TLE TLMP - Data.gov.uk

DSS/00099
Appendix 2 to
SNITS Annex C
Target Locator Equipment (TLE)
Through Life Management Plan
Dismounted Soldier Systems Project Team
3rd December 2009
Issue 1.0
List of contents
1
Mission and Objectives
1.1
Objective of TLMP
1.2
Project Overview
1.3
Military and Capability Context
1.4
Capability Gap
1.5
Customers
1.6
Project Status and Approvals
1.7
Assumptions, Constraints and Drivers
1.8
Project Objectives
1.9
Customer Supplier Agreements Targets
1.9.1
Programme Deliverables
1.9.2
Capability Time Lines
2
Stakeholders
2.1
Project Organisation
2.2
Project Governance
2.3
Stakeholder Interfaces
2.4
Stakeholder Responsibility Matrix
11
11
11
12
13
3
Strategies
3.1
TLM Strategy
3.2
Training DLOD
3.3
Equipment DLOD
3.3.1
Procurement Strategy
3.3.2
Risk Strategy
3.3.3
Transition Strategy
3.3.4
Requirements Management Strategy
3.4
Personnel DLOD
3.4.1
Safety and Environment Strategy
3.5
Information DLOD
3.5.1
Operational Information
3.5.2
Non Operational Information
3.6
Doctrine and Concepts DLOD
3.7
Organisation DLOD
3.8
Infrastructure DLOD
3.9
Logistics DLOD
3.9.1
Support Aim
3.9.2
Support Strategy
3.9.3
Security Strategy
3.10
Interoperability
14
14
14
14
14
15
15
15
15
15
16
16
16
16
16
16
16
16
17
17
17
4
Plans and Processes
4.1
Training DLOD
4.2
Equipment DLOD
4.2.1
Procurement Plan
18
18
18
18
Issue 1.0
Page 3
7
7
7
7
8
8
9
9
9
9
9
9
4.2.2
4.2.3
4.2.4
4.3
4.3.1
4.4
4.4.1
4.4.2
4.5
4.6
4.7
4.7.1
4.7.2
4.7.3
Risk Plan
Transition Plan
Requirements Management
Personnel DLOD
Safety and Environment Management Plan
Information DLOD
Operational Information
Configuration Control
Organisation DLOD
Infrastructure DLOD
Logistics DLOD
Integrated Logistics Support Plan (ILSP)
Obsolescence and Disposal
Support Solutions Envelope (SSE)
18
19
19
19
19
19
19
19
20
20
20
20
20
21
5
Resources
5.1
Whole Life Costs
5.2
Master Data and Assumptions List (MDAL)
5.3
Through Life Finance
22
22
22
22
6
Evaluation of Success
6.1
TLMP Review Process and Updates
6.2
Accepted Milestones
6.3
Success Criteria
6.4
Post Project Evaluation Plan
23
23
23
23
23
Issue 1.0
Page 4
7
Glossary
24
8
List of Annexes
26
ANNEX A TO
27
TLE TLMP
27
ANNEX B TO
32
TLE TLMP
32
ANNEX C TO
33
TLE TLMP
33
ANNEX D TO
36
TLE TLMP
36
ANNEX E TO
38
TLE TLMP
38
ANNEX F TO
39
TLE TLMP
39
ANNEX G TO
41
TLE TLMP
41
ANNEX I TO
49
TLE TLMP
49
ANNEX J TO
50
TLE TLMP
50
Issue 1.0
Page 5
Administration page
Customer Information
Customer reference number
n/a
Project title
Target Locator Equipment Through Life
Management Plan
Customer Organisation
DE&S Dismounted Soldier Systems
Customer contact
Contract number
Milestone number
WP2 TLMP
Date due
T0+14
Record of changes
Issue 1.0
Date 03 /12/ 09
Issue 1.0
Detail of Changes n/a
Page 6
1
Mission and Objectives
This section describes the background and the bounds of the TLE project.
1.1
Objective of TLMP
The objective of this Through Life Management Plan (TLMP) is to provide the single
source of strategic management information for the Target Locator Equipment
(TLE) programme and provides access to more detailed information required by
staff and others to manage their activities. This document is owned by the
Dismounted Soldier Systems (DSS) Project Team (PT) and is managed by the
Project Board (in particular DSS-STA-Proj1). This document provides a single
planning focal point for all team members and stakeholders and is the access point
to the detailed ‘knowledge base’ and planning documentation. It is the authoritative
document for the management of the programme and will contain the latest agreed
versions of schedules, objectives, strategies, plans etc. Persons requiring access to
the key documents referenced throughout this TLMP should note that many have
protective markings and some also have commercial restrictive markings.
