The Project Network The Critical Path

Introduction to Management Science
8th Edition
by
Bernard W. Taylor III
Chapter 8
Project Management
Chapter 8 - Project Management
1
Chapter Topics
The Elements of Project Management
The Project Network
Probabilistic Activity Times
Activity-on-Node Networks and Microsoft Project
Project Crashing and Time-Cost Trade-Off
Formulating the CPM/PERT Network as a Linear
Programming Model
Chapter 8 - Project Management
2
Overview
Uses networks for project analysis.
Networks show how projects are organized and are used to
determine time duration for completion.
Network techniques used are:
CPM (Critical Path Method)
PERT (Project Evaluation and Review Technique)
Developed during late 1950’s.
Chapter 8 - Project Management
3
Elements of Project Management
Management is generally perceived as concerned with
planning, organizing, and control of an ongoing process or
activity.
Project Management is concerned with control of an activity
for a relatively short period of time after which management
effort ends.
Primary elements of Project Management to be discussed:
Project Team
Project Planning
Project Control
Chapter 8 - Project Management
4
The Elements of Project Management
The Project Team
Project team typically consists of a group of individuals from
various areas in an organization and often includes outside
consultants.
Members of engineering staff often assigned to project
work.
Most important member of project team is the project
manager.
Project manager is often under great pressure because of
uncertainty inherent in project activities and possibility of
failure.
Project manager must be able to coordinate various skills of
team members into a single focused effort.
Chapter 8 - Project Management
5
The Elements of Project Management
The Project Network
A branch reflects an activity of a project.
A node represents the beginning and end of activities,
referred to as events.
Branches in the network indicate precedence relationships.
When an activity is completed at a node, it has been
realized.
Figure 8.2
Network for Building a House
Chapter 8 - Project Management
6
The Project Network
Planning and Scheduling
Network aids in planning and scheduling.
Time duration of activities shown on branches:
Figure 8.3
Network for Building a House with Activity Times
Chapter 8 - Project Management
7
The Project Network
Concurrent Activities
Activities can occur at the same time (concurrently).
A dummy activity shows a precedence relationship but
reflects no passage of time.
Two or more activities cannot share the same start and end
nodes.
Figure 8.4
Expanded Network for Building a House Showing Concurrent Activities
Chapter 8 - Project Management
8
The Project Network
Paths Through a Network
Table 8.1
Paths Through the House-Building Network
Chapter 8 - Project Management
9
The Project Network
The Critical Path (1 of 2)
The critical path is the longest path through the network;
the minimum time the network can be completed. In Figure
8.5:
Path A: 1  2  3  4  6  7, 3 + 2 + 0 + 3 + 1 = 9
months
Path B: 1  2  3  4  5  6  7, 3 + 2 + 0 + 1 + 1
+ 1 = 8 months
Path C: 1  2  4  6  7, 3 + 1 + 3 + 1 = 8 months
Path D: 1  2  4  5  6  7, 3 + 1 + 1 + 1 + 1 = 7
months
Chapter 8 - Project Management
10
The Project Network
The Critical Path (2 of 2)
Figure 8.6
Alternative Paths in the Network
Chapter 8 - Project Management
11
The Project Network
Activity Scheduling – Earliest Times
ES is the earliest time an activity can start. ESij = Maximum
(EFi)
EF is the earliest start time plus the activity time. EFij = ESij
+ tij
Figure 8.7
Earliest Activity Start and Finish Times
Chapter 8 - Project Management
12
The Project Network
Activity Scheduling – Earliest Times
LS is the latest time an activity can start without delaying
critical path time. LSij = LFij - tij
LF is the latest finish time. LFij = Minimum (LSj)
Figure 8.8
Latest Activity Start and Finish Times
Chapter 8 - Project Management
13
The Project Network
Activity Slack
Slack is the amount of time an activity can be delayed
without delaying the project.
Slack Time exists for those activities not on the critical path
for which the earliest and latest start times are not equal.
Shared Slack is slack available for a sequence of activities.
