that is identified will be accomplished during normal maintenance times, without impacting passenger service. SafeTrack: Surge 1 Detailed Report 6/22/2016 Asset Class (public reporting) Track Track Track Track WMATA Unit TRST TRST TRST TRST Key Tasks Crosstie renewal Insulator renewal Fastener renewal Spot rail renewal Third rail maintenance Joint elimination Structures TRST Track bed cleaning Structures TRST Drain maintenance Structures TRST Leak repair Structures Power Tunnel light repair/relamp Automatic Train Control (ATC) Intrusion Detection Warning (IDW) System Renewal System Traction Power Power Cables Traction PowerPower Expansion Cables Track TRST Track TRST unit # crossties # insulators # fasteners # linear feet # linear feet cover board # joints welded # linear feet # linear feet # leaks # units Completed During Surge 1,856 541 2,214 3,184 Planned 1,980 475 1,680 ‐ 410 16 3,150 4,191 20 17 1,800 25 1,950 3,195 17 17 # IDW systems # cables # cables 208 130 30 27 24 24
© Copyright 2026 Paperzz