CHAPTER 16 MATERIALS REQUIREMENTS PLANNING Teaching Notes This chapter describes MRP, one of the standard topics in operations management today. The basic elements of any MRP system and the different uses of the term MRP are described including the evolution to ERP. The chapter also explains why MRP systems are needed and why they are difficult to implement in practice. After reading the chapter the student should have a grasp of not only what MRP is, but also how it can be successfully used. When I teach this chapter I start by describing the different possible definitions of MRP. In this connection, I find Figure 16.1, or something like it, to be a useful aid. Then I put a parts explosion example on the overhead PowerPoint like Table 16.4. This example brings out computational questions and also helps to illustrate some of the concepts behind MRP. I finish by discussing issues related to MRP implementation and its impact on manufacturing and service companies. In teaching this chapter you may find Plossl’s (1994) book on Orlicky’s approach to MRP in the original Orlicky (1975) book to be useful references. The other good references are the book by Toomey (1996) and the article by Rondeau and Lewis (2001) “…from reorder point to ERP”. Answers to Questions 1. Independent demand inventories exist to provide customer service. These inventories should be managed by a replenishment philosophy to constantly keep a supply of the product on hand. When independent demand inventories drop to a low level they are replenished. Dependent demand inventories exist for a different reason--to support manufacturing operations. These inventories should be managed by a requirements philosophy. More inventory is ordered only when dictated by the needs of the master production schedule. 2. Raw materials and work-in-process inventories should be based on the master schedule which reflects future production requirements rather than past demand history. Demand history reflects only past usage, and is usually not a reliable indicator of future manufacturing requirements. 3. Either of them could be correct since lead time depends on priority. The vendor is probably quoting an average or typical lead time of ten weeks. If your order is given high enough priority by the vendor, it may be possible to get it in only three weeks. 16 - 1 4. Historically, inventory was controlled by replenishment methods which relied on sophisticated mathematical models. MRP uses very simple mathematics but complicated information processing which requires data accuracy, massive data manipulation, and behavioral changes in the users. Thus, MRP requires a change in orientation away from sophisticated mathematical analysis and toward information systems management and behavioral issues. 5. A replenishment philosophy is reflected by an order point or target inventory system which replenishes the stock when it runs low. This approach is necessary since the company cannot control customer demand. On the other hand, a requirements philosophy is based on the procurement of inventory to support the master production schedule. Stock is not automatically replenished when it runs low, only when it is needed to meet future requirements. Since the company controls the master production schedule it also controls the demand for dependent demand inventories. 6. It is difficult to apply the ABC principle to manufacturing component inventories, because no component is of lesser importance than any other. For example, an expensive machine, which is being assembled, might be delayed for shipment due to lack of a C item just as for the lack of an A item. In this sense all components are critical for completion of the manufacturing task. 7. Enough safety stock should be carried to cover uncertainties in demand and lead times and still meet service level goals. Some safety stock of finished goods may be carried to act as a buffer between the customer and the master production schedule. Safety stock of partly assembled components may be carried so that finished products can be quickly assembled, and safety stock of raw materials may be carried as a buffer between vendors and the company. If the master production schedule is fixed and lead times are constant, no safety stock is needed. The role of safety stock is, therefore, to absorb variations in the master production schedule or in manufacturing or purchasing lead time. 8. The potential effects of an inflated master production schedule are unrealistic due dates for components, perhaps straining capacity, and additional inventory which is not needed. These effects can result in an MRP system which has low data accuracy and low usefulness because the results of the system are not believable. 