DSS/00099 Appendix 2 to SNITS Annex C Target Locator Equipment (TLE) Through Life Management Plan Dismounted Soldier Systems Project Team 3rd December 2009 Issue 1.0 List of contents 1 Mission and Objectives 1.1 Objective of TLMP 1.2 Project Overview 1.3 Military and Capability Context 1.4 Capability Gap 1.5 Customers 1.6 Project Status and Approvals 1.7 Assumptions, Constraints and Drivers 1.8 Project Objectives 1.9 Customer Supplier Agreements Targets 1.9.1 Programme Deliverables 1.9.2 Capability Time Lines 2 Stakeholders 2.1 Project Organisation 2.2 Project Governance 2.3 Stakeholder Interfaces 2.4 Stakeholder Responsibility Matrix 11 11 11 12 13 3 Strategies 3.1 TLM Strategy 3.2 Training DLOD 3.3 Equipment DLOD 3.3.1 Procurement Strategy 3.3.2 Risk Strategy 3.3.3 Transition Strategy 3.3.4 Requirements Management Strategy 3.4 Personnel DLOD 3.4.1 Safety and Environment Strategy 3.5 Information DLOD 3.5.1 Operational Information 3.5.2 Non Operational Information 3.6 Doctrine and Concepts DLOD 3.7 Organisation DLOD 3.8 Infrastructure DLOD 3.9 Logistics DLOD 3.9.1 Support Aim 3.9.2 Support Strategy 3.9.3 Security Strategy 3.10 Interoperability 14 14 14 14 14 15 15 15 15 15 16 16 16 16 16 16 16 16 17 17 17 4 Plans and Processes 4.1 Training DLOD 4.2 Equipment DLOD 4.2.1 Procurement Plan 18 18 18 18 Issue 1.0 Page 3 7 7 7 7 8 8 9 9 9 9 9 9 4.2.2 4.2.3 4.2.4 4.3 4.3.1 4.4 4.4.1 4.4.2 4.5 4.6 4.7 4.7.1 4.7.2 4.7.3 Risk Plan Transition Plan Requirements Management Personnel DLOD Safety and Environment Management Plan Information DLOD Operational Information Configuration Control Organisation DLOD Infrastructure DLOD Logistics DLOD Integrated Logistics Support Plan (ILSP) Obsolescence and Disposal Support Solutions Envelope (SSE) 18 19 19 19 19 19 19 19 20 20 20 20 20 21 5 Resources 5.1 Whole Life Costs 5.2 Master Data and Assumptions List (MDAL) 5.3 Through Life Finance 22 22 22 22 6 Evaluation of Success 6.1 TLMP Review Process and Updates 6.2 Accepted Milestones 6.3 Success Criteria 6.4 Post Project Evaluation Plan 23 23 23 23 23 Issue 1.0 Page 4 7 Glossary 24 8 List of Annexes 26 ANNEX A TO 27 TLE TLMP 27 ANNEX B TO 32 TLE TLMP 32 ANNEX C TO 33 TLE TLMP 33 ANNEX D TO 36 TLE TLMP 36 ANNEX E TO 38 TLE TLMP 38 ANNEX F TO 39 TLE TLMP 39 ANNEX G TO 41 TLE TLMP 41 ANNEX I TO 49 TLE TLMP 49 ANNEX J TO 50 TLE TLMP 50 Issue 1.0 Page 5 Administration page Customer Information Customer reference number n/a Project title Target Locator Equipment Through Life Management Plan Customer Organisation DE&S Dismounted Soldier Systems Customer contact Contract number Milestone number WP2 TLMP Date due T0+14 Record of changes Issue 1.0 Date 03 /12/ 09 Issue 1.0 Detail of Changes n/a Page 6 1 Mission and Objectives This section describes the background and the bounds of the TLE project. 1.1 Objective of TLMP The objective of this Through Life Management Plan (TLMP) is to provide the single source of strategic management information for the Target Locator Equipment (TLE) programme and provides access to more detailed information required by staff and others to manage their activities. This document is owned by the Dismounted Soldier Systems (DSS) Project Team (PT) and is managed by the Project Board (in particular DSS-STA-Proj1). This document provides a single planning focal point for all team members and stakeholders and is the access point to the detailed ‘knowledge base’ and planning documentation. It is the authoritative document for the management of the programme and will contain the latest agreed versions of schedules, objectives, strategies, plans etc. Persons requiring access to the key documents referenced throughout this TLMP should note that many have protective markings and some also have commercial restrictive markings. 1.2 Project Overview The TLE project is a category D single gate procurement project aimed at delivering a replacement for the currently in-service LH40c TLE system to support Fire Support Teams (FST), in particular for the Mortar Fire Controller and Forward Observation Officer of the Mortar Division and Royal Artillery respectively. The project is currently in the Assessment Phase, post Pre Qualification Questionnaire (PQQ) with Trials Contracts being issued. The TLE project will provide a handheld system that will deliver a rapid, simple and precise method of determining range, bearing and inclination in order that, when combined with own position data, will