1.2
Project Overview
The TLE project is a category D single gate procurement project aimed at delivering
a replacement for the currently in-service LH40c TLE system to support Fire
Support Teams (FST), in particular for the Mortar Fire Controller and Forward
Observation Officer of the Mortar Division and Royal Artillery respectively. The
project is currently in the Assessment Phase, post Pre Qualification Questionnaire
(PQQ) with Trials Contracts being issued.
The TLE project will provide a handheld system that will deliver a rapid, simple and
precise method of determining range, bearing and inclination in order that, when
combined with own position data, will give accurate location of a sighted target and
allow for fall of shot corrections.
The TLE project will deliver a system that will provide a 24 hour surveillance
capability, with the same target recognition performance, with improved mobility
over the current in-service system.
The TLE project will provide a Commercial Off The Shelf (COTS) or Military Off The
Shelf (MOTS) solution that will be tested by the Infantry Trials and Development
Unit (ITDU) and XXX with the aim of achieving acceptance against all Key User
Requirements (KURs) which can be found in Annex A.
1.3
Military and Capability Context
The proposed Single Statement of User Needs states that: “TLE must provide the
Mortar Fire Controller and Forward Observation Officer with a rapid, simple and
precise method of determining range, bearing and inclination in order that when
combined with accurate own position data will give accurate location of a sighted
target and fall of shot corrections.’’1
1
TLE User Requirements Document, (DES LE ICG-DSS-STA-ReqMgr), Ver 2.0
dated 3 Aug 2009
Issue 1.0
Page 7
TLE will support the role of Intelligence, Surveillance, Target Acquisition and
Reconnaissance (ISTAR) by replacing the current LH40c TLE equipment as it
comes to the end of its service life.
Figure 1 Operational Graphic2.
TLE will be used as an offensive capability for Dismounted Close Combat (DCC). It
will primarily be used in support of Hasty Attack for which the TLE is the primary
means of accurate fire control. In this role it is assumed that the TLE will be used
by the Alpha Mortar Fire Controller (MFC) and Fire Support Team (FST).
1.4
Capability Gap
1.5
Customers
The Military customers and prime contractor for TLE are as follows:
Sponsor – CAP GM: Defines the capability required; owner of the business case
and URD; managing acceptance of capability; EP funding
User – D Inf: Focal point for majority of users; influences requirements documents
End User – RSA/SCHINF/etc: Represents the user groups (tri-service and multiarm) that currently use the LH40c TLE system.
Prime Contractor –XXX: Responsible for manufacture, supply and initial 5 year
support of SSARF and STLS.
HQ Land – Overall co-ordinator; responsible for the fielding plan and manages the
Lines of Development.
2
TLE MODAF Architecture, (DES LE ICG-DSS-STA-ReqMgr), 12 May 2009
_____
Issue 1.0
Page 8
1.6
Project Status and Approvals
The TLE project is an EP programme introduced by a PR09 Option, with funding
allocated in 09/10, 10/11 and 11/12. TLE is a single gate CAT D project and is
currently in the Assessment Phase. Main Gate approval is planned for May 2010.
DSS PT has down selected 3 potential suppliers via a Pre Qualification
Questionnaire process. Trials contracts have now been issued to these suppliers to
provide equipment for planned trails in January. An Invitation To Tender (ITT) will
be released concurrent with the trials.
1.7
Assumptions, Constraints and Drivers
The existing TLE equipment LH40c is approaching its OSD. In order to maintain a
light weight and mobile ISTAR capability the TLE programme is required to replace
the hand held TLE system to the designated User Community as defined by D Inf.
It is assumed that the TLE capability will be required for 10 years with an In Service
Date (ISD) of July 2011 (50%) an OSD of May 2022. It is expected that there will be
at least TLE systems distributed according to the TLE fielding plan which is
assumed to be similar to the SSARF fielding plan of September 2009. As at this
issue of the TLMP, there are no improvements or upgrades expected. Detailed
project assumptions, with their associated owners, can be found in the Master Data
and Assumptions List (MDAL) at Annex H.
1.8
Project Objectives
The objective of the TLE project is to replace and, where possible, improve the
current TLE system. This shall be accomplished by meeting the required levels of
capability defined in the URD and SRD, by provisioning a hand held target locator
equipment.
