SEMCOM
Page 1 of 31
CHARUTAR VIDYA MANDAL’S
SEMCOM
VALLABH VIDYANAGER
Faculty Name: Dr. Kamlesh Vaishnav
Class: T.Y.B.C.A.
Subject: Operation Research
Topic: Study Material
Date: 22-06-2015
UNIT – 4
1. Project Scheduling in PERT/CPM
2. Sequencing Problems
3. Dynamic Programming
1. Project Scheduling in PERT-CPM
Introduction
A project defines a combination of interrelated activities which must be executed in a
certain order before the entire task can be completed. The activities are interrelated in
a logical sequence in such a way that some activities cannot start until some others are
completed. An activity in a project is usually viewed as job requiring time and
resources for its completion.
Until recently, planning was seldom used in the design phase. As the technological
development took place at a very rapid speed and the designs become more complex
with more inter-departmental dependence and interaction, the need for planning in the
development phase become inevitable.
Until five decades ago, the best known ‘planning tool’ was the so called Gantt Bar
Chart (GBC) which specifies the start and finish times for each activity on a
horizontal time-scale. The disadvantage of Gantt Chart (GBC) is that the
interdependency between different activities (that mainly controls the progress of the
project) cannot be determined from the bar chart (GBC). Growing complexities of
modern projects have demanded more systematic and effective planning techniques
with the objective of optimizing the efficiency of executing the project. Efficiency
implies effecting the utmost reduction in the time required to complete the project
while accounting for economic feasibility of using available resources. Project
Management has evolved as a new field with the development of two ‘analytic’
techniques for planning, scheduling and controlling of projects. These are the Critical
Path Method (CPM) and the Project Evaluation and Review Technique (PERT).
SEMCOM
Historical Development of CPM / PERT Techniques
Page 2 of 31
In 1956-58, above two techniques were developed by two different groups almost
simultaneously. CPM was developed by Walker from E. L. du pont de Nemours
Company to solve project scheduling problems and was later extended to a more
advanced status by Mauchly Associates. During the same time, PERT was developed
by the team of engineers working on the Polar’s Missile Programme of US Navy.
This was a large project involving many departments and there were many activities
about which they had a very little information about the duration of the project.
Under such conditions, the project was to be completed within a specified time. To
coordinate activities of various departments, this group used PERT and devised the
technique independent of CPM.
The methods are essentially network-oriented techniques using the same principle.
PERT and CPM are basically time-oriented methods in the sense that they both lead
to the determination of a time schedule for the project. The significant difference
between two approaches is that the time estimates for the different activities in CPM
were assumed to be deterministic while in PERT these were described
probabilistically. Now-a-days, PERT and CPM actually comprise one technique and
the differences, if any are only historical. Therefore, these techniques are referred to
as ‘project scheduling’ techniques, and together called PERT/CPM.
Applications of PERT / CPM Techniques
These methods have been applied to a wide variety of problems in industries and have
found acceptance even in government organizations.
These include:
(i)
Construction of a dam or canal system in a region,
(ii)
Construction of a building or highway,
(iii)
Maintenance or overhaul of airplanes or oil refinery,
(iv)
Space flight,
(v)
Cost control of a project using PERT / COST,
(vi)
Designing a prototype of a machine,
(vii) Development of supersonic planes.
Network Diagram Representation
In point project scheduling; the first step is to sketch an arrow diagram which shows
inter-dependencies and the precedence relationship among activities (as defined
SEMCOM
Page 3 of 31
below) of the project. Certain basic definitions used in a network representation of a
project are given below.
1.
Activity
Any individual operation, which utilizes resources and has an end and a beginning, is
called activity. An arrow () is commonly used to represent an activity with its head
indicating the direction of progress in the project (See Figure-4). These (activities)
are usually classified into following four categories:
(i)
Predecessor activity
Activities that must be completed immediately prior to the start of
another activity are called predecessor activities.
(ii)
Successor activity
Activities that cannot be started until one of more of other activities are
completed, but immediately succeed them are called successor
activities.
(iii)
Concurrent activity
Activities which can be accomplished concurrently are known as
concurrent activities. It may be noted that an activity can be a
predecessor or successor to an event or it may be concurrent with one
or more of the other activities.
(iv)
Dummy activity
An activity which does not consume any kind of resource but merely
depicts the technological dependence is called a dummy activity.
It may be noted that the dummy activity is inserted in the network to
clarify the activity pattern in the following two situations:
(i)
(ii)
to make activities with common starting and finishing points
distinguishable, and
to identify and maintain the proper precedence relationship
between activities that are not connected by events.
For example, consider a situation where A and B are concurrent
activities, C is dependent on A, and D is dependent on A and B both.
Such a situation can be handled by using a dummy activity as follows
(Figure – 1).
SEMCOM
Page 4 of 31
Figure – 1
In another situation, consider the following diagram where job B and C
have the same job reference and they can be started independently on
completion of A. But, D could be started only after completion of B
and C. This relationship is shown by the dotted line (Figure – 2).
Figure – 2
2.
Event
An event represents a point in time signifying the completion of some
activities and the beginning of new ones. This is usually represented by a
circle ‘O’ in a network which is also called a node or connector.
The events can be further classified into following three categories (as shown
below in the Figure – 3).
(i)
Merge event
When more than one activity comes and joins an event, such event is
known as merge event.
