LIU-SPS, 15 April 2015 Paul Cruikshank 1 In the beginning…. • First slide that Brennan gave me – everything decided ! LIU-SPS, 15 April 2015 Paul Cruikshank 2 Recall: • Starting point: • Extensive work already made by SPS-U and SPS-LIU teams • • • • J.Bauche, B.Goddard, V.Mertens, M.Taborelli, P. Costa-Pinto, P. Chiggiato …… Recent discussions with above, plus C.Bertone, P.Bestmann, J.Ferreira, J.PerezEspinos, Experience of 16 MB and 5 Quad aC coated chambers in SPS – handling, performance, ageing, etc. General assumptions for activity: • • • • • LS2 activity and 5 working days/week. 8 months aC duration ( 1m ramp-up + 6m cruise + 1m ramp down) Chamber is coated in the magnet Machine components returns to initial slot Consider arc and DS machine components only (for now): • • • aC coat all 744 dipoles = 6 dipoles/working day aC coat all 192 quads = 1.5 quads/day (new scope) aC coat all 192 SSS = 1.5 SSS/day (new scope) LIU-SPS, 15 April 2015 Paul Cruikshank 3 Scope today • aC coating – Dipole (74% SPS ) • • • Baseline update Variants aC coating – Quads & SSS (15 % SPS ) • additional aC scope - without/with impedance reduction Cells 84+12 Arc+DS % SPS 88.9 Chamber type X-section (mm) Form Units /cell Chamber (mm) Chamber /cell MBA 152 x 36.5 Rect 4 6660 26640 41.6 37.0 MBB 129 x 48.5 Rect 4 6640 26560 41.5 36.9 QF mag 152 x 38.3 Elipse 1 3346 3346 5.2 4.6 QD mag Dia 83 Round 1 3346 3346 5.2 4.6 152 x 36.5 Ellipse 1 2052 2052 3.2 2.8 1 2052 2052 3.2 2.8 63995 100.0 88.9 QF SSS QD SSS • • • Dia 83 Round % cell % SPS Doesn’t (yet) address aC for LSS components Doesn’t (yet) address other consolidation needs Doesn’t (yet) address impact on other LS2 activities LIU-SPS, 15 April 2015 Paul Cruikshank 4 Radiation considerations • Extensive SPS radiation campaign Feb 2013 for LS1: • • • MB range 0.1 - 100 uSv/hr @ 40 cm Quad & SSS range 1 - 1000 uSv/hr @ 40 cm Need to make detailed assessment for each MB, Quad, SSS to coat Dose ‘cost’ for each item to aC coat – list to compile • Public road limitations < 5 uSv/hr – otherwise ‘transport containment’ required • • Avoid road transport aC activity 1 hr, 1 MB aC activity 1 hr, 744 MB 1 uSv/hr @ 40 cm 1 uSv 744 uSv 10 mSv/hr @ 40 cm 10 uSv Sextant 1 • (worst) aC activity 1 hr, 192 Quad 1920 uSv Sextant 5 (best) LIU-SPS, 15 April 2015 Paul Cruikshank 5 Costs – the existing numbers • Baseline: (J.Bauche 2009/2010) • • • • Consider 744 MB in ECX/EXA5 6 dipoles/day in 124 days 3957 kCHF APT: LIU e-cloud study • • Considers 744 MB and studies 4.590 kCHF (2015 - 2020) LIU-SPS, 15 April 2015 Paul Cruikshank 6 aC typical sequence: Disconnect (vac + mech) Transport Clean + aC coat Transport Survey (x,y,z,tilt) Reconnect (vac + mech Survey (smoothing) aC factory options Transit Surface transport Surface activity Underground activity aC ex-situ factory BHA5 Other ? BA2 lift BA3 lift BA6 lift Adjacent quads can’t be simultaneously removed 192 SSS 192 Quad 744 MB aC ex-situ factory B867 via BA3 & road P1.8 via BA6 & road B?? via road Other ? BA4 crane BA5 crane Baseline Tunnel transport Transit aC in-situ factory LIU-SPS, 15 April 2015 aC ex-situ factory ECX/ECA5 TCC6 Other ? Paul Cruikshank 7 Underground to surface: • MB, Quad, SSS to