give accurate location of a sighted target and allow for fall of shot corrections. The TLE project will deliver a system that will provide a 24 hour surveillance capability, with the same target recognition performance, with improved mobility over the current in-service system. The TLE project will provide a Commercial Off The Shelf (COTS) or Military Off The Shelf (MOTS) solution that will be tested by the Infantry Trials and Development Unit (ITDU) and XXX with the aim of achieving acceptance against all Key User Requirements (KURs) which can be found in Annex A. 1.3 Military and Capability Context The proposed Single Statement of User Needs states that: “TLE must provide the Mortar Fire Controller and Forward Observation Officer with a rapid, simple and precise method of determining range, bearing and inclination in order that when combined with accurate own position data will give accurate location of a sighted target and fall of shot corrections.’’1 1 TLE User Requirements Document, (DES LE ICG-DSS-STA-ReqMgr), Ver 2.0 dated 3 Aug 2009 Issue 1.0 Page 7 TLE will support the role of Intelligence, Surveillance, Target Acquisition and Reconnaissance (ISTAR) by replacing the current LH40c TLE equipment as it comes to the end of its service life. Figure 1 Operational Graphic2. TLE will be used as an offensive capability for Dismounted Close Combat (DCC). It will primarily be used in support of Hasty Attack for which the TLE is the primary means of accurate fire control. In this role it is assumed that the TLE will be used by the Alpha Mortar Fire Controller (MFC) and Fire Support Team (FST). 1.4 Capability Gap 1.5 Customers The Military customers and prime contractor for TLE are as follows: Sponsor – CAP GM: Defines the capability required; owner of the business case and URD; managing acceptance of capability; EP funding User – D Inf: Focal point for majority of users; influences requirements documents End User – RSA/SCHINF/etc: Represents the user groups (tri-service and multiarm) that currently use the LH40c TLE system. Prime Contractor –XXX: Responsible for manufacture, supply and initial 5 year support of SSARF and STLS. HQ Land – Overall co-ordinator; responsible for the fielding plan and manages the Lines of Development. 2 TLE MODAF Architecture, (DES LE ICG-DSS-STA-ReqMgr), 12 May 2009 _____ Issue 1.0 Page 8 1.6 Project Status and Approvals The TLE project is an EP programme introduced by a PR09 Option, with funding allocated in 09/10, 10/11 and 11/12. TLE is a single gate CAT D project and is currently in the Assessment Phase. Main Gate approval is planned for May 2010. DSS PT has down selected 3 potential suppliers via a Pre Qualification Questionnaire process. Trials contracts have now been issued to these suppliers to provide equipment for planned trails in January. An Invitation To Tender (ITT) will be released concurrent with the trials. 1.7 Assumptions, Constraints and Drivers The existing TLE equipment LH40c is approaching its OSD. In order to maintain a light weight and mobile ISTAR capability the TLE programme is required to replace the hand held TLE system to the designated User Community as defined by D Inf. It is assumed that the TLE capability will be required for 10 years with an In Service Date (ISD) of July 2011 (50%) an OSD of May 2022. It is expected that there will be at least TLE systems distributed according to the TLE fielding plan which is assumed to be similar to the SSARF fielding plan of September 2009. As at this issue of the TLMP, there are no improvements or upgrades expected. Detailed project assumptions, with their associated owners, can be found in the Master Data and Assumptions List (MDAL) at Annex H. 1.8 Project Objectives The objective of the TLE project is to replace and, where possible, improve the current TLE system. This shall be accomplished by meeting the required levels of capability defined in the URD and SRD, by provisioning a hand held target locator equipment. The top level needs for the TLE are to replace the current LH40c system with a system that is small and light, yet offers 24 hr passive surveillance and detection capability and which also provides fall of shot information. 