CAA reference to the Competition Commission for Stansted Airport April 2008 Supporting paper IV Advice to the CAA on the Calculation of Incremental Costs Advice to the CAA on the Calculation of Incremental Costs Final Report by Europe Economics Europe Economics Chancery House 53-64 Chancery Lane London WC2A 1QU Tel: (+44) (0) 20 7831 4717 Fax: (+44) (0) 20 7831 4515 www.europe-economics.com 29 April 2008 Introduction TABLE OF CONTENTS 1 INTRODUCTION............................................................................................1 2 STANSTED AIRPORT AND REGULATION ................................................3 Features of Stansted Airport and the market for airport capacity in the South East..............3 Regulatory Issues.............................................................................................................................5 Interpretation and Implications of Options 4 & 5 .........................................................................7 3 LONG RUN AVERAGE INCREMENTAL COST CONCEPT ......................9 Introduction to LRAIC ......................................................................................................................9 Key Estimation Issues .................................................................................................................. 10 a) Definition of Increment ............................................................................................................. 10 b) Time Period of Estimation........................................................................................................ 15 c) Basis of Forecasts and Assumptions .................................................................................... 16 4 COMPETITION LAW ISSUES AND LRAIC...............................................19 Economic Analysis Regarding “Excessive Price”.................................................................... 19 Competition Cases Reviewed...................................................................................................... 21 Interpretation of “Excessive Price”............................................................................................. 25 5 RECOMMENDATIONS ...............................................................................26 Summary of Desired Properties .................................................................................................. 26 Recommendations on LRAIC Methodology .............................................................................. 26 Application of the LRAIC estimate in Options 4 and 5............................................................. 30 APPENDIX 1: LRAIC — REGULATORY PRECEDENTS...................................34 Use of LRAIC in Other Sectors .................................................................................................... 34 Regulatory Precedent on Increment........................................................................................... 35 Regulatory Precedent on Time Period........................................................................................ 36 Regulatory Precedent on Basis of Costs ................................................................................... 37 APPENDIX 2: REVIEWED COMPETITION CASES............................................38 www.europe-economics.com Introduction 1 INTRODUCTION 1.1 The CAA is required to set a price limit at Stansted for the period 2009 – 2014 (referred to as Q5). Two of the options set out in the CAA’s consultation paper would be informed by long run average incremental cost (LRAIC), and the objective of this report is to discuss alternative methods by which such an estimate might be made. The numbers required in undertaking the calculations would be calculated or estimated at a later stage, but the methodology chosen would influence the type of information required for the purpose of setting a price control. 1.2 The CAA explains in the consultation paper that it wishes to adopt a form of price control that would: (a) Prevent over-charging if Stansted were in the future to acquire sufficient market power to make this possible; and (b) Avoid distorting competition between Stansted and other airports and investment decisions at Stansted or elsewhere. 1.3 The CAA’s January consultation paper outlines five possible forms of price control. LRAIC estimates would be particularly relevant for Option 4 (a Market Led Price Cap) and Option 5 (a Precautionary Price Cap). 1.4 These two options for price control are described as follows: (a) Option 4 — Market Led Price Cap (MLPC) — sets the price at the lowest level consistent with not distorting investment incentives or competition between airports. (b) Option 5 — Precautionary Price Cap (PPC) — sets the price at a level just below that which would be likely to be deemed excessive under competition legislation. 1.5 The difference between the two options is explored in Section 2 below. The CAA has advised that either case of the price control could be applied in a way that would limit charges over a regulatory period as a whole rather than annual price caps. 1.6 Advice on the issues identified in the terms of reference requires an understanding in some detail of: (a) The relevant features of the market for airports in the South East of England and the particular situation of Stansted, and the CAA’s statutory duties (discussed in Section 2 of this report). (b) Issues involved in an estimation of LRAIC and what experience of the use of LRAIC in other sectors and different circumstances may have to offer (Section 3 and Appendix 1). 1 Introduction (c) Whether Competition Act principles might inform price setting and how price levels consistent with these principles might compare with LRAIC (Section 4). 1.7 This report works through these issues, finally developing a range of possibilities for the CAA to consider for the application of LRAIC to inform its decisions about the form of price control to implement, and in particular to Options 4 & 5 (Section 5). It discusses: (a) The options for the methodology for estimating LRAIC, together with their advantages and disadvantages. (b) The input assumptions required for the calculation of LRAIC under these methodologies. 2 Stansted Airport and Regulation 2 STANSTED AIRPORT AND REGULATION 2.1 This section briefly notes the particular features of Stansted Airport in the market for airport services in the South East of England and the issues involved in its regulation that are particularly relevant for this study. Features of Stansted Airport and the market for airport capacity in the South East 2.2 A common view, shared by the CAA, is that a significant increase in airport capacity in the South East of England in the reasonably near future would probably be desirable. Views differ on the degree to which the details of such expansion should be decided by Government planners or be the result of market forces. 2.3 It is likely that such a substantial increase in capacity would have to come from one or two new runways and associated terminal capacity rather than entirely from small increases in a number of different airports. 2.4 However, it is not certain that the South East airport expansion should take place at Stansted, and there is also an issue of the appropriate timing and specification of expansion, relative to other potential sources of capacity. There is controversy over environmental and other planning aspects at all the possible places for airport expansion. The CAA has noted its concern that investment decisions might be distorted by the form of economic regulation of Stansted. 2.5 The Secretary of State for Transport found in her decision that together the airports owned by BAA, comprising Heathrow, Gatwick and Stansted, possess substantial market but that viewed as a separate entity Stansted is not currently in that position Prices at Stansted are below the maximum permitted under the present cap, there is some spare capacity at both Stansted and Luton airports and there is potential for some airline services to switch away from the airport, although many of these issues are the subject to ongoing debate. There is uncertainty about likely market power of Stansted in the long run; a key issue is whether and if so how quickly such market power may arise. 2.6 The Department for Transport found that potential competitive constraints on Stansted come from a number of other airports as well as limits on airlines’ and passengers’ willingness to pay. The most important competitor airport to Stansted is probably Luton, whilst the evidence concerning the competitive constraint posed by airports outside the South East was found to be mixed. Indeed, the Secretary of State’s finding of a likelihood of substantial market power in the future was finely balanced and depends to a considerable extent on whether or not there is investment in capacity expansion in the South East. 2.7 The extent of market power at Stansted remains a contentious issue. However, this paper considers the application of LRAIC in the context of Options 4 and 5. As the CAA has noted that these options would be pursued based on a view that the airport’s market 3 Stansted Airport and Regulation power was limited, this paper takes as its basis that Stansted does not currently, considered alone, possess significant market power. 2.8 Other features of the situation that will be important in the analysis include: (a) The ‘product’ delivered by an airport is a bundle of services supplied jointly, whose quality may be hard to measure. (b) The CAA has advised us to consider the LRAIC in the context of a single till.1 (c) The business is capital intensive, and investment to increase capacity will at some point become very ‘lumpy’ (meaning that the most efficient means of expansion will involve large expenditure on new runways and terminal facilities). (d) With lumpy investment, efficient pricing such as would be expected in a competitive context is likely to involve higher (or above-average) prices when capacity is short, so that its use is efficiently allocated, then lower (or below-average) prices following the assumed investment, to make best and most profitable use of the new capacity. In Chart 2.1 below the date that new capacity comes available to use shown with the dashed vertical lines.2 1 2 Under the single-till approach, forecast non-aeronautical revenues are subtracted from total revenue requirement to arrive at a forecast of the revenue required from aeronautical operations, which is then divided by passenger numbers to achieve a perpassenger price cap. Long term contracts and other inertia effects mean that in reality the price drop probably is not as dramatic or fast as illustrated here. 4 Stansted Airport and Regulation Chart 2.1: Stylised path of short-term competitive market price with lumpy investment Price Stylised path of competitive market price Time (e) For this and other reasons prices would at some point have to be significantly above the long term average level at which investment would be