surface: • • • • • • BA1 – nothing. BA2 – lift, requires mobile crane + crane driver for loading BA3 – lift, usual exit point, coactivity with cavity works BA4 – crane, requires opening ECX4 wall & extr.septum removal BA5 – crane, coactivity new dump, requires opening of ECX5 wall BA6 – lift, coactivity with P1 (LHC & ATLAS) ground logistics • • • Handling team at (each) surface location Lorry driver(s) if aC factory is elsewhere Handling team at (each) aC factory • • • BA3 exit gives access to Prevessin infrastructure BA6 exit gives access to P1.8 infrastructure BA2 exit would block 1 of the 2 CERN mobile cranes (plus road trans) • • Several exit points create flexibility (C.Bertone) Night shift will add 50% to manpower costs For cost estimate, consider 1 exit point MB, 1 exit point Quad & SSS Many constraints ! • • 65k ???k 100k 130k 65k 130k • LIU-SPS, 15 April 2015 Paul Cruikshank 8 Ex-situ v in-situ aC coating Ex-situ benefits: Working environment Radiation constraints Access Combined consolidations In-situ benefits: Transport & logistics needs Building space needs Disconnection needs Realignment needs To avoid too many combinations in cost estimate consider: All Dipoles ex-situ or in-situ aC All Quadrupoles + SSS ex-situ aC only All Quadrupoles + SSS ex-situ aC only, with impedance reduction LIU-SPS, 15 April 2015 Paul Cruikshank 9 Cost estimates and considerations: • TE/VSC • • • • • • • EN/SU – P.Bestmann • • • MB ex-situ, MB re-alignment MB in-situ, Quad & SSS re-alignment EN/HE – C.Bertone • • • • aC coating, MB ex-situ aC coating, MB in-situ Wet cleaning, MB ex-situ Plasma cleaning, MB ex-situ Plasma cleaning, MB in-situ Impedance reduction variants for Quad & SSS Underground to surface MB transport & logistics Quad & SSS transport & logistics TE/MSC & DG/SCR • From 2010 cost estimates LIU-SPS, 15 April 2015 Paul Cruikshank 10 Cost for aC options: • Preliminary totals to be checked by experts • Excludes on-going TE/VSC works to validate: • • • Long hollow cathode solutions eg 13 m Plasma cleaning as pre-treatment to aC coating Plasma cleaning with p.port shields not removed LIU-SPS, 15 April 2015 Paul Cruikshank 11 aC cost estimate details and variants LIU-SPS, 15 April 2015 Paul Cruikshank 12 aC coating – MB ex-situ (baseline) • 3 day aC cycle, 6 MB/day = 18 MB in work • • Coating in MB pairs = 9 coating stations (+1 reserve) • • • • 1 pumping group with gas inj, RGA, pc 2 cathode trains (6.6m) with 150 mm linear drive Total 10 stations 70 kCHF 2 x 30 kCHF 1300 kCHF aC coating manpower (8 months) • • • pumping, coating, cathode cooling 4 FSU (coating - 2 x 2 teams) 1 FSU (sample measurements) 312 kCHF 78 kCHF Surface of 360 m2 (15 x 24 m) • • • 10 Coating stations = 2 x MB length + footpath 2 transit stations Min spacing between MB = 1 metre LIU-SPS, 15 April 2015 Paul Cruikshank 13 aC coating, MB in-situ • 5 day aC cycle • • Insert cathode, pump, coat 1, coat 2, cathode cooling, demount • • Goal 6 MB/day or 30 MB/5 days MB string (4 x MB) together, so 7.5 strings/5 days Adjacent quads cannot be removed so working space is 2m • Coating MB strings = 8 coating stations • • • • 2 pumping group with gas inj, RGA, pc 2 cathode trains (13.2m) with 150 mm