9. DEVELOPMENT OF A STRATEGY A number of performance indicators have been taken into consideration in determining what projects best fit into the overall road network strategy. These are: • • • • • • • to encourage the use of existing principal elements of the road network to enhance overall safety by removing unnecessary vehicle movements along local roads to move heavy good vehicles onto arterial elements of the network and away from local roads to enhance the amenity of Marine Parade by reducing heavy goods vehicle movements along it to enhance existing elements of the road network so that they operate efficiently and safely in the future to enhance the area by minimising the environmental impact of traffic growth to provide an economically practical solution A number of these indicators can potentially work against each other, this is to be expected, but the failure to satisfy any one of the indicators does not necessarily mean the project is unsatisfactory as part of the overall strategy should be dropped. 9.1 Strategic Elements The following are the proposed elements of the 2026 Strategic Network: 1. Hastings Southern Arterial – Alignment A This element has an economically positive result both as a stand-alone project and as part of the overall strategy whilst significantly relieving particularly congested parts of the existing local Hastings network. It also helps reinforce the use of the Hawke's Bay Expressway. 2. Hastings Northern Arterial – Alignment A This element has a stand-alone economically beneficial result. It improves access to the Hawke's Bay Expressway whilst reducing potentially unnecessary light and heavy vehicle movements within the local northern area of Hastings. Both the Hastings Northern and Southern Arterials act in a complementary manner rather than compete with each other for the same traffic streams. 3. Whakatu Outlet - Alignment B This element has a stand-alone economically beneficial result. It improves access to the Hawke's Bay Expressway for HGV movements from the southeast thereby reducing HGV flow along SH2 into Napier. 4. Whakatu – Tomoana Link - Alignment B This element has an economically positive result whilst significantly improving access between these two important employment areas. Hawke’s Bay Regional Traffic Study Page 9-1 5. Awatoto - Expressway Connection - Alignment A This element does not currently produce a benefit stream sufficient to result in funding as the total road user benefits are expected to be less than the cost of the project. However, it does have the potential to reduce the HGV flow along SH2 thereby improving the amenity of the foreshore area. It is also an important element of the overall strategy for reducing HGV flow along Marine Parade if any form of regulation was to be placed HGV traffic along Marine Parade and adjacent parallel routes. 6. Four lane Prebensen Drive from Expressway to Hyderabad with Overpass This element has an economically positive result whilst significantly improving access between the port and eastern industrial areas. When taken in association with other elements of the strategy, it provides a very important alternative route for HGV traffic accessing the port away from some congested areas of the Napier network. 7. Pakowhai / Expressway Flyover This element has a economically positive result as it enhances access to the Hawke's Bay Expressway at a congested location. Whilst it does not attract significant additional traffic to the Hawke's Bay Expressway from surrounding roads it does significantly improve the performance of the intersection for the significant number of northbound vehicles using the intersection from Pakowhai Road. 8. Four lane Hawke’s Bay Expressway from Omahu to Pakowhai with southern extension Alignment B This element as whole has a borderline economically positive result. However, it does substantially reduce the number of long distance trips from the south into Napier along SH2 by redirecting them onto the preferred Hawke’s Bay Expressway. A sub-option of this element, involving the extension to the expressway only, would have an economically positive result. 9. Four lane Hawke’s Bay Expressway from Pakowhai to Kennedy This element currently does not have an economically beneficial result. It however substantially reduces the number of long distance trips from the south into Napier along SH2 and draws trips onto itself from lower standard parallel routes. 