The top level needs for the TLE are to replace the current LH40c system with a
system that is small and light, yet offers 24 hr passive surveillance and detection
capability and which also provides fall of shot information.
1.9
Customer Supplier Agreements Targets
1.9.1
Programme Deliverables
Due to this project currently being pre Main Gate (MG) there have been no formal
agreements of deliveries. This section will be further updated post MG.
1.9.2
Capability Time Lines
ITT
-
Jan 2010 (50%)
MG -
May 2010 (50%)
Offer Contract -
June 2010 (50%)
EDD -
April 2011 (50%)
LSD -
June 2011 (50%)
ISD (PACE ) -
July 2011 (50%)
FOC -
May 2012 (50%)
OSD -
May 2022 (50%)
Issue 1.0
Page 9
Issue 1.0
Page 10
2
Stakeholders
This section details the TLE project stakeholders and their relationships in terms of
Responsible, Accountable, Consult, Inform, and Financial (RACI£) stakeholder
analysis and the Defence Lines of Development (DLODs) and will contain the
details outlined below.
2.1
Project Organisation
The TLE project organisation and responsibilities are held in the project team
organisation chart in Annex B. Responsibilities, governance and stakeholder
interface map are held below.
2.2
Project Governance
Governance of the TLE programme for both the Sponsor and the User DLOD
responsibilities and inputs are depicted in Figures 2 and 3 respectively.
Figure 2 Sponsor Governance
Issue 1.0
Page 11
Figure 3. User Governance
2.3
Stakeholder Interfaces
The stakeholder map detailed below at Figure 4 shows the relationship between the
stakeholders of the TLE programme.
Issue 1.0
Page 12
Figure 4. TLE Stakeholder Interfaces
2.4
Stakeholder Responsibility Matrix
A stakeholder matrix showing the responsibilities and roles of each key stakeholder
can be found at Annex D. In addition, the table shows the results of a Responsible,
Accountable, Consult, Inform, Financial (RACI£) analysis that determines the nature
of each stakeholders’ responsibilities in the context of the DLODs.
Issue 1.0
Page 13
3
Strategies
This section contains the high level Strategies mapped by DLODs that guide and
drive the TLE project. An overview project “plan on a page” detailing the major
milestones of the project can be found at Annex E.
3.1
TLM Strategy
Through Life Management is set in accordance with the Acquisition Operating
Framework (AOF) guidelines. It provides a whole life system outlook, using system
engineering principles throughout the CADMID lifecycle from Concept phase to final
Disposal, across all DLODs. In so doing it will provide the tools to produce better
informed, more timely decision making (through the TLMP). It will also proactively
engage stakeholders throughout the project lifecycle enabling better through life
thinking and producing achievable targets that are then agreed within a defined
stakeholder community.
The TLMP will be owned by the DSS PT and managed by the Programme Manager
(STA-Proj1). The first issue will be produced and distributed to stakeholders and will
be updated thereafter following the achievement of significant project milestones, or
at least on an annual basis. The TLMP will fulfil two main functions within the
project; it will act as an information management tool that will allow for strategic
through life decision making to occur It will provide a single planning focal point for
all DSS PT members and stakeholders and act as the access point to the detailed
‘knowledge base’ and planning documentation.
3.2
Training DLOD
The TLE system will require specialist training and a Train the Trainer package will
be a contractual deliverable placed on the prime contractor, with a tailored schedule
to be produced once the contract is let. A Training Needs Analysis (TNA) is
currently not planned to be produced for this system.
In addition, the TLE system will be supplied with relevant military format technical
documentation (e.g. AESP, Inf Pubs) by the prime contractor.
3.3
Equipment DLOD
3.3.1
Procurement Strategy
The procurement strategy3 for TLE is based on competitively assessed tendered
solutions. A Potential Future Purchase (PFP) has been advertised in the Defence
Contracts Bulletin and responders will be invited to go through a Pre-Qualification
Questionnaire (PQQ) to enable a short list to be produced. Following assessment of
these responses a Trial Equipment Contract will be issued to procure equipment for
Trials. Concurrently an Invitation To Tender (ITT) will be produced and issued to
those companies selected for trials.
ITT responses are expected by the end of the trials period. A Tender Assessment
Panel (TAP) will be set up comprising all relevant stakeholders to select a prime
contractor based upon results from trials and their response to the ITT.
3
Procurement Strategy for the TLE, REF:DSS/20/165/13
Page 14
Following MG Approval of the proposed system, contract negotiations will be
concluded with the selected supplier for the provision of production quantities of
systems and their support.
