Agenda Item No.5a Materials Resource Management Contract (MRMC) Briefing Note for SESSC March 2010 Background Members will know that it is proposed to let a long-term contract to manage household waste that has not been recycled under the existing Recycling & Wastes Handling Contract (otherwise referred to as 'Reclaim'). The proposed new arrangements, referred to as the Materials Resource Management Contract (MRMC), will place a great emphasis on reducing landfill requirements. This Committee was consulted several times leading up to the procurement and a Member Task Force oversaw the process. Members’ approval was given in September 2008 to select Biffa Waste Services Limited (BWSL) to deliver the contract, which involved the building of a Mechanical Biological Treatment (MBT) plant to convert “black bag” waste to a Refuse Derived Fuel (RDF). Investigations are being carried out to determine whether there is a market for the RDF. If a suitable market cannot be found, an Advanced Thermal Treatment (ATT) plant would be constructed which would provide a source of power. The County Council determined that the project would be delivered in 2 distinct phases. Through the negotiations, the preferred funding route has been clarified. For the first phase, the project would be funded through prudential borrowing and a 10% equity stake from Biffa rather than project finance. Sites for both developments were identified near Horsham and it was agreed that, to give the County Council an additional level of security, the sites would be purchased by the County Council. Current Status The Project Team, assisted by legal, financial and technical advisors with experience in the field, have conducted many months of intensive negotiation with Biffa. With a 25 year contract, it is essential that the County Council does not expose itself to inappropriate risks or expenditure, and discussions to reach a point at which the County Council can be comfortable with the contract and payment provisions have taken longer than was anticipated. Some of the issues causing the delay are extremely commercially sensitive. The potential impact of those and the means of resolution was discussed in Part II by Policy & Resources Committee on 4 March 2010 with SESSC Members invited to attend. The negotiations have proceeded well since that Policy & Resources meeting and are now in their final stages with only a very small number of issues yet to be resolved. Although the County Council will enter into just one Project Agreement with a Special Purpose Vehicle (SPV) (a limited company called Biffa West Sussex Ltd created specifically to deliver the contract), there are a significant number of other contracts underpinning the agreement, the key one being with the contractor who will build the MBT, MW High Tech Projects UK Ltd (formerly MW Zander). With the delays in the progress to contract signature, it has been agreed that the County Council will enter into a 3 month Preliminary Works Agreement (PWA) with MW. From the contractor’s viewpoint this allows preparatory work to start and enables its suppliers to prepare for and be ready to deliver their products and services on time when the full contract is let. The County Council has secured a number of conditions to this PWA, the most important being that the price and timetable that has been agreed will be fully protected as long as Materials Resource Management Contract (MRMC) Briefing Note for SESSC March 2010 negotiations are complete and commercial and financial agreements are formalised (Financial Close) is achieved by 20th May which has been agreed by both sides as being achievable. Way ahead The Project Team will continue to finalise all negotiations, calling on the Wastes Contract Board (a body chaired by the Executive Director for Communities whose responsibilities include the overall management of the procurement) when appropriate for approvals. Design work under the PWA will commence on 1st April at a cost of £900,000 per month. The Council retains the right to terminate the PWA without penalty at any time and has the added comfort of retaining the intellectual property rights over the designs produced at the time of termination, which can then be used by the Council to develop any future facility. Phase 2 After the Project Agreement has been signed and Financial Close reached on or before 20th May, the Council will need to consider its approach to the second phase of work. There are several stages to this second phase, including a funding competition to determine which option provides the best value for money for the Council and a review to determine whether there is a market for the output of the MBT. An initial market review has already been carried out by consultants and their report will be finalised shortly. Target dates have been set for this Phase and both the Council and the SPV are contracted to meet those dates. The Council will need to determine whether it wishes to commission the ATT facility by December 2010 and, if it does, is currently anticipated that Financial Close for Phase 2 will be in the Autumn of 2011. Summary A protracted and challenging procurement is reaching its conclusion with the anticipated signing of a 25 year contract with an SPV to build and operate a MBT on a site at Horsham. Final negotiations are well advanced and it is anticipated that the contract will be signed on or before 20th May 2010. Consideration of Phase 2 will need to conclude by December. It is still anticipated that the price will prove affordable within the limits of the existing provision in the Waste budget and the commitments in the County Council’s Finance Strategy. Contact Officer: Andy Forsyth x 56614 MRM – Site Location Map Crown Copyright. All rights reserved WSSCC Licence 100023447 (2008 1
© Copyright 2026 Paperzz