1.9 Customer Supplier Agreements Targets 1.9.1 Programme Deliverables Due to this project currently being pre Main Gate (MG) there have been no formal agreements of deliveries. This section will be further updated post MG. 1.9.2 Capability Time Lines ITT - Jan 2010 (50%) MG - May 2010 (50%) Offer Contract - June 2010 (50%) EDD - April 2011 (50%) LSD - June 2011 (50%) ISD (PACE ) - July 2011 (50%) FOC - May 2012 (50%) OSD - May 2022 (50%) Issue 1.0 Page 9 Issue 1.0 Page 10 2 Stakeholders This section details the TLE project stakeholders and their relationships in terms of Responsible, Accountable, Consult, Inform, and Financial (RACI£) stakeholder analysis and the Defence Lines of Development (DLODs) and will contain the details outlined below. 2.1 Project Organisation The TLE project organisation and responsibilities are held in the project team organisation chart in Annex B. Responsibilities, governance and stakeholder interface map are held below. 2.2 Project Governance Governance of the TLE programme for both the Sponsor and the User DLOD responsibilities and inputs are depicted in Figures 2 and 3 respectively. Figure 2 Sponsor Governance Issue 1.0 Page 11 Figure 3. User Governance 2.3 Stakeholder Interfaces The stakeholder map detailed below at Figure 4 shows the relationship between the stakeholders of the TLE programme. Issue 1.0 Page 12 Figure 4. TLE Stakeholder Interfaces 2.4 Stakeholder Responsibility Matrix A stakeholder matrix showing the responsibilities and roles of each key stakeholder can be found at Annex D. In addition, the table shows the results of a Responsible, Accountable, Consult, Inform, Financial (RACI£) analysis that determines the nature of each stakeholders’ responsibilities in the context of the DLODs. Issue 1.0 Page 13 3 Strategies This section contains the high level Strategies mapped by DLODs that guide and drive the TLE project. An overview project “plan on a page” detailing the major milestones of the project can be found at Annex E. 3.1 TLM Strategy Through Life Management is set in accordance with the Acquisition Operating Framework (AOF) guidelines. It provides a whole life system outlook, using system engineering principles throughout the CADMID lifecycle from Concept phase to final Disposal, across all DLODs. In so doing it will provide the tools to produce better informed, more timely decision making (through the TLMP). It will also proactively engage stakeholders throughout the project lifecycle enabling better through life thinking and producing achievable targets that are then agreed within a defined stakeholder community. The TLMP will be owned by the DSS PT and managed by the Programme Manager (STA-Proj1). The first issue will be produced and distributed to stakeholders and will be updated thereafter following the achievement of significant project milestones, or at least on an annual basis. The TLMP will fulfil two main functions within the project; it will act as an information management tool that will allow for strategic through life decision making to occur It will provide a single planning focal point for all DSS PT members and stakeholders and act as the access point to the detailed ‘knowledge base’ and planning documentation. 3.2 Training DLOD The TLE system will require specialist training and a Train the Trainer package will be a contractual deliverable placed on the prime contractor, with a tailored schedule to be produced once the contract is let. A Training Needs Analysis (TNA) is currently not planned to be produced for this system. In addition, the TLE system will be supplied with relevant military format technical documentation (e.g. AESP, Inf Pubs) by the prime contractor. 3.3 Equipment DLOD 3.3.1 Procurement Strategy The procurement strategy3 for TLE is based on competitively assessed tendered solutions. A Potential Future Purchase (PFP) has been advertised in the Defence Contracts Bulletin and responders will be invited to go through a Pre-Qualification Questionnaire (PQQ) to enable a short list to be produced. Following assessment of these responses a Trial Equipment Contract will be issued to procure equipment for Trials. Concurrently an Invitation To Tender (ITT) will be produced and issued to those companies selected for trials. ITT responses are expected by the end of the trials period. A Tender Assessment Panel (TAP) will be set up comprising all relevant stakeholders to select a prime contractor based upon results from trials and their response to the ITT. 3 Procurement Strategy for the TLE, REF:DSS/20/165/13 Page 14 Following MG Approval of the proposed system, contract negotiations will be concluded with the selected supplier for the provision of production quantities of systems and their support. It is envisaged that CLS support will be provided on an Ad Hoc basis, when repairs beyond Maintenance Level 1 are needed. 