9. The advantages of cycle counting over an annual physical inventory are: - more accurate inventory records - possibly less cost and effort - no loss of production due to plant closure for inventory counting - less expediting and stock chasing to locate lost parts - more accurate storeroom locations of parts - better physical security of the stockroom 16 - 2 10. A shop floor control system is needed for all manufacturing systems except those with a very simple product line, those with a short production lead time or those with a repetitive master schedule. In the case of a simple product line, e.g., a few products, the progress of manufacturing can be easily determined. Likewise, if the manufacturing lead time is short, there is not much work-in-process inventory on the shop floor and therefore little need for a shop floor control system. When the schedule is repetitive, in JIT systems, shop floor control is managed by means of a visual pull system. 11. The best financial control system stems from control of the physical flow of materials, people, and capacity in manufacturing. Financial control is the same as physical control except in different units of measure--dollars instead of physical units. While it is possible to establish financial control in aggregate dollar terms without physical control, the resulting financial control is not fully effective. 12. The company president may be right. The company should use MRP only if the potential benefits exceed the costs of installation and operation. In many cases, however, very small companies can receive sufficient benefits relative to cost -- due to the low cost of PC-based MRP software. 13. The loop should be closed unless the company has excess capacity or capacity can be easily adjusted. Otherwise, the master production schedule may be infeasible with respect to capacity, and as a result order priorities will be wrong. 14. a. Hotel. MRP could be used to explode the requirements for rooms into labor and materials needed. Each room generates requirements for maintenance, maid service, food service, food, linens, etc. b. Legal Office. The demand for various types of legal services could be exploded into labor needed including lawyers' time, secretarial time, research time, etc. These requirements could be time phased based on the actual times required for delivery of services. Answers to Problems 1. Gross Requirements On-hand/Scheduled Receipts Net requirements Planned Order Releases 1 2 80 50 270 16 - 3 Week 3 4 100 300 -200 270 5 200 200 2. a. Materials Plan: NAME: ***************** DATE: 18-Dec-02 SECT: ********* CHAPTER 16, PROBLEM 2 MATERIALS PLAN OLD HICKORY FURNITURE COMPANY WEEK *****PART***** ---------- -------------------CHAIR GROSS REQUIREMENTS: SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------LEG GROSS REQUIREMENTS: ASSEMBLY SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------BACK GROSS REQUIREMENTS: ASSEMBLY SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------SEAT GROSS REQUIREMENTS: SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------RAILS GROSS REQUIREMENTS: SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------LEGS GROSS REQUIREMENTS: SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ---------- -------------------- 1 2 ------- ------0 0 0 0 100 100 0 0 0 0 ------- ------0 0 0 0 50 50 0 0 0 350 ------- ------0 0 0 0 25 25 0 0 0 0 ------- ------0 0 0 0 40 40 0 0 360 300 ------- ------0 1400 0 0 100 100 0 1300 1300 1200 ------- ------0 1400 0 0 150 150 0 1250 1250 1200 ------- ------- 16 - 4 3 ------0 0 100 0 0 ------0 0 50 0 300 ------0 0 25 0 375 ------0 0 40 0 0 ------1200 0 0 1200 0 ------1200 0 0 1200 0 ------- 4 5 ------- ------0 500 0 0 100 100 0 400 400 300 ------- ------400 300 0 0 50 0 350 300 0 0 ------- ------400 300 0 0 25 0 375 300 300 0 ------- ------400 300 0 0 40 0 360 300 0 0 ------- ------0 0 0 0 0 0 0 0 0 0 ------- ------0 0 0 0 0 0 0 0 0 0 ------- ------- 6 ------300 0 0 300 0 ------0 0 0 0 0 ------0 0 0 0 0 ------0 0 0 0 0 ------0 0 0 0 0 ------0 0 0 0 0 ------- WEEK *****PART* **** 1 2 3 4 5 6 TOP GROSS REQUIREMENTS: 0 0 375 300 0 0 SCHEDULED RECEIPTS 0 0 0 0 0 0 PROJECTED ON HAND 30 30 30 0 0 0 NET REQUIREMENTS 0 0 345 300 0 0 PLAN. ORDER RELEASES 345 300 0 0 0 0 ---------- -------------------- ------- ------- ------- ------- ------- ------SPINDLE GROSS REQUIREMENTS: 0 0 1500 1200 0 0 SCHEDULED RECEIPTS 0 0 0 0 0 0 PROJECTED ON HAND 80 80 80 0 0 0 NET REQUIREMENTS 0 0 1420 1200 0 0 PLAN. ORDER RELEASES 1420 1200 0 0 0 0 ---------- -------------------- ------- ------- ------- ------- ------- ------CAPACITY PLAN FOR ASSEMBLY 1 2 3 4 5 6 ---------- -------------------- ------- ------- ------- ------- ------- ------CHAIR ASSEMBLY HOURS 0 0 0 800 600 0 LEG ASSEMBLY HOURS 0 350 300 0 0 0 BACK ASSEMBLY HOURS 0 0 375 300 0 0 ---------- -------------------- ------- ------- ------- ------- ------- ------TOTAL ASSEMBLY HOURS 0 350 675 1100 600 0 3. b. Seats, rails, legs, tops, and