It is envisaged that CLS support will be provided on an Ad Hoc basis, when repairs
beyond Maintenance Level 1 are needed.
3.3.2
Risk Strategy
The TLE project does not have a separate Risk Management Plan (RMP), but
operates under the umbrella of DE&S Risk policy. TLE is fully compliant with the
DE&S risk policy and strategy following guidance from JSP 525.
3.3.3
Transition Strategy
There are no planned capability upgrades or improvements to the TLE capability
beyond ISD and final product acceptance. The in service life for TLE is planned for
10 years. Any costs beyond the figures detailed in Annex H will be met either via
review notes by CAP GM or by moving funds from other procurement projects.
3.3.4
Requirements Management Strategy
Acceptance Strategy - The acceptance of the TLE military capability will be based
on the progressive accumulation of evidence to form a reasoned, auditable
acceptance case to support a decision on whether the system satisfies the
Technical Solution, URD and SRD as illustrated below in Figure 4. This process will
record both success and failure together with the rationale for any additional
required activities with the associated success criteria.
Figure 5 System Engineering ‘V’ Diagram
3.4
Personnel DLOD
3.4.1
Safety and Environment Strategy
TLE Safety and Environment Management will comply with the DSS PT Safety,
Equipment Management Strategy (SEMS) and is in accordance with the limits set
within DEF STAN 00-56
SSARF safety philosophy is applied with guidance from JSP 454 and additional
information ensuring equipment safety will also be used in production of the
Programme Safety Management Plan (PSMP).
Page 15
3.5
Information DLOD
3.5.1
Operational Information
Currently there is an aspiration to have a TLE Networked Enabled Capability,
however due to the timelines for the development and fielding of the TLE system,
and with there being little scope for the addition of bespoke elements to the MOTS
or COTS system, it is expected that Networked Enabled elements will be
incorporated when TLE is in service.
In the interim, TLE will use an external in service GPS system and will use an
external in service communication system (most probably the Future Integrated
Soldier Technology (FIST) system).
3.5.2
Non Operational Information
Documentation associated with the TLE project will be held by the relevant
responsible stakeholder. The URD and SRD and ITEA database will be produced
and held in a DOORS system, with DOORS managing the linkages between the
documents.
3.6
Doctrine and Concepts DLOD
The development of Doctrine and Concepts underpins the work on several other
lines of development, especially those of Personnel, Organisation and Training.
The TLE Concept of Employment – CONEMP (V1.1 dated 19 July 2009) will form
the basis of the TLE Concept of Use (CONUSE) post Main Gate with the ultimate
output from this process being tactical doctrine to inform the user on how to employ
the system. It will be necessary to ensure that the use of TLE remains coherent
with the concepts being developed for training systems and environments.
3.7
Organisation DLOD
It is not foreseen that any changes will need to be made to the current LH40c
organisational requirements.
3.8
Infrastructure DLOD
Current Infrastructure is maintained by HQ Land Forces and it is envisaged that the
additional requirements of TLE will be minimal with little to no changes required to
the current LH40c infrastructure.
However, if the TLE system were later to become further “network enabled” then
infrastructure would need to be revisited to scope whether changes were needed.
3.9
Logistics DLOD
3.9.1
Support Aim
The aim of the support strategy of the TLE project is to maximise the operational
availability of the TLE system in the most cost effective manner.
Page 16
3.9.2
Support Strategy
The TLE system support strategy will be achieved through the application of ILS
methodology in accordance with DEFSTAN 00-60. TLE will also fully comply with
the Support Solutions Envelope (SSE). The TLE system will be procured to support
a minimum annual Peace time usage of 730 hours per equipment. Sufficient
capacity will be further provided to support an operation peak of XXX hrs over a six
month period per deployed equipment, with an annual budget of XXX hrs per
deployed equipment. XXX hours TBD.
Software support is highly likely due to the technology within TLE. The Contractor’s
Software Support Capability will need to cover all software used in any part of the
system.
LSA Strategy. The Logistic Support Analysis (LSA) Strategy identifies how the LSA
tasks will be tailored to meet the needs of the TLE when analysing and optimising
the proposed equipment and its support environment.
The LSA Strategy has yet to be produced.
3.9.3
Security Strategy
The Security Strategy has yet to be produced.
3.10
Interoperability
TLE has several dependencies on other systems currently in service or being
brought in to service. Interoperability issues are highlighted to CIWG and are then
considered and resolved.