3.3.2 Risk Strategy The TLE project does not have a separate Risk Management Plan (RMP), but operates under the umbrella of DE&S Risk policy. TLE is fully compliant with the DE&S risk policy and strategy following guidance from JSP 525. 3.3.3 Transition Strategy There are no planned capability upgrades or improvements to the TLE capability beyond ISD and final product acceptance. The in service life for TLE is planned for 10 years. Any costs beyond the figures detailed in Annex H will be met either via review notes by CAP GM or by moving funds from other procurement projects. 3.3.4 Requirements Management Strategy Acceptance Strategy - The acceptance of the TLE military capability will be based on the progressive accumulation of evidence to form a reasoned, auditable acceptance case to support a decision on whether the system satisfies the Technical Solution, URD and SRD as illustrated below in Figure 4. This process will record both success and failure together with the rationale for any additional required activities with the associated success criteria. Figure 5 System Engineering ‘V’ Diagram 3.4 Personnel DLOD 3.4.1 Safety and Environment Strategy TLE Safety and Environment Management will comply with the DSS PT Safety, Equipment Management Strategy (SEMS) and is in accordance with the limits set within DEF STAN 00-56 SSARF safety philosophy is applied with guidance from JSP 454 and additional information ensuring equipment safety will also be used in production of the Programme Safety Management Plan (PSMP). Page 15 3.5 Information DLOD 3.5.1 Operational Information Currently there is an aspiration to have a TLE Networked Enabled Capability, however due to the timelines for the development and fielding of the TLE system, and with there being little scope for the addition of bespoke elements to the MOTS or COTS system, it is expected that Networked Enabled elements will be incorporated when TLE is in service. In the interim, TLE will use an external in service GPS system and will use an external in service communication system (most probably the Future Integrated Soldier Technology (FIST) system). 3.5.2 Non Operational Information Documentation associated with the TLE project will be held by the relevant responsible stakeholder. The URD and SRD and ITEA database will be produced and held in a DOORS system, with DOORS managing the linkages between the documents. 3.6 Doctrine and Concepts DLOD The development of Doctrine and Concepts underpins the work on several other lines of development, especially those of Personnel, Organisation and Training. The TLE Concept of Employment – CONEMP (V1.1 dated 19 July 2009) will form the basis of the TLE Concept of Use (CONUSE) post Main Gate with the ultimate output from this process being tactical doctrine to inform the user on how to employ the system. It will be necessary to ensure that the use of TLE remains coherent with the concepts being developed for training systems and environments. 3.7 Organisation DLOD It is not foreseen that any changes will need to be made to the current LH40c organisational requirements. 3.8 Infrastructure DLOD Current Infrastructure is maintained by HQ Land Forces and it is envisaged that the additional requirements of TLE will be minimal with little to no changes required to the current LH40c infrastructure. However, if the TLE system were later to become further “network enabled” then infrastructure would need to be revisited to scope whether changes were needed. 3.9 Logistics DLOD 3.9.1 Support Aim The aim of the support strategy of the TLE project is to maximise the operational availability of the TLE system in the most cost effective manner. Page 16 3.9.2 Support Strategy The TLE system support strategy will be achieved through the application of ILS methodology in accordance with DEFSTAN 00-60. TLE will also fully comply with the Support Solutions Envelope (SSE). The TLE system will be procured to support a minimum annual Peace time usage of 730 hours per equipment. Sufficient capacity will be further provided to support an operation peak of XXX hrs over a six month period per deployed equipment, with an annual budget of XXX hrs per deployed equipment. XXX hours TBD. Software support is highly likely due to the technology within TLE. The Contractor’s Software Support Capability will need to cover all software used in any part of the system. LSA Strategy. The Logistic Support Analysis (LSA) Strategy identifies how the LSA tasks will be tailored to meet the needs of the TLE when analysing and optimising the proposed equipment and its support environment. The LSA Strategy has yet to be produced. 