NWPPA Annual Conference Allen Burns, President

2017 CG MOD 33 updates
CG Planning Meeting
Feb 9, 2017
1
In This Presentation
 Review of MOD 33 meeting in Jan 10
 Meeting Action Items
2
Jan 2017 Meeting Review
 Discussion of the MOD 33 standards and technical
issues, prepared to develop a CG process document.
 Review Existing Process from CAISO
 Discussion for future training and work group activities
3
Action Item: Process Document
 Outline for MOD 33 process document will be sent out at
the end of February
 The final MOD 33 process document around 6/1/2017
 Chelan PUD offer to share their MOD 33 process document
to members when finalized.
 Confirm with NERC of using 6/30/2019 as the deadline
Power Flow and Dynamic validation evidence. (confirmed)
4
Action Item: Event Selection
 CG MOD 33 will focus on major system events and main
grid validation.

Members can perform their own validation of local events on local
system
 A MOD 33 work group will be formed for selected events



Utilities will report in CG planning meeting for any significant events
that can be used for MOD 33 validation.
CG will call for participation after an event has been selected for MOD 33
purpose by at least one member.
Once an event has been selected, a workgroup will be formed to hold
regular meetings to work on the MOD 33 validation for this event.
 It should be no less than 2 months (planning meeting
intervals), after an event being submitted to form a work
group
5
Action Item: Data Acquisition
 Members provide CG an official authorizations for using
measurement data (e.g. from Peak RC).
6
Action Item: Base case preparation
 MOD 33 will be primarily performed for event scenario.
Power Flow and Dynamic validation can be performed
using the same event together.
 MOD 33 base cases can be derived from two sources: Peak
RC, or self developed by CG and members.
 On top of the base cases developed for MOD 33 events, CG
will facilitate to develop certain peak hour cases (heavy
summer or heavy winter) for power flow validation purpose
(no event necessary).
7
Action Item: Acceptable Discrepancy
 At this point, members cannot determine the appropriate
quantitative metrics for acceptable discrepancy. It is
expected to use some general ranges with exception
allowed. The range is expected to improve along the
process.
 CG will obtain an existing recent validation case and
measurement data from BPA, do some comparison and get
an idea of the discrepancy. The discrepancy will be sent to
members for review.
8
Action Item: Unacceptable Discrepancy
 In CG process document, a general guideline can be used
for resolution of the unacceptable discrepancies.
 The unsolved discrepancy should also address the
discrepancy come from the software aspects.
 Peak RC should also be involved for certain type of
discrepancy observed.
9
Action Item: Software Platform
 PowerWorld will be the main tool
10
Action Item: Training
 CG will check with WECC for a training of preparing base
cases for MOD 33 purpose. If available, CG will host a
workshop.
 On the workshop, BPA will also give a training on local data
validation and tutorial on base case tools.
11
Question:
Bo Gong, [email protected]
12