ENGM 631 Optimization Ch. 10: PERT/CPM Variability of Activity Duration Until now we considered estimates of activity duration to be “most likely” times: a single, deterministic value for each activity and, hence, for project completion time Variability of Activity Duration The duration of an activity is not fixed Consider the time it takes to drive to some destination Project Duration –Variability of Activity Duration Activity duration is not a single, deterministic value There is a range of possible durations for most activities The range of possible activity durations can be presented as a distribution curve: Now consider a network of activities … Project Duration –Variability of Activity Duration Project duration is determined by the duration of activities on the critical path But the duration of each activity is variable. Each activity has a duration distribution: Project Duration: Example Longest path is A-D-E-G So project duration is 16 days But there is variability … Project Duration • In reality, actual activity times will vary, hence so will project completion time. • Might say that, e.g., project will be completed in 16 days, but also acknowledge it will likely be completed earlier or later than that. PERT (cont’d) • Program Evaluation and Review Technique • PERT is a method that treats completion times as probabilistic (stochastic) events • PERT was developed to deal with uncertainty in projects, and to estimate project duration when activity times are hard to estimate • PERT answers questions e.g. – What is probability of completing project within 20 days? – If we want a 95% level of confidence, what should the project duration be? PERT history Was developed in the 1950’s for the USA Polaris Missile-submarine program • USA Naval Office of Special Projects • Lockheed Corporation (now Lockheed-Martin) • Booz, Allen, Hamilton Corporation PERT Technique Assume duration of every activity is range of times represented by probability distribution PERT Technique (Cont’d) Distribution is based upon three estimates for each activity: a = optimistic m = most likely b = pessimistic a m b? The estimates are presumably based upon experience What should the pessimistic duration be? PERT Technique (Cont’d) Definite cut-off point for the pessimistic value PERT Technique (Cont’d) Now, given the a, b and m estimates, for every activity compute expected time te Where a = optimistic m = most likely b = pessimistic Example: Assume a = 3, m = 6, b = 15 Then te =7 PERT Technique (Cont’d) Also, given the a, b and m estimates, for every activity compute the standard deviation, Example: assume a = 3, m = 6, b = 15 Then = 2 PERT Technique (Cont’d) These formulas are based on assumption that each activity duration conforms to Beta distribution (not Normal distribution) Beta Distribution: – Not necessarily symmetrical – Definite cut-off points – A single peak a m b PERT Technique (Cont’d) Step 1: • For each activity calculate the te value (a + 4m + b)/6 • Everywhere in network, insert expected time, te Assume times shown are te, PERT Technique (Cont’d) Step 2: Identify the critical path, based on te values CP is A-D-E-G, which indicates expected project completion time is 16 days What is probability that project will be completed in 20 days? PERT Technique (Cont’d) Step 3: Consider the summative distribution of all activities on the critical path Assume distribution of project completion is normal, not skewed (justified by the Central Limit Theorem – discussed later) σ = standard deviation of project duration PERT Technique (Cont’d) Step 3 (Cont’d) Consider the summative distribution of all activities on the critical path An expected project completion date of 16 days means a 50% probability of duration being less than 16 days, (and 50% probability of it exceeding 16 days) 50% 50% PERT Technique (Cont’d) Step 3 (Cont’d): Consider the summative distribution of all activities on the critical path To determine the probability of finishing the project within 20 days, compute the area to left of 20 on distribution, P (x ≤ 20) ? PERT Technique (Cont’d) Te Ts z = (Ts – Te) / σ = standard deviation for project Z = number of standard deviations from mean project duration Technique (cont’d) Te Te = 16 Ts Ts =20 Te = expected project duration = Σ t e Ts = project completion time of interest Technique (cont’d) Step 4: Compute Te, , and variance for the critical path Assume the following: CP te 2 = V =variance A 1 1 1 D 7 2 4 E 2 1 1 G 6 1 1 16 = Te 7=V Vproject = ∑ VCP = ∑2 = 7 (see later why we add up variances) Technique (cont’d) Thus, VP = ∑ = 7, so = 7 Compute z–value Te Te = 16 For project duration of 20 days: Z= Ts - ∑ te p = 20 - 16 √ 7 = 1.52 Ts Ts =20 Technique (cont’d) P (z ≤ 1.52) = 0.93 (approximately 93%. As estimates are used, higher accuracy does not make sense) Technique (cont’d) Hence, conclude that there is a 93% probability that the project will be completed in 20 days or less Summary: The Role of PERT PERT does not reduce project duration However, it does the following: 1. Given a network with estimates a, m, and b as well as a value for project duration, it provides a probability figure for finishing on time 2. Alternatively, given a network with estimates a, m, and b as well as a desired level of confidence (probability figure, say 99%), it can calculate a project duration that corresponds with the level of confidence 3. It provides insight in the effect of variability of activity duration on the critical path Interpretation • Now the question is: How confident are we in the 93% estimate? How much do you trust that estimate? • 93% is high percentage. So, can we be very confident that project will be finished in less than 20 days? Interpretation Answer: 1. Confidence in estimates a, m, and b – If estimates are based upon experience backed by historical data, maybe we can believe the 93% estimate – If a, m, and b are guesses, be careful! If any of these estimates are substantially incorrect, the computed % will be meaningless 2. The method only considers the critical path and is misleading when near-critical paths could become critical PERT only considers the critical path There are often “near critical” paths Shortcoming: PERT only considers the critical path PERT only considers the critical path and is misleading when near-critical paths could become critical Merge-point bias: Two paths merging, each 50% chance of being on time 25% chance of finishing on time (or early) Merge-point bias Five paths merging, each with 50% chance of being on time Probability of project finishing on time = (0.5 5 .03 or 3%) c.a. 3% chance of finishing on time
© Copyright 2025 Paperzz