spindles should be ordered immediately. c. The 1000 hour capacity limit in assembly will cause problems in week 4, since the assembly time required to meet the plan is 1100 hours. Possible solutions include overtime, splitting lots so that some work is done in week 3 or 5 instead, or smoothing the master schedule so that there aren't so many assembly hours required during week 4. d. Using the assumptions in part(c), Changing the master schedule to 300 chairs in week 5 and 400 chairs in week 6 balances the assembly hours required so that now 150 hours are required in week 2, 575 in week 3, and 800 each in weeks 4 and 5. This plan would solve the problem in week 4 in assembly. a. Product Structure A ┌───────────┴───────────┐ B C ┌─────┴──────┐ ┌─────┴─────┐ D(2) E D F 16 - 5 b. To produce 200 units of A requires ordering 600 of D, 200 of E, and 200 of F. It requires assembling 200 of B, 200 of C, and 200 of A from the component parts. 4. a. NAME : ***************** DATE : 18-Dec-02 SECT : ************** CHAPTER 16, PROBLEM 4 MATERIALS PLAN FOR PRODUCT A PART ------ -------------------A GROSS REQUIREMENTS SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ------ -------------------B GROSS REQUIREMENTS SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ------ -------------------C GROSS REQUIREMENTS SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ------ -------------------D GROSS REQUIREMENTS SCHEDULED RECEIPTS PROJECTED ON HAND NET REQUIREMENTS PLAN. ORDER RELEASES ------ -------------------- 1 2 ---------- ------0 0 0 0 75 75 0 0 0 0 ---------- ------0 0 0 0 100 100 0 0 100 500 ---------- ------0 0 0 0 50 50 0 0 0 0 ---------- ------0 0 0 0 125 125 0 0 275 1125 ---------- ------- 3 ------0 0 75 0 0 ------200 0 100 100 0 ------0 0 50 0 200 ------400 0 125 275 250 ------- 4 5 ------- ------0 200 0 0 75 75 0 125 125 250 ------- ------500 0 0 0 0 0 500 0 0 0 ------- ------250 500 0 0 50 0 200 500 500 0 ------- ------1125 250 0 0 0 0 1125 250 0 0 ------- ------- 6 ------250 0 0 250 0 ------0 0 0 0 0 ------0 0 0 0 0 ------0 0 0 0 0 ------- b. 275 of part D and 100 of part B should be ordered immediately. c. (Projected inventory is in the solution of part a.) d. If 3 weeks is required to get part D, either the master schedule needs to be pushed back or lots should be split. An attempt to expedite the part could be made. In any case, the master schedule as it exists cannot be met. 16 - 6 5. a. He would need to know the following: - Are the parts available, either from inventory or from the supplier, within the lead time required? - Can the present work be expedited or the master production schedule changed to allow for the additional work? - Is capacity available in the form of additional worker hours, overtime, or subcontracting? b. The press hours are available - only 400 are scheduled on week 2 versus the 500 available. Assembly hours are not available, however, since over 700 of the 800 available hours are scheduled, and 300 additional hours are required. Based on the shop loadings, the additional 100 widgets cannot be made. c. Actions include: - Subcontracting - Overtime - Compressing the work done on widgets during weeks 3 and 4 so that some of the assembly could be done then. - Change the production schedule of other products to accommodate the extra widgets. - Negotiate for a later due date for part or all of the extra lot of 100 widgets. 16 - 7 6. a. Scissors Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 2 Left Side Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 2 50 100 50 400 Right Side Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 2 75 200 Screw Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 3 4 300 5 400 200 400 400 200 3 200 4 400 5 50 400 3 200 4 400 100 5 325 325 2 3 200 4 400 5 500 100 100 b. No effect, because the order of 200 Right-hand sides is not needed until week three. c. Maintain safety stock. _ __ ss = L (Z) = 1 (1.65)(50) = 82.5 Keep 83 pairs of scissors as safety stock to meet unanticipated demand at least 95% of the time. d. The preferred course of action is to ask the suppliers to reduce the variability of delivery lead time. If that is not possible, a safety lead time that gives the desired protection of the production schedule is recommended. For example, if each of the three component parts was ordered for delivery two weeks prior to the date of the planned order release, the probability of meeting the production schedule would be: (Probability associated with two standard deviations = .9772) Probability of having all three parts when needed = .9772 x .9772 x .9772 = .9331 16 - 8 7. a. NAME: ************************ DATE: 18-Dec-02 SECT: *********** CHAPTER 16, PROBLEM 7 LAMP ASSEMBLY **** WEEK **** *****PART***** 1 2 3 4 5 6 7 8 ------- -------------------- ----- ----- ----- ------ ------ ------ ------ -----LAMP