Figure 8.9
Earliest and Latest Activity Start and Finish Times
Chapter 8 - Project Management
14
The Project Network
Calculating Activity Slack Time (1 of 2)
Slack, Sij, computed as follows: Sij = LSij - ESij or Sij = LFij EFij
Figure 8.10
Activity Slack
Chapter 8 - Project Management
15
The Project Network
Calculating Activity Slack Time (2 of 2)
Table 8.2
Activity Slack
Chapter 8 - Project Management
16
Probabilistic Activity Times
Activity time estimates usually can not be made with
certainty.
PERT used for probabilistic activity times.
In PERT, three time estimates are used: most likely time
(m), the optimistic time (a) , and the pessimistic time (b).
These provide an estimate of the mean and variance of a
beta distribution:
mean (expected time): t  a  4m  b
6

2
variance: v   b - a 
 6 
Chapter 8 - Project Management
17
Probabilistic Activity Times
Example (1 of 3)
Figure 8.11
Network for Installation Order Processing System
Chapter 8 - Project Management
18
Probabilistic Activity Times
Example (2 of 3)
Table 8.3
Activity Time Estimates for Figure 8.11
Chapter 8 - Project Management
19
Probabilistic Activity Times
Example (3 of 3)
Figure 8.12
Network with Mean Activity Times and Variances
Chapter 8 - Project Management
20
Probabilistic Activity Times
Earliest and Latest Activity Times and Slack
Figure 8.13
Earliest and Latest Activity Times
Chapter 8 - Project Management
21
Probabilistic Activity Times
Earliest and Latest Activity Times and Slack
Table 8.4
Activity Earliest and Latest Times and Slack
Chapter 8 - Project Management
22
Probabilistic Activity Times
Expected Project Time and Variance
The expected project time is the sum of the expected times
of the critical path activities.
The project variance is the sum of the variances of the
critical path activities.
The expected project time is assumed to be normally
distributed (based on central limit theorem).
In example, expected project time (tp) and variance (vp)
interpreted as the mean () and variance (2) of a normal
distribution:
Critical Path Activity
 = 25 weeks
2 = 6.9 weeks
Variance
13
35
57
79
total
Chapter 8 - Project Management
1
1/9
16/9
4
62/9
23
Probability Analysis of a Project Network (1 of 2)
Using normal distribution, probabilities are determined by
computing number of standard deviations (Z) a value is from
the mean.
Value is used to find corresponding probability in Table A.1,
Appendix A.
Chapter 8 - Project Management
24
Probability Analysis of a Project Network (2 of 2)
Figure 8.14
Normal Distribution of Network Duration
Chapter 8 - Project Management
25
Probability Analysis of a Project Network
Example 1 (1 of 2)
Z value of 1.90 corresponds to probability of .4713 in Table
A.1, Appendix A. Probability of completing project in 30
weeks or less: (.5000 + .4713) = .9713.
2 = 6.9  = 2.63
Z = (x-)/  = (30 -25)/2.63 = 1.90
Chapter 8 - Project Management
26
Probability Analysis of a Project Network
Example 1 (2 of 2)
Figure 8.15
Probability the Network Will Be Completed in 30 Weeks or Less
Chapter 8 - Project Management
27
Probability Analysis of a Project Network
Example 2 (1 of 2)
Z = (22 - 25)/2.63 = -1.14
• Z value of 1.14 (ignore negative) corresponds to probability
of .3729 in Table A.1, appendix A.
• Probability that customer will be retained is .1271
Chapter 8 - Project Management
28
Probability Analysis of a Project Network
Example 2 (2 of 2)
Figure 8.16
Probability the Network Will Be Completed in 22 Weeks or Less
Chapter 8 - Project Management
29
Probability Analysis of a Project Network
CPM/PERT Analysis with QM for Windows
Exhibit 8.1
Chapter 8 - Project Management
30
Activity-on-Node Networks and Microsoft Project
The project networks developed so far have used the
“activity-on-arrow” (AOA) convention.
“Activity-on-node” (AON) is another method of creating a
network diagram.