(ii)
Burst event
SEMCOM
Page 5 of 31
When more than one activity leaves an event, such event is known as a
burst event.
(iii)
Merge and burst event
An activity may be a merge and burst event at the same time as with
respect to some activities it can be a merge event and with respect to
some other activities it may be a burst event.
Figure – 3
Figure – 4
Remarks:
1. An event is that particular instant of time at which some specific part of a
project has been or is to be achieved. An activity is actual performance of a
task. An activity requires time and resources for its completion.
Examples of events: design completed, pipe line laid, etc.
Examples of activities: assembly of parts, mixing of concrete, preparing
budget, etc.
2.
Events are described by such words as: completed, started, issued, approved,
tested, etc.
While the words like: design, procure, test, develop, prepare etc. shows that
work is being accomplished and thus represent activities.
SEMCOM
Page 6 of 31
3.
While drawing networks, it is assumed that (i) time flows from left to right,
and (ii) head events always have number higher than that of tail event. Thus
activity (i – j) always means that the job which begins at event ‘i’ is completed
at event ’j’. Because i is the head event and j is the tail even in the activity
(ij).
4.
Network representation is based on the following two axioms:
(i)
An event is not said to be complete until all the activities flowing into
it are completed.
(ii)
No subsequent activity can begin until its tail event is reached or
completed.
Rules for Drawing Network Diagram
Rules for drawing network diagrams are summarized as follows:
Rule 1
Each activity is represented by one and only one arrow in the
network
This implies that no single activity can be represented twice in the
network. This is to be distinguished from the case where one activity
is broken into segments. In such a case, each segment may be
represented by a separate arrow. For example, in laying down a pipe,
this may be done in sections rather than as one job.
(a)
(b)
Figure – 5
SEMCOM
Rule 2
Page 7 of 31
No two activities can be identified by the same end events
For example, activities a and b (Figure – 5(a)) have the same end
events. The procedure is to introduce a dummy activity either between
a and one of end events or between b and one of the end events.
Modified representations after introducing the dummy d are shown in
Figure – 5(b). As a result of using the dummy d, activities a and b can
now be identified by unique end events. It must be noted that a
dummy activity does not consume any time or resources.
Dummy activities are also useful in establishing logic relationship in
the arrow diagram which otherwise cannot be represented correctly.
Suppose jobs a and b in a certain project must precede the job c. On
the other hand, the job e is preceded by the job b only. Figure – 6 (a)
shows, the incorrect way since, though the relationship between a, b
and c are correct, the diagram implies that the job e must be preceded
by both the jobs a and b. The correct representation using the dummy
activity d is shown in Figure-6 (b) that shows/justifies the indicated
precedence relationships clearly.
Figure – 6
Rule 3
In order to ensure the correct precedence relationship in the arrow
diagram, following questions must be checked whenever any
activity is added to the network.
(i)
What activity must be completed immediately before this
activity can start?
SEMCOM
Page 8 of 31
(ii)
(iii)
What activities must follow this activity?
What activities must occur simultaneously with this activity?
A few important suggestions for drawing good networks are given
below:
Suggestions:
If two or more individuals draw the same network for a given project, it seldom
happens that some of them will look alike. As a matter of fact, no two of them may
even look similar. The reason is that there are many ways to draw the same network.
However, there will be same network representation drawn from above set of rules
which are much easier to follow than the other. In the case of a large network, it is
essential that certain ‘good habits’ be practiced to draw an ‘easy to follow’ network.
(1)
(2)
(3)
(4)
(5)
(6)
Try to avoid arrows which cross each other.
Use straight arrows.
Do not attempt to represent duration of activity by its arrow length.
Use arrows from left to right (or right to left). Avoid mixing two directions.
Vertical (standing) arrows may be used if necessary.
Use dummies freely in rough draft but final network should not have any
redundant dummies.
The network has only one entry point – called the start event and one point of
emergence (coming out) – called the end event.
In many situations, all these may not be compatible with each activity and some of
them are violated. The idea of having a simple network is to facilitate easy reading
for all those who are involved in the project.
Common Errors in Drawing Networks
Three types of errors are most commonly observed in drawing network diagrams.
(1)
Dangling
To disconnect an activity before the completion of all activities in a network
diagram is known as dangling. As shown in the Figure – 7, activities (5-10)
and (6-7) are not the last activities in the network. So the diagram is wrong
and indicates the error of dangling.
SEMCOM
Page 9 of 31
Figure – 7: Dangling Error Diagram
(2)
Looping (or Cycling)
Looping error is also known as cycling error in a network diagram. Drawing
an endless loop in a network is known as an error of looping as shown in the
following figure (Figure – 8).
Figure – 8: Looping (or Cycling) Error Diagram
(3)
Redundancy
Unnecessarily inserting the dummy activity in a network logic is known as the
error of redundancy as shown in the following diagram (Figure – 9).
SEMCOM
Page 10 of 31
Figure – 9 : Redundancy Error
LABELLING: FULKERSONS’S ‘I-J’ RULE
For the network representations, it is necessary that various nodes be properly labeled.
For convenience, labeling is done on the network diagram. A standard procedure,
called the ‘I-J’ rule developed by D.R. Fulkerson, is most commonly used for this
purpose. Main steps of this procedure are:
(a)
A start event is the one which has arrows emerging from it but none entering
it. Find the start event and number it as unity (1).
