SafeTrack: Surge 1

SafeTrack: Surge 1
June 4‐16:
Ballston to East Falls Church Track 1, Continuous Single Tracking
Final report: Data as of 06/22/16
The focus of Surge 1 is to repair/replace track and other rail infrastructure elements to provide a system that is free from safety defects, improves service reliability by eliminating speed restrictions and improves ride quality.
Surge 1 finished on June 16, 2016, with almost all tasks completed. As a result, this section of track 1 from Ballston to East Falls Church was brought into a state of good repair.
Overall Progress (% Planned Work Complete)
Actual Work Complete
All
0%
20%
40%
60%
0%
20%
40%
60%
40%
60%
20%
40%
60%
20%
40%
60%
Track
Structures
0%
Automatic
Train Control System
0%
20%
Traction Power
0%
|
|
|
80%
100%
|
|
|
|
80%
100%
|
|
|
|
80%
100%
|
|
|
80%
100%
|
|
*Rescheduled Work
|
80%
100%
During the surge, priority was given to addressing potential safety defects and repairing or replacing critical rail infrastructure that affects train speeds and ride quality. Additional regular and preventive maintenance activities were fit in as time permitted. These maintenance activities are and will continue to be conducted on a regular basis during non‐revenue hours to keep the infrastructure in a state of good repair.
Critical tasks accomplished during the surge include:
+ Replacement of over 1,800 crossties
+ Renewal of over 540 insulators
+ Renewal of over 3,100 linear feet of spot rail
+ Inspection and repair of 30 power cables and 24 expansion cables
In some cases, work crews were able to accomplish more than originally planned, such as renewing about 500 additional fasteners and inspecting and repairing about 70 additional Intrustion Detection Warning (IDW) systems. *Rescheduled work: one task remains for traction power +Two junction boxes will be inspected and repaired when crews return to this area during surge 5 at the end of July
*Surge #1 results are preliminary and subject to quality control processes which will remain continuous throughout the duration of SafeTrack. Any remediation work that is
identified will be accomplished during normal maintenance times, without impacting passenger service.
SafeTrack: Surge 1 Detailed Report
6/22/2016
Asset Class (public reporting)
Track
Track
Track
Track
WMATA Unit
TRST
TRST
TRST
TRST
Key Tasks
Crosstie renewal
Insulator renewal
Fastener renewal
Spot rail renewal
Third rail maintenance
Joint elimination
Structures
TRST
Track bed cleaning
Structures
TRST
Drain maintenance
Structures
TRST
Leak repair
Structures
Power
Tunnel light repair/relamp
Automatic Train Control (ATC) Intrusion Detection Warning (IDW) System Renewal
System
Traction Power
Power Cables
Traction PowerPower
Expansion Cables
Track
TRST
Track
TRST
unit
# crossties
# insulators
# fasteners
# linear feet
# linear feet cover board
# joints welded
# linear feet
# linear feet
# leaks
# units
Completed During Surge
1,856
541
2,214
3,184
Planned
1,980
475
1,680
‐
410
16
3,150
4,191
20
17
1,800
25
1,950
3,195
17
17
# IDW systems
# cables # cables 208 130
30 27
24 24