justified by expected revenues over the whole life of the asset. (f) In unregulated airports markets, this pattern of pricing would provide an incentive for airports and airlines to agree long term contracts. However, the policy of “constructive engagement” – designed to mimic the commercial interaction of airports and airlines – between the parties that has contributed to planning at Heathrow and Gatwick has been less successful at Stansted, and such contracts cannot be assumed in this context. (g) CAA has since 2003 (for Q4) set price limits for Heathrow, Gatwick and Stansted airports on an individual basis, and will do the same for Q5. We were asked by the CAA to prepare this report against an assumption of BAA’s continued ownership structure and not to make any assumptions in respect of the findings of the Competition Commission’s market inquiry into BAA. We were asked to assume that stand-alone regulation continued to apply. Regulatory Issues Section 41 2.9 The CAA has some powers to regulate airport conduct through Section 41 of the Airports Act 1986. However, these powers relate to similar forms of conduct that are prohibited 5 Stansted Airport and Regulation under competition law and do not appear to have a significant influence for the present analysis. Potential distortions of investment incentives 2.10 The CAA is aiming to avoid distortions to investment incentives in either direction: it wishes to avoid giving incentives to invest where, in a competitive market, the airport would not invest, or to deter investment that would occur in a competitive market either at Stansted or elsewhere. The CAA is also concerned not to distort decisions about the specification for possible investment (size, quality of facilities, etc.). The risk of discouraging efficient investment would clearly arise if the price limits were too low, i.e. below the competitive market level (which would give efficient investment incentives). The concern not to artificially encourage excessive capital expenditure relates to a specific effect that the existing regulatory approach could have at Stansted, as explained in the consultation document and summarised below. 2.11 A significant distortion to investment incentives could result from using the RAB based price cap in Q5. The issue is as follows: (a) Stansted has in the past not been able to charge up to the regulatory price limits. The actual level of airport charges has been determined through commercial arrangements between the airport and its users, at significantly less than the regulatory ceiling. (b) Possible cross - subsidies from Heathrow and Gatwick to Stansted (before price controls were set on the basis of the financial projections for the individual airports in 2003), combined with depreciation schedules that might not reflect the actual useful economic lives of these assets, have led to a situation in which a traditional RABbased price cap might come into effect at an artificially low level, and require charges to be limited even when Stansted does not possess significant market power. (c) As a result, the CAA has argued that if the regulatory system is not changed Stansted might have an incentive to incur capital expenditure that would not otherwise be commercially justified simply in order to increase the value of the RAB and to allow it to increase charges to reach the competitive level. 2.12 Either Option 4 or Option 5 would deal with this problem — because they would not make use of the current concept of a RAB and neither should lead to a price cap below the market level regardless of whether Stansted undertakes investment or not. 2.13 In setting price limits for Stansted, a major objective is that price limits should neither be set too low and thus discourage otherwise efficient investment at Stansted (or induce inefficient investment elsewhere), nor set too high so that if Stansted were to acquire significant market power it would then be able to charge excessive prices to its users. 6 Stansted Airport and Regulation Interpretation and Implications of Options 4 & 5 2.14 The CAA consultation document explains the difference between the two options as: (a) Option 4 — Market Led Price Cap (MLPC) — sets the price at the lowest level consistent with not distorting investment incentives or competition between airports. (b) Option 5 — Precautionary Price Cap (PPC) — sets the price at a level just below what would be likely to be deemed excessive under competition legislation, i.e. just before users of the airports might have to resort to (costly) litigation. 2.15 By definition, investment incentives and competition are not distorted if prices are set at the competitive level. The major attraction of LRAIC is that, when implemented appropriately, it can mimic the expected outcomes for Stansted in a competitive market. It is therefore directly relevant to both options. A regulator setting charges based on LRAIC would allow a normally efficient supplier to recover its costs, including normal profit margins reflecting the riskiness of investment. This implies that suppliers have an incentive to invest in upgrading or adding to their service infrastructure that is in principle neither stronger nor weaker than it would be in a competitive sector not subject to economic regulation. 2.16 It may be asked why should Option 4 (MLPC) not equal Option 5 (PPC) and both be measured by LRAIC? It has been necessary to develop a further understanding of Options 4 & 5, to identify differences between the two options. 2.17 There are two key defining differences — one about the expectations of degree of market power and the other, linked to the first, about the time period over which the regulation is defined. MLPC is taken to be the lowest average price level over the long term that would be consistent with the competitive level, and the PPC is the level above which prices would not rise at any point in time except as a result of exploitation of a position of substantial market power. Chart 2.2 below illustrates the conceptual difference between the two options 2.18 The precautionary price cap (PPC) is drawn slightly above where the highest level of the competitive market price could be expected to be at any point in time (i.e. the short-term competitive price level). The market led price cap (MLPC) might be drawn slightly above the level of the competitive market price on average over time (i.e. above the long-term competitive price level). The maximum prices might be set slightly above the LRAIC estimate due to: the degree of market power being uncertain; the uncertainties of LRAIC estimation; and, the need to maintain investment incentives under a price cap that prevents prices rising to the full extent implied by the path of competitive prices. 7 Stansted Airport and Regulation Chart 2.2: Drawing the difference between Options 4 (MLPC) and Option 5 (PPC) Price PPC MLPC LRAIC competitive price path Time 2.19 Under this interpretation the MLPC would be applied over a long time period, very probably stretching beyond a single price control period. The PPC, on the other hand, would provide a check on the price level at any one point in time (e.g. in any one year). 2.20 A key factor for the CAA to consider in choosing between the PPC and MLPC approaches is the expected likelihood and degree of market power Stansted has or might attain. The stronger the expectation of significant market power, the more assurance with regard to possible over-charging the CAA could obtain from MLPC relative to PPC. This is because MLPC would make the company accountable for the average level of charges over time, while the PPC would limit only the highest price over the cycle. 2.21 Both approaches, however, could make use of the LRAIC estimate. The next section considers alternative LRAIC concepts and estimation methods. 8 Long Run Average Incremental Cost Concept 3 LONG RUN AVERAGE INCREMENTAL COST CONCEPT Introduction to LRAIC 3.1 The long run average incremental cost (LRAIC) of a service or product is equal to the change in total cost in the long run resulting from a specified variation in output, averaged over the units of output supplied. The components of the acronym can be defined as follows: (a) Long run — the estimation is done with a long enough time span to be relevant to planning and investment decisions.3 (b) Average — the incremental cost could be averaged in several ways. Usually, this is done by dividing the cost of the increment by the units of output it provides. (c) Incremental — refers to the defined change in either services or in volume of services, the cost of which is the object of investigation. (d) Cost — self-explanatory at one level, but there are important differences in the way estimates may be made. 3.2 Different approaches to the above elements determine the properties of the resulting estimates, their applicability to different settings, and their suitability with respect to different regulatory goals. 3.3 Implemented appropriately, LRAIC can estimate the maximum prices Stansted would be able to charge on average over time in a competitive market, assuming normal levels of efficiency. Another benefit of basing price controls on LRAIC is that it can reduce the reliance on information supplied by the incumbent. This occurs when the LRAIC is calculated on the basis of an efficient benchmark rather than on the basis of incumbent costs and investment plans. 3.4 One drawback of LRAIC is that its implementation can be quite complex, requiring a number of assumptions that may be open for discussion. This also introduces significant regulatory discretion in the determination. 3.5 A summary of regulatory precedents for the use of LRAIC in other sectors is set out in Appendix 1. 3 This is different from a textbook definition of the long run as the period in which all inputs are variable. 9 Long Run Average Incremental Cost Concept Key Estimation Issues 3.6 The differences in the objectives of LRAIC estimation in the different sectors have contributed to alternative implementations of the various building blocks in LRAIC estimation. The main choices, which define the characteristics of the LRAIC estimate, relate to: (a) Definition and measurement of the increment. (b) Time period (definition of the long run). (c) Basis of forecasts (whose, on what assumptions) to inform the required input assumptions on: – Demand for the increment over the relevant time period. – Design and costs of the capital assets within the increment. – Operating costs relevant for the increment and time scale. – Cost of capital used as the basis of the allowed return (and the discounting method used to set annual prices, if applicable). 3.7 In addition to the above, different implementations of LRAIC could be accompanied by differing approaches to remuneration of existing assets, and the new assets over time (e.g. when they have become part of the existing asset base). If the principle of LRAICbased charging were applied across the whole airport this might imply a revaluation of existing RAB. 3.8 We briefly discuss each of the above key determinants in turn. a) Definition of Increment 3.9 Defining the increment is the first step in the LRAIC estimation. It defines the service and the capacity of the service whose costs the LRAIC method estimates. It is likely to have the largest impact on the final result, as well as the fundamental characteristics of the final result. 