(b)
Delete all arrows emerging from all numbered events. This will create at least
one new start event out of preceding events.
(c)
Number all new start events ‘2’, ‘3’, and so on (no definite rule is necessary,
but numbering from ‘top to bottom’ may facilitate other users in reading the
network when there are more than one new start events.
(d)
Go on repeating steps number (b) and (c) until the end is reached.
Now consider the network diagram of Figure – 10for ‘labelling’ by Fulkerson’s rule.
Figure – 10 : Activity duration on the network
SEMCOM
Page 11 of 31
Figure – 11
To number the nodes using Fulkerson’s rule, numbering of nodes 1 and 2 is obvious.
Apply step 2. The bottom node is the only ode from jobs which is emerging out but
none entering it. This is number 3.
Figure – 12
Applying step 2 again, node number 4 is easily obtained and likewise 5 can also be
determined.
Using step 2 again, there are two starting points, and either one of them could be
numbered 6. Keeping in view the case of numbers 4, 5 and 6 all in a row, the top
mode is numbered 6. Rest of the numbering procedure is simple and the complete
network with numbers is shown in Figure – 13.
SEMCOM
Page 12 of 31
Figure - 13
The importance of good numbering procedure can hardly be claimed in a simple
network, but the Fulkerson’s procedure has certain distinct advantages when the
network is large. First, the Fulkerson’s procedure will always detect a close loop in
the network if there is any. In network methods, a close loop represents an impossible
event. Second, numbers are smaller toward the start side and become larger on the
end. A third advantage will become apparent when a matrix representation of the
network is brought for computerization.
Forward Pass Computations (For Earliest Event Time)
Before starting computations, the occurrence time of initial network event is fixed.
Then, the forward pass computation yields the earliest start and earliest finish time
for each activity (i, j), and indirectly the earliest expected occurrence time for each
event. This is mainly done in three steps.
Step 1
The computations begin from the ‘start’ node and move towards the
‘end’ node. For easiness, the forward pass computations start by
assuming the earliest occurrence time of zero for the initial project
event.
Step 2
(i)
Earliest starting time of activity (i, j,) is the earliest event time
of the tail end event i.e., (Es)ij = Ei.
(ii)
Earliest finish time of activity (i, j) is the earliest starting time +
the activity time i.e., (Ef)ij = (Es)ij + Dijor (Ef)ij = Ei+ Dij.
(iii)
Earliest event time for event j is the maximum of the earliest
finish times of all activities ending into that event. That is, Ej =
SEMCOM
Page 13 of 31
max [(Ef)ijfor all immediate predecessor of (i, j)] or Ej = max
i
i
[Ei + Dij]
The computed ‘E’ values are put over the respective circles representing each event.
Backward Pass Computations (For Latest Event Time)
The latest event times (L) indicates the time by which all activities entering into that
event must be completed without delaying the completion of the project. These can be
computed by reversing the method of calculation used for earliest event times. This is
done in the following steps:
Step 1
For ending event assume E = L. Remember that all E’s have been
computed by forward pass computations.
Step 2
Latest finish time for activity (i, j) is equal to the latest event time of
event j, i.e., (Lf)ij = Lj.
Step 3
Latest starting time of activity (i, j) = the latest completion time of (i, j)
– the activity time.
Step 4
Latest event time for event i is the minimum of the latest start time of
all activities originating from that event, i.e., Li = min [(Ls)ij for all
j
immediate successors of (i, j)] = min [(Lf)ij – Dij] = min [Lj – Dij]
j
l
The computed ‘L’ values are put over the respective circles representing each event.
Determination of Floats and Slack Times
When the network diagram is completely drawn, properly labelled, and earliest (E)
and latest (L) event times are computed as discussed so far, the next object is to
determine the floats and slack times defined as follows:
There are mainly following kinds of floats:
(1)
Total float
The amount of time by which the completion of an activity could be delayed
beyond the earliest expected completion time without affecting the overall
project duration time.
SEMCOM
Page 14 of 31
Mathematically, the total float of an activity (i – j) is the difference between
the latest start time and earliest start time of that activity. Hence the total float
for an activity (i – j), denoted by (Tf)ij, can be calculated by the formula: (Tf)ij
= (Latest start – Earliest start) for activity (i – j) or (Tf)ij= (Ls)ij – (Es)ijor (Tf)ij
= (Lj – Dij) - Ei.
This is the most important type of float because of concerning with the overall
project duration.
(2)
Free float
The time by which the completion of an activity can be delayed beyond the
earliest finish time without affecting the earliest start of a subsequent
(succeeding) activity.
Mathematically, the free float for activity (i, j), denoted by (Ff)ij, can be
calculated by the formula: (Ff)ij = (Ej – Ei) - Dij.
In other words, Free float for (i – j) = (Earliest time for event j – Earliest time
for event i) – Activity time for (i, j).
This float is concerned with the commencement of subsequent activity.
(3) Independent Float (Short Question: What is independent float?)
The amount of time by which the start of an activity can be delayed without effecting
the earliest start time of any immediately following activities, assuming that the
preceding activity has finished at its latest finish time.
