GREY POWER SUBMISSION On The ELECTRICITY SECURITY OF SUPPLY POLICY REVIEW Consultation Paper For the Electricity Commission Dated March 2007 Greypower Federation Energy Committee Contact: John Noble, e-mail: [email protected] April 2007 SUMMARY: SALIENT POINTS 1. We agree that the economically efficient level of unserved energy should be calculated and from that the required energy margin established. 2. We consider that there are factors that have not been taken into account in Castalia’s calculations. These factors are noted in section 4 3. We consider that the concept of ring fenced reserve energy should be discarded, and that the energy margin should be provided from within the market. The means of doing this is considered in section 3 4. We consider that the concept of an energy margin should be complemented with a means of predicting shortages (including high spot prices in the run up to shortages) in order to allow the early dispatch of thermal plant (while managing the risk of fuel wastage). This would result in a reduced energy margin. A suggested method is described in section 2. 1: GENERAL: We congratulate Castalia on producing a reasoned and well analysed consultation paper. However, we believe that the prescription for the review in the Government Policy Statement (paragraphs 35-67) has perhaps inhibited Castalia from taking a more fundamental view of the present arrangements. The paper sets out to examine the status quo system, ask if there is a market failure, and if so, decide what’s the least cost “intervention”. It doesn’t appear to acknowledge that the status quo is not a market system at all, but is an intervention in its own right, Asking “where is the market failure” seems a little strange… We prefer an approach that asks what’s the most sensible way in a market system to ensure sufficient energy is available in a dry year. Our suggestion is not very different from the ECNZ system, but that system can be much improved through the availability today of much better information and modelling systems. We also note the government’s ambition to reduce the proportion of thermal generation, and eventually phase it out completely. At present, security of supply in dry years is provided by thermal backup to NZ’s hydro generation. How security of supply can be ensured in the future, in a system with a high proportion of renewables (some, like wind, with intermittent and highly variable outputs) and a low or negligible thermal proportion, is extremely difficult to assess. This is, of course, outside the terms of reference for the present review, but needs to be borne in mind in forming policy. 1.1: Systematic Market Failure The Cause of the Market Failure PA Management Consultants has pointed out in a report to the Electricity Commission’s Security Advisory Group that historically there has been more than enough thermal capacity, had it been run to its operational limit, to avoid shortages in dry years. The problem is that in the early stages of a prospective dry year there is no way of knowing how dry it will become or when inflows will pick up; and therefore of knowing whether running thermal generation at a very early stage is a necessary precaution or a waste of fuel. The prudent approach involves an energy margin, the cost of which can be balanced against the potential wastage of fuel. The need to define a class of “reserve energy” which is subsidised by a levy and is ring fenced in ways that limit its use, is basically an admission that the “ordinary” market is expected to fail to supply adequate electricity in dry years. We thus disagree with the Castalia comment (p, 12) “If the market failure turns out to be sustained and systematic— unlikely as it is [emphasis added]—this will become obvious due to frequency and scale of intervention needed…” We consider the failure to be systematic, noting that it results from: a) A shortage of capacity, and/or b) The imprudent deployment of capacity. With regard to a), we contend that the market is set up in such a way that there is a disincentive for adding new capacity, in that the prospect of electricity shortages raises spot prices towards rationing levels (ie, above the cost of the most expensive generation in use). This results in windfall profits derived from consumers with spot price exposure, and provides an opportunity for generators and retailers to raise prices to other consumers. These increased prices are observed to stay high after the shortage is over. The following chart (from data supplied by NZ Tariff and Fuel Consultants and from the centralised data set and data from Comitfree) demonstrates this for large retail contracts. In August 2001 the price increased from about 3.3 to 5.2c/kWh because of the 2001 shortage, and did not fall back significantly. In June 2003 it rose again to about 7c (2003 shortage), and did not fall back. From October 2005 it ramped up and steadied at about 8c/kWh. (2005-6 scare). NZTF contracts compared to spot price haywards, averaged monthy and yearly 25 2006 1997 5 Oct-06 Oct-05 Apr-06 Oct-04 Apr-05 Oct-03 Apr-04 Oct-02 Apr-03 Oct-01 Apr-02 Oct-00 Apr-01 -15 Oct-99 0 Apr-00 -10 Oct-98 5 Apr-99 -5 Oct-97 10 Apr-98 0 Apr-97 15 Oct-96 c/kWh, monthly 20 10 c/kWh, yearly NZTF index spot prices NZTFyearly spot price yearly Thus shortages are profitable for generators, especially in comparison with adding new capacity which would both increase their capital investment and tend to reduce prices. However, the threat of regulation causes the generators to limit