10. Four lane Hawke’s Bay Expressway from Kennedy to Prebensen This element as whole has a borderline economically positive result. However, it does help reduce the number of long distance trips from the south into Napier along SH2. As it forms part of an overall strategy of increasing capacity along this important element of the network, it should be kept as part of the overall strategy network. Hawke’s Bay Regional Traffic Study Page 9-2 11. Four lane Kennedy Road – Riverbend to Wellesley This element has an economically positive result whilst significantly relieving a particularly congested and important part of the existing Napier network. Safety would be enhanced and local amenity improved by removing a substantial amount of through traffic from parallel local residential roads. 9.2 Strategy Impact Figure 85 shows the proposed 2026 Strategy Network. The overall impact on vehicle movement due to the implementation of this Strategy can be seen in Figures 86 and 87. Clearly, there has been a significant reduction in the level of traffic using local Hastings and Napier roads. Traffic flow has been redirected onto the new elements of the strategy and further funnelled onto the Hawke's Bay Expressway in preference to SH2 and Marine Parade. The strategy network could result in approximately a 16% increase in traffic onto the Hawke’s Bay Expressway from the surrounding network predominantly from SH2 which could drop by 1000 vpd each way, a 14% reduction. Flow along Havelock Road would be expected to decrease by 3200 vpd each way, a 29% reduction. 80% of this reduction would be expected to transfer onto the Hastings Southern Arterial with the remaining 20% transferring onto the Northern Arterial. Flow along Frederick Street, Grove Road, Heretaunga Street, Omahu Road, Maraekakaho Road, Pakowhai Road and Karamu Road is expected to decrease thereby enhancing the environment within the Hastings Area. The implementation of the Hastings Southern Arterial would result in an increase in traffic along Flaxmere Avenue as a means of accessing Flaxmere rather than using Omahu Road. The improvements to the expressway and Kennedy Road have succeeded in drawing traffic away from surrounding local roads. Taradale Road, Marine Parade, Georges Drive and Willowbank Avenue would all have a reduction in flow. Movement onto the Hawke's Bay Expressway would drop traffic flow along Georges Drive by approximately 700-800 vpd each way. Heavy Goods Vehicles have been redirected onto the higher elements of the arterial network with the associated reduction in the number of HGVs on the surrounding roads. The improvements to the Hawke's Bay Expressway would result in an increase of 500 HGVs each way along the expressway between Taradale and Prebensen. HGV traffic along Meeanee Quay is expected to drop by 75 per day each way. The implementation of the Hastings Northern and Southern Arterials would result in a decrease of 170 HGVs each way along Havelock Road in and out of Hastings. The strategy improvements are expected to result in a 220 each way increase in HGVs along the expressway, a 19% increase. This corresponds to a 24% decrease in HGV movements along SH2 at Waitangi Bridge. This decrease continues along Marine Parade where there would be a drop of 110 HGVs per day each way (18% of total HGV traffic). It is clear however that for there to be a complete removal of HGV through traffic along Marine Parade some form of regulatory option would need to be implemented if there was a desire to remove all through HGVs from Marine Parade. The impact of such a regulation was discussed Section 8.3.5 and also in greater detail in the Hawke’s Bay Regional Heavy Transport Management Plan. Hawke’s Bay Regional Traffic Study Page 9-3 The overall strategy has reduced significant portions of the Hawke’s Bay road network to operational Levels of Service of D or better. In some instances these improvements have resulted in increased delays on side roads at minor intersections. This is particularly noticeable along Kennedy Road where a number of side roads are expected to face increased delays in the 2026 evening peak periods. These side roads have not been upgraded as part of the strategy as there a