Mathematically, independent float of an activity (i, j) denoted by (If)ij can be
calculated by the formula:
(If)ij = (Ej – Li) – Dij
The negative independent float is always taken Zero. This float is concerned with
prior and subsequent activities.
It can be observed that: Independent float <= Free Float <= Total Float
Remarks:
Floats are used to represent under-utilized resources and flexibility of the schedule.
Note that whenever a float in a particular activity is utilized, the float of other
activities would also change.
SEMCOM
Page 15 of 31
Remarks
1.
We know that (Tf)ij = (Lj – Ei) – Dij. But, Lj>Ej as latest event time is
always greater than or equal to the earliest event time. Therefore,
(Tf)ij> (Ej – Ei) – Dij or (Tf)ij> (Ff)ij. Hence for all activities, free float
can take values from zero up to total float, but it cannot exceed total
float.
2.
Free float is very useful for rescheduling the activities with minimum
disruption of earlier plans.
Determination of Critical Path
Before defining critical path, let us first discuss about the meaning of critical event
and critical activity.
Critical Event
Since the slack of an event is the difference between the latest and earliest event times,
i.e., slack(i) = Li – Ei, the events with zero slack times are called critical events.
In other words, the event (i) is said to be critical if Ei = Li.
Critical activity
Since the difference between the latest start time and earliest start time of an activity
is usually called as total float, the activities with zero total float are known as critical
activities.
In other words, an activity is said to be critical if a delay in its start will cause a
further delay in the completion date of the entire project.
Obviously, a non – critical activity is such that the time between its earliest start and
its latest completion dates (as allowed by the project) is longer than its actual
duration. In this case, non-critical activity is said to have a slack or float time.
Critical Path
SEMCOM
Page 16 of 31
The sequence of critical activities in a network is called the critical path.
The critical path is the longest path in the network from the starting event to ending
event and defines the minimum time required to complete the project.
By the term ‘path’ we mean a sequence of activities such that it begins at the starting
event and end at the final event. The length of a path is the sum of the individual
times of the activities lying on the path.
If the activities on critical path are delayed by a day, the project would also be
delayed by a day unless the times of the future critical activities are reduced by a day
by different means. The critical path is denoted by double or darker lines to make
distinction from the other non-critical paths.
Main features of critical path
The critical path has two main features:
(i)
If the project has to be shortened, then some of the activities on that path must
also be shortened. The application of additional resources on other activities
will not give the desired result unless that critical path is shortened first.
(ii)
The variation in actual performance from the expected activity duration time
will be completely reflected in one-to-one fashion in the anticipated
completion of the whole project.
The critical path identifies all critical activities of the project. The method of
determining such a path is explained by the following numerical example.
Example 1.Consider the following network where nodes have been numbered
according to the Fulkerson’s rule. Numbers along various activities represent the
normal time (Dij) required to finish that activity, e.g. activity (3) – (6) will take 5 days
(months, weeks, hours depending on the time units). For this project, we are
interested to find out the time it will take to complete this project. What jobs are
critical to the completion of the project in time, etc?
SEMCOM
Page 17 of 31
Figure - 14
Solution. For this, it is necessary to find out the earliest and the latest completion time
for each activity in the network. The earliest and the latest times are re-calculated by
using ‘forward pass’ and ‘backward pass’ computations, respectively.
To understand the procedure, we define:
Ei= the earliest expected occurrence time of event i,
Lj= the latest allowable event occurrence time for event j. This is the latest time by
which the event j must be started without increasing the project duration.
Dij= the expected duration to complete the activity i–j.
The solution now starts by the forward pass computation.
Step 1
Determination of Earliest Time (Ej): Forward Pass Computation
The purpose of the forward pass computation is to find out earliest start
times for all the activities. For this, it is necessary to assign some initial
value to the starting node 1. Usually this value is taken to be zero so
that the subsequent earliest time could be interpreted as the project
duration up to that point in question.
Rules for the computation are as follows:
Rule 1
Initial event is supposed to occur at time equal to zero, that is, E1= 0.
SEMCOM
Rule 2
Page 18 of 31
Any activity can start immediately when all preceding activities are
completed. The earliest time Ej for node j is given by Ej= max [Ei +
i
Dij], where i is the collection of nodes which precede node j.
Rule 3
Repeat step 2for the next eligible activity until the end node is reached.
Numerical Calculation:
Consider the network (Figure - 14) by assumption E1 = 0 and E2 = max [Ei + Di2].
i
For node 2, node 1 is the only predecessor and hence i = 1 contains only one element.
Therefore, E2 = E1 + D12 = 0 + 2 = 2.
Likewise, values of E3, E4, E5, and E6can be computed as:
E3 = E1 + D13 = 0 + 2 = 2, E4 = E1 + D14 = 0 + 2 = 2, E5 = E2 + D25 = 2 + 4 = 6, E6 =
E3 + D36 = 2 + 5 = 7.
Consider node 7, where there are three emerging entering activities, i.e., E7 = max (Ei
i
+ Di7),
The collection i consists of nodes 3, 4 and 6 that are preceding node 7. Therefore,
E7 = max [E3 + D37 = 2 + 8 = 10, E4 + D47 = 2 + 4 = 6,E6 + D67 = 7 + 0 = 7] = 10
E8 = max [E5 + D58 = 6 + 2 = 8, E6 + D68 = 7 + 4 = 11] = 11
E9 = max [E8 + D89 = 11 + 3 = 14, E7 + D79 = 10 + 5 = 15*] = 15
and E10 = E9 + D9,10 = 15 + 4 = 19.