3.10 In principle, there are many different sized increments that could be measured, as well as different dimensions over which to measure the increments. However, these might be grouped into four different categories under two subheadings: (a) Increments based on (hypothetical or expected) variations in capacity to supply an existing service or set of services: – a small change in the volume of or demand for a particular service; or – a large change in the volume of or demand for a particular service. 10 Long Run Average Incremental Cost Concept (b) Increments based on (hypothetical or expected) variations in services: 3.11 – the addition of a specific service; or – of a group of services. The first definition of the increment involves measuring the cost associated with providing a small change in output. The second definition is usually taken to be large enough to trigger capital investment, so that LRAIC might be estimated for a particular investment program. The third definition may apply to services of very different sizes and is often referred to as service-based LRAIC. The last category is the broadest definition of an increment and one variant of that definition of the increment has been used extensively in telecommunications to set interconnection charges. Possible increments for Stansted 3.12 In the case of airports, service-based increments might be imagined, for example drawing a distinction between baggage handling and passenger handling services within the aeronautical services group. It may also be noted that, under easyJet’s proposed “terminal tendering approach”, a service-based increment could be used, defining “runway access service” as the increment. 3.13 However, the use of a service-based increment would seem problematic in the case of Stansted. Indeed, the CAA has consulted extensively in the past on a move to a dual-till system – which might be more suited to a service-based approach – but decided to retain the single-till approach for the previous price control period. The reasons for the single-till approach remain valid; the services provided by an airport are to a large degree mutually dependent. 3.14 Viewing the whole airport as a single increment would be consistent with the single till approach, and might have some desirable properties relative to volume based increments. 3.15 However CAA’s concern not to distort competition or investment decisions relates most closely to costing new projects and the associated operating costs e.g. new runway capacity and associated terminal infrastructure. Increment based on variations in capacity 3.16 With regard to volume-based definitions, long run cost can be calculated using either: (a) The average incremental cost (AIC) approach. This involves calculating the forwardlooking unit cost of meeting a projected growth in demand, i.e. the cost per unit of the planned investment program and associated net operating expenditure. (b) The marginal incremental cost (MIC) approach, also sometimes known as the Turvey approach, after Professor Ralph Turvey. This involves calculating the implications for 11 Long Run Average Incremental Cost Concept unit cost of a small change to projected demand, i.e. the forecast unit cost increase or reduction resulting from the implied change in the planned investment program and associated operating expenditure. 3.17 The two approaches can produce different results depending on the nature of investment program. Both can be relevant in different circumstances. 3.18 The AIC approach would help to ensure that prices charged for additional units of consumption cover the avoidable costs of supplying those units, including any required investments. It would therefore provide an answer to the question of what price would have to be charged such that, over the life time of the assets, investments in additional capacity recover their costs. 3.19 The MIC approach provides estimates of the cost of small changes in volume and in some circumstances may provide more efficient price signals. 3.20 These approaches are therefore aimed at different questions that can both be relevant in different circumstances. 3.21 Figures 3.1 and 3.2 illustrate the two methods. Figure 3.1 shows a situation in which there is a capacity surplus at the start of the period, but due to projected growth in demand additional investment will be required at T1. The LRAIC according to the AIC method would be calculated as follows: (a) Present value (PV) of operating cost of delivering the shaded volume of service; plus (b) PV of investment triggered at time T1; all divided by (c) PV of the shaded volume of service (the additional number of passengers using the airport). 3.22 That is, the AIC is calculated as the net present value cost of supplying the additional passenger throughput, divided by the net present value of incremental passengers, where the present values are calculated for the full asset life of the investment. 12 Long Run Average Incremental Cost Concept Figure 3.1: Illustration of AIC approach to LRIC Volume Investment planning horizon Life of new assets Available capacity Existing consumption Additional demand T1 3.23 Time The LRAIC according to the MIC method, on the other hand, considers the forwardlooking cost per unit of a hypothetical permanent incremental change to the existing investment plan, as illustrated by Figure 3.2.4 This increment would be additional to the forecast increase in demand, and in this example would require the company to bring forward investment in new capacity. (It would also be possible to construct an example in which the size of the required investment increased.) The LRAIC according to the MIC method would be calculated using the information presented in Figure 3.2 as follows: (a) PV of operating cost of delivering the shaded capacity (the increment); plus (b) PV cost of bringing forward the planned investment from T1 to T2; all divided by (c) PV of the shaded capacity (PV of the increment of passengers). 3.24 That is, the marginal incremental LRAIC is calculated as the net present value of the additional costs of the hypothetical increment on the original investment program and associated operating costs, divided by the numbers of passengers served. 13 Long Run Average Incremental Cost Concept Figure 3.2: Illustration of MIC approach to LRIC Volume Investment brought forward Increment to projected demand T2 T1 3.25 Time Given the above, there are several potential ways to calculate LRAIC, including: (a) AIC approach based on delivering the forward-looking investment program. (b) MIC approach based on an increment of demand specified by the CAA. (c) MIC or “perturbation” approach using different increments and decrements and averaging the results. 3.26 4 However, the relevance and applicability of the MIC approach in the current case is doubtful. The investments involved in increasing capacity at airports are not homogenous, and can vary widely between investment in say, security infrastructure, additional baggage handling capacity and marginal runway capacity. Further, it is likely that to increase a planned new runway capacity by X per cent at the design stage would add less than proportionately to its cost (due to economies of scale within the project), so that the investment might not be justified by charges based on MIC even if overall it would cover its total costs. The increment of demand is assumed to be permanent here for clarity of exposition. The approach can in principle be applied to any postulated size of increment lasting any postulated amount of time. It can also be applied to a decrement in demand. 14 Long Run Average Incremental Cost Concept 3.27 The AIC approach seems more aligned with CAA’s objectives of avoiding distortions to the decisions about possible significant expansion at Stansted. This still leaves open the question of exactly what the increment is, what service levels are to be specified (a contentious issue) and against what baseline it is measured. The alternative to an AIC type approach would seem to be to define the increment as the whole airport or the whole system of runways. This could also be consistent with the CAA’s underlying objective of not distorting investment incentives or competition between the airports. 3.28 The two approaches do, however, have different strengths and weaknesses, discussed further below and in Section 5. b) Time Period of Estimation 3.29 Two issues arise regarding the time period of the estimation. 3.30 First is the definition of the long run that should be used. Here a relatively straightforward interpretation is available. The length of the time period considered for LRAIC should be the longest term relevant for planning and decision making in the industry. It also should be coherent with the definition of the increment used. 3.31 A second group of questions arises in the context of Stansted. LRAIC estimation under the AIC view of the increment considers only the forward looking costs of the increment. When investment is lumpy and so not undertaken continuously, as spare capacity comes into use and the time of the next investment becomes nearer the prices estimated by LRAIC would rise. However, in the period after the investment, the forward looking LRAIC estimate would be relatively low due to the (new) spare capacity in the system. Indeed, this reflects one of the desirable qualities of LRAIC — it mimics the behaviour of prices in a competitive market. The result is the “saw tooth” pattern of LRAIC estimates done at different points in time relative to dates of investment, similar to that in a competitive market (see Chart 2.1 in paragraph 2.8). 3.32 In the case of Stansted the effect would be as follows: in the run up to a time when investment is most likely to be needed the price cap based on LRAIC would rise. Once the investment is complete, recalculation of a price cap based on LRAIC would fall, as one would expect to happen in a competitive market. However, if the company were to fear that the regulatory limit imposed would be lower than it would expect to be able to charge in a competitive market this would act as a disincentive to invest, and it would be appropriate for the regulator to explain clearly how the methodology would be intended to be applied in successive periods. 3.33 The issue would not arise under the “whole service” definitions of the increment, typical to telecommunications implementations of LRAIC, as they involve the forward-looking valuation of the full asset base (or equivalent, see below). That would be beneficial from a regulatory consistency point of view. However, it would also mean that the resulting price controls less accurately reflect competitive market outcomes in the case of Stansted. The use of LRAIC based on the unit costs of a forward looking investment plan (the AIC 15 Long Run Average Incremental Cost Concept approach) has been used as an input towards structuring charges (energy sector), or as signals towards efficient long term investment and use (water sector). 