Samdo case study discussion Chris Chapman and Stephen Ward Chapman and Ward HMPOR case slide 1 © 2011 John Wiley & Sons Ltd Discussion starting point Start with a working assumption about the objective: maximizing the expected value of M = R – C, where M = margin (contribution to profit) per year R = revenue C = cost (direct and amortisation of capital) Assume we want to understand the expected values of M, R and C plus associated opportunity and risk, and begin by considering R Chapman and Ward HMPOR case slide 2 © 2011 John Wiley & Sons Ltd Key components of R (revenue) • base load power sales to Ontario Hydro • waste heat (low pressure steam) • back-up emergency power We need to size these components, then identify associated key sources of uncertainty, and associated key responses (decisions) Chapman and Ward HMPOR case slide 3 © 2011 John Wiley & Sons Ltd Key components of C (cost) • amortised capital cost • fuel cost • other costs We need to size these components, then identify associated key sources of uncertainty, and associated key responses (decisions) Chapman and Ward HMPOR case slide 4 © 2011 John Wiley & Sons Ltd Creative thinking putting this together • New untested design CCTG plant? • Defer emergency power business? • Back-to-back contract with Ontario Hydro? • Back-to-back contract with gas supplier? • Timing issues? Chapman and Ward HMPOR case slide 5 © 2011 John Wiley & Sons Ltd Some concluding comments • The top-down process starting point is useful here • Many of the key generic process ideas can be applied to all opportunity, risk and uncertainty management processes • Designing processes for contexts is an overarching key idea • Seeking simplicity systematically in these processes is another key idea, part of the overarching opportunity efficiency concept Chapman and Ward HMPOR case slide 6 © 2011 John Wiley & Sons Ltd Transcon 1 case study discussion 1 of 4 2011 Chris Chapman and Stephen Ward Chapman and Ward HMPOR case slide 7 © 2011 John Wiley & Sons Ltd Discussion starting point Start with a working assumption about the objective: maximizing the expected value of M = B – C, where M = margin (contribution to profit) B = bid (price) C = cost (direct), and assume we want to understand the expected values of M, P and C and associated risk. Start with C for two components which are useful examples. Chapman and Ward HMPOR case slide 8 © 2011 John Wiley & Sons Ltd Initial operations and training example 1 Cumulative probability 0.8 indicates expected cost (also median) 0.6 Astro 0.4 Zoro 0.2 0 0.7 0.9 1.1 1.3 1.5 Direct cost (£m) Chapman and Ward HMPOR case slide 9 © 2011 John Wiley & Sons Ltd Convert existing programmes example Sysdoc 1 Cumulative probability 1 Datapol Sysdoc 2 Sysdoc 3 0.8 0.6 indicates expected cost (also median) 0.4 0.2 0 0.5 1.0 1.5 2.0 Direct cost (£m) Chapman and Ward HMPOR case slide 10 © 2011 John Wiley & Sons Ltd Linking this to common practice • The value of simple ‘other objective’ assessments early on • The value of simple initial cost estimates • The value of the ‘risk efficiency’ concept and its assessment via simple linear cumulative probability distributions Chapman and Ward HMPOR case slide 11 © 2011 John Wiley & Sons Ltd Some concluding comments • The key estimating process ideas have been used very successfully by a limited number of organisations • Many of the key ideas can be applied to all opportunity, risk and uncertainty management processes Chapman and Ward HMPOR case slide 12 © 2011 John Wiley & Sons Ltd Transcon 2 case study discussion 2 of 4 2011 Chris Chapman and Stephen Ward Chapman and Ward HMPOR case slide 13 © 2011 John Wiley & Sons Ltd Discussion starting point Keep the working assumption that we are maximizing the expected value of M = B – C, where M = margin (contribution to profit) B = bid (price) C = cost (direct), and we want to understand the expected value of C, associated