From this computation, it can be inferred that this job will take 19 days to finish as
this is the longest path of the network. Activities along this longest path are: 1 – 3, 3 –
7, 7 – 9 and 9 – 10. This longest path is called the critical path. In any network, it is
not possible that there can be only one critical path. For example, if in the above
network let D36 = 6 days, then two critical paths exist having the same duration for
completion of project.
Step 2
Determination of Latest Time (Li): Backward Pass Computation
In forward pass computation, the earliest time when a particular
activity will be completed is known. It is also seen that some activities
are not critical to the completion of the job. The question, a manager
SEMCOM
Page 19 of 31
would like to ask is: Can their starting time be delayed so that the total
completion time is still the same? Such a question may arise while
scheduling the resources such as: manpower, equipment, finance and
so on. If delay is allowable, then what can be the maximum delay? For,
this is the latest time for various activities which is desired. The
backward pass computation procedure is used to calculate the latest
time the latest time for various activities. In the forward pass
computation, assignment E1 = 0 was arbitrary, likewise for the
backward pass computation, it is possible to assign the project terminal
event date on which the project should be over. If no such date is
prescribed, then the convention is of setting latest allowable time
determined in forward pass computation.
Rule 1
Set Li = Ei or Ts where Ts is the scheduled date for completion and Ei is
the earliest terminal time.
Rule 2
Li = min {Lj – Dij}, i.e. the latest time for activities is the minimum of
j
the latest time of all succeeding activities reducing their activity time.
Rule 3
Repeat rule 2until staring activity is reached.
Latest times for activities of the network are calculated below:
By rule 1, set L10 = 19. Applying rule 2, it is to determine L9, L8 and L7,
L9 = min {Lj – D9, j} = 19 – 4 = 15 for j = 10.
j
L8 = min {Lj – D8, j} = L9 – D8, 9 = 15 – 3 = 12.
j
(j contains only one node 9)
L7 = min {Lj – D7, j} = L9 – D7, 9 = 15 – 5 = 10.
j
(j contains node 9)
Now consider node 6. For this node, there are two succeeding activities, namely 6 – 8
and 6 – 7.
L7 D6, 7
Hence, L6 = min [Lj – D6, j] = min
= min
j ( 7, 8 )
L8 D6, 8
Similarly, L5 = L8 – D5, 8 = 12 – 2 = 10,
10 0 10
12 4 8 * = 8.
L4 = L7 – D4, 7 = 10 – 4 = 6
SEMCOM
Page 20 of 31
L6 D3, 6
L3 = min
= min
L7 D3, 7
853
10 8 2 * = 2, L2 = L5 – D2, 5 = 10 – 4 = 6
624
L1 = min [Lj – D1, j] = min 2 2 0 * = 0.
j ( 2, 3, 4 )
6 2 4
Figure - 15
The minimum value of L1 = 0 is no surprising result. Since, started with Li = Ei, it is
always possible to lave L1 = 0. If this is not so, it means that some error is made in
calculations of forward pass or backward pass values. Figure – 15 shows earliest and
latest times of each event.
Recall that path 1 – 3 – 7 – 9 – 10 was defined as the critical path of this network.
Along this path, it is observed that the latest and earliest times are the same implying
that any activity along this path cannot be delayed without affecting the duration of
the project.
Step 3
Computation of Floats
By definition, for the activity 8 – 9, the float is one day (L8 – E8 = 12 –
11 = 1). This float represents the amount by which this particular
activity can be delayed without influencing the duration of the project.
SEMCOM
Page 21 of 31
Also, by definition, free float, if any, will exist only on the activities
merge points. To illustrate the concept of free float, consider path 1 – 2
– 5 – 8 – 9, total float on activity 8 – 9 is one day and since this is the
last activity prior to merging two activities, this float is free float also.
Similarly, consider the activity 5 – 8 which has a total float of 4 days
but has only 3 days of free float because 1 day of free float is due to
the activity 8 – 9. If the activity 5 – 8 s delayed up to three days, the
early start time of no activity in the network will be affected.
Therefore, the concept of free float clearly states that the use of free
float time will not influence any succeeding activity float time.
If free float of any activity comes out to be negative, it is taken zero.
For example, independent float of (1, 2) = free float of (1, 2) – (L1 –
E1) = 0 – (0 – 0) = 0.
Step 4
To identify Critical Path
The earlier calculation shows that the path or paths which have zero
float are called the critical ones. If this logic is extended little further,
it would provide a guide rule to determine the next most critical path,
and so on. Such an information will be useful for managers in the
control of projects. In this example, path 1 – 3 – 8 – 9 – 10 happens to
be next to critical path; because it has float of one day on many of its
activities.