Page 17
4
Plans and Processes
This section contains the plans and processes used by DSS PT to meet the
Strategies identified in Section 3. Within this section each plan and process will be
examined in terms of the related DLOD mirroring Section 3 – Strategies.
4.1
Training DLOD
Detailed planning information for the Training DLOD is to be based on the FIST
TNA that is currently in development.
4.2
Equipment DLOD
4.2.1
Procurement Plan
Procurement will be spread through from FY10/11 until FY11/12 and it is expected
that the expenditure will tail off significantly by FY12/13. The total CDEL is
expected to be £XXX. There has also been £XXX identified for support over the 10
years of expected equipment life. More detailed project plans relating to
procurement can be found at Annex E, G and Section 5 of this report.
4.2.2
Risk Plan
The Risk Management Plan is a description of how risk is to be managed within a
project. It defines roles, responsibilities, methodology, tools and techniques. A TLE
risk register containing the high level programme risks can be found in Annex F.
The Risk Management process is detailed below:
Figure 6
Risk Management Process
Identification: The objective of the identification stage is to identify the widest
possible categories of Risks associated with the programme. At this stage, DSS PT
will ensure that all TLE stakeholders are consulted and understand the
requirements of the project.
Assessment: The objective in this phase is to assist in the prioritisation of the
identified risks. All risks within the TLE project will be analysed to determine their
probability of occurrence and likely impact.
Page 18
Planning: The objective of the planning stage is to establish what action should be
taken to manage the risks. The actions will be prioritised accordingly and important
decisions and the reasons for the action taken recorded.
Management: This is the formulation of the management plan. As TLE is a
Category D project it will operate under the umbrella of the DSS Risk Management
Plan.
4.2.3
Transition Plan
The transition costs between EP spend and Short Term Plan (STP) spend through
the life of the TLE project are detailed in Annex G.
4.2.4
Requirements Management
ITEA Plan – The Integrated Test Evaluation and Acceptance Plan (ITEAP) is owned
by the DSS Project Team and managed by the DSS Requirements Manager. It is
part of a set of documents used in DSS PT for Requirements and Acceptance
Management. Key requirement and acceptance documents include the TLE
Ministry of Defence Architecture Framework (MODAF), the URD and the SRD. The
plan will be updated regularly as decisions are made and as the project progresses
through the CADMID cycle.
It is envisaged that the two principal Acceptance Events; System Acceptance and
In-Service Date will form the basis of TLE acceptance.
System Acceptance will take place by agreement of the DSS PT that the
candidate system has satisfied the terms of contract. This will be achieved by
verifying and declaring contractual conformance with each SRD requirement. Also
before the system acceptance can take place DSS PT must have qualified and
certified the equipment and have deemed it fit for purpose.
In-Service Date will occur when the capability across all the DLODs come together
to deliver the required TLE military capability and the system is therefore deemed
as available for operational use in its minimum deployable form.
4.3
Personnel DLOD
4.3.1
Safety and Environment Management Plan
To be completed by DSS-STA-Proj1
4.4
Information DLOD
4.4.1
Operational Information
TLE will be used alongside the current in service GPS system. There are also
aspirations for a FIST/BOWMAN interface. TLE will be used alongside these other
systems and will not integrate directly with them.
4.4.2
Configuration Control
TLMP - The TLMP is an active document which must contain the latest relevant
information, and will be reviewed on a regular basis by the owner (TLE project
Page 19
team). The reviews will take place during project meetings which coincide with
major programme milestones. Stakeholders are involved in these meetings,
however if the plan is to be re-issued it will first be promulgated to ALL stakeholders
for comment and acceptance. All comments will be fed back to the TLMP owner for
inclusion into the re-issued TLMP.
Non Operational Information - A schematic indicating the signoff process for TLE
documentation can be found at Annex I.
4.5
Organisation DLOD
The TLE systems will be distributed to the various user groups as needed. The
confirmed fleet distributions will be decided at a later date in accordance with the
TLE fielding plan that is currently under development.
4.6
Infrastructure DLOD
The existing infrastructure is maintained by HQ Land Forces and the internal
provision of training systems and services are maintained by DSS PT and D InF.
These facilities provide comprehensive support to similar systems and it is
envisaged that the additional requirements of TLE will be minimal.
4.7
Logistics DLOD
4.7.1
Integrated Logistics Support Plan (ILSP)
The aim of the ILSP (reference DCC/20/165) is to identify and document the logistic
requirements and constraints; describe the required logistic actions, tasks and
milestones and ensure that all relevant ILS elements and tasks are considered.