3.34 In other regulatory contexts the LRAIC methodology has been applied in a situation of confirmed significant market power. In such a setting, the price cap is expected to bind more or less continuously, so the regulators can focus on ensuring that the incumbents earn only normal returns and recover only efficient costs over time, recalculated every five years. Indeed, there is little discussion in the regulatory precedent about the length of the price control period not matching the length of the investment horizon used for the LRAIC estimates. 3.35 In the case of Stansted, the price cap may not bind - at least in the near term, or following a significant increment in capacity. Further, the incremental capacity increasing investment at Stansted is likely to be lumpy compared to some other sectors, which would lead to higher variations in the before and after investment LRAIC estimates. This will need to be taken into account in the application of LRAIC in setting price limits for Stansted. Relevant time frame for Stansted 3.36 Economic logic and regulatory precedent both point towards interpreting the “long run” as the longest term relevant for planning and decision making in the industry. c) Basis of Forecasts and Assumptions 3.37 Any implementation of LRAIC requires the following input estimates or assumptions: (a) Demand over the relevant time period. (b) Design and costs of capital assets within the increment. (c) Operating costs relevant for the increment and time scale. (d) Cost of capital used as the basis of the allowed return. 3.38 There are two broad approaches to establishing the above estimates or assumptions. Using the convention of naming from the telecoms sector, these can be broadly defined to be: (a) A “top-down” approach, which is based on the actual costs of the regulated operator as posted in the financial statements, allocated to product groups, and the incumbent company’s forecasts of demand and costs in the context of a planned expansion. (b) A “bottom-up” approach, a forward looking approach which considers modern equivalent assets, efficient design of the capital assets (e.g. network structure), and efficient (if hypothetical) net operating costs consistent with the efficient layout and utilisation of modern assets. 16 Long Run Average Incremental Cost Concept 3.39 The cost of capital could be established using the approach developed elsewhere for the price controls of Heathrow and Gatwick. Top down approach — pros and cons 3.40 In a top-down application of LRAIC the starting source of information for estimating the costs of services is normally the costs actually incurred, or envisaged, by the regulated company. The recorded costs are allocated, through a number of intermediate steps, to final services. The resulting charges have a direct link with the company’s actual accounts. A top-down approach can also be applied with a current cost adjustment to the asset values — the historic cost figures need to be “adjusted” into current cost figures. In some cases this may lead to certain costs incurred by the modelled company being excluded. 3.41 The benefits of the approach are generally taken to be that the resulting costs can be traced back to the formal accounts of an existing company, helping to ensure that all relevant costs are accounted for. 3.42 However, there are several drawbacks to this approach. Depending on the definition of the increment, the development of estimates can be more resource intensive and time consuming than a bottom-up approach, and the resulting estimates could incorporate the incumbent’s inefficiencies in the layout, type or design of the assets, or in their use. Further, if the estimates are based on proprietary data, it might not be possible for third parties to examine the estimates and provide expert views on them. Bottom-up approach — pros and cons 3.43 The bottom-up approach uses demand projections as a starting point and determines, by using economic, engineering and accounting principles, an efficient structure capable of serving that demand, independently from the incumbent’s actual or planned structure. In principle, bottom-up models give the model developer more flexibility regarding efficiency considerations and reduce dependence on the company for data. All of these are desirable qualities in terms of implementation of LRAIC with the object of obtaining an estimate of the maximum price Stansted would be able to charge in a competitive market on average over the long term (assuming normal levels of efficiency). 3.44 The bottom-up approach is more appropriate in cases where a hypothetical efficient company is assumed. Accounting for efficiencies (technical and operational) is much easier in a bottom-up context as legacy asset issues are less of a problem than in a topdown approach. The bottom-up approach also does not need to refer to a specific company — the thought experiment is that of a hypothetical efficient entrant, or hypothetical efficient investment to satisfy capacity demand — effectively reducing the dependence on the incumbent, and increasing effectiveness of consultation in determining the cost and demand assumptions. 3.45 However, there is a danger that bottom-up models may understate the costs of efficient companies particularly where technologies are rapidly changing. In practical terms, 17 Long Run Average Incremental Cost Concept particularly forecasts of operating expenditure can be difficult to model in a bottom-up setting. 3.46 In principle, both methods should lead to the same result. In practice though, this can only happen if the same assumptions are made (e.g. regarding asset types, layout and operational efficiency). Consequently in telecommunications it is often observed that bottom-up and top-down models are used in parallel with a view to reconciling the results of the two models and developing a hybrid model, so as to minimise the weaknesses of the two models and take better advantage of their strengths. Basis of forecasts 3.47 If a top-down approach is chosen, the main data source typically used is the modelled company’s accounts (or investment plans). On the other hand, bottom-up models also use data gathered from market participants, equipment suppliers and other publicly available information. In both cases, though, the required information for proper LRAIC estimation is extensive and requires the exercise of discretion. In the case of top-down models it is sometimes very difficult to audit or review the results since the necessary data are confidential. The information gathering powers provided to the CAA would reduce this latter concern. 3.48 In LRAIC methods there may arise some problems related to the knowledge of the cost of the assets. For instance, some elements may be customized and may not have a welldefined market price, or the future usage of different assets may affect the choice of what constitutes efficient equipment. For technology dependent increments, forecasts of technological progress are needed both for proper determination of LRIC technology and for determining demand forecasts. However, the weight of this factor depends on the sector. For instance, it is more important to better predict technological changes regarding a core telecommunications network than a water network. Possibilities for Stansted 3.49 It seems that a forward looking, bottom-up approach would be preferable in the case of Stansted. It would not be overly reliant on information from BAA, and allow for direct consultation of and input from independent experts. It would be more consistent with the view of utilising LRAIC as an estimate of maximum Stansted would be able to charge in a competitive market in the long term, and avoiding distorting incentives for investment. 3.50 Indeed, if the relevant increment is taken to be an increase in existing capacity, the likely absence of forward looking information held by Stansted would necessitate a bottom-up type approach. Even then, more emphasis could be placed on independent forecasts, estimates and designs, rather than relying on information from the incumbent. 18 Competition Law Issues and LRAIC 4 COMPETITION LAW ISSUES AND LRAIC 4.1 Option 5 requires a view on what might be judged to be an excessive price level from the view of the competition authorities. Article 82 4.2 The Article 82 prohibition of the consolidated EC treaty is the basis of the competition law on abuse of dominance as it may affect trade between Member States. The Competition Act 1998 extends Article 82 to apply also in cases where the dominance only affects trade within the UK. The full Article 82 text is as follows: “Any abuse by one or more undertakings of a dominant position within the common market or in a substantial part of it shall be prohibited as incompatible with the common market insofar as it may affect trade between Member States. Such abuse may, in particular, consist in: (a) directly or indirectly imposing unfair purchase or selling prices or other unfair trading conditions; (b) limiting production, markets or technical development to the prejudice of consumers; (c) applying dissimilar conditions to equivalent transactions with other trading parties, thereby placing them at a competitive disadvantage; (d) making the conclusion of contracts subject to acceptance by the other parties of supplementary obligations which, by their nature or according to commercial usage, have no connection with the subject of such contracts." 4.3 The interpretation of Article 82 is a subject of much debate and some case law. The charging of excessive prices is only one of several ways in which a dominant position might be judged to have been abused within the legislation — “unfair prices” is only a part of one of the four distinct abuses of dominant position, and case law on the point is relatively limited. Economic Analysis Regarding “Excessive Price” 4.4 Economic interpretation of an excessive price has to start with the characteristics of a “normal” competitive market price. 4.5 Normally, in a competitive market, prices would at all times be at a level that covers the short run marginal costs of production. In the long term, in order for production to be sustainable, prices would cover, on average, the long term costs of production, including a return on investment (i.e. normal profit). The required return on investment, or the normal profit, is determined by the cost of capital to the industry. There is, therefore, a difference between the prevailing competitive price level in any given period (the short-term 19 Competition Law Issues and LRAIC competitive price level) and the average level of prices in a competitive market over the longer-term. 4.6 If prices do not achieve this level on average over the long term, there would be exit from the market, followed by a reduction in supply and, other things being equal, an increase in the price (for a given level of demand). If prices exceed the competitive level, the resulting excess profits would be eroded away through entry into the market. As discussed above, LRAIC can be used to estimate such a long term average price level. 