Latest
Activity Duration Earliest
(i– j)
(Dij)
Start Finish
Start
(4)
(5)
(1)
(2)
(3)
= (3) +
=(6)- (2)
(2)
1–2
2
0
2
4
1–3
2
0
2
0
1–4
2
0
2
4
2–5
4
2
6
6
3–6
5
2
7
3
3–7
8
2
10
2
4–7
4
2
6
6
5–8
2
6
8
10
6–8
4
7
11
8
7–9
5
10
15
10
Finish
Float
Total Free
(6)
6
2
6
10
8
10
10
12
12
15
4
0
4
4
1
0
4
4
1
0
0
0
0
0
0
0
4
3
0
0
SEMCOM
8–9
9 – 10
3
4
11
15
14
19
12
15
Start
Activity Duration
(i – j)
(Dij)
EarliestEi LatestLi
(1)
(2)
(3)
(4)
15
19
Finish
Earliest
LatestLj
Ej
(5)
= (3) +
(2)
(6)= (4)
+ (2)
Page 22 of 31
1
1
0
0
Float
Total
(7)
= (4) –
(3)
Free
(8)
= Ej –
Ei of
successive
activity
1–2
1–3
1–4
2–5
3–6
3–7
4–7
5–8
6–8
7–9
8–9
9 – 10
2
2
2
4
5
8
4
2
4
5
3
4
0
0
0
2
2
2
2
6
7
10
11
15
4
0
4
6
3
2
6
10
8
10
12
15
2
2
2
6
7
10
6
8
11
15
14
19
6
2
6
10
8
10
10
12
12
15
15
19
4
0
4
4
1
0
4
4
1
0
1
0
0
0
0
0
0
0
4
3
0
0
1
0
The method discussed earlier is easily adoptable on computers. In the case of small
networks, we can perform most of the calculations right on the diagram. In an event
that a person would like to use tableau format to find floats, etc, such methods are also
available. Table above summarizes float times and other information.
SEMCOM
Page 23 of 31
2. JOB SEQUENCING
Definition of Job Sequencing
Suppose there are 𝑛 jobs (1, 2, . . ., n), each of which has to be processed one at a time
at each of m machines A, B, C , . . . The order of processing each job through
machines is given. The time that each job must require on each machine is known.
The problem is to find a sequence among (𝑛!)𝑚 number of all possible sequences for
processing the jobs so that the total elapsed time for all jobs will be minimum.
Mathematically, let
𝐴𝑖 = time for job 𝑖 on machine A,
𝐵𝑖 = time for job 𝑖 on machine B,
T = time from start of first job to completion of the last job.
Then, the problem is to determine for each machine a sequence of
jobs𝑖1 , 𝑖2 , 𝑖3 ,. . . , 𝑖𝑛 , where (𝑖1 , 𝑖2 , 𝑖3 ,. . . , 𝑖𝑛 ) the permutation of the integers which
will minimize T.
PROCESSING 𝒏 JOBS THROUGH TWO MACHINES
The problem can be described as: (i) only two machines A and B are involved (ii)
each job is processed in the order AB, and (iii) the exact or expected processing time
𝐴1 , 𝐴2 , 𝐴3 , . . . , 𝐴𝑛 , ; 𝐵1 , 𝐵2 , 𝐵3 ,. . . , 𝐵𝑛 are known.
Processing times
𝐴𝑖
𝐵𝑖
1
𝐴1
𝐵1
2
𝐴2
𝐵2
Job (i)
3
𝐴3
𝐵3
..
..
..
..
..
..
n
𝐴𝑛
𝐵𝑛
Problem is to sequence (order) the jobs so as to minimize the total elapsed time T.
The solution procedure adopted by Johnson (1954) is given below.
JOHNSON’S ALGORITHM FOR 𝒏 JOBS 𝟐 MACHINES
Then Johnson’s iterative procedure for the determining the optimal sequence for an njob 2-machine sequencing problem can be outlined as follows.
Step1.
Examine the 𝐴𝑖 ′𝑠 and 𝐵𝑖 ′𝑠 for 𝑖 = 1, 2,. . . , 𝑛) and find out min[𝐴𝑖 , 𝐵𝑖 ].
Step2.
(i)
𝑖
(ii)
Step3.
(i)
If this minimum be 𝐴𝑘 for some𝑖 = 𝑘, do (process) the 𝑘 𝑡ℎ job first
of all. (as the given order is AB)
If this minimum be 𝐵𝑟 for some 𝑖 = 𝑟, do (process) the 𝑟 𝑡ℎ job last
of all. (as the given order is AB)
If there is a tie for minimum𝐴𝑘 = 𝐵𝑟 , process the 𝑘 𝑡ℎ job first of all
SEMCOM
Page 24 of 31
𝑡ℎ
and 𝑟 job in the last.
If the tie for minimum occurs among the𝐴𝑖 ′𝑠, select the job
corresponding to the minimum of 𝐵𝑖 ′𝑠 and process it first of all.
(iii) If the tie for minimum occurs among the𝐵𝑖 ′𝑠, select the job
corresponding to the minimum of 𝐴𝑖 ′𝑠 and process it in the last. Go
to next step.
Cross out the jobs already assigned and repeat steps 1 to 3 arranging the jobs
next to first of next to last, until all the jobs have been assigned.
(ii)
Step4.
The resulting ordering will minimize the elapsed time T.
Example
Consider the five jobs 1, 2, 3, 4, and 5 needs to be processed on two machines A and
B in the order AB. The time for processing each job on both the machines are give
below.
Processing Time (in Hours)
Job
1
2
3
4
5
Time for A
5
1
9
3
10
Time for B
2
6
7
8
4
Determine a sequence for five jobs that will minimize the elapsed time T. Calculate
the total idle time for the machines in this period.