Logistic Support Committee (LSC) Meeting will be attended by the MILSM and his
team will be held to discuss the ILS processes and status of the TLE project in
greater depth these meetings will be held quarterly. The results/actions of the each
LSC meeting will be documented by DSS PT and reviewed by the MILSM prior to
distribution.
Due to low system numbers required () the preferred support solution for TLE is adhoc repair, with a spares pack through traditional Joint Supply Chain (JSC) support.
The contractor shall suggest an Initial Spares Pack (with costings) of all Level 1
spares to support the equipment for the first two years of its In Service life, with
options for a further three years. The initial spares requirement is funded from within
the EP and will be procured and placed in the Supply Chain to support the defined
levels of usage.
The maintenance policy for the TLE system will be based on Level 1 repairs at 1st
Line and Level 2 annual equipment inspection at 1st Line. The contractor will carry
out all other level repairs at 4th line. All repairs will be conducted by the Contractor
will be processed through the JSC.
LSA Plan. The Tenderer shall prepare and submit a Logistic Support Analysis Plan
(LSAP), in accordance with DEF STAN 00-60 UK DID 0002, as part of the ISP in
accordance with the ILS SOW (Ref DSS 20/165).
4.7.2
Obsolescence and Disposal
The Contractor shall supply information relating to disposal, both in-service and end
of life, to include; the supply of equipment disposal costs, the identification of all
Page 20
Safety, Health and Environmental hazards associated with disposal. This
information will include disposal instructions for all identified hazards including:
a) The policy and procedure for the disposal of items consumed in routine and
operational use.
b) The policy and procedure for the bulk disposal of back-loaded items.
c) The environmental impacts of disposal.
It is envisaged that all routine disposal will take place at Contractors site, however
unusual circumstances of use decree that details of localised disposal/destruction
are addressed.
4.7.3
Support Solutions Envelope (SSE)
The DSS Project Team is aware of the SSE requirements for TLE, as defined within
the AOF. The SSE elements are currently under development by the MILSM.
Page 21
5
Resources
5.1
Whole Life Costs
The Through Life Finance (TLF) cost of TLE is £XXX at 50% confidence, inclusive
of 10 years support.
It is unknown who will become the prime contractor for the Demonstration,
Manufacture and initial In service phase. However estimated costs have been
based on the procurement of similar systems.
The following cost estimates have been calculated:
5.2
Resources Costs (RDEL)
-
XXXX £M
Capital Costs (CDEL)
-
XXXX £M
Master Data and Assumptions List (MDAL)
The figures above have all been based upon the major assumption that the TLE will
have a similar cost to a comparable system that is currently being procured and will
have a service life of 10 years with an ISD 2011 and OSD 2022. A project MDAL
containing the major data and assumptions affecting the programme has also been
produced and can be found at Annex H.
5.3
Through Life Finance
A summary of the forecasted costs over the life of TLE are detailed below:
Near Cash Forecast
2009-2012
2012-2020
Total Life
£M
£M
£M
DE&S total
Value of above already on contract
Breakdown of DE&S forecast:
Equipment costs
Upgrades (none planned)
Spares (Repair, WMR, attrition)
Support
Disposal
Assessment
Other costs
TLE PR10 Bid
CDEL
RDEL
A more detailed cost breakdown over the life of the TLE project can be found at
Annex G.
Page 22
6
Evaluation of Success
6.1
TLMP Review Process and Updates
The TLMP is an active document which must contain the latest relevant information,
and will be reviewed on a regular basis by the owner (or on behalf of the owner by
the TLE project team). The reviews will take place during project meetings which
coincide with major programme milestones. Stakeholders are involved in these
meetings, however if the plan is to be re-issued it will first be promulgated to ALL
stakeholders for comment and acceptance. All comments will be fed back to the
TLMP owner for inclusion into the re-issued TLMP.
6.2
Accepted Milestones
TLE acceptance will be based upon two major system acceptance events:
System Acceptance will be agreed by DSS PT upon the verification that the system
is fully conformant and satisfies the contractual requirements of the SRD at all
levels. Before System acceptance can take place DSS PT will have to qualify and
certify the equipment as fit for purpose taking into account human factors,
sustainability, logistic support issues and the users’ CONEMP and CONUSE.
In-Service Date will be declared by the Sponsor when the full capability comprising
all the DLoDs come together to deliver the required TLE military capability and the
system is assessed as available for operational use in its minimum deployable form.
6.3
Success Criteria
A matrix detailing the TLE project success criteria, across the CADMID cycle and
ordered by DLOD can be found at Annex J.