4.7 However, such a cost-based definition of a “normal” long term price level is not directly useful for determining what might be an excessive price at any point in time. This is because, in the short run, the market price could fluctuate substantially (and nonsystematically) around the long term average that would deliver cost recovery and normal profit. A major source of such short term movements in the price is likely to be changes in demand, possibly amplified by real-options effects given irreversible investment in the presence of uncertainty.5 4.8 Indeed, such price fluctuations are necessary for the long term cost recovery price to be achieved. Without market power, companies are fully exposed to the effect of demand fluctuations in the market. Therefore, to achieve long term viability, companies must be able to take advantage of favourable market circumstances (e.g. increase their price) to compensate for periods of bad market outcomes (e.g. times of low demand leading to lower than the long term average prices). 4.9 The implication is that the price at any one point in time could be substantially above the long term average level as estimated by LRAIC, and yet not be considered “excessive”. This is why it is appropriate that competition law would not contemplate the possibility of prices being excessive except in circumstances in which the supplier has significant market power. 4.10 In the case of airports, a major cause of short term price fluctuations could be movements in demand while capacity remains relatively fixed. The demand at airports can vary annually, according to the season, as well as according to the time of day with substantial potential differences in peak and off-peak demand. The daily peak price to average price variation provides one indication of how much prices may move, in the absence of market power, between periods of high demand and low demand. 5 If there are irreversible costs to investment and there is an option to wait and there are not other countervailing factors (such as the possibility to pilot scalable investment), following a positive demand shock, causing prices to rise and firms to make positive profits, firms will wait before investing just in case prices fall back down again and the irreversible costs of investment are lost. Similarly, negative demand shocks will not instantly stimulate exit, for the market may pick up in the future. Prices may rise above average total cost for a period without stimulating entry or investment, and may be sustained for some time below average total cost without stimulating exit or disinvestment. There is thus greater/more sustained variance in the path of prices under irreversibility and uncertainty than in the standard competitive model. This analysis is set in the Dixit-Pindyck framework, which is also referred to by the CAA in paragraph 4.13 of the consultation paper. 20 Competition Law Issues and LRAIC 4.11 Economic intuition, then, would indicate that an excessive price might be defined as a price higher than that which could reasonably be expected to result from short term demand or other fluctuations, above a long term average price that would ensure efficient cost recovery (including normal profit). Real-options analysis could also be relevant to reflect the full potential for variation in competitive prices.6 Competition Cases Reviewed 4.12 The published decision documents of the some relevant cases have been reviewed with particular reference to the definitions of excessive prices, and any comments on the tests and data used to determine whether a price is excessive or not. The list of cases reviewed is in Appendix 1. 4.13 The cases that seemed to establish the most relevant and directly useful precedent were the United Brands (1978), Sacem (1987), Port of Helsingborg (2004), AttheRaces (2005), Deutsche Telekom (1997), and the Napp Pharmaceuticals (2001) cases. The Albion Water case might also be particularly relevant. However, the Competition Appeals Tribunal has not yet given its final decision on the case. 4.14 As might be expected, the competition authorities responsible for the decisions have been reluctant to specify precisely what is meant by an excessive price and how exactly to judge whether a price is excessive. The courts have seemed particularly loath to prescribe any particular price level as the threshold over which prices should not rise, lest they appear to be price regulators. Nevertheless, some useful lessons can be learned from the past cases. United Brands (1978) 4.15 In United Brands case, the European Court of Justice (ECJ) set out a definition of what may constitute an excessive or unfair pricing abuse under Article 82. The judgment set out what is essentially a two part test, which defines a price as excessive “because it has no reasonable relation to the economic value of the product supplied”. The ECJ did not explain how it supposed that the “economic value” of a product should be determined, although the decision (paragraph 251) implied that the profit margin could be determined objectively if it were possible to objectively calculate the cost of production and compare that to the selling price. This would disclose the amount of the profit margin, though the judgment did not say how it would be determined whether the profit margin was excessive or not. 4.16 However, the ECJ further stated, in paragraph 252, that “[t]he questions therefore to be determined are whether the difference between the costs actually incurred and the price actually charged is excessive, and, if the answer to this question is in the affirmative, 6 This is also referred to in paragraph 4.13 in the CAA consultation paper. 21 Competition Law Issues and LRAIC whether a price has been imposed which is either unfair in itself or when compared to competing products”. The two part test inferred from the judgment is: (a) First, a comparison of price to costs of production, and if the price is found to be excessive in this sense; (b) Second, a consideration whether the price is unfair in itself or when compared to competing products. 4.17 This leaves many questions open — most importantly the amount by which price should be above the costs for the second stage to become relevant (profits to be excessive), and what constitutes a price that is unfair in itself (question about the definition of the economic value). The comparison to prices of other competing products could however, be useful in the case of Stansted. Also, an indirect implication of the test is that the ECJ seems to consider at least some level of profit over “costs actually incurred” to be acceptable. SACEM (1987) 4.18 In the SACEM case, the ECJ considered that the production costs to be taken into account are those of an efficient firm, and not necessarily those of the investigated firm. This recognises the fact that prices may be excessive even if profits are not high, as the investigated firm may have inflated production costs because of its dominant position (Xinefficiency). 4.19 The excessive price test actually employed in the SACEM case was a comparison to prices in other geographic markets. However, the notion of using an efficient firm as the basis of comparison would be consistent with the way in which LRAIC is implemented in some settings, or to put it another way, LRAIC could be used to calculate the costs of the efficient firm. 4.20 The notion of the efficient costs was also employed in the KLM (2000) case by the Dutch competition authority. Deutsche Telekom (1997) and Napp Pharmaceuticals (2001) 4.21 The Deutsche Telekom (1997) and the Napp Pharmaceuticals (2001) cases are the only two cases of those reviewed that provide any direct indication of what was and what was not regarded as an excessive margin on costs of production. 4.22 In the Deutsche Telekom (DT) case, following a complaint made in 1996 against the conditions imposed on third parties for access to DT’s infrastructures the European Commission initiated proceedings against the company. An independent price survey carried out on behalf of the Commission demonstrated DT’s inability to prove that its prices were cost-orientated, and found the DT price level to be 100 per cent higher than on comparable competitive markets. 22 Competition Law Issues and LRAIC 4.23 DT was invited to adjust the tariffs “to real economic conditions”, so that they in the Commission’s opinion cannot constitute an abuse of a dominant position. DT lowered its tariffs by 38 per cent for access to the local network and 78 per cent for access to the long-distance network, and the Commission decided to terminate the investigation. Depending on the exact margin on the services provided before the new prices suggested by the incumbent, the new lower prices still could retain substantial headroom above efficient costs (as defined by prices in comparable but competitive markets). 4.24 In the Napp Pharmaceuticals case, the OFT applied a similar test to the United Brands test by benchmarking price-cost margins, and by benchmarking prices themselves. The OFT found both to be significantly higher than those of relevant competitors. In an appeal to the CCAT (now the CAT), Napp argued that brand value and premium to compensate for ex-ante uncertainty was not taken into account in OFT’s analysis. Both the OFT and the CCAT argued that a brand value premium could not be as high as 40 per cent. (The CCAT also rejected the arguments that ex ante uncertainty justified high ex post prices.) However, the judgment on excessive prices was given in a context of another abuse of dominant position — exclusion of access. It is not clear whether the 40 per cent difference between Napp and competitor prices would have been judged excessive on its own. 4.25 The implication from these two cases is that the headroom above a LRAIC estimate that competition authorities might allow could be quite large before prices are deemed as excessive. Port of Helsingborg (2004) 4.26 The judgment in the case against Port of Helsingborg (HHAB) explicitly followed the methodology set out by the ECJ in the United Brands judgment. The judgement: (a) Compared the costs actually incurred by HHAB in providing the products/services in question, and made a comparison to the prices charged. (b) Investigated whether the prices were unfair when compared to prices charged to other users or by other ports. (c) Investigated whether the prices were unfair in themselves. 4.27 The first test differs somewhat from the interpretation in the SACEM case in two respects. First, in considering stage 1 of the test the Commission used the costs actually incurred by HHAB, including explicitly rejecting the use of a forward looking costing method (replacement value of assets) in favour of the historical book value of the existing assets as part of the stage 1 analysis of costs actually incurred. Second, the allocation of costs to the services was also based on audited financial results of HHAB, rather than, say, an allocation that was considered somehow explicitly efficient. 