Solution
Step-1: Mini [Ai, Bi] = 1 for A2. So, place A2 job first:
2
Step-4: Remaining Jobs are:
1
5
2
3
9
7
4
3
8
5
10
4
Step-1: Mini [Ai, Bi] = 2 for B1. So, place B2 job last:
2
1
Step-4: Remaining Jobs are:
3
9
7
4
3
8
5
10
4
SEMCOM
Page 25 of 31
Step-1: Mini [Ai, Bi] = 3 for A4. So, place A4 job at first empty position that is after
A2:
2
4
1
Step-4: Remaining Jobs are:
3
9
7
5
10
4
Step-1: Mini [Ai, Bi] = 4 for B5. So, place B5 job previous to last:
2
4
5
1
Thus the final sequence of jobs are
2
4
3
5
1
Minimum elapsed time corresponding to the optimal sequencing 2-4-3-5-1
Job Sequence
2
4
3
5
1
Machine – A
Time In
Time Out
0
1
1
4
4
13
13
23
23
28
Machine – B
Time In
Time Out
1
7
7
15
15
22
23
27
28
30
The idle time for machine – A: 28-30 (2 Hours)
The idle time for machine – B: 0-1, 22-23, 27-28 (3 Hours).
Hence, the Total elapsed time is 5 Hours.
Examples
In a machine shop 8 different products are being manufactured each requiring time on
two different machines A and B are given in the table below:
Product
1
2
3
4
5
6
7
8
Machine-A
30 45
15
20
80
120
65
10
Machine-B
20 30
50
35
35
40
50
20
Find an optimal sequence of processing of different product in order to minimize the
total manufactured time for all product. Find total ideal time for two machines and
elapsed time.
In a machine shop 6 different products are being manufactured each requiring time on
two different machines A and B are given in the table below:
Product
1
2
3
4
5
6
Machine-A
30
120
50
20
90
110
Machine-B
80
100
90
60
30
80
SEMCOM
Page 26 of 31
Find an optimal sequence of processing of different product in order to minimize the
total manufactured time for all product. Find total ideal time for two machines and
elapsed time.
In a printing shop 7 different books are printed and bounded on two different
machines A and B. Time required on two machines are given in the table below:
Product 1
2
3
4
5
6
7
Printing 3
4
8
3
6
7
5
Binding 8
6
3
7
2
8
4
Find an optimal sequence of processing of different product in order to minimize the
total manufactured time for all product. Find total ideal time for two machines and
elapsed time.
Assumptions in Sequencing Problem
Short Question:
Write down any two assumptions used for solving sequencing problem.
Answer (Write down any two)
1. No machine can process more than one operation at a time.
2. Each operation, once started, must be performed till completion.
3. A job is an entity, i.e. even though the job represents a lot of individual parts,
no lot may be processed by more than one machine at a time.
4. Each operation must be completed before any other operation, which it much
precede, can begin.
5. Time intervals for processing are independent of the order in which operations
are performed.
6. These is only one of each type of machine.
7. A job is processed as soon as possible subject to ordering requirements.
8. All jobs are known and are ready to start processing before the period under
consideration begins.
9. The time required to transfer jobs between machines is negligible.
SEMCOM
Page 27 of 31
3. DYNAMIC PROGRAMMING
Introduction
Dynamic programming is a mathematical technique dealing with the optimization of
multistage decision process. The word ‘programming’ has been used in the
mathematical sense of selecting an optimum allocation of resources, and it is
‘dynamic’ as it is particularly useful for problems where decisions are taken at several
distinct stages, such as every day or every week.
Richard Bellman developed this technique in early 1950 and invented its name.
Dynamic programming can be given a more significant name as recursive
optimization.
In dynamic programming, a large problem is split into small sub-problems each of
them involving only a few variables. This technique converts one problem of n
variables into n sub-problems (stages), each in one variable.
The optimum solution is obtained in an orderly manner starting from one stage to the
next, and is completed till the final stage is reached.
To convert a verbal problem into a multistage structure is not always simple, and
sometimes it becomes very difficult and even looks easy to apply. Recursion
equations are of standard nature and its computer program runs in a standard routine.
An important point is that – the problem of successive stages be treated separately
even though by the very nature of the problem these stages are dependent? The
answer of this question is based on ‘Bellman’s Principle of Optimality’ which is
stated in the following section.
Discrete and continuous, deterministic as well as probabilistic models can be solved
by this method. Thus dynamic programming method is very useful for solving
various problems, such as inventory, replacement, allocation, linear programming,
etc. A single constraint problem is relatively simple, but in the problem of more than
two constraints more complexities appear.
(i)
While solving the problem we use the concepts of stage and state. Moreover,
the problem is solved stage by stage and to ensure that suboptimal solution
does not result, we cumulated the objective function value in a particular way.
Working backwards, for every stage, we found the decisions in that stage that
SEMCOM
Page 28 of 31
will allow us to reach the final destination optimally, starting from each of the
states of the stage. These decisions could be taken optimally, without the
knowledge of how we actually reach the different states. This has been stated
as the “principle of optimality in dynamic programming literature.”
(ii)
State: The variable that links up two stages is called a state variable. At any
stage, the status of the problem can be described by the values the state
variable can take. These values are referred to as states.