number of possible improvements for each intersection. It is also likely that authorities may want to rationalise some intersections and their controls. These improvements to the strategic network are aimed at reinforcing and improving a number of existing important routes within the road hierarchy. Their improvement draws traffic from the secondary road network along which shorter local trips are undertaken. This in turn enables those vehicles using these secondary elements to operate more efficiently. As a number of public transport routes use both the secondary network for their local activity and the upgraded arterial network for their longer distance routes, it is expected that there would be some improvement to their future operation as a result of the strategy. Hawke’s Bay Regional Traffic Study Page 9-4 KEY New Component Upgraded Component Hyderabad Overpass Prebensen Kennedy Awatoto Pakowhai Overpass HB Expressway Widening Whakatu Outlet Tomoana Link Expressway Extension Hastings Northern Arterial Hastings Southern Arterial Hawke’s Bay Regional Traffic Study 2026 Proposed Strategy Network Figure 85 Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study Page 9-5 -1254 -1606 373 214 2224 1779 689 1680 1979 779 -708 -967 -400 -518 -87 9 -11 20 -484 8 -10 -98 -528 1718 77 1970 -1 77 -574 -661 -2 -484 -681 -474 1718 42 75 -1 -1 -223 1970 -123 8 12 -9 16 61 51 49 -1 01 0 -84 1 -75 -1 01 -3 67 65 -2 97 59 -12 72 058 -11 3 4 343 -5 -5 8 46 2033 2029 9 -3 40 52 -2 91 19 25 39 7 -2 -3 9 26 26 3 0 137 -1 08 -681 48 52 -254 -259 12 12 Traffic Increase Traffic Decrease 5.0km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Traffic Flow Change Strategy vs Do-Minimum Figure 86 Page 9-6 93 62 -214 -181 585 411 90 200 238 115 -136 -14 9 -17 9 -111 -34 236 -45 -41 6 -34 -70 -116 203 236 1 -1 203 -165 -29 -34 3 -1 -1 -12 -70 94 12 34 -69 1 10 240 264 236 -13 2 -10 -93 240 -1 -1 1 2 11 15 11 -16 -79 -1 49 3 3 4 -10 -10 Traffic Increase Traffic Decrease 5.0km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 HGV Traffic Flow Change Strategy vs Do-Minimum Figure 87 Page 9-7 Figure 88 shows the modelled aggregate AM Peak and PM Peak LOS for 2003 and 2026. It compares the total kilometres of road affected by LOS’s F, E and D as it exists today, in 2026 with only a Do-minimum network and 2026 with the Strategy Network in place. Figure 88 Network LOS Total Change 2003- 2026 200.0 KM's 150.0 100.0 50.0 0.0 AM BASE 2003 AM BASE 2026 AM STRATEGY 2026 LOS F 0.2 km 8.3 km 0.7 km LOS E 20.8 km 39.5 km 27.6 km LOS D 51.0 km 85.4 km 70.5 km Model Period 200.0 KM's 150.0 100.0 50.0 0.0 PM BASE 2003 PM BASE 2026 PM STRATEGY 2026 LOS F 2.4 km 10.9 km 1.3 km LOS E 23.7 km 51.8 km 33.0 km LOS D 60.0 km 106.3 km 89.9 km Model Period Hawke’s Bay Regional Traffic Study Page 9-8 This figure shows that after the implementation of the Strategy, during both the 2026 AM and PM Peaks, the lengths of road throughout the study area at LOS F and E are expected to reduce to levels very close to those existing now. This can also be shown in the following Figures 89 to 96 show the Levels of Service throughout the study area for 2026 before and after the Strategy. Should elements of the strategy be implemented there will be improvements in LOS. Namely: • The Hawke’s Bay Expressway has improved to LOS D and better in all locations south of Prebensen Drive, • Kennedy Road has improved to a minimum of LOS D between Wycliffe Street and Wellesley Road, • The existing length of Prebensen Drive between the expressway and Hyderabad Road has improved to LOS D, • SH2 has improved to LOS D and better, • Havelock Road has improved to LOS E and better, • Priority intersections along Havelock Road and Heretaunga Street have improved to LOS D and better, • Pakowhai Road south of Evenden Road has improved to LOS E and better, • Priority intersections along Pakowhai Road have improved to LOS D and better, • Omahu Road has improved to LOS E and better, • Frederick Street has improved to LOS D or better, As a result of additional traffic being attracted to some routes described in the strategy, a number of minor intersections are expected to experience a reduction service. These intersections are detailed in the following section. As there are a number of possible improvements that could be undertaken at these