PPRP Meetings
•
•
First meeting was at RIBA, London on 5th Sept. 06
Second meeting was at Daresbury on 11th Oct06.
Panel consisted of
Jon Butterworth (Chair)
Iain Steele
Steve Boyd
Steve Holmes (FNAL)
Daniel Schulte (CERN)
Additional input from
External referees
ILC GDE R&D Board
LC-ABD programme addresses closely-connected areas
Beam Delivery System
Crab Cavity
Beam Dumps
Beam Quality and Stability:
Luminosity Production
LC-ABD: PPRP, 5 September 2006
Main Linac
Cavity Wakefields
Instrumentation
and Diagnostics
Fast Feedback
Survey, Alignment
and Stabilisation
Energy Spectrometer
Damping Rings
Polarised
Positron Source
A.Wolski
3
LC-ABD timescale is well-aligned with GDE project timescale
LC-ABD: PPRP, 5 September 2006
A.Wolski
4
PPRP Feedback
• Despite frequent requests for feedback, no
official response until Science Committee met on
31st Jan 07.
• We had submitted a letter to SC re-emphasizing
the quality of our work and the need for a 3-year
programme.
• We were given one year “bridging” funds of £3M.
• We were also asked to produce a 3-year
programme at approximately £3M p.a., which is
also in line with the PPRP priorities; details will be
provided by the WP managers later.
PPRP Scenarios
Visiting
Panel
• Optimal: represents the best use of
resources to maximise return, ~ 70% of
original cost
• Cut A: represents potential loss of
leadership, ~50% of original cost.
• Cut B: represents a strategic retreat from
the current successful position ~40% of
original proposed costs – aim to continue to
do some areas properly and pull out of others
completely.
I am still waiting for a detailed agenda from PPARC
The situation
is
made
harder
by:
SUMMARY
• The revised agreement between PPARC and CCLRC
whereby there will be no explicit contribution from
CCLRC to the ILC. Currently the CCLRC contribution
is approximately £0.5M p.a.
• Erosion of the cash value by Full Economic Costing.
For example, the cost of a university RA has
increased in some cases from around £50k p.a. to
£70k p.a. (both in 2006 £).
• Erosion of the cash value by inflation.
• The cessation of the accelerator studentships
programme; any project studentships will now have
to be supported from the project award.
• The completion of the EuroTeV programme. EuroTeV
funds had been used to bolster the PPARC/CCLRC
resource for LC-ABD phase 1
The Phase 2 SUMMARY
WP managers came up with
2 scenarios:
All in £k
2007/8 2008/9 2009/10 Total by WP
Scenario 1 3000.0 3316.8 3064.1
9380.9
Scenario 2 3000.0 4827.5
4553.2
12380.7
• Scenario 1 is likely to be (broadly) funded.
• The fine details of Scenario 1 are being worked out.
• Scenario 2 is an aspiration, as input to the STFC
Accelerator science review, due for this year. It represents,
approximately, the PPRP “cut A” scenario plus some delay.
Current
Status
SUMMARY
• A programme has been worked out under 2
scenarios (see above)
• The detailed programmes have been worked
out by WP managers/task leaders.
• Some optimisation is being addressed within
the Accelerator Institutes with respect to their
internal programmes.
• Some fine tuning with respect to the detailed
funding profile (new posts, key hardware etc.)
is ongoing.
• Phase 2 should have started April 1st 2007…