risk and decisions. Now look at C when discrete events are explicitly involved. Chapman and Ward HMPOR case slide 14 © 2011 John Wiley & Sons Ltd Decision tree for the additional memory issue pre-install Astro pay in advance Cost to Astro £0.6m expected cost = £0.6m (1.0 x £0.6m) probability = 1.0 post-install if necessary extra memory needed Astro have to pay expected cost = £0.1m (0.2 x 0.5 x £1.0m) 0.2 0.5 ? Astro do not have to pay £1.0m £0m 0.5 no extra memory needed Key: 0.8 decision node choices available indicated above ‘choice branches’ expected values indicated below ‘choice branches chance node alternative outcomes indicated above ‘chance branches’ probabilities indicated below chance branches’ Chapman and Ward HMPOR case slide 15 © 2011 John Wiley & Sons Ltd £0m Cumulative probability distribution portrayal pre-install 1 post-install if necessary Cumulative probability 0.8 0.6 indicates expected cost 0.4 0.2 0 0.5 1.0 Direct cost (£m) Chapman and Ward HMPOR case slide 16 © 2011 John Wiley & Sons Ltd The ‘post-install if necessary’ option’s extra memory ‘risk’ consistent with probability-impact grid portrayal 1 Probability 0.8 0.6 0.4 0.2 0 0.5 1.0 Direct cost (£m) Chapman and Ward HMPOR case slide 17 © 2011 John Wiley & Sons Ltd A revised decision tree to generalise Astro pay in advance pre-install Cost to Astro £0.4–0.8m expected cost = £0.6m (1.0 x £0.6m) post-install if necessary extra memory needed expected cost = £0.1m (0.2 x 0.5 x £1.0m) 0.1 – 0.3 probability = 1.0 Astro have to pay 0.3 – 0.7 Astro do not have to pay £0.9-1.1m £0m 0.7- 0.3. no extra memory needed £0m Key: 0.8 decision node choices available indicated above ‘choice branches’ expected values indicated below ‘choice branches chance node alternative outcomes indicated above ‘chance branches’ probabilities indicated below chance branches’ Chapman and Ward HMPOR case slide 18 © 2011 John Wiley & Sons Ltd Revised cumulative probability distribution with 0.7- 0.9 probability post-install needed 1 Cumulative probability post-install if necessary 0.8 0.6 0.4 pre-install indicates expected cost 0.2 0 0.5 Chapman and Ward HMPOR case slide 19 © 2011 John Wiley & Sons Ltd 1.0 Direct cost (£m) Some concluding comments • The value of simple ‘other objective’ assessments early on • The value of simple initial cost estimates • The value of decision trees that do not need exact probabilities or consequences • The value of the generality of a minimalist view of uncertainty as part of a clarity efficient perspective • Many of the key ideas can be applied to all risk management processes Chapman and Ward HMPOR case slide 20 © 2011 John Wiley & Sons Ltd Transcon 3 case study discussion 3 of 4 2011 Chris Chapman and Stephen Ward Chapman and Ward HMPOR case slide 21 © 2011 John Wiley & Sons Ltd Discussion starting point Still use the working assumption that the objective is maximizing the expected value of M = B – C, where M = margin (contribution to profit) B = bid (price) C = cost (direct), but assume we want to understand the expected value of C in total, and associated risk. Chapman and Ward HMPOR case slide 22 © 2011 John Wiley & Sons Ltd Cost estimate summary sheet example comp item/option base min max exp choices/assumptions 1 mainframe etc 3.6 3.6 3.6 3.6 no choice 2 Astro 0.3 0.3 0.3 0.3 no choice Zenith 1.0 1.1 1.3 1.2 total 1.5 3 Zoro 1.0 1.2 1.4 1.3 if no hostile takeover Astro 0.8 0.7 1.1 0.9 preferred option 4 … omitted 5 to avoid making this slide too complex ___________________________________________________ total direct cost 10.9 14.2 12.5 (£ million) Could we interpret this as 12.5 +/- 2 £ million? Chapman and Ward HMPOR case slide 23 © 2011 John Wiley & Sons Ltd Layered curves can show contributions, including simple linear curves if discrete outcomes are not portrayed, as shown here Cumulative probability 1.0 0.5 1 2 3 … 5 even if precise non-linear curves are used, this