3.9.3 Security Strategy The Security Strategy has yet to be produced. 3.10 Interoperability TLE has several dependencies on other systems currently in service or being brought in to service. Interoperability issues are highlighted to CIWG and are then considered and resolved. Page 17 4 Plans and Processes This section contains the plans and processes used by DSS PT to meet the Strategies identified in Section 3. Within this section each plan and process will be examined in terms of the related DLOD mirroring Section 3 – Strategies. 4.1 Training DLOD Detailed planning information for the Training DLOD is to be based on the FIST TNA that is currently in development. 4.2 Equipment DLOD 4.2.1 Procurement Plan Procurement will be spread through from FY10/11 until FY11/12 and it is expected that the expenditure will tail off significantly by FY12/13. The total CDEL is expected to be £XXX. There has also been £XXX identified for support over the 10 years of expected equipment life. More detailed project plans relating to procurement can be found at Annex E, G and Section 5 of this report. 4.2.2 Risk Plan The Risk Management Plan is a description of how risk is to be managed within a project. It defines roles, responsibilities, methodology, tools and techniques. A TLE risk register containing the high level programme risks can be found in Annex F. The Risk Management process is detailed below: Figure 6 Risk Management Process Identification: The objective of the identification stage is to identify the widest possible categories of Risks associated with the programme. At this stage, DSS PT will ensure that all TLE stakeholders are consulted and understand the requirements of the project. Assessment: The objective in this phase is to assist in the prioritisation of the identified risks. All risks within the TLE project will be analysed to determine their probability of occurrence and likely impact. Page 18 Planning: The objective of the planning stage is to establish what action should be taken to manage the risks. The actions will be prioritised accordingly and important decisions and the reasons for the action taken recorded. Management: This is the formulation of the management plan. As TLE is a Category D project it will operate under the umbrella of the DSS Risk Management Plan. 4.2.3 Transition Plan The transition costs between EP spend and Short Term Plan (STP) spend through the life of the TLE project are detailed in Annex G. 4.2.4 Requirements Management ITEA Plan – The Integrated Test Evaluation and Acceptance Plan (ITEAP) is owned by the DSS Project Team and managed by the DSS Requirements Manager. It is part of a set of documents used in DSS PT for Requirements and Acceptance Management. Key requirement and acceptance documents include the TLE Ministry of Defence Architecture Framework (MODAF), the URD and the SRD. The plan will be updated regularly as decisions are made and as the project progresses through the CADMID cycle. It is envisaged that the two principal Acceptance Events; System Acceptance and In-Service Date will form the basis of TLE acceptance. System Acceptance will take place by agreement of the DSS PT that the candidate system has satisfied the terms of contract. This will be achieved by verifying and declaring contractual conformance with each SRD requirement. Also before the system acceptance can take place DSS PT must have qualified and certified the equipment and have deemed it fit for purpose. In-Service Date will occur when the capability across all the DLODs come together to deliver the required TLE military capability and the system is therefore deemed as available for operational use in its minimum deployable form. 4.3 Personnel DLOD 4.3.1 Safety and Environment Management Plan To be completed by DSS-STA-Proj1 4.4 Information DLOD 4.4.1 Operational Information TLE will be used alongside the current in service GPS system. There are also aspirations for a FIST/BOWMAN interface. TLE will be used alongside these other systems and will not integrate directly