GROSS REQUIREMENTS: 0 0 0 0 0 0 1000 1500 ON HAND/SCH RECEIPTS 200 0 0 0 0 0 0 0 NET REQUIREMENTS 0 0 0 0 0 0 800 1500 PLAN. ORDER RELEASES 0 0 0 0 0 800 1500 0 ------- -------------------- ----- ----- ----- ------ ------ ------ ------ -----SHADE GROSS REQUIREMENTS: 0 0 0 0 0 800 1500 0 ON HAND/SCH RECEIPTS 400 0 0 0 0 0 0 0 NET REQUIREMENTS 0 0 0 0 0 400 1500 0 PLAN. ORDER RELEASES 0 0 400 1500 0 0 0 0 ------- -------------------- ----- ----- ----- ------ ------ ------ ------ ------ 16 - 9 7. a. (continued) **** WEEK **** *****PART***** FRAME GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------NECK GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------SOCKET GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------BASE GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------- 1 0 100 0 0 ----0 0 0 700 ----0 300 0 0 ----0 200 0 500 ----- 2 0 0 0 0 ----0 0 0 1500 ----0 0 0 400 ----0 0 0 1500 ----- 3 0 0 0 0 ----0 0 0 0 ----0 0 0 1500 ----0 0 0 0 ----- 4 0 0 0 700 -----700 0 700 0 -----700 0 400 0 -----700 0 500 0 ------ 5 0 0 0 1500 -----1500 0 1500 0 -----1500 0 1500 0 -----1500 0 1500 0 ------ 6 800 0 700 0 -----0 0 0 0 -----0 0 0 0 -----0 0 0 0 ------ 7 1500 0 1500 0 -----0 0 0 0 -----0 0 0 0 -----0 0 0 0 ------ 8 0 0 0 0 -----0 0 0 0 -----0 0 0 0 -----0 0 0 0 ------ Actions to be taken immediately include ordering 700 necks and 500 bases. 7. b. CAPACITY PLAN FOR ASSEMBLY ***WEEK*** 1 2 3 4 ------- -------------------- ----- ----- ----- -----FRAME ASSEMBLY MINUTES 0 0 0 10500 LAMP ASSEMBLY MINUTES 0 0 0 0 ------- -------------------- ----- ----- ----- -----TOTAL ASSEMBLY MINUTES 0 0 0 10500 TOTAL ASSEMBLY HOURS 0 0 0 175 16 - 10 5 6 7 8 ------ ------ ------ -----22500 0 0 0 0 4000 7500 0 ------ ------ ------ -----22500 4000 7500 0 375 66.67 125 0 175 hours are required in week 4, 375 in week 5, 66 2/3 in week 6, and 125 hours in week 7. If insufficient assembly time is available, the firm can either use overtime or adjust the master schedule. 8. c. If the lead time for assembly of lamps will be extended from one to two weeks, it will be necessary to find a way to obtain the 500 bases and 700 necks required to meet the 1000 lamps required in week 7. Perhaps the orders can be expedited or the 2 week lead time for frames compressed. a. 200 phones can be delivered from inventory in week 1, 250 can be assembled from handset and base subassemblies and delivered in week 2, and 125 can be assembled from component parts and delivered in week 3. Materials Plan: Phone Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 200 200 Handset Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 250 300 Base Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 250 250 Handle Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 75 200 Cord Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 75 75 250 2 250 3 125 250 125 125 2 125 50 75 3 2 125 3 75 125 125 16 - 11 2 3 125 2 3 Case Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 125 200 2 Circuit Board Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 125 150 2 Face Plate Gross Requirements On Hand/Scheduled Receipts Net Requirements Planned Order Release 1 125 300 2 b. c. 75 3 25 3 175 Week 1 200 300 200 75 250 200 150 300 Phones Handset Handle Cord Base Case Circuit Board Face Plates 3 Week 2 250 125 125 0 125 75 25 175 Week 3 125 0 125 0 0 75 25 175 This will not change the Materials Plan because we need handsets and bases before we can make more phones; our inventory of handsets and bases is zero. Our inventory of circuit boards is 25, indicating that more circuit boards are not required to assemble more phones. 16 - 12 9. a. **** WEEK **** *****PART***** BODY GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------HEAD GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------ARM GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------LEG GROSS REQUIREMENTS: ON HAND/SCH RECEIPTS NET REQUIREMENTS PLAN. ORDER RELEASES ------- -------------------- 1 0 25 0 175 ----0 50 0 0 ----0 60 0 340 ----0 80 0 0 ----- 2 0 0 0 0 ----0 0 0 150 ----0 0 0 0 ----0 0 0 320 ----- 3 200 0 175 0 ----200 0 150 0 ----400 0 340 0 ----400 0 320 0 ----- 4 0 0 0 0 -----0 0 0 0 -----0 0 0 0 -----0 0 0 0 ------ All orders are allowed one week for assembling. To meet the plan we need to order immediately 340 arms and 175 bodies. b. 25 robots can be assembled in one week and delivered to the customer ASAP. The implication from this example is that this MRP system needs one week in order to assemble the final product. For orders bigger than 25 we need the full four weeks to be able to deliver on time. c. This will move the order for heads one week ahead, so we need to place an immediate order for 150 units from that supplier. This will protect the MRP schedule and allow for assembly by week 4 as planned. 16 - 13
© Copyright 2026 Paperzz