The two different conventions accomplish the same thing,
but there are a few differences.
An AON diagram will often require more nodes than an
AOA diagram.
An AON diagram does not require dummy activities
because two “activities” will never have the same start and
end nodes.
Microsoft Project handles only AON networks.
Chapter 8 - Project Management
31
Activity-on-Node Networks and Microsoft Project
Node Structure
This node includes the
activity number in the upper
left-hand corner, the activity
duration in the lower left-hand
corner, and the earliest start
and finish times, and latest
start and finish times in the
four boxes on the right side of
the node.
Figure 8.17
Activity-on-Node Configuration
Chapter 8 - Project Management
32
Activity-on-Node Networks and Microsoft Project
AON Network Diagram
Figure 8.18
House-Building Network with AON
Chapter 8 - Project Management
33
Activity-on-Node Networks and Microsoft Project
Microsoft Project (1 of 4)
Exhibit 8.2
Chapter 8 - Project Management
34
Activity-on-Node Networks and Microsoft Project
Microsoft Project (2 of 4)
Exhibit 8.3
Chapter 8 - Project Management
35
Activity-on-Node Networks and Microsoft Project
Microsoft Project (3 of 4)
Exhibit 8.4
Chapter 8 - Project Management
36
Activity-on-Node Networks and Microsoft Project
Microsoft Project (4 of 4)
Exhibit 8.5
Chapter 8 - Project Management
37
Project Crashing and Time-Cost Trade-Off
Definition
Project duration can be reduced by assigning more
resources to project activities.
Doing this however increases project cost.
Decision is based on analysis of trade-off between time and
cost.
Project crashing is a method for shortening project duration
by reducing one or more critical activities to a time less than
normal activity time.
Crashing achieved by devoting more resources to crashed
activities.
Chapter 8 - Project Management
38
Project Crashing and Time-Cost Trade-Off
Example Problem (1 of 5)
Figure 8.19
Network for Constructing a House
Chapter 8 - Project Management
39
Project Crashing and Time-Cost Trade-Off
Example Problem (2 of 5)
Crash cost and crash time
have linear relationship:
total crash cost/total crash
time = $2000/5 = $400/wk
Figure 8.20
Time-Cost Relationship for Crashing Activity 12
Chapter 8 - Project Management
40
Project Crashing and Time-Cost Trade-Off
Example Problem (3 of 5)
Table 8.5
Normal Activity and Crash Data for the Network in Figure 8.19
Chapter 8 - Project Management
41
Project Crashing and Time-Cost Trade-Off
Example Problem (4 of 5)
Figure 8.21
Network with Normal Activity Times and Weekly Activity Crashing Costs
Chapter 8 - Project Management
42
Project Crashing and Time-Cost Trade-Off
Example Problem (5 of 5)
As activities are crashed, the critical path may change and
several paths may become critical.
Figure 8.22
Revised Network with Activity 12 Crashed
Chapter 8 - Project Management
43
Project Crashing and Time-Cost Trade-Off
Project Crashing with QM for Windows
Exhibit 8.6
Chapter 8 - Project Management
44
Project Crashing and Time-Cost Trade-Off
General Relationship of Time and Cost (1 of 2)
Project crashing costs and indirect costs have an inverse
relationship.
Crashing costs are highest when the project is shortened.
Indirect costs increase as the project duration increases.
Optimal project time is at minimum point on the total cost
curve.
Chapter 8 - Project Management
45
Project Crashing and Time-Cost Trade-Off
General Relationship of Time and Cost (2 of 2)
Figure 8.23
A Time-Cost Trade-Off
Chapter 8 - Project Management
46
The CPM/PERT Network
Formulating as a Linear Programming Model
The objective is to determine the earliest time the project
can be completed (i.e., the critical path time).