portrayal suggests limited cost risk 0 Cost (£) Chapman and Ward HMPOR case slide 24 © 2011 John Wiley & Sons Ltd Linking this to common practice • The value of simple estimating processes • The value of more complex estimating processes in their own right and as the basis of simple estimates • The key estimating process ideas have been used very successfully by a limited number of organisations Chapman and Ward HMPOR case slide 25 © 2011 John Wiley & Sons Ltd Some concluding comments • Many of the key process ideas can be applied to all opportunity, risk and uncertainty management processes • Designing processes for contexts is an overarching key idea • Seeking simplicity systematically in these processes is another key idea, introducing complexity where it pays being a crucial part of this Chapman and Ward HMPOR case slide 26 © 2011 John Wiley & Sons Ltd Transcon 4 case study discussion 4 of 4 2011 Chris Chapman and Stephen Ward Chapman and Ward HMPOR case slide 27 © 2011 John Wiley & Sons Ltd Discussion starting point Still use the working assumption that the objective is maximizing the expected value of M = B – C, where M = margin (contribution to profit) B = bid (price) C = cost (direct), but assume now that we want to use an expected value for C from part 3, assume values for B, and understand the implications for M. Chapman and Ward HMPOR case slide 28 © 2011 John Wiley & Sons Ltd Cost estimate summary sheet example comp item/option base min max exp choices/assumptions 1 mainframe etc 3.6 3.6 3.6 3.6 no choice 2 Astro 0.3 0.3 0.3 0.3 no choice Zenith 1.0 1.1 1.3 1.2 total 1.5 3 Zoro 1.0 1.2 1.4 1.3 if no hostile takeover Astro 0.8 0.7 1.1 0.9 preferred option 4 5 ___________________________________________________ total direct cost 10.9 14.2 12.5 (£ million) Say we round £12.5 million to £13 million Chapman and Ward HMPOR case slide 29 © 2011 John Wiley & Sons Ltd Probability of winning curve examples Key: 1 c1 example discrete values c2 c3 P(B), probability of winning 0.8 b discrete values of particular interest preliminary probability of winning curve 0.6 assumed underlying curve possible extrapolations 0.4 0.2 a 0 10 Chapman and Ward HMPOR case slide 30 15 20 © 2011 John Wiley & Sons Ltd B, Bid (£m) 25 Bid decision summary sheet example Assuming expected direct cost estimate C = £13 million B 15 16 17 18 19 20 P(B) conditional M unconditional M 0.8 15 -13 = 2 2 x 0.8 = 1.6 0.66 3 2.0 0.52 4 2.1 0.38 5 1.9 0.24 6 1.4 0.1 7 0.7 notes buy work? optimum for M nominal price overstretched? The key risk is loosing business you want? Chapman and Ward HMPOR case slide 31 © 2011 John Wiley & Sons Ltd Linking this to common practice • The value of simple ‘other objective’ assessments early on • The value of simpler and more complex cost estimates • The value of simpler and more complex bid curve (probability of winning) estimates What do more complex bid curve estimates involve? Chapman and Ward HMPOR case slide 32 © 2011 John Wiley & Sons Ltd Probability of winning curves for composite competitor k and component competitor i, where k = i + j Probability of winning 1 the space between these lines indicates the impact of competitor j 0.8 composite competitor k 0.6 competitor i 0.4 0.2 0 10 15 20 Adjusted bid (£m) Chapman and Ward HMPOR case slide 33 © 2011 John Wiley & Sons Ltd Some concluding comments • The key bidding process ideas have been used very successfully by a limited number of organisations • Many of the key process ideas can be applied to all opportunity, risk and uncertainty management processes • Designing processes for contexts is an overarching key idea • Seeking simplicity systematically in these processes is another key idea, introducing complexity where it pays being a crucial part of this, part of the overarching opportunity efficiency concept Chapman and Ward HMPOR case slide 34 © 2011 John Wiley & Sons Ltd
© Copyright 2025 Paperzz