intersections as part to the strategy, this study has simply pointed out these resulting deficiencies but not endeavoured to dictate an intersection management improvement. Table 78 details the network wide benefits for the Strategy Network as a whole when compared to 2026 Do-Minimum. Table 78 Road User Benefit / Cost Analysis Road User Benefit Project Cost Estimated B/C Ratio Full Strategy $70.54M $73.51M 0.96 Indicative network wide emission outputs from each alignment model are detailed in Table 79. Hawke’s Bay Regional Traffic Study Page 9-9 2026 Daily Network Wide Emission Output Comparison Do-Minimum Noise Pressure (Pascal squared hours) Carbon Dioxide (Tonnes) Carbon Monoxide (Tonnes) Hydrocarbons (Tonnes) Nitrous Oxides (Tonnes) Particulate Matter (Tonnes) Fuel Use ‘000 Litres 31.711 909.346 43.756 6.067 7.450 0.291 344.116 Table 79 Change from Base 5.556 -66.957 -3.556 -0.507 0.023 -0.006 -6.568 It shows that the strategy network would have a general beneficial impact on emission output. Hawke’s Bay Regional Traffic Study Page 9-10 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Northern Study Area Do-Minimum AM Peak LOS Diagram Figure 89 Page 9-11 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Northern Study Area Strategy AM Peak LOS Diagram Figure 90 Page 9-12 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Southern Study Area Do-Minimum AM Peak LOS Diagram Figure 91 Page 9-13 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Southern Study Area Strategy AM Peak LOS Diagram Figure 92 Page 9-14 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Northern Study Area Do-Minimum PM Peak LOS Diagram Figure 93 Page 9-15 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Northern Study Area Strategy PM Peak LOS Diagram Figure 94 Page 9-16 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Southern Study Area Do-Minimum PM Peak LOS Diagram Figure 95 Page 9-17 KEY = LOS F = LOS E = LOS D 2.5km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Hawke’s Bay Regional Traffic Study 2026 Southern Study Area Strategy PM Peak LOS Diagram Figure 96 Page 9-18 9.3 Marine Parade HGV Ban Assessment The strategy network is reasonably effective in taking heavy goods traffic away from Marine Parade diverting some 18% of the 1200 heavy vehicles per day on that road in 2026. However, that is not sufficient to remove the environmental effects of the heavy vehicles, so the effect of a possible bylaw was tested. The change in heavy goods vehicle flow if it is put in place is shown on Figure 97. The total heavy goods vehicle flow on Marine Parade drops to about 10 vpd (opposite Tennyson), which is mainly the goods vehicles accessing the central area, and which have a legitimate reason to be there, even with a bylaw in place. It does however, give an appreciation of the amount of heavy goods traffic that is using Marine Parade as a through route. An analysis was also undertaken to assess the impact of the HGV Marine Parade ban on the performance of the network and performance of the recommended roading strategy in particular. It was found that even though the ban moves HGV traffic onto alternative routes the reassignment is not large enough to affect the total network performance. This is because HGV traffic makes up a small proportion of total traffic. The bylaw will impose a cost on the goods vehicle operators. The additional cost to the operators is 2,100 vehicle kilometres per day that will attract additional road user charges and operating costs. These can all vary considerably depending on link speeds, link gradient, exact vehicle type and maximum gross weight. For example if: • The affected trucks were all three-axle (1 single tyred and 2 twin tyred) with a maximum gross weight of 18 tonnes then the charge rate would be 20 cents/km that would result in an extra $420 per day (or $153,300 per year (420 X 365)) cost to the HGV operators. However, if the affected trucks were all three-axle with a maximum gross weight of 22 tonnes then the charge rate would be 37.3 cents/km resulting in additional road user charges of $783.3 per day (or $285,904 per year) [according the LTSA’s ‘Road User Charges 2002’ handbook]; and • The affected trucks were all HCV-I type trucks and they travelled at an average speed of 50 km/hr on flat terrain then the running costs would