(iii)
Stage: The points at which decisions called for are referred to as stages. Each
stage can be thought of having a beginning and an end. The different stages
come in a sequence, with the ending of a stage marking the beginning of the
immediately succeeding stage.
BELLMAN’S PRINCIPLE OF OPTIMALITY
Ideally, if an optimal solution is obtained for a system, any portion of it must be
optimal. This is called the “Bellman’s Principle of Optimality” on which the concept
of dynamic programming is based.
Short Question: State the “Bellman’s Principle of Optimality”
Answer: An optimal policy (set of decisions) has the property that whatever the initial
state and decisions are, the remaining decisions must constitute an optimal policy with
regard to the state resulting from the first decision.
Explanation: "...suppose that the fastest route from Los Angeles to Boston passes
through Chicago. The principle of optimality translates to the obvious fact that the
Chicago to Boston portion of the route is also the fastest route for a trip that starts
from Chicago and ends in Boston."
In my humble formulation: If you have found an optimal policy that takes you from A
to C by visiting B, you cannot find a policy for going from B to C that is better than
the B to C portion of your original A-B-C policy.
The problem which does not satisfy the principle of optimality cannot be solved by
the dynamic programming method.
Question: Shortest route problem
Answer: Given a road network and a starting node S, we want to determine the
shortest path to all the other nodes in the network (or to a specified destination node).
See Figure below.
SEMCOM
Page 29 of 31
This is a variation of Shortest Path Problem in Graph Theory.
In graph theory, the shortest path problem is the problem of finding a path between
two vertices (or nodes) in a graph such that the sum of the weights of its constituent
edges is minimized. Note that the graph can be directed. The weights on the links/arcs
are costs.
Figure: Shortest path (A, C, E, D, F) between vertices A and F in the weighted directed graph
The problem is also sometimes called the single-pair shortest path problem, to
distinguish it from the following variations:
The single-source shortest path problem, in which we have to find shortest paths
from a source vertex v to all other vertices in the graph.
The single-destination shortest path problem, in which we have to find shortest
paths from all vertices in the directed graph to a single destination vertex v. This can
be reduced to the single-source shortest path problem by reversing the arcs in the
directed graph.
The all-pairs shortest path problem, in which we have to find shortest paths
between every pair of vertices v, v' in the graph.
These generalizations have significantly more efficient algorithms than the simplistic
approach of running a single-pair shortest path algorithm on all relevant pairs of vertices.
Some of the most important algorithms for solving this problem are:
Dijkstra's algorithm solves the single-source shortest path problem.
SEMCOM
Page 30 of 31
Bellman–Ford algorithm solves the single-source problem if edge weights may be
negative.
A* search algorithm solves for single pair shortest path using heuristics to try to
speed up the search.
Floyd–Warshall algorithm solves all pairs shortest paths.
Johnson's algorithm solves all pairs shortest paths, and may be faster than Floyd–
Warshall on sparse graphs.
Viterbi algorithm solves the shortest stochastic path problem with an additional
probabilistic weight on each node.
Q: Introduction to Traveling Salesman Problem
A:
The Travelling
Salesman
Problem (TSP)
is
an NP-hard
(Nonin combinatorial optimization studied
in operations research and theoretical computer science.
deterministic Polynomial-time hard) problem
Given a list of cities and their pairwise distances, the task is to find the shortest
possible route that visits each city exactly once and returns to the origin city.
The problem can simply be stated as: if a traveling salesman wishes to visit exactly
once each of a list of m cities (where the cost of traveling from city i to city j is cij )
and then return to the home city, what is the least costly route the traveling salesman
can take?
The problem was first formulated as a mathematical problem in 1930 and is one of the
most intensively studied problems in optimization. It is used as a benchmark for many
optimization methods.
In the traveling salesman problem we wish to find a tour of all nodes in a weighted
graph so that the total weight is minimized. The traveling salesman problem is NPhard but has many real world applications so a good solution would be useful.
The idea of the traveling salesman problem (TSP) is to find a tour of a given number
of cities, visiting each city exactly once and returning to the starting city where the
length of this tour is minimized.
The standard or symmetric traveling salesman problem can be stated mathematically
as follows: Given a weighted graph G = (V, E) where the weight cij on the edge
between nodes i and j is a non-negative value, find the tour of all nodes that has the
minimum total cost. Currently the only known method guaranteed to optimally solve
the traveling salesman problem of any size, is by enumerating each possible tour and
searching for the tour with smallest cost. Each possible tour is a permutation of 123 . .
. n, where n is the number of cities, so therefore the number of tours is n!. When n
SEMCOM
Page 31 of 31
gets large, it becomes impossible to find the cost of every tour in polynomial time.
Many different methods of optimization have been used to try to solve the TSP.
Applications of the TSP
Scheduling Jobs on Machines
Controlling satellites, telescopes, microscopes, lasers...(Vehicle Routing)
Computing DNA Sequences
Designing Telecommunications Networks
Designing and testing VLSI circuits (Computer Wiring)
X-Ray Crystallography
Clustering Data Arrays
The Influence of the TSP
Operational Research
Discrete Mathematics
Theoretical Computer Science
Artificial Intelligence
Disclaimer
The study material is prepared by subject teacher 2015-2016. The basic objective
of this material is to supplement teaching and discussion in the classroom in the
subject. Students are required to go for extra reading in the subject through
library work.