6.4
Post Project Evaluation Plan
The Post Project Evaluation (PPE) Plan will be conducted after ISD and will be
reviewed annually at progress meetings in line with the extension of the support
solution.
Page 23
7
Glossary
AOF
Acquisition Operating Framework
ATDU
Artillery Trials and Development Unit
CADMID
Concept, Assessment, Development, Manufacture, Inservice, Disposal (Phases)
CAP
Capability
CDEL
Capital Expenditure
CLS
Contractor Logistics Support
CONEMP
Concept of Employment
CONUSE
Concept of Use
COTS
Commercial Of The Shelf
D Inf
Directorate Infantry
DAGR
Defence Advanced GPS Receiver
DCC
Dismounted Close Combat
DE&S
Defence Equipment & Support
DEME(A)
Directorate of Electrical and Mechanical Engineers
(Army)
DLOD
Defence Line Of Development
DRA
Directorate Royal Artillery
DSS
Dismounted Soldier Systems
FAC
Forward Air Controller
FIST
Future Integrated Soldier Technology
FOC
Full Operating Capability
FOO
Forward Observation Officer
FP
Force Protection
FST
Fire Support Team
FY
Financial Year
GM
Ground Manoeuvre
GPS
Global Positioning System
HQ
Head Quarters
HQ AIR
Head Quarters Air Command
HQ FLEET
Head Quarters Fleet
HQ LF
Head Quarters Land Forces
ILS
Integrated Logistics Support
ILSP
Integrated Logistics Support Plan
Page 24
Inf Pub
Infantry Publications
ISD
In Service Date
ISTAR
Intelligence, Surveillance, Target Acquisition and
Reconnaissance
ITDU
Infantry Trials and Development Unit
ITEA
Integrated Trials Evaluation and Assessment
ITT
Invitation To Tender
JFI
Joint Fire Integrator
JSP
Joint Service Publication
KUR
Key User Requirement
LH40c
Current In service TLE system
LSD
Logistical Support Date
MDAL
Master Data and Assumptions List
MFC
Mortar Fire Controller
MG
Main Gate
MODAF
Ministry of Defence Architecture Framework
MOTS
Military Of The Shelf
NEC
Network Enabled Capability
OSD
Out of Service Date
PFP
Potential Future Purchase
PQQ
Pre-Qualification Questionnaire
PT
Project Team
RACI£
Responsibility, Accountability, Consulted, Informed,
Financial
RAF
Royal Air Force
RATD
Recce Armoured Tactics Division
RDEL
Resource Expenditure
RSA
Royal School of Artillery
SCHINF
School of Infantry
SPGR
Specialist Personal GPS Receiver
SRD
System Requirement Document
SSARF
Surveillance System And Range Finder
SSE
Support Solution Envelope
STA
Surveillance and Target Acquisition
STLS
Surveillance and Target Locating System
SWS
Support Weapons School
TAP
Tender Assessment Panel
TLE
Target Locator Equipment
Page 25
8
TLF
Through Life Finance
TLM
Through Life Management
TLMP
Through Life Management Plan
TNA
Training Needs Analysis
UOR
Urgent Operational Requirement
URD
User Requirement Document
WLC
Whole Life Cost
List of Annexes
A.
Key User Requirements
B.
DSS PT Organisation
C.
TLE stakeholder information list
D.
TLE project RACI£ matrix
E.
TLE project plan on a page
F.
TLE project key risk register
G.
Through Life Finances
H.
Project Master Data and Assumptions List
I.
DSS PT signoff diagram
J.
TLE project Success Criteria Matrix
Page 26
ANNEX A TO
TLE TLMP
DATED OCT 09
Key User Requirements
Object
Identifier
SR
Ref
Object Text
Threshold
MOE
Objective
MOE
Priority
Justification
Page 27
Status
Validation
Criteria
Validation
Category
UR
Owner
Remarks
Page 28
Page 29
Page 30
Page 31
ANNEX B TO
TLE TLMP
DATED OCT 09
DSS Project Team Organisation Chart
Page 32
ANNEX C TO
TLE TLMP
DATED OCT 09
Stakeholder List
CIWG CHAIR
Appt (E-Mail)
Name
Maj Mike Baxter
Mil No.
94381
2360
94381
2675
BT No.
01985
222360
01985
222392
Mob No.
