Christchurch Convention Centre Timeline June 2016 2016 Q3 2017 Q4 Q1 2018 Q2 Q3 Q4 Q1 2019 Q2 Q3 Q4 Enabling Works (Utility services diversion) Design Review & Development Early Site Works Procurement Early Site Works (Contamination remediation) Main Contractor Procurement Early Site Works (Ground Works) Foundation Excavation Main Construction Q1 Q2 Q3 Q4