be 50.5 cents/km that would result in additional running costs of $1,060 per day (or $387,082 per year). However, if the affected trucks were all HCV-II type trucks and they travelled at average speed of 55 km/hr on the gradient of 5% then the running costs would equal 106.9 cents/km that would result in additional running costs of $2,244 per day (or $819,388 per year) [according to Transfund’s Project Evaluation Manual 2002 (A5-14)]. These additional costs need to be balanced against environmental gains in terms of noise, vibration and visual intrusion on Marine Parade. The Marine Parade is an area of Napier City that is environmentally complex. It is a highly modified coastal environment characterised by a mix of uses, including residential activities, hotels and motels and various tourist related commercial activities. These types of activity conflict with heavy vehicle movements particularly during the seasonal peaks where increases in the number of the heavy vehicle movements coincide with some of the busiest tourist periods. However, a HGV ban on Marine Parade would have the effect of displacing them to other parts of the network that could also be environmentally sensitive. Hawke’s Bay Regional Traffic Study Page 9-19 The following Assessment of Environmental Effects compares the 2026 do-minimum roading scenario against the environmental impacts of the: (a) • Roading strategy (outlined earlier in this report); and the • Roading strategy with the addition of a ban on HGV through traffic along Marine Parade. Noise Impacts The noise-impacts of heavy vehicles on the Marine Parade have been the centre of discussions for many years. The physical characteristics of the street provide little opportunity to improve separation distances between the activities and the traffic. No on-site monitoring has taken place to gauge the current impact of heavy vehicles. However for the purposes of this desk top assessment comparative assessment has been undertaken based on the changes in total heavy vehicle movements over a 24hour period. Under the Marine Parade HGV Ban the total number of heavy goods vehicle movements will decrease by 95.2% compared with the 2026 Do Minimum. With the roading strategy in place the ban would result in a 18% decrease in HGV movements along Marine Parade. This may have a significant impact on the noise levels on the Marine Parade at the peak of the season. The impacts of the ban must also be considered on the alternative routes. For Georges Drive the total number of heavy vehicle movements will decrease by 3.5 % under the 2026 do minimum option. However, comparing this with the roading strategy in place, the ban would increase the number of movements by 46.4 %. Provided that the Marine Parade HGV ban as well as the Strategy Network is in place, the noise impacts are likely to be little different to what is currently being experienced. (b) Air Emissions The traffic model has been able to produce specific emission levels for heavy goods vehicles on the Marine Parade over a 24-hour period. For heavy goods vehicles Nitrogen Oxide and Particulate Matter have been used as the measure of emissions as these types of emissions are characteristic of diesel engines and help to differentiate the impacts of heavy vehicles as opposed to normal traffic. With the roading strategy in place Marine Parade experiences a 16% reduction in nitrogen oxide emissions (17.7% decrease for HGVs) and a 21% reduction in total Particulate Matter emissions (with a 17.6 reduction for HGV’s) over the 2026 do minimum option. With the ban in place these reductions are 53% for nitrogen oxide (93.6% reduction from HGVs) and 92.7% for particulate matter emissions (93.5% reduction for HGVs) . There are significant positive impacts on emissions levels for the Marine Parade itself. With the ban in place consideration must be given to impacts on the alternative route, Georges Drive. With the roading strategy in place there is a 21% decrease in the level of nitrogen oxide emissions (40% reduction in emissions for HGVs) and a 40% reduction in particulate matter emissions (38.9% reduction in emissions for HGVs) over the do minimum option. Hawke’s Bay Regional Traffic Study Page 9-20 With the ban in place the level of emission reduction over the do minimum option is a 8.6 % reduction in the