07747
791211
07827
928331
HQ DInf - Cap
Dinf-Cap-AD
Col Mike Thornton
CIWG Sec
EC SPONSOR
Dinf-Cap-PlansISTAR-SO2
Cap GM
EQUIPMENT
EC GM-SO2 DCC
Maj Connar O'Hara
96218
0604
02072
180604
07884
111263
93523
7177
93523
7122
94331
2570
94381
2113
94381
8759
01179
137177
01179
137122
DSS PT
DES DSS-STA-Proj1
Mr Trevor Lawrence
DSS PT
DES DSS-STA-ReqMgr
Major Justin Prowse
HQ LF - Eqpt
LF-Eqpt-CE DCC SO2
Maj Lewis Hartman
ITDU
DInf-ITDU-SW-SO2
Maj Tim Hutchison
ITDU
DINF-ITDU-STA-SO2
Maj Rob Yuill
TRAINING
Page 33
01985
222113
INFORMATION
DOCTRINE AND CONCEPTS
ORGANISATION
INFRASTRUCTURE
LOGISTICS AND SUSTAINABILITY
USER / OPS
Page 34
SAFETY
COMMERCIAL
FINANCE
Page 35
ANNEX D TO
TLE TLMP
DATED OCT 09
Stakeholder Responsibility Matrix
D Inf / DRA / DRAC
(User)
HQ Land
RSA/SCHINF/Etc
(End User)
CI(A)
??
(Prime Contractor)
Information
Organisation
I
C
I
C
I£
I£
R
R
I
I
I
I
RA
RA
R
C
R
C
AR
R
I
C
- Deals with the
overarching doctrine
issues.
- Representatives of
relevant User communities
A
C
AR£
A
I
A
C
R
C
C
C
C
C
C
C
C
- Accountable for
interoperability of the TLE
- Manufacturer
- CSA contract
- Produces various
R£
C
I
C
I
R
R
I
I
I
Page 36
Logistics
A£
Doctrine
Concept
C£
Responsibility & Role
- Runs Business Case
- EP Funding
- Sanctions changes to
cost, performance and
time
- Provides equipment
support
- Project Management
- Provides User comments
and representation
Personnel
Equipment
DSS PT
Training
Stakeholder
CAP GM (Sponsor)
Infrastructure
&
DLOD (Responsible, Accountable, Consult, Inform, £money)
C1
I
R
R
Scrutineers
ITDU
documentation relating to
equipment e.g. Safety
Plan; training plan etc…
- SME’s
- Provides technical
assistance
- Responsible for technical
trials
- Ensure that all
documents produced are
fully compliant within its
area.
- User trials authority
- Represents the User in
terms of design changes
etc….
I
C
I
I
I
I
I
C
I
I
I
I
I
I
I
I
C
C
I
I
I
I
I
C
Page 37
ANNEX E TO
TLE TLMP
DATED OCT 09
Plan on a page
Page 38
ANNEX F TO
TLE TLMP
DATED OCT 09
Key Risk Register
Impact
Risk
Prob
Proposed Mitigation
P
C
T
Mitigation Success/Progress
Status
(R/A/G)
G
G
G
G
Page 39
G
Page 40
ANNEX G TO
TLE TLMP
DATED OCT 09
Through Life Finances
Totals
Assessment
Assume 5
contenders
Assume 2
samples of
each
Assume XX
costs of
Assume User
environmental
trial at cost of
Manufacturing
Equipment
costs
Safety Case
ILS
Assume Repair
Pool @
Assume WMR
@
Assume
attrition @
2/year
In Service
5 years support
@ 5% of
procurement
cost per year
Last 5 yrs to be
noted
Disposal
Disposal say
5
2008-2009
2009-2010
2010-2011
11-12
12-13
5
4.00%
2.00%
2
£
Page 41
13-14
14-15
15-16
16-20
1%
Grand Costs
Page 42
ANNEX H TO
TLE TLMP
DATED OCT 09
Ser No
Master Data and Assumptions List (MDAL)
Entry
Date
Description
Authority
Last
Review
Reviewed Date
Page 43
Owner
Value
Comments
Page 44
Page 45
Page 46
Page 47
Page 48
ANNEX I TO
TLE TLMP
DATED OCT 09
TLMP Document Control Process
Page 49
ANNEX J TO
TLE TLMP
DATED OCT 09
Success Criteria and Objectives
Target Locator Equipment (TLE) CADMID Cycle Phases
Assessment
Manufacture
InDisposal
Service
DLOD
Training




Equipment
Personnel
Information
Concepts
and Doctrine
Organisation
Infrastructure
Logistics












Page 50