PROJECT TEAM MEETING September 8, 2005 – 12:00 Noon CBJ Assembly Chambers MINUTES (UNAPPROVED) VOTING MEMBERS PRESENT Mary Becker, School Board Member Jeff Bush, CBJ Assembly Member Bob Van Slyke, School Board Member Bill Peters, School Board Member EX OFFICIO MEMBERS PRESENT Peggy Cowan, Facilitator/JSD Superintendent Deb Morse, JSD Facilities Planning Coordinator David Means, JSD Business Manager GUESTS Sarah Lewis, CBJ Engineering Bob Millard, CBJ Engineering Gary Gillette, CBJ Engineering Paul Voelckers, MRV Architects Mike Notar, Juneau Building Trades Council CALL TO ORDER Superintendent Cowan called the meeting to order at 12:07 PM in the CBJ Assembly Chambers. APPROVAL OF AGENDA The agenda was approved as presented. There were no objections. APPROVAL OF MINUTES Jeff Bush moved and Mary Becker seconded to approve the minutes of the June 9, 2005 meeting as presented. Motion passed with unanimous consent, there were no objections. INFORMATION ITEM: DISCUSSION ON NEW HIGH SCHOOL – PHASE I SITE UPDATE Bob Millard reported that the start up period and first three months of the site work have not gone smoothly. Clearing and excavation of the building pad and staging areas, as well as the ordering of equipment and materials, have proceeded too slowly; jeopardizing the completion schedule of March 1, 2006. (Motion Passed) The contractor had various reasons for why they were behind on the project such as; equipment failure, community work force issues, and material problems at Stablers Point. To date, these issued have all been resolved. There has also been a change in the contractor’s on-site management, causing concern for their ability to complete the work within the time allowed. The contractor has reiterated his commitment to the project and to intensify his efforts to a level necessary to get the work done. The contractor has submitted a revised construction schedule demonstrating that the work will be done on time. (Available Upon Request) Project Team Minutes September 8, 2005 Page 2 INFORMATION ITEM: CONTINUED DISCUSSION ON NEW HIGH SCHOOL – PHASE I SITE UPDATE A potential Additive Alternate for this contract still remains: Excavation and site preparation for a future synthetic field. It is the recommendation of the design engineer and CBJ Engineering that this alternate be awarded on the condition that it doesn’t jeopardize the building phase construction budget. To allow time for a clearer view of the building construction estimate, the site bid documents require that the successful bidder guarantee the Additive Alternate price until December, 2005. A decision may need to be made about this Additive Alternate item shortly after the Phase Two Design Development Estimate is submitted in October. Discussion followed. The Team expressed concerns about the impact on the Additive Alternate if the Site Work Phase I was not completed by March 1st. Mr. Mallard stated there would be no impact, as the site work has been broken into two phases and the contractor has until July 15 to complete the second phase. INFORMATION ITEM: DISCUSSION ON NEW HIGH SCHOOL – PHASE II PROJECT UPDATE Sarah Lewis reported that the design team is nearing completion of the Design Development (DD) Phase, with a due date for document review on September 14, 2005. Schematic Phase plans, approved by the Project Team in May, have continued to develop. The completed DD estimate and document review are anticipated for October 5 and will be brought before the Project Team at the October 13, 2005 meeting. Paul Voelckers distributed design development drawings showing details of the site plan, the overall first and second floor plans, and an enlarged classroom wing. As previously reported, the Schematic Design Estimate for Phase II came in $2.7 million higher than the budgeted amount of $33,244,000. To cover this anticipated shortfall, CBJ staff identified $1.4 million in bond interest earnings, $700,00 excess funds within the Floyd Dryden renovation, and $600,000 in miscellaneous school project accounts. It is anticipated that this deficit will increase significantly when the DD Estimate is submitted, due to the current rising costs of world market materials. Ms. Lewis reported that the five artists selected to design artwork for the building have been working together, and with the design team. The collaboration between artists and architects is bringing out the best of both groups (Available upon request) Project Team Minutes September 8, 2005 Page 3 INFORMATION ITEM: CONTINUED DISCUSSION ON NEW HIGH SCHOOL – PHASE II PROJECT UPDATE Upcoming artwork design milestones are: final artwork proposals due from the artists on October 24; Art Selection Panel meets to approve proposals the week of November 1; recommended proposals brought before the Project Team November 10, 2005. Due to the recent significant rise in energy costs, this past June the Project Team approved a review of the energy conservation measures that did not prove cost –effective for pay back at the previous analysis. A draft re-analysis of these conservation measures has been completed. The following three additional measures that have been shown, under present and future conditions, to have a payback period of 25 years or less: Upgraded window glazing – This upgrade is a substantial increase in energy efficiency, but adds about $9/sq.ft. to the glazing costs for an increase of approximately $110,000. Added