level nitrogen oxide and no change at all in the level of particulate matter. The roading strategy has a positive impact by moving vehicles away but any gains in emission reduction would be lost with the ban being imposed. (c) Cultural Impacts Cultural impacts are an important consideration for the Marine Parade. There is a site of significance to maori in the vicinity of the Coote Road intersection. The Marine Parade is an important cultural facility for the region, with many tourist and historic associations. The Norfolk pine trees are part of the cultural identity of the Parade. (d) Impact on Non-Renewable Resources There are no non-renewable resources related to the use of the Marine Parade as a heavy vehicle route. (e) Impact on Waterways There should not be any impact on waterways as a result of the continued use of the Marine Parade or on routes resulting from a ban on the Marine Parade. (f) Impacts on Economic Development The effects of the ban on economic development in the study area are likely to be significant. The Marine Parade is the focus of Napier City’s tourism development and on this basis increasing heavy traffic in this area is not sustainable in the long term. However, there will be negative impacts on some businesses by means of increased transport costs. Any alternative must provide transport operators with an efficient means of access to the Port. Uninterrupted linkages through to the expressway will provide the most positive effects. (g) Access and Mobility Access and mobility for non-HGV traffic will be improved on the Marine Parade by reducing heavy traffic, particularly during the peak season at the Port. (h) Safety The potential for conflict on the Marine Parade is high with large numbers of pedestrians and visitors to the City interacting with the heavy vehicle traffic. There will be positive impacts from the introduction of the strategy and even more so with a heavy vehicle ban. Conversely the impacts of the additional traffic on alternative parts of the current network will create some adverse traffic safety issues. There will be a greater level of heavy vehicles interacting with residential activities and this will have significant level of adverse impacts on safety. There are significant positive impacts resulting from a heavy traffic ban on the Marine Parade. This does come at a cost to the alternative route. These positive impacts must be weighed against the other economic and traffic costs and benefits. It is also recommended that a detailed noise assessment on the routes be undertaken prior to any network decisions being made. Summaries of the effects of the Marine Parade HGV Ban are contained in the following two tables: Hawke’s Bay Regional Traffic Study Page 9-21 Table 80 assesses the impact of the roading strategy on Marine Parade and Georges Drive against the 2026 do-minimum. It shows that the strategy reduces HGV traffic on both the Marine Parade AND Georges Drive resulting in a beneficial environmental result for both areas. Impact Of The Roading Strategy on Marine Parade and Georges Drive Table 80 Environmental Issues* Marine Parade Effects 2026 with strategy in place Georges Drive Effects 2026 with strategy in place Noise sensitive activities Air Quality Vibration / shaking Cultural Impacts Effects on non-renewable resources Impact on waterways Economic Development (viability for Commerce) Access and Mobility (community severance) Safety Total +1 +1 +1 +1 0 0 +3 +3 +4 +14 +3 +2 +1 0 0 0 +4 +4 +3 +17 +31 *assessed against 2026 do minimum Table 81 assesses the impact of the roading strategy with the Marine Parade ban on Marine Parade against the 2026 do-minimum. It shows that while the ban appears to have a beneficial environmental outcome for the Marine Parade the overall result is tempered by the negative impacts of moving the HGV traffic onto Georges Drive. Impact Of The Roading Strategy with the Marine Parade Ban Environmental Issues* Noise sensitive activities Air Quality Vibration / shaking Cultural Impacts Effects on non-renewable resources Impact on waterways Economic Development (viability for Commerce) Access and Mobility (community severance) Safety Total Table 81 Georges Drive Effects 2026 with ban (off-site effects) 0 0 -1 Marine Parade Effects 2026 with ban (on- site effects) +5 +5 +5 +4 0 0 +3 +3 +4 29 0 