the severity of the shortages; they tread a fine line between maximising their profits, and suffering regulation. Put another way, it is the threat of regulation more than the balance between demand and supply that has driven market decisions during and following low-hydro episodes. This is, by definition, a market failure. Recent Shortages Similarly, with regard to b), the early deployment of thermal capacity to conserve hydro storage in prospective shortages tends to reduce prices and also requires increased fuel stockpiles. A partial cause of the 2001 shortage was the late entry of thermal generation. Fortunately, sufficient natural gas was available to run the thermal generation, when it did enter the market, at a high load factor. In 2003 much less natural gas was available, and it was low coal (and oil, for New Plymouth) stockpiles that contributed to the severity of the shortage. In 2005-6 the thermal generation did start early. The threat of regulation (and, as we understand it, direct political intervention with the generators) ensured that coal had been stockpiled and available for generation. Yet spot prices rose far above the marginal cost of coal generation – leading to several months of high spot prices. Even though the spot price fell in May, well before winter began, the spot price averaged over the calendar year 2006 was the highest ever. 1.2: Disadvantages of a Reserve Energy Approach Thus we consider the market’s unwillingness to provide adequate supply during dry years is a product of the way the market was designed, that is, a systematic failure. The solution to this is to overcome this design flaw, not to provide additional but circumscribed capacity external to the market, which inevitably causes an economic distortion. By Castalia’s analysis the distortion on investment in generating capacity is small. We argue that there are other distortions. Reserve Energy and the Ring Fence We contend that the selection of a particular type of “reserve energy” (low capital high running cost), the ring fence around it, and the insistence on not deploying it until the last moment for fear of distorting the operation of the “ordinary” market inhibits more flexible and economically efficient solutions. In fact, the requirement for (subsidised) low capital cost high running cost plant to ensure security of supply is a product of the ring fenced reserve energy policy, because the ring fencing and prohibition on it not operating until the last moment means that it cannot earn an adequate return. This policy also means that a relatively high MW reserve capacity is required, because it has to compensate for the hydro shortfall over a short period of time. For example, Castalia has calculated that a 15% energy marginabout 6000GWh- will result in the economically efficient level of unserved energy, with a security standard of 1:20. The 1:20 year hydro shortfall is about 3000GWh. Their assumption is that the compensation will have to take place over a period of three months, and therefore, allowing for the economic level of unserved energy, a yearly margin of 6000GWh is required. 2: A PREDICTIVE APPROACH TO SECURITY Early Dispatch of Thermal Generation We agree with Castalia’s attempt to establish the economically efficient level of supply security (chapter 4) although we have some reservations about the outcome. We consider that this needs to be complemented by developing a means to dispatch thermal generation in a prudent manner in the early stages of a prospective shortage. As we noted above, this happened in the 2005-06 hydro scare, because of the threat of regulation and, as we understand it, direct intervention with the generators by the government. While it worked that time, we do not consider this to be a satisfactory long term solution. The Value of Hydro Storage Thermal generation needs to be dispatched to conserve hydro storage when the probable cost of an impending shortage equals the probable cost of the fuel (and possibly additional generating capacity) required to avoid it. A possible method of evaluating these factors is through the calculation of the opportunity value of the hydro storage. New Zealand at the moment needs both hydro and thermal generation to meet its annual consumption; the thermal generation is needed both to supply a proportion of the energy, and to help meet the peak demand. In this situation any usage or shortfall of hydro storage potentially commits compensating thermal generation in the future. The water can thus be valued at the cost of the thermal generation that would be committed by such a shorfall. This, essentially, was the method used by NZE to give hydro a value that could be incorporated in the generation merit order. Calculation and Trigger Point Of course, the inflow and consumption probabilities have to be factored into this assessment. But, in general terms, the data is available to develop scenarios based on the economically efficient merit orders associated with the inflow and consumption probabilities at a particular time and storage level. From this, the probability of an impending shortage, its cost and the cost of avoiding it, can all be estimated- and thus, the prudent timing and quantity of thermal generation dispatch. These calculations could be triggered by hydro storage falling to a level, as an example, where the 10th percentile low inflow probability and the expected consumption produce a shortage before the end of September in a particular year. The objective of the calculation is to bring thermal generation on line to conserve hydro storage while managing the risk that the fuel will be wasted, with the aim of reducing the energy margin required. Note that in the NZE days, this was done by human judgement, not by a formal assessment of probabilities. 