linear drive Total 8 stations aC coating manpower (8 months) • • • • 2 x 70 kCHF 2 x 50 kCHF 1920 kCHF 4 FSU (coating - 2 x 2 teams) 1 staff eng + 1 staff tech 1 FSU (sample measurements) 312 kCHF 78 kCHF Considerations • • No MB transport or alignment required. Requires removal of SSS and Quads • • • Remove all SSS Remove alternate quads – coat MB – reinstall quad – realign quad – remove adjacent quad. Implies plasma cleaning LIU-SPS, 15 April 2015 Paul Cruikshank 14 Wet cleaning – MB ex-situ (baseline) • 0.5 d wet cleaning cycle, 6 MB/day = 3 MB in work • • create a table (acetone, detergent, rinse, dry) 3 cleaning stations (+ reserve) • • • • • • • ~3 m3 demin rinsing water/MB Recirculating pumps, tanks, heaters, blowers Rinsing water tanks (30) Hand/foot contamination detector Dose rate monitors + balisette?? Total 4 stations 100 kCHF 10 kCHF 20 kCHF 40 kCHF 170 kCHF Cleaning manpower (8 months) • • 2 FSU (60 CHF/hr) 156 kCHF Surface of 120 m2 (6 x 20m) • • • • • 4 Cleaning stations = MB length + protection zone 4 transit stations Min spacing between MB = 1 metre Independent wet zone Considerations • • Remove/clean/reinstall RF shielding with wet cleaning Local system to cleaning, rinse, dry LIU-SPS, 15 April 2015 156 kCHF 30 kCHF Paul Cruikshank 15 Plasma cleaning – MB ex-situ • • Under vacuum cleaning O2 injection and cold plasma discharge to remove hyrocarbons • • • • + System built to remove aC coating + No pumping shield removal + No waste water + No contamination transfer • • 0.5 d plasma cleaning cycle, 6 MB/day = 3 MB in work Sequence – insert anode train, pump, plasma clean, extract train. • Plasma cleaning in MB pairs = 2 stations ( 1 reserve) • • • • - As aC pre-treatment, to validate. - With p.port shielding to validate - No dust removal 1 pumping group with gas inj, RGA, pc 2 anode trains (6.6m) Total 2 stations 70 kCHF 2 x 15 kCHF 200 kCHF Plasma cleaning manpower (8 months) • • 2 FSU (60 CHF/hr) 156 kCHF Surface of 60 m2 (15 x 4m) • • Plasma cleaning station = 2 x MB length + footpath Min spacing between MB = 1 metre LIU-SPS, 15 April 2015 Paul Cruikshank 16 Plasma cleaning – MB in-situ • Under vacuum cleaning – O2 injection and plasma discharge • Consider 1 day plasma cleaning cycle for 4 MB string • Goal 6 MB/day or 30 MB/week, so 7.5 cleaning cycles/week • Plasma cleaning MB strings = need 2 stations • • • • 2 x 70 kCHF 2 x 30 kCHF 400 kCHF Plasma cleaning manpower (8 months) • • 2 pumping groups with gas inj, RGA, pc 2 anode trains (13.2m) Total 2 stations 4 FSU (cleaning & tunnel logistics - 2 x 2 teams) 312 kCHF Considerations: • • • Requires removal of SSS and Quads (special sequence) Requires tunnel logistics Requires set-up (2 x SPS dipole) to validate in 2015 LIU-SPS, 15 April 2015 Paul Cruikshank 17 MB underground transport + aC logistics (baseline) • Underground transport to ECX5 • • • • 292 kCHF 2 FSU for cleaning & aC coating factory 50 m2 for transit handling (6 magnets) 130 kCHF Additional handling infrastructure: • • • • • • 585 kCHF Underground logistics in ECX5 & ECA5 for 8 months • • • 4 hrs x 3 FSU per MB = ~ 800 CHF* x 744 Remove-transport to ECX5-return transport-reinstall If over night activity add 50% coefficient 1 