0 -4 -4 -3 -12 +17 *assessed against 2026 do minimum A bylaw is not easy to implement. It will require significant community consultation, tests of reasonableness, and legislative procedures to be followed that make the outcome very problematic. Also, the success of a bylaw is a function of enforcement, and enforcement of a bylaw is the responsibility of the Police. Because it is not a safety concern, bylaw enforcement tends to have a lower priority than factors affecting safety. Hawke’s Bay Regional Traffic Study Page 9-22 KEY Increased HGV Traffic Marine Marine Ahuriri Ahuriri Decreased HGV Traffic 1,500 1,500 500 500 500 500 0 0 0 ULT OPT ULT OPT 0 127 127 1,000 1,000 1,000 1,000 983 983 1,500 1,500 1,529 1,529 2,000 2,000 (Line thickness indicates volume) 2,298 2,298 2,500 2,500 ULT OPT ULT OPT Expressway Expressway 3,257 3,257 2,000 2,000 2,936 2,936 3,000 3,000 Georges Georges 1,000 1,000 500 500 0 400 400 ULT OPT ULT OPT 427 427 0 300 300 100 100 0 0 184 184 200 200 ULT OPT ULT OPT 1.0km Hawke’s Bay Regional Traffic Study Gabites Porter (NZ) Ltd Change in HGV 2026 All Day Flow Strategy Network vs Strategy Network with HGV Ban on Marine Parade Hawke’s Bay Regional Traffic Study Figure 97 Page 9-23 9.4 Remaining Deficiencies After the construction of the Strategy Network, there are still expected to be some locations of Level of Service worse than D. This is due to locations either not benefiting from the strategy improvements or having their LOS dropped as a result of altered travel patterns resulting from the Strategy. The locations having not benefited from strategy improvements are as follows: • Main North Road and Hawke's Bay Expressway north of Prebensen Drive remains at LOS E in places, • Kennedy Road from York Avenue to Taradale Road remains at LOS E in places, • Meeanee Road between Gloucester Street and the Hawke's Bay Expressway remains at LOS E/F in places, • Kennedy Road between Bill Hercock Street and Wycliffe Street remains at LOS E in places, • Prebensen Drive between Austin Street and the Hawke's Bay Expressway remains at LOS E, • Thackeray and Carlyle Streets remains at LOS E in places, • Niven Street remains at LOS E, • Kennedy Overpass off-ramp right turn intersection with Kennedy Road remains at LOS E in the AM Peak and increases to F in the PM Peak. New intersection management required, • Intersection of Bill Hercock Street and Kennedy Road remains at LOS F. New intersection management required, • Omahu Road between Hawke's Bay Expressway and Pakowhai Road improves to LOS E, • Pakowhai Road between Omahu Road and Evenden Road improves to LOS E, • Havelock Road improves to LOS E, • Heretaunga Street East improves to LOS E, The locations having reduced LOS as a result of flow-on effects from the strategy improvements are as follows: • Intersection of Prebensen and Tamatea drops to LOS F. management required, • Intersection of Prebensen Drive and Severn Street drops to LOS F in the PM. New intersection management required, • The merge from the proposed Awatoto Expressway onto the Hawke's Bay Expressway will need careful design, • Numerous priority intersections along Kennedy Road from Tom Parker Avenue to McDonald Street drop to LOS E. New intersection managements required, • Karamu Road remains at LOS E/F, • Intersection of Links Road and Hawke's Bay Expressway drops to LOS E/F. New intersection management required, Hawke’s Bay Regional Traffic Study New intersection Page 9-24 9.5 Potential Strategy Time Frame Whilst the study has not looked at a specific order in which the various elements of the proposed strategy could be implemented, the result of each elements analysis indicates the following possible timing: Short-term: Preset – 2016 • Whakatu – Tomoana Link • Whakatu Outlet • Four Lane Kennedy Road – Riverbend to Wellesley • Hastings Southern Arterial • Hastings Northern Arterial Medium-term: 2016-2026 • Pakowhai / Expressway flyover • Four Lane Prebensen Drive from Expressway to Hyderabad Road with overpass Long-term: past 2026 • Four lane Hawke’s Bay Expressway from Omahu to Pakowhai with southern extension • Four Lane Hawke’s Bay Expressway from Pakowhai to Kennedy • Four Lane Hawke’s Bay Expressway from Kennedy to Prebensen • Awatoto - Expressway Connection. Hawke’s Bay Regional Traffic Study Page 9-25
© Copyright 2026 Paperzz