3: PRACTICAL IMPLEMENTATION Trigger Point and Critical Period As Castalia have noted, the energy margin is expected to remain above 15% until 2015. We argue that by the pre-emptive but prudent dispatch of thermal generation, this margin can be reduced. Castalia’s figure of a 15% energy margin is based on a three month critical period; if this could be doubled, the margin could be halved. Until 2015, then, there is no need to set a specific energy margin; by then there should be enough experience to estimate what the trigger point for the calculations should be, and over a critical period of what length the energy margin needs to be deployed. Energy Margin We agree with Castalia’s methodology for determining the energy margin in general (but see section 4 for our reservations regarding the calculations). The energy margin should be calculated, and the generators encouraged to maintain it. Castalia considers that if the margin is eroded to a level below that required, the Commission should contract reserve generation to compensate. We see no difficulty in estimating the energy margin for several years in the future (as Castalia have already done). If the margin falls below the required level, we suggest that the Commission should issue a Request for Proposals for additional generation to both existing generators and possible new entrants. This could take the form of additional capacity in an already planned conventional plant (geothermal, for example), embedded generation (running on biofuel?), fuel substitution, as was done by Southpower in 1991 and 1992, or any other available form of generation or conservation. Embedded capacity could help reduce transmission and distribution investment as well as contribute to the energy margin. The Commission should then decide on the most suitable proposal, and arrange for it to be implemented. This would include protecting it from gaming, for example by arranging for it to receive a pro rata share of existing hedges. We note that the Rules would have to be changed to make this possible. Trigger Point A trigger point for the predictive process will be estimated before 2015 (or when the energy margin is predicted to fall to the required level), based on past experience at that time. The trigger point may, for example, correspond to a particular storage level (analogous to the NZE rule of thumb that the lakes should be full by April each year) possibly in combination with an inflow probability as suggested above. The objective of the trigger point is to provide an early signal of a possible shortage. Predictive Process When the trigger point has been passed, scenarios based on the merit orders associated with various probabilities of inflow should be produced and updated. If or when some of the scenarios indicate a possible shortage (or even that hydro is moving up the merit order, indicating that spot prices are liable to increase to the point that production from the electricity intensive industries will be reduced) the probability weighted estimated cost of the unserved energy can be compared to the cost of fuel required to avoid the consumption restraint. This calculation should be made publicly available, to give thermal generators and demand-side participants the impetus to correct the situation. Energy Conservation Should be Part of the Strategy It is possible to assign a value to the electricity saved by various types of conservation campaign in terms of the cost of the non-supply. Castalia have calculated a cost which ramps up from the nominal residential electricity price of 18c/kWh at a rate of 20c/kWh for every percentage point of restraint. Thus conservation campaigns can also be inserted in the merit order. We consider this to be a sensible move, as it will both conserve storage and also reduce the extreme spot price volatility that occurs during the run up to a shortage. Demand-side alternatives include dual-fuel space or water heating systems, running on natural gas or LPG (the latter was used by Southpower), or firewood or pellets. Dairy farms generally use electric water heating, and their rapid expansion suggests an opportunity for dual-fuel systems able to switch in dry years. 4: CRITQUE OF ENERGY MARGIN CALCULATIONS While we agree with Castalia’s energy margin methodology in general, we have reservations about some details of the calculation (apart from assuming a three month critical period mentioned above). “Natural” Market Security Standard We note that the pre-emptive dispatch of thermal generation happens naturally within the market. The current limitation of contracting no more than 1200GWh of reserve energy is, as we understand it, based on the difference between the “natural” security standard afforded by the market (thought to be about 1:15) and the desired standard of 1:60. Castalia have calculated the energy margin required to produce an economic level of unserved energy in dry years. They have not allowed for the market’s “natural” security standard. Our aim is to extend the natural security standard by means of a predictive system for dispatching thermal generation. Double Counting Castalia’s advice seems to be that the energy margin should be calculated as the supply capability allowing for maintenance, average contingency