with them. 4.4.2 Configuration Control TLMP - The TLMP is an active document which must contain the latest relevant information, and will be reviewed on a regular basis by the owner (TLE project Page 19 team). The reviews will take place during project meetings which coincide with major programme milestones. Stakeholders are involved in these meetings, however if the plan is to be re-issued it will first be promulgated to ALL stakeholders for comment and acceptance. All comments will be fed back to the TLMP owner for inclusion into the re-issued TLMP. Non Operational Information - A schematic indicating the signoff process for TLE documentation can be found at Annex I. 4.5 Organisation DLOD The TLE systems will be distributed to the various user groups as needed. The confirmed fleet distributions will be decided at a later date in accordance with the TLE fielding plan that is currently under development. 4.6 Infrastructure DLOD The existing infrastructure is maintained by HQ Land Forces and the internal provision of training systems and services are maintained by DSS PT and D InF. These facilities provide comprehensive support to similar systems and it is envisaged that the additional requirements of TLE will be minimal. 4.7 Logistics DLOD 4.7.1 Integrated Logistics Support Plan (ILSP) The aim of the ILSP (reference DCC/20/165) is to identify and document the logistic requirements and constraints; describe the required logistic actions, tasks and milestones and ensure that all relevant ILS elements and tasks are considered. Logistic Support Committee (LSC) Meeting will be attended by the MILSM and his team will be held to discuss the ILS processes and status of the TLE project in greater depth these meetings will be held quarterly. The results/actions of the each LSC meeting will be documented by DSS PT and reviewed by the MILSM prior to distribution. Due to low system numbers required () the preferred support solution for TLE is adhoc repair, with a spares pack through traditional Joint Supply Chain (JSC) support. The contractor shall suggest an Initial Spares Pack (with costings) of all Level 1 spares to support the equipment for the first two years of its In Service life, with options for a further three years. The initial spares requirement is funded from within the EP and will be procured and placed in the Supply Chain to support the defined levels of usage. The maintenance policy for the TLE system will be based on Level 1 repairs at 1st Line and Level 2 annual equipment inspection at 1st Line. The contractor will carry out all other level repairs at 4th line. All repairs will be conducted by the Contractor will be processed through the JSC. LSA Plan. The Tenderer shall prepare and submit a Logistic Support Analysis Plan (LSAP), in accordance with DEF STAN 00-60 UK DID 0002, as part of the ISP in accordance with the ILS SOW (Ref DSS 20/165). 4.7.2 Obsolescence and Disposal The Contractor shall supply information relating to disposal, both in-service and end of life, to include; the supply of equipment disposal costs, the identification of all Page 20 Safety, Health and Environmental hazards associated with disposal. This information will include disposal instructions for all identified hazards including: a) The policy and procedure for the disposal of items consumed in routine and operational use. b) The policy and procedure for the bulk disposal of back-loaded items. c) The environmental impacts of disposal. It is envisaged that all routine disposal will take place at Contractors site, however unusual circumstances of use decree that details of localised disposal/destruction are addressed. 4.7.3 Support Solutions Envelope (SSE) The DSS Project Team is aware of the SSE requirements for TLE, as defined within the AOF. The SSE elements are currently under development by the MILSM. Page 21 5 Resources 5.1 Whole Life Costs The Through Life Finance (TLF) cost of TLE is £XXX at 50% confidence, inclusive of 10 years support. It is unknown who will become the prime contractor for the Demonstration, Manufacture and initial In service phase. However estimated costs have been based on the procurement of similar systems. The following cost estimates have been calculated: 5.2 Resources Costs (RDEL) - XXXX £M Capital Costs (CDEL) - XXXX £M Master Data and Assumptions List (MDAL) The figures above have all been based upon the major assumption that the TLE will have a similar