GNA

3.2.2010 / Nygård Magnus
TRAFIKVERKET
GNA
- Nya kontraktstyper och samarbetsformer
- New contract models and increased
cooperation
Magnus Nygård
Trafikverket, Vägavdelningen
Finland
(Finnish Transport Agency)
[email protected]
3.2.2010 / Nygård Magnus
GNA reports from earlier work (2008)
TRAFIKVERKET
Entreprise- og samarbeidsformer
- GNA Rapport Utveckling av entreprenadformer och alternative
samarbetsformer (pdf)
- Summary Report Developing of Project Delivery (Contracting)
Methods and Modes of Co-operation-Closer Co-operation (doc)
- Ad hoc rapport anskaffelser (pdf)
- Project alliance (final report)
GNA
2
3.2.2010 / Nygård Magnus
TRAFIKVERKET
Discussion on possible areas for cooperation (2008):
• Meetings 1... 2 / year, to follow-up the procurement issues in practice.
• Client's issues and client organisation regarding to procurement.
• Follow-up would be interesting within a couple of years: what has
changed? Have the recommendations come into practice?
• Competence - how to ensure the competence on market so that the new
procurement methods can be utilized and that they will work well. Quite a
lot of procurement methods have been done, but the competence of the
personnel have not been developed to the needs in new methods.
Education must be real education, not informal discussion and seminars together with clients, consultants and contractors.
• Systematical benchmarking should be more carefully described. Bench
marking should normally be used on well prepared, and well defined issues instead of a very wide scope.
• Proposal for continuation of the work needs to be done.
GNA
3
3.2.2010 / Nygård Magnus
Market changed dramatically
TRAFIKVERKET
• spring 2008 still a lot of infrastructure and housebuilding projects
ongoing
• problems with prices in competitive bidding processes
• similar problems in Nordic countries
• autumn 2008 the finance crisis started
• investments stopped on private sector
• more bids coming in in bidding processes
• price decreased
• future of Public Private Partnership -projects?
• price of "private money"?
• lessons learned?
• the change occurred quickly
• more Design-Bid-Build instead of Design-Build in high economic activity
• revival package; some new projects, mostly small projects - larger ones take time to
start
• some cooperation done within this area between Nordic countries
• GD Roads working groups: within in price estimates, market situation
GNA
4
3.2.2010 / Nygård Magnus
Development projects with contract types and
increased cooperation
TRAFIKVERKET
• no systematical information exchange has been done during 20082009
•
• Finland and Sweden starting with new organisations; road + rail in
same organisation
• effects of this in procurement?
• Contracts types
• cooperation within investement projects
• PPP
• Increased cooperation (possible issues)
• possibility for in depth study, or,
• describing a common model for cooperation, or
• defining the "cornerstones" of cooperation, and describing good ways to use them
GNA
5
3.2.2010 / Nygård Magnus
Finnish development projects
TRAFIKVERKET
• Alliance contracting: no pilot project yet, still aiming towards pilot
study
• Ideas on Lean construction; how to use it within road building
•both for client and contractor
• PPP projects starting: new road and railroad investment projects
• Innovative procurement methods - a study possibly starting
• Development of service agreements, European PBSA project, phase 2
starting
• systematised cooperation with branch within maintenance (lead by
Association of infrastructure contractors, consultants and clients)
• Partnering: some pilots on the way
• aiming to start new pilots, for example on: routine maintenance, periodic maintenance
investement projects,
• pilots going on within periodic maintenance
GNA
6
3.2.2010 / Nygård Magnus
TRAFIKVERKET
Chairman/leader
Organization
Network
Responsible strategic network
Magnus Nygård
Trafikverket, FI
Contract types
Karin Brännström
Vägverket, SE
Co-operation
models
Jukka Karjalainen
Lars Jacobsson/Stefan Engdahl
Magnus Nygård
Trafikverket
Finland
[email protected]
Claus Nødgaard
Vejdirektoratet
Danmark
[email protected]
Jan Eirik Henning
Statens vegvesen
Norge
[email protected]
Frode Rosenkilde
Jernbaneverket
Norge
[email protected]
Camilla Ahston
Banverket
Sverige
[email protected]
Karin Brännström
Vägverket
Sverige
[email protected]
Kristina GöranssonRudberg
Vägverket
Sverige
[email protected]
Sara Sjöberg
Vägverket
Sverige
[email protected]
Participants
GNA
7
3.2.2010 / Nygård Magnus
Starting the work year 2010
TRAFIKVERKET
• first meeting March-April
• common objectives for work
• developing a work plan / agenda for group
• information exchange included
• describing best practices
• follow-up of recommendations from earlier phase
• client's organisation within procurement
• new ideas?
GNA