outages, load factor effects and consumption uncertainties minus the expected consumption. We believe there is an element of double counting here, because it is unlikely that all the adverse effects will happen in the same year. We would suggest that each margin is calculated separately, and the required margin should be the root mean square of these. Reductions in Production Caused by High Spot Prices We would argue that the cost of shortages is not just the cost of residential unserved energy, but also the cost to the economy of reduced production caused by high spot prices in the run up to the shortage. The GDP loss caused by the 1992 shortage was estimated at $500M; in 2001, $200M; in 2003, $100M. But the rise in spot prices caused by shortage scares, as in 2005-6, also damages the economy in three ways: first by the direct loss of production by the electricity intensive industries, which seems to occur at spot prices well below $200/MWh (which might be called the cost of unserved industrial energy); second by the knock on effect on their suppliers; and third because of the effect of supply and cost uncertainties on businesses. These effects are included in the GDP losses quoted above. There are of course many more shortage scares than actual shortages, and the scares tend to last longer. However, it is very difficult to estimate their cost. Production cuts might cost about $150/MWh on average. Assuming the reduction in consumption of the major industries to be, say, 17GWh per week in the pre-shortage period the reduction in GDP could be $2.5M/wk or more. These very preliminary assumptions suggest the costs could be about the same as for domestic consumers, but they occur much more frequently than conservation campaigns leading to domestic consumer consumption restraints. Lowest Capital Cost Generation Option We disagree that the “lowest capital cost generation option” of diesel fuelled open cycle gas turbine generators (Castalia, sect 4.3) is necessarily the correct one. It is, only if reserve energy is considered to be separate from the market. None of the large thermal plants run at their maximum annual outputs in hydrologically normal years. The least cost source of additional electricity is to increase their outputs (zero fixed cost, low variable cost). However, they will tend to run at full output during actual shortages, so their outputs can only be increased outside these periods. That is why a means of predicting impending shortages is required. We also point out that the use of diesel fuelled generation is not consistent with the government’s energy strategy, Marginal Cost of Increasing Security of Supply We believe that both the variable and fixed costs of diesel fuelled open cycle gas turbine generation have been underestimated in sect. 4.3. The variable cost should include both the fuel cost and the variable maintenance cost. We estimate the fuel cost at present oil prices to be around 25c/kWh and rising, with an additional 1c/kWh for the variable cost of maintenance. In sect. 4.3, Castalia have calculated the fixed cost of a diesel fuelled gas turbine generator running in the reserve energy mode as 4c/kWh. This is based on the plant running continuously during the critical three month period. However, if this happened at all, it would only happen once in 20 years, with perhaps some shorter periods of operation in between. Because of this, we would expect the fixed cost to be considerably higher. Calculation of Energy Margin .Having taken these factors into account, an economically efficient level of unserved energy can be calculated (including both domestic and industrial restraint) and from that, the appropriate energy margin. 5. CONCLUSION Today’s system for contracting for reserve energy aims for an extremely high “security” level. “Conservation campaigns” are planned to be needed when hydro flows are less than 1 year in 60. This was an arbitrary figure, chosen after the 1992 hydro shortage, and has never been contested by consumers’ willingness to pay the very high cost of maintaining that standard. Today spot prices have increased, in each of the three years of low hydro flows, for progressively longer periods. As a result, high-price years have seen average prices over the whole year, typically twice the average prices in medium or wet years. Contract prices have increased each time the spot prices rose, but have not fallen when spot prices fell. Domestic consumer prices have followed a similar trend, leading to an average increase of consumer prices in real terms of 5.5% per year from 2000 to 2005. (The trend is reported to have been similar, in 2006,) Domestic price rises are causing increasing fuel poverty, with more and more consumers unable to afford to heat their houses to healthy temperatures, Some consumers, who have alternative space heating options, could well be invited to contract for reserve energy as dry years approach, and some generators could also be contracted for dry year energy. If these true market solutions for the “dry year problem” were called on by the Commission, the recent high spot price events might be avoided, The key is to put objective information into the market that would guide the tendering to meet the energy margin. This would put this concept back into the market, and allow it to be provided by lower-cost means than the remote, diesel fired Whirinaki gas turbine or other “reserve” generation. This would reduce the cost of dry-year energy to the benefit of all consumers.
© Copyright 2026 Paperzz