cost to a comparable system that is currently being procured and will have a service life of 10 years with an ISD 2011 and OSD 2022. A project MDAL containing the major data and assumptions affecting the programme has also been produced and can be found at Annex H. 5.3 Through Life Finance A summary of the forecasted costs over the life of TLE are detailed below: Near Cash Forecast 2009-2012 2012-2020 Total Life £M £M £M DE&S total Value of above already on contract Breakdown of DE&S forecast: Equipment costs Upgrades (none planned) Spares (Repair, WMR, attrition) Support Disposal Assessment Other costs TLE PR10 Bid CDEL RDEL A more detailed cost breakdown over the life of the TLE project can be found at Annex G. Page 22 6 Evaluation of Success 6.1 TLMP Review Process and Updates The TLMP is an active document which must contain the latest relevant information, and will be reviewed on a regular basis by the owner (or on behalf of the owner by the TLE project team). The reviews will take place during project meetings which coincide with major programme milestones. Stakeholders are involved in these meetings, however if the plan is to be re-issued it will first be promulgated to ALL stakeholders for comment and acceptance. All comments will be fed back to the TLMP owner for inclusion into the re-issued TLMP. 6.2 Accepted Milestones TLE acceptance will be based upon two major system acceptance events: System Acceptance will be agreed by DSS PT upon the verification that the system is fully conformant and satisfies the contractual requirements of the SRD at all levels. Before System acceptance can take place DSS PT will have to qualify and certify the equipment as fit for purpose taking into account human factors, sustainability, logistic support issues and the users’ CONEMP and CONUSE. In-Service Date will be declared by the Sponsor when the full capability comprising all the DLoDs come together to deliver the required TLE military capability and the system is assessed as available for operational use in its minimum deployable form. 6.3 Success Criteria A matrix detailing the TLE project success criteria, across the CADMID cycle and ordered by DLOD can be found at Annex J. 6.4 Post Project Evaluation Plan The Post Project Evaluation (PPE) Plan will be conducted after ISD and will be reviewed annually at progress meetings in line with the extension of the support solution. Page 23 7 Glossary AOF Acquisition Operating Framework ATDU Artillery Trials and Development Unit CADMID Concept, Assessment, Development, Manufacture, Inservice, Disposal (Phases) CAP Capability CDEL Capital Expenditure CLS Contractor Logistics Support CONEMP Concept of Employment CONUSE Concept of Use COTS Commercial Of The Shelf D Inf Directorate Infantry DAGR Defence Advanced GPS Receiver DCC Dismounted Close Combat DE&S Defence Equipment & Support DEME(A) Directorate of Electrical and Mechanical Engineers (Army) DLOD Defence Line Of Development DRA Directorate Royal Artillery DSS Dismounted Soldier Systems FAC Forward Air Controller FIST Future Integrated Soldier Technology FOC Full Operating Capability FOO Forward Observation Officer FP Force Protection FST Fire Support Team FY Financial Year GM Ground Manoeuvre GPS Global Positioning System HQ Head Quarters HQ AIR Head Quarters Air Command HQ FLEET Head Quarters Fleet HQ LF Head Quarters Land Forces ILS Integrated Logistics Support ILSP Integrated Logistics Support Plan Page 24 Inf Pub Infantry Publications ISD In Service Date ISTAR Intelligence, Surveillance, Target Acquisition and Reconnaissance ITDU Infantry Trials and Development Unit ITEA Integrated Trials Evaluation and Assessment ITT Invitation To Tender JFI Joint Fire Integrator JSP Joint Service Publication KUR Key User Requirement LH40c Current In service TLE system LSD Logistical Support Date MDAL Master Data and Assumptions List MFC Mortar Fire Controller MG Main Gate MODAF Ministry of Defence Architecture Framework MOTS Military Of The Shelf NEC Network Enabled Capability OSD Out of Service Date PFP Potential Future Purchase PQQ Pre-Qualification Questionnaire PT Project Team RACI£ Responsibility, Accountability, Consulted, Informed, Financial RAF Royal Air Force RATD Recce Armoured Tactics Division RDEL Resource Expenditure RSA Royal School of Artillery SCHINF School of Infantry SPGR Specialist Personal GPS Receiver SRD System Requirement Document SSARF Surveillance System And Range