4.28 However, in determining whether the prices were unfair in themselves, the Commission emphasised the importance of demand factors above the simple costs of production, and 23 Competition Law Issues and LRAIC in a competitive context the demand factors would incorporate forward-looking cost expectations. The clear implication is that the “economic value” cannot be determined by adding a pre-determined percentage profit margin on the production costs. Therefore, according to this precedent, finding a positive difference between production costs (including a normal profit) and price would not necessarily lead to the conclusion that the price is excessive, provided that the price has a reasonable relation to the economic value of the service supplied. 4.29 Apart from referencing the importance of demand factors, the judgement does not give a specific opinion on how the effect of the demand factors might be taken into account. Nevertheless, it is compatible with the view that the price estimated by LRAIC would not give a ceiling of excessive price, and the CAA should provide some head room above it. AtTheRaces versus British Horseracing Board (2007) 4.30 The ATR case provides further insight to the importance of demand factors in determining the economic value of the product under the United Brands test. ATR argued that the prices charged include an excessive margin over any reasonable costs of the data provided by BHB. BHB, on the other hand, argued that it added value to British racing through its governance role, the cost base should reflect all costs in organising British horse racing, and the pre-race data had distinct value to bookmakers. 4.31 The High Court and the Court of Appeal both accepted that “competitive price” could reflect the economic value of the product to the user. The Court of Appeal found also that the wider cost base of the BHB than that relating strictly to the data should be taken into account, in line with BHB’s claim. The Court explicitly stated that if consumers and competition were unaffected competition law should be silent on the proportion of the value that each supplier should earn. 4.32 Albion Water (ongoing) 4.33 Although this case is still ongoing, it is relevant as it provides the most recent example of a case that is clearly about excessive prices. The case relates to an appeal by Albion Water to the CAT about Ofwat’s conclusion that Dŵr Cymru did not abuse its dominant position by engaging in excessive pricing. The test applied by Ofwat was whether the access price offered by Dŵr Cymru could be said to “bear no reasonable relation to the economic value of the service provided, when judged by reference to the difference between the costs actually incurred by Dŵr Cymru and the price charged”. 4.34 The initial judgment by the CAT (November 2006) found that evidence strongly suggested that the access price was excessive, but was careful to leave room for further submissions to be made. A further judgment in December 2006 set out the CAT’s views on excessive pricing in more detail. The Tribunal is clear that the test it is applying is that set out in United Brands and moves a step closer to a final judgment. In particular, the CAT’s December 2006 judgment emphasised the importance of further investigation of costs when assessing whether the price is “unfair”. 24 Competition Law Issues and LRAIC 4.35 The CAT has received further submissions covering a variety of cost estimates, including LRAIC estimates, and has yet to deliver a final judgment. An important issue in this case is whether or the extent to which cost estimates or a specific service may be derived from wider average cost estimates (e.g. of supplies all industrial users of Dŵr Cymru’s services). Interpretation of “Excessive Price” 4.36 The framework set out in the United Brands case seems to have been established as the way in which competition authorities would consider whether a price charged by a supplier with substantial market power is excessive. As discussed, the test would seem at least not inconsistent with intuition about how an excessive price might be defined. 4.37 It would be preferable to view the relevant cost base in the way it has been interpreted in the SACEM case, rather than the interpretation in the HHAB case. This interpretation allows for efficient forward looking costs to be considered, and would seem to avoid the possibility of abuse of dominance through inflation of costs as well as inefficiency of the incumbent operator. The interpretation in the HHAB case would rule out the use of forward looking LRAIC estimates in a way that can approximate a long term average outcome in a competitive setting. The forthcoming CAT judgement on Albion’s appeal will provide a further important indication on the treatment of costs. 4.38 The relationship between the LRAIC estimate and the “excessive price” would be determined by some mark up on the LRAIC estimate to allow for the effect of fluctuations in demand and other factors. The competition case review indicates that this mark up over efficient costs (including normal profit) could be quite substantial while remaining acceptable from the competition authorities’ point of view. 25 Recommendations 5 RECOMMENDATIONS Summary of Desired Properties 5.1 The LRAIC approach adopted for Stansted should be: (a) Theoretically robust. (b) Consistent with CAA’s statutory powers and responsibilities. (c) Avoid distortions to investment incentives and to competition between the airports. (d) Consistent with viewing Stansted as an independent economic entity (free of effects of cross subsidy). (e) Practical and understandable to implement. Recommendations on LRAIC Methodology Appropriateness of LRAIC with view to overall objectives 5.2 LRAIC is an appropriate methodology to use to establish the cost base for price control under either Options 4 or 5. This is because: (a) LRAIC is a forward looking methodology that can estimate the maximum level that Stansted would be able to charge, on average over time, in a competitive market. As such, it has a robust theoretical basis and can ensure that investment incentives and competition between airports are not distorted by regulation applied to Stansted. (b) It is consistent with the viewing Stansted as an independent economic entity, avoiding issues about past or future cross-subsidies. (c) It is consistent with a reasonable interpretation of the precedent in competition law cases. Its use would be consistent with CAA’s statutory duties. 5.3 LRAIC estimation and use in setting price limits involves three main steps: defining the increment7; measuring its cost and translating that cost to a price (or revenue) limit. 5.4 It will need to be applied in a way that is appropriate to Stansted’s particular circumstances. 7 Or decrement; this complication does not change the analysis in a way that is relevant here and is ignored for simplicity of exposition. 26 Recommendations Definition of the Increment 5.5 Service based increments (e.g. in terms of aeronautical and non-aeronautical services) seem tenuous, and indeed divisions of that type have been investigated and rejected in the past by the CAA. The use of a capacity based increment would be consistent with single-till regulation, which has been judged preferable. 5.6 There are three main options for defining the increment: (a) A small increment (b) A new runway and associated terminal expansion (c) Stansted as a whole. 5.7 There would be serious disadvantages of estimating LRAIC with regard to a small increment. The nature of airports is such that expansion may involve lumpy investment, an aspect that sits uncomfortably with measuring the costs of small changes. It is unlikely that this approach would be credible. 5.8 If the increment is defined as a new runway and associated terminal costs, this would probably seem a realistic basis to many. It leaves major issues to be settled (as discussed in Section 3 and below), but in principle, provided that prices charged at Stansted for the use of the new runway etc. bore a reasonable relation to prices charged for the use of the existing assets, it would allow price limits to be set for Stansted as a whole. 5.9 The third option for the definition of the increment would be the services provided by Stansted as a whole, including any new runway etc. regarded as necessary. This would involve estimating the cost of providing the existing services through the use of modern equivalent assets. It would have the advantage of explicitly treating the costs of any proposed new runway in the same way as those of existing assets, and like the previous option would avoid the need to use the historical RAB. In some respects, this approach would echo that used in many telecommunication applications of LRAIC. However, it would involve a major additional estimation exercise, the uncertainties in which would probably reduce the credibility of the result. 5.10 The provisional view is that CAA should concentrate on the application of the second of these options for the definition of the increment, and turn to the third only if problems with the second appear insurmountable. 5.11 Within the increment of a very large increase in capacity at the existing airport, there remain various possibilities of how exactly the increment should be specified. The increment could be defined as a runway, or a run way and increased terminal capacity (with associated infrastructure). These relate to assumptions to be used in cost and demand forecasting, as well as design of the investment which we return to below. 27 Recommendations Timescale of LRAIC estimation 5.12 The definition of “long run” in this context does not mean an infinitely long period. Practical estimations need to be made; and there is a point beyond which future uncertainties would be irrelevant. The practical requirements include avoiding distorting investment decisions, including in a possible new runway etc. that would have a long but it may be assumed finite life. This suggests a timeframe of 40 to 50 years. 5.13 If such a timeframe is used, the assumptions made about long- run economic trends in matters such as technological advance, and relative input prices, will have a large influence and will need careful thought. 5.14 The LRAIC estimate would be applied in a regulatory setting in which price limits are set for five years at a time, and within Q5 the price control may not be binding. The implications of this are also discussed below, in considering the application of LRAIC estimates in price controls on Stansted. Basis of engineering and other input assumptions 5.15 The absence of any consensus between BAA and the airlines using Stansted means that difficult issues are involved in deciding the basis for engineering and other cost assumptions. Several questions arise, and a number of options may be considered. 