slab insulation – An addition of 1” rigid insulation under the entire building will offer further benefits of protecting the under-floor vapor barrier from the concrete and will warm up the slab, protecting it against interior condensation. This will cost an additional $1/sq.ft, for a total of $110,000. Increase rigid insulation at exterior walls – The new analysis shows it would be cost-effective to increase the 1” foil-faced, polyisocyanurate insulation on the interior face of all exterior wall studs to 1-1/2”. The cost increase is estimated at $35,000. The total cost increase for the three upgrades is approximately $255,000, an amount which will be offset by energy savings over the next 25 years. Following discussion, Deb Morse requested a breakdown on each upgrade as to what their individual savings and payback times would be. Mr. Voelckers stated that this information will be available for the September 20 Facilities Meeting. Ms. Morse reported that several high school staff workshops will be held September to review the Design Development plans for each of the programmed areas. The architects will present the plans to high school staff members and respond to staff comments and proposed plan refinements. This series of workshops will be the last opportunity for high school staff to review and propose changes to the design. Project Team Minutes September 8, 2005 Page 4 INFORMATION ITEM: CONTINUED DISCUSSION ON NEW HIGH SCHOOL – PHASE II PROJECT UPDATE In addition to overall building design comments, staff will be asked at the workshops to make a decision on the small group rooms proposed in the design. There will be three options to choose from: 1) retain the rooms as planned; 2) reduce the number of small group rooms currently planned; 3) remove the small group rooms from the plan entirely. Mary Becker requested that the staff be informed on what the difference in classroom square footage would be with our without the small group rooms. Ms. Morse stated that the square footage information would be included and the collected feedback from staff will be reported at the October Project Team Meeting. INFORMATION ITEM: DISCUSSION ON JDHS RENOVATION – PHASE II PROJECT UPDATE – FIELD/UPPER LOT Phase II renovation work primarily involves site improvements and was broken up into several stages to accommodate changing weather conditions. Stage one included reconstruction of the main entry parking lot, construction of a new parking lot adjacent to the proposed playfield, and paving the service entry drive at the northwest end of the building. Stage two involved preparation for the new playfield and installation of lighting fixtures. Gary Gillette reported that some of the stage two work was done during stage one, as it coincided with the work and equipment the contractor had on site. This work included retaining walls at the play field, new concrete steps at the northwest corner of the play field, and a series of steel bollards at the northeast corner of the building. The recent rainy weather has halted work on the final grading of the playfield. The situation will be analyzed and a determination made whether work should proceed or be halted until Spring. In either case the playfield turf, stage three, would not be installed until Spring. INFORMATION ITEM: DISCUSSION ON JDHS RENOVATION – 1% FOR ART Mr. Gillette reported that the 1% for Art Committee has made a selection from the first round of art proposals; the piece has been approved by the Assembly, will cost $100,000, and is scheduled to be installed in the Atrium during the Summer 2006. The panel will reconvene in the next couple of weeks to make a decision on the remaining art budget of $60,000. Project Team Minutes September 8, 2005 Page 5 INFORMATION ITEM: DISCUSSION ON JDHS RENOVATION – PHASE III SUMMER 2006 – SCOPE AND TIMELINE Phase III renovation work includes installation of the new synthetic turf, landscaping of selective areas, and a number of building related items to be completed. Building items will include the following: Upgrading for both locker rooms and the corridor between the main gym and locker rooms. An entry door from the Music wing into the auxiliary gym ADA upgrades, which include a cane detection warning and automatic doors in key locations. A new student health center on the 1st floor Underground oil storage tank in the north parking lot will be replaced. The design documents are nearly completed for this work and it is planned to be bid in November. Ms. Morse reported that also included are whiteboards for each classroom, new exterior signage and an electronic reader board, additional desks and tables, the greenhouse will be looked at for leakage repairs, and a classroom realigned for a Teen Health Center. OTHER ITEMS DISCUSSED: Mary Becker asked about the parking situation for the downtown campuses. Staff has been commenting on the inadequate parking spaces available. Discussion followed. Superintendent Cowan stated that the District is aware of the situation and is working to resolve it. NEXT SCHEDULED MEETING(S) NEXT MEETING AGENDA ITEMS New HS – Design Development Documents New HS – Budget Update (Action Item) ADJOURNMENT There being no further business, Superintendent Cowan adjourned the meeting at 1:00 PM Thursday October 13, 2005; 12 Noon in the Juneau Fire Hall Conference Room. (Action item moved to 10/27/05 meeting)
© Copyright 2026 Paperzz