General linear programming model:
Minimize Z = xi
subject to:
xj - xi  tij for all activities i  j
xi, xj  0
Where:
xi = earliest event time of node i
xj = earliest event time of node j
tij = time of activity i  j
Chapter 8 - Project Management
47
The CPM/PERT Network
Example Problem Formulation and Data (1 of 2)
Minimize Z = x1 + x2 + x3 + x4 + x5 + x6 + x7
subject to:
x2 - x1  12
x3 - x2  8
x4 - x2  4
x4 - x3  0
x5 - x4  4
x6 - x4  12
x6 - x5  4
x7 - x6  4
xi, xj  0
Chapter 8 - Project Management
48
The CPM/PERT Network
Example Problem Formulation and Data (2 of 2)
Figure 8.24
CPM/PERT Network for the House-Building Project with Earliest Event Times
Chapter 8 - Project Management
49
The CPM/PERT Network
Example Problem Solution with Excel (1 of 4)
Exhibit 8.7
Chapter 8 - Project Management
50
The CPM/PERT Network
Example Problem Solution with Excel (2 of 4)
Exhibit 8.8
Chapter 8 - Project Management
51
The CPM/PERT Network
Example Problem Solution with Excel (3 of 4)
Exhibit 8.9
Chapter 8 - Project Management
52
The CPM/PERT Network
Example Problem Solution with Excel (4 of 4)
Exhibit 8.10
Chapter 8 - Project Management
53
Probability Analysis of a Project Network
Example Problem – Model Formulation
xi = earliest event time of node I
xj = earliest event time of node j
yij = amount of time by which activity i  j is crashed
Minimize Z = $400y12 + 500y23 + 3000y24 + 200y45 + 7000y46 +
200y56 + 7000y67
subject to:
y12  5
y23  3
y24  1
4
y34  0
y45  3
y46  3
y56  3
Chapter 8 - Project Management
y12 + x2 - x1  12
y23 + x3 - x2  8
y24 + x4 - x2  4
y34 + x4 - x3  0
y45 + x5 - x4  4
y46 + x6 - x4  12
y56 + x6 - x5  4
x7  30
y67  1
x67 + x7 - x6 
xj, yij  0
54
Probability Analysis of a Project Network
Example Problem – Excel Solution (1 of 3)
Exhibit 8.11
Chapter 8 - Project Management
55
Probability Analysis of a Project Network
Example Problem – Excel Solution (2 of 3)
Exhibit 8.12
Chapter 8 - Project Management
56
Probability Analysis of a Project Network
Example Problem – Excel Solution (3 of 3)
Exhibit 8.13
Chapter 8 - Project Management
57
PERT Project Management Example Problem
Problem Statement and Data (1 of 2)
Given the following data determine the expected project
completion time and variance, and the probability that the
project will be completed in 28 days or less.
Chapter 8 - Project Management
58
PERT Project Management Example Problem
Problem Statement and Data (2 of 2)
Activity
12
13
23
24
34
35
45
Chapter 8 - Project Management
Time Estimates (weeks)
a
m
b
5
7
3
1
4
3
3
8
10
5
3
6
3
4
17
13
7
5
8
3
5
59
PERT Project Management Example Problem
Solution (1 of 4)
Step 1: Compute the expected activity times and variances.
t  a  4m  b
6





v b-a
6
Activity
12
13
23
24
34
35
44
Chapter 8 - Project Management
t
v
9
10
5
3
6
3
4
4
1
4/9
4/9
4/9
0
1/9
2





60
PERT Project Management Example Problem
Solution (2 of 4)
Step 2: Determine the earliest and latest times at each node.
Chapter 8 - Project Management
61
PERT Project Management Example Problem
Solution (3 of 4)
Step 3: Identify the critical path and compute expected
completion time and variance.
Critical path (activities with no slack): 1  2  3  4  5
Expected project completion time (tp): 24 days
Variance: v = 4 + 4/9 + 4/9 + 1/9 = 5 days
Chapter 8 - Project Management
62
PERT Project Management Example Problem
Solution (4 of 4)
Step 4: Determine the Probability That the Project Will be
Completed in 28 days or less.
Z = (x - )/ = (28 -24)/5 = 1.79
Corresponding probability from Table A.1, Appendix A, is .4633
and P(x  28) = .9633.
Chapter 8 - Project Management
63