5.16 First, it will be necessary to make a reasonably clearly specified and practical definition of the runway and associated facilities whose costs are to be estimated, including quality as well as capacity. In order to do this, BAA could be asked for its view of the type and size of facilities most likely to be a successful investment. Alternatively, CAA could make its own estimates, informed by consultation with both the airlines and with BAA. Thirdly, in theory the task could be sub-contracted to expert advisers. The guiding principle is the investment plan that would be adopted by an efficient supplier, expecting to be able to charge competitive prices but not expecting to be able to abuse any position of dominance or substantial market power. 5.17 Secondly, the basis for the cost estimates will need to be decided. Again, the possible sources include BAA estimates, and independent (but inevitably in some respects probably less well-informed) assessments from outside the company. 5.18 The provisional view taken here, with regard both to the specification of the new runway etc and with regard to its likely costs, is that CAA will have to be responsible for settling the assumptions to be used. In both cases, BAA’s views should be fully considered, but weight should also be given to independent assessments. However, these assumptions should be put in context. Whilst they determine the level of the price cap they do not define what must be built by the airport operator. 5.19 CAA would also need to take responsibility for economic assumptions such as the rate of improvement to be assumed in operating cost efficiency, any important relative price 28 Recommendations assumptions, and the cost of capital, again taking account of the views of BAA and others concerned. Demand assumptions and LRAIC calculation 5.20 A similar approach will be needed to the demand assumptions to be used. Long term forecasts from the Department for Transport and others can be used up to a point, but ad hoc analysis would also be needed. Again, it should be envisaged that the regulator would ultimately decide on the forecasts to be used, having consulted with interested parties. 5.21 When the costs of the increment have been estimated, and divided by the forecast numbers of passengers, the LRAIC per passenger will have been estimated. Allowing for expected commercial revenues it would be of the form of the average charge per passenger that, over the very long term, would be required to justify the investment in a competitive context. In the context of an increment based on a forward looking investment plan over some time horizon (AIC approach), at a very high level the calculation would be of the form: LRAIC = 5.22 Sum of the present value of net costs forecast over the investment horizon Sum of the present value of number of passengers over the investment horizon Calculation of the present value of net costs requires: (a) Estimate of expected costs to be incurred in each year of the estimation period (capital and operating expenditure, and financing costs), in constant prices. (b) Estimate of expected net commercial and freight revenues in each year of the estimation period, in constant prices. (c) Subtracting (b) from (a) to gain the net expected cost in each year of the estimation period. (d) Estimate of the cost of capital, used as the discount rate to express the result in (c) in present value terms. 5.23 Calculation of the present value of the number of passengers requires the expected passenger numbers for each year of the estimation period, discounted using the cost of capital to express the volume in present value terms. 5.24 The overall result, therefore, is the long run incremental cost, averaged over the expected number of passengers. It need hardly be said, but should be underlined, that a large margin of uncertainty will attach to the estimate, and due allowance would need to be made for this in the light of sensitivity analyses. 29 Recommendations Application of the LRAIC estimate in Options 4 and 5 5.25 It remains to consider the application of the LRAIC estimate for both the PPC and MLPC options. 5.26 The essential difference between the two options was set out in Section 2, above. Chart 2.2 is reproduced here for convenience. Chart 2.2 [copied from above]: Drawing the difference between Options 4 & 5 Price PPC MLPC LRAIC competitive price path Time 5.27 To recapitulate briefly, the difference between the two approaches is taken to be that the long run MLPC would be somewhat above the LRAIC estimate, to reflect: uncertainties in estimation; uncertainties about the likelihood that Stansted will experience a period in which it has significant market power; and the need to maintain investment incentives under a price cap that prevents prices rising to the full extent implied by the path of competitive prices. 5.28 The stronger the expectation that Stansted would have substantial market power, the more assurance the regulator would have in preventing excessive charges through applying MLPC rather than PPC limits. 5.29 The regulatory argument for using PPC limits is that, for suppliers without market power, periods of strong demand and high returns are likely to be balanced by weaker periods. A regulatory intervention that prevented prices from rising to these peak levels would have a serious adverse effect on the overall returns that would be expected from investment. 30 Recommendations Application of LRAIC estimate in setting MLPC 5.30 An allowance will be needed for expected commercial revenues in setting either MLPC or PPC, since a single till approach is assumed. 5.31 The MLPC could be based on the LRAIC, as an approximation to the long term average of the maximum that Stansted would be able to charge in a competitive market. Due allowance for uncertainties would need to be made. Provisions for rolling forward underor over- charging in relation to the long run average would be employed within and between price control periods. 5.32 CAA has to set price limits for each five year period, whereas the LRAIC estimate would be relevant to, say, a 40 year period. If in some periods Stansted were not able to charge up to the limit, but in others it would have been able to charge more, then the application of the LRAIC as a limit in each period would risk preventing the investment being justified. As discussed in Section 3, this would be particularly pertinent if the LRAIC is calculated on the basis of new runway and associated terminal investment in a truly forward looking manner. 5.33 This problem might be resolved or alleviated if CAA were to make credible commitments relating to the whole period. The consultation document discusses some ways in which this might be done. The CAA is limited in its ability to commit its successors, but use might be made of regulatory policy statements. 5.34 It would in any case not seem desirable to consider annual application of the MLPC price cap set at a level that was close to LRAIC, due to the fact that the short term movements in the market price should be permitted within the cap. Within any five year period, there should be maximum flexibility with clear provision for carry forward of pricing allowances unused in any year. Application of LRAIC estimate in setting PPC 5.35 Considering the PPC option, the question arises; how much above the long term average market price should the precautionary price cap be set? The competition case review in Section 4 indicates that the competition authorities would be likely to allow significant margins over the long term cost level, before a price is deemed excessive. They would also be likely to take into account the charges being levied at other airports. 5.36 In the case of the airports, relatively short term movements in price could arise due to demand fluctuations with capacity being fixed; either longer term fluctuations from one year to the next, seasonal fluctuations, or, in the very short term, daily peak and off-peak variance. The ratios between charges over time, and between peak and average charges, may provide an indication of the ratio between the LRAIC and the price that might be regarded as excessive by the competition authorities. 5.37 As such ratios will vary, the approach would be to tabulate a set of such ratios and review how and why they vary (over time, between airports, between time frames – daily, 31 Recommendations seasonal, etc) in order to draw from them a ratio that could be applied to the LRAIC average to derive the PPC. Process at successive periodic reviews 5.38 There could be an issue about revisions to the input assumptions used in the LRAIC estimates over time and between different price control periods (if a five year price control period remains in place). The basic input assumptions about design and costs might be reviewed every five years, as usual in price reviews. This would have the effect of increasing the LRAIC until the point of investment, and would be desirable in terms of efficiency of the signal to competitors and the incumbent operator. However, as the CAA’s discussion document suggests, this would need to be done in a way that avoided reopening the basis on which the LRAIC had been estimated in a way that would amount to a disincentive to investment. 5.39 It will also be necessary to explain the relation between the LRAIC-based price limits and accounting returns. If market conditions improve so that charges at Stansted can be increased in the course of Q5, this will result in improved returns to the existing assets. An increase in returns in the period before an investment is what would be expected in a competitive situation. 5.40 The following table summarises the main information requirements of the alternative approaches to the estimation of LRAIC as the basis for the legally-required price control at Stansted. 