Dumont 1 Volk tractor 1 trailer Other handling tooling Total 250 kCHF 80 kCHF 30 kCHF 20 kCHF 380 kCHF Other underground aC options? • TCC6 tunnel (demount 100m of TI2, TT60 for 170 m2 area) LIU-SPS, 15 April 2015 Paul Cruikshank 18 Quad & SSS transport to surface • Underground transport to lift (BA2, BA3, BA6) • • • • Sequence: Remove-transport to surface–return from surface–reinstall Manpower 585 kCHF for 744 dipoles, so….. For 372 Quad & SSS (really 384) 292 kCHF 50% coefficient for night shift 146 kCHF Surface logistics: Handling team per location • Additional tunnel infra for SSS: • • • 130 kCHF 1 Pratt side-loader renovation 1 small trailer 70 kCHF 20 kCHF Additional tunnel infra for quad if MB are removed • • • 1 Dumont (quad config) 1 Volk tractor 1 trailer 250 kCHF 80 kCHF 30 kCHF • If MB coated in-situ, no additional infrastructure 0 kCHF LIU-SPS, 15 April 2015 Paul Cruikshank 19 MB aC ex-situ – MB alignment • Inputs & constraints: • Consider MB must return to initial position • • • Is this essential? – field quality, geometry, pumping port, other…. Tilt alignment before vacuum connections (on-line) Alignment in transport passage (need HE & SU decoupling!) • SU request 0.5 d for 4 MB string (8 MB/day capacity) • Manpower needs: • • 2 FSU for 8 months – MB & smoothing 156 kCHF Equipment needs: • Laser tracker, small tooling 30 kCHF • LIU-SPS, 15 April 2015 Paul Cruikshank 20 MB aC in-situ – Quad alignment • Inputs & constraints: • • • • • Returning quad aligned wrt to quad neighbours Tilt alignment before vacuum connections No SSS reinstallation until QF & QD realigned Alignment in trans passage (need HE & SU decoupling) 6 MB/day = 1.5 Quads/day & 1.5 SSS/day • SU request 0.5 d for 2 quads & 0.5 d for 2 SSS • Manpower needs: • • 2 FSU for 8 months – Quad, SSS & smoothing 156 kCHF Equipment needs: • Laser tracker, small tooling LIU-SPS, 15 April 2015 30 kCHF Paul Cruikshank 21 Impedance reduction during aC • max inter min Drift 513 432 0 BPH 494 206 0 max inter min Drift 386 130 0 BPV 325 none 0 QF Totals (kCHF) 773 1780 206 844 0 0 QD Total (kCHF) 405 1116 none 130 0 0 • New chamber with off-line aC coating Modified chamber (upstream flange config) then on-line aC coating Modified shielding with & isolation then on-line coating Inputs from J.Perez-Espinos: 192 Quads, 192 SSS of arc & DS, Where applicable includes cutting/demounting/remounting/welding, All transport costs in aC estimate, Additional building surface needs for max and intermediate solutions to do, Max = 2896 kCHF, min = 0 kCHF LIU-SPS, 15 April 2015 Paul Cruikshank 22 Summary • Updated costs: • aC variants - to be checked by experts Impedance variants (0 - 2893 kCHF) – to be checked by experts • • Next steps • • • • • Radiation ‘cost’ per magnet TE/VSC Developments (long hollow cathode, plasma for aC, etc) Add LSS components to aC cost estimate Check compatibility of aC variants with other LS activities Find opportunity to make aC pilot run on significant zone of SPS (with fixed budget), to validate procedures & process, measure performance, gather knowledge for SPS deployment and other CERN needs. Thanks for your attention ! LIU-SPS, 15 April 2015 Paul Cruikshank 23
© Copyright 2026 Paperzz