Finder SSE Support Solution Envelope STA Surveillance and Target Acquisition STLS Surveillance and Target Locating System SWS Support Weapons School TAP Tender Assessment Panel TLE Target Locator Equipment Page 25 8 TLF Through Life Finance TLM Through Life Management TLMP Through Life Management Plan TNA Training Needs Analysis UOR Urgent Operational Requirement URD User Requirement Document WLC Whole Life Cost List of Annexes A. Key User Requirements B. DSS PT Organisation C. TLE stakeholder information list D. TLE project RACI£ matrix E. TLE project plan on a page F. TLE project key risk register G. Through Life Finances H. Project Master Data and Assumptions List I. DSS PT signoff diagram J. TLE project Success Criteria Matrix Page 26 ANNEX A TO TLE TLMP DATED OCT 09 Key User Requirements Object Identifier SR Ref Object Text Threshold MOE Objective MOE Priority Justification Page 27 Status Validation Criteria Validation Category UR Owner Remarks Page 28 Page 29 Page 30 Page 31 ANNEX B TO TLE TLMP DATED OCT 09 DSS Project Team Organisation Chart Page 32 ANNEX C TO TLE TLMP DATED OCT 09 Stakeholder List CIWG CHAIR Appt (E-Mail) Name Maj Mike Baxter Mil No. 94381 2360 94381 2675 BT No. 01985 222360 01985 222392 Mob No. 07747 791211 07827 928331 HQ DInf - Cap Dinf-Cap-AD Col Mike Thornton CIWG Sec EC SPONSOR Dinf-Cap-PlansISTAR-SO2 Cap GM EQUIPMENT EC GM-SO2 DCC Maj Connar O'Hara 96218 0604 02072 180604 07884 111263 93523 7177 93523 7122 94331 2570 94381 2113 94381 8759 01179 137177 01179 137122 DSS PT DES DSS-STA-Proj1 Mr Trevor Lawrence DSS PT DES DSS-STA-ReqMgr Major Justin Prowse HQ LF - Eqpt LF-Eqpt-CE DCC SO2 Maj Lewis Hartman ITDU DInf-ITDU-SW-SO2 Maj Tim Hutchison ITDU DINF-ITDU-STA-SO2 Maj Rob Yuill TRAINING Page 33 01985 222113 INFORMATION DOCTRINE AND CONCEPTS ORGANISATION INFRASTRUCTURE LOGISTICS AND SUSTAINABILITY USER / OPS Page 34 SAFETY COMMERCIAL FINANCE Page 35 ANNEX D TO TLE TLMP DATED OCT 09 Stakeholder Responsibility Matrix D Inf / DRA / DRAC (User) HQ Land RSA/SCHINF/Etc (End User) CI(A) ?? (Prime Contractor) Information Organisation I C I C I£ I£ R R I I I I RA RA R C R C AR R I C - Deals with the overarching doctrine issues. - Representatives of relevant User communities A C AR£ A I A C R C C C C C C C C - Accountable for interoperability of the TLE - Manufacturer - CSA contract - Produces various R£ C I C I R R I I I Page 36 Logistics A£ Doctrine Concept C£ Responsibility & Role - Runs Business Case - EP Funding - Sanctions changes to cost, performance and time - Provides equipment support - Project Management - Provides User comments and representation Personnel Equipment DSS PT Training Stakeholder CAP GM (Sponsor) Infrastructure & DLOD (Responsible, Accountable, Consult, Inform, £money) C1 I R R Scrutineers ITDU documentation relating to equipment e.g. Safety Plan; training plan etc… - SME’s - Provides technical assistance - Responsible for technical trials - Ensure that all documents produced are fully compliant within its area. - User trials authority - Represents the User in terms of design changes etc…. I C I I I I I C I I I I I I I I C C I I I I I C Page 37 ANNEX E TO TLE TLMP DATED OCT 09 Plan on a page Page 38 ANNEX F TO TLE TLMP DATED OCT 09 Key Risk Register Impact Risk Prob Proposed Mitigation P C T Mitigation Success/Progress Status (R/A/G) G G G G Page 39 G Page 40 ANNEX G TO TLE TLMP DATED OCT 09 Through Life Finances Totals Assessment Assume 5 contenders Assume 2 samples of each Assume XX costs of Assume User environmental trial at cost of Manufacturing Equipment costs Safety Case ILS Assume Repair Pool @ Assume WMR @ Assume attrition @ 2/year In Service 5 years support @ 5% of procurement cost per year Last 5 yrs to be noted Disposal Disposal say 5 2008-2009 2009-2010 2010-2011 11-12 12-13 5 4.00% 2.00% 2 £ Page 41 13-14 14-15 15-16 16-20 1% Grand Costs Page 42 ANNEX H TO TLE TLMP DATED OCT 09 Ser No Master Data and Assumptions List (MDAL) Entry Date Description Authority Last Review Reviewed Date Page 43 Owner Value Comments Page 44 Page 45 Page 46 Page 47 Page 48 ANNEX I TO TLE TLMP DATED OCT 09 TLMP Document Control Process Page 49 ANNEX J TO TLE TLMP DATED OCT 09 Success Criteria and Objectives Target Locator Equipment (TLE) CADMID Cycle Phases Assessment Manufacture InDisposal Service DLOD Training Equipment Personnel Information Concepts and Doctrine Organisation Infrastructure Logistics Page 50
© Copyright 2026 Paperzz