32 Recommendations Table 5.1: Comparison of information requirements MLPC PPC Traditional RAB-based building block method Demand forecasts Yes Yes Yes Capex plans (design and costs) Yes Yes Yes Opex projections Yes Yes Yes LRAIC estimation (a) Increment defined by new investment MEA of existing assets No No No (but RAB estimation) Cost of capital Yes Yes Yes Yes Yes No Relationship between average and maximum likely competitive price No Yes No Consideration of carry-forward of regulatory commitments between price control periods Yes (important) Yes Yes (b) Increment is airport as a whole including new investment As above, except: MEA of existing assets Application to price control 33 Appendix 1: LRAIC — Regulatory Precedents APPENDIX 1: LRAIC — REGULATORY PRECEDENTS Use of LRAIC in Other Sectors Telecoms A1.1 The telecommunications sector provides many examples of LRAIC use in setting price controls — it has been used to set access prices in both Europe and the USA, and has become the dominant cost standard approach used in telecoms regulation. The European Commission has recommended the use of ‘forward looking’ LRAIC for the assessment of cost oriented interconnection tariffs, as it “is most compatible with competitive market”. This recommendation has been confirmed in a subsequent study carried out by Europe Economics. The concept has also been used in estimation of limits to be applied to charges for call termination. A1.2 The use of forward-looking LRAIC in the telecoms regulation has been predicated on the desire to send efficient ‘build-or-buy’ signals to potential entrants (i.e. to send efficient signals on whether an entrant should buy access to the incumbent‘s network, or build its own alternative networks). These signals are particularly important in the telecoms industry due to potential for new network technologies to emerge that might challenge the essential facility status of incumbent networks. They are also clearly important in the case of airports in the South East of England. Energy A1.3 Unlike in telecoms, in the energy sector LRAIC estimates have been used mostly to structure charges calculated on standard building block approach, rather than to set the actual level of charges. For example, according to the National Grid’s most recent Statement of the Use of System Charging Methodology, charges are calculated on an incremental cost basis rather than on average costs so as to promote the optimal use of and investment in the transmission system. 8 A1.4 The reason given is that efficient economic signals are provided to users when services are priced to reflect the incremental costs of supplying them. Therefore, charges should reflect the impact that users of the transmission system at different locations would have on the Transmission Owner's costs, if they were to increase or decrease their use of the respective systems. Water9 A1.5 8 9 Ofwat has considered that use of long run marginal cost (LRMC) can help to achieve: National Grid (April 2008): “The statement of the use of system charging methodology” http://www.nationalgrid.com/NR/rdonlyres/BC5D87D0-4682-4C56-9375-7B932A1BD726/24475/UoSCMI4R0FINAL.pdf MD 159 and MD 170. Note that the examples from the water industry quoted here all use the concept of forward looking average incremental costs (unit costs of a future investment program) to calculate what is referred to by them as LRMC. 34 Appendix 1: LRAIC — Regulatory Precedents (a) more cost-effective use of existing assets; (b) least cost investment in new assets to balance supply and demand; and (c) conditions to ensure that entry into the market for water services is beneficial to customers. A1.6 Ofwat considers that volumetric rates should reflect LRMC as closely as possible to provide appropriate incentives to promote economy in the use of water. Ofwat has further considered the role of LRMC estimates to include: (a) To signal about opportunities for bulk supplies for cross-border trading of water. (b) Forming a basis of assessment of avoidable costs in charging access to incumbent networks for common carriage, as LRMC should approximate the (long term) savings made by an incumbent as a result of not having to supply water or sewerage services. (c) Guiding long term water resource planning. (d) Providing a benchmark to assess company leakage targets. A1.7 Ofwat has also used LRMC in its evidence to the Competition Appeals Tribunal (CAT) in the Albion case, where demand was expected to rise so that the relevant part of the network was close to capacity; it was argued that LRMC would give appropriate signals of the opportunity cost of providing third party access. A1.8 The Canadian Water and Wastewater Authority uses LRMC not to set the overall price control, but as a basis of the volumetric charge that has the objective to encourage efficient use of water and financial resources (there is a fixed charge also to ensure total cost recovery). A1.9 In Australia the Queensland Competition Authority considers that the volumetric charges in two part tariffs should be set using LRMC. Regulatory Precedent on Increment A1.10 The CAA preferred the ‘perturbations’ approach in 2001, using a comparison of capacity expansion to a modified “do-minimum” case. The increment was large enough that it might be considered an application of the AIC rather than the MIC method. The CAA chose its preferred increment as the one it considered provided the best measure of incremental costs and incremental outputs — a forward looking investment program to deliver a substantial capacity increase. A1.11 In telecommunications the norm has been to measure the costs of large service - based increments (namely the core and access networks) where part of the common interincrement costs are also allocated to the regulated services. 35 Appendix 1: LRAIC — Regulatory Precedents A1.12 In the water sector, following responses to MD 170, Ofwat required LRMC estimates of the water companies to be based on the AIC method only. Ofwat did, however, note that the MIC approach could be relevant if companies are anticipating significant changes due to competition, bulk supplies, or changes to levels of service. A1.13 In the energy sector at least three different variations of the increment have been used: (e) The direct current load flow (DCLF) investment cost related pricing (ICRP) transport model in the UK electricity sector calculates the marginal costs of investment in the transmission system that would be required as a consequence of an increase in demand or generation at each connection point or node on the transmission system. This is based on a study of peak conditions on the transmission system.10 The increment is measured as a variation in demand of 1MW. The methodology is closest to the MIC approach. (f) In the New South Wales electricity sector, the increment is based on new generation capacity (as opposed to the inclusion of existing installed capacity). The increment considered was a substantial factor of the existing load. This is closer to the AIC approach. 11 (g) In the setting of the UK gas transmission network, incremental entry capacity means capacity in excess of the volume of obligated entry capacity determined in accordance with paragraph 14(5)(g) of part 2 of Special Condition 28B of Transco’s gas transmission license. Increments of varying sizes have been used, but in general the methodology seems most in line with the AIC approach above.12 A1.14 In relation to the water sector in Australia, the QCA defines the increment as the next most economically efficient discrete augmentation possible. This also seems to be in line with the AIC approach. Regulatory Precedent on Time Period A1.15 In the water sector, Ofwat specified in Report C of MD170 that the time period over which LRMC should be conducted to be the lifetime of an investment plan. The reason given by Ofwat for this was the saw tooth effect described in Section 3. The consideration of the whole lifetime of the investment plan alleviates the saw-tooth effect in the sector, as the horizon includes several equal investments (the investment is “indivisible”, rather than “lumpy” in the sense of an airport investment). Indeed, Ofwat noted that the planning horizon used by companies varies between 10 and 50 years and recommended that, in 10 11 12 See “The Statement of the Use of System Charging Methodology, April 2008” See “The long run Marginal cost of Electricity Generation in New South Wales A Report to the Independent Pricing and Regulatory Tribunal February – 2004” See “Incremental Entry Capacity Release Statement”, October 2002. 36 Appendix 1: LRAIC — Regulatory Precedents their LRMC calculations, companies used a horizon of at least 25 years as this time period is consistent with the water resource plans. A1.16 In the energy sector, the definition of the long run ranges between 10 and 30 years. A1.17 In telecoms regulation, as the definition of the increment used in the sector includes all assets used in providing the service, recalculated periodically, the time period considered is the assumed asset life of the service increments. Regulatory Precedent on Basis of Costs A1.18 In the telecommunications sector, Oftel (now Ofcom) considered two principal methods of estimating forward-looking costs: a bottom-up approach which used an engineering economic model reflecting best practice, and a top-down approach using BT’s management and financial data as the starting point. Oftel then reconciled the results of the two models and produced a hybrid figure. The models considered two increments; core and access. A1.19 Regarding mobile termination, Oftel began in 2000 a review of competition in the market. During the review, Oftel also met mobile and fixed operators to discuss the calculation of mobile charges based on LRIC. Oftel concluded that the target charges for 2005/2006 should be based on LRIC figures on which equal proportionate mark-up is applied to allocate common costs and an estimate of the value of network externalities is added on the resulting figure. A1.20 In the energy sector, users who are Generators or Interconnector Asset Owners provide to National Grid a forecast for the following Financial Year of the highest Transmission Entry Capacity (TEC) applicable to each Power Station or Interconnector for that Financial Year. For the Financial Year 2008/9 Scottish Generators or Interconnector Asset Owners provide to National Grid a forecast of the equivalent highest ‘export’ capacity figure. A1.21 Users who are owners or operators of a User System (e.g. distribution companies) provide a forecast for the following Financial Year of the Natural Demand attributable to each Grid Supply Point equal to the forecasts of Natural Demand under both Annual Average Cold Spell (ACS) Conditions and a forecast of the average metered Demand attributable to such Grid Supply Point for the National Grid Triad. A1.22 If no data are received from the User, then National Grid will use the best information available for the purposes of calculation of the TNUoS tariffs. This will normally be the forecasts provided for the previous Financial Year. A1.23 In the water sector, the LRMC estimates are based on companies’ forecasts of demand and estimates of the investment costs required to maintain supply-demand balance. 37 Appendix 2: Reviewed Competition Cases APPENDIX 2: REVIEWED COMPETITION CASES A2.1 We reviewed the final decision documents of the following cases with the view of extracting out the definitions of excessive prices, and any comments on the tests and data used to determine whether a price is excessive or not. (h) General Motors Continental NV (1976) (i) United Brands (1978) (j) Sacem (1987) (k) Scandlines v Port of Helsingborg (2004) (l) Deutsche Telekom (1997) (m) Deutsche Post AG – Interception of Cross border Mail (2002) (n) Alpha Flight Services/Aéroports de Paris (1998) (o) Deutsche Grammophon v. Metro (1971) (p) Aeroportos e Navegacao Aerea (1999) (q) Frankfurt Case (1998) (r) Ilmailulaitos/Luftfartsverket (1999) (s) AtTheRaces Vs British Horseracing Board (2007) (t) Napp Pharmaceuticals (2001) (u) Albion Water v. Water Services Regulatory Authority (2006) (v) Veraldi-Alitalia (2000) (w) Verengingg Vrije Vogel v. KLM and Stweart v. KLM (2000) 38
© Copyright 2026 Paperzz