Grid capacity constraints and the potential for nodal pricing SAPVIA Networking Event Corné van der Westhuizen 27 July 2016 Disclaimer The calculations presented are done at a high level and only for the purpose of framing an opinion. The results are preliminary and based on multiple assumption that need further refining. Question 1: Is there a grid connection block? Level 1: Substation Connection Capacity Data Source: Eskom 2022 GCCA, 2016 Level 1: Substation Connection Capacity Data Source: Eskom 2022 GCCA, 2016 Level 2: Area Transfer Limit Data Source: Eskom 2022 GCCA, 2016 Level 2: Area Transfer Limit Data Source: Eskom 2022 GCCA, 2016 Level 2: Area Transfer Limit per Substation Data Source: Eskom 2022 GCCA, 2016 Level 3: Corridor Transfer Limits ? Response to Question 1: Is there a grid connection block? 1. Yes, there are immediate constraints in the central Northern Cape. These constraints can be overcome by 2022, but will require significant transmission infrastructure investment by Eskom 2. Neighbouring areas currently still have large amounts of grid capacity available both at a substation and area transfer limit level. There is thus a grid connection block, but only in the [available] highest resource areas Question 2: Can lower yields be offset by savings on transmission losses and the cost of new transmission infrastructure? For simplicity this analysis will focus on Solar PV technology Solar PV Yields kWh/kWpeak/annum Data Source: GEOModel Solar, 2013 Freely available from DEA Solar PV Yield Variances Data Source: Own interpretation of GEOModel Solar, 2013 Single Axis Tracker Solar PV Yield Variances with Area Transfer Limits 2015 Data Source: Eskom 2022 GCCA, 2016 and own interpretation of GEOModel Solar, 2013 Assumptions Transmission losses • Losses in the transmission network vary between 3 – 10%, depending on the length and loading of lines. The average losses for the entire transmission network is 3.2%. • One can assumed approximately 5% losses from remote (500 – 1000 km from major load centres) highest solar resource areas on a constrained grid. With next best resource areas being half the distance to major load centres these losses can probably be reduced the 2.5% - thus a 2.5% saving New transmission infrastructure costs • For every 600 - 1000 MW generation added in the remote high resource areas an additional 500 1 000 km 400kV line at a cost of R 4 - 6 Mil/km (excluding substations) needs to be built. • At an average cost of 5 Mil/km for a 750 km line that can transmit 800 MW, it translates to R 350 Mil per 75 MWac generation capacity added in the remote highest yielding solar PV areas. • With a 20 year payback of lines, and thus a 10% (R35 Mil) per annum repayment, and 2200 kWh/kWpeak/annum yield of a 86 MWdc single axis tracker plant (189 GWh/annum ), the transmission infrastructure cost would be 18 c/kWh (or 25% increase on a 70 c/kWh tariff) for dedicated transmission infrastructure. Source: Eskom Strategic Transmission Planning, pers. comm., 2016 Response to Question 2: Can lower yields be offset by savings on transmission losses and new transmission infrastructure costs? Yes, with about 2.5% reduction in transmission losses and R 350 Mil / 75 MWac (or 18c/kWh) transmission infrastructure costs to keep developing the highest resource areas, it would seem like large parts of the country with lower (~10%) solar PV yields could be developed at the same or lower overall cost to the consumer. Further benefits of moving solar PV development out of the highest resource areas include: • • • • • Existing and already paid infrastructure Eskom capital Time Dedicated vs shared infrastructure Utilisation (regionally centralised battery storage?) Source: Eskom Strategic Transmission Planning, pers. comm., 2016 Question 3: What would the tariff effect of nodal pricing need to be to enable development in lower resource areas? Tariff (R/kWh) Correlation Between Single Axis Tracker Yield and Tariff 1000 1200 1400 1600 1800 2000 Yield (kWh/kWpeak) 2200 2400 2600 2800 3000 Tariff Variance Map Single Axis Tracking Nodal Pricing Requirement Assumption: Tariff in highest yielding areas is 70 ZARc/kwh) Data Source: Own interpretation of GEOModel Solar, 2013 Response to Question 3: The effect of nodal pricing would need to be approximately 10 ZARc/kWh to enable the development of single axis tracking in neighbouring areas with available grid connection capacity. With a 20 ZARc/kWh nodal pricing development in Gauteng, Limpopo and Mpumalanga with all its available grid infrastructure would be on equal footing Question 4: How could nodal pricing be applied across different technologies? Nodal Pricing Across Technologies • Would one find the same results when doing similar calculations for other technologies such as Wind and CSP? - Probably not • If PV can be relocated and other technologies not, should available grid in areas with high wind and CSP potential be ring-fenced for those technologies and PV developed somewhere else? - Probably yes • Should there then be different nodal pricings applied to different technologies - Probably not Conclusion • The grid is only constrained in the highest resource areas. • For Solar PV the lower yields in some areas could be offset by reduced transmission losses, savings on grid infrastructure investment, and the more efficient utilisation of existing and new transmission infrastructure. • The same is probably not true for Wind and CSP development where the yield losses cannot be offset by these savings. • Nodal pricing could be used to enable development of lower solar resource areas and in doing so immediately overcoming current grid constraints. • The effect of nodal pricing would need to be in the region of 10 ZARc/kWh to achieve the objective of migrating solar PV development to areas with available grid capacity. This is significantly less than the >18c/kWh saving associated with the migration. • Nodal pricing should be determined from actual transmission losses, infrastructure costs, and other socio-economic considerations. • The same nodal pricing should be applied across all technologies. On Track Corné van der Westhuizen Project Development Manager juwi Renewable Energies (Pty) Ltd Tel. +27 (0)21 831 6129 [email protected] Questions?
© Copyright 2026 Paperzz