Higher Level Skills Demand Led Training, Risk Management A South West Higher Level Skills Pathfinder Report This paper focuses on the key lessons learnt, through the pathfinder projects and other higher skills initiatives in respect of identifying and exploring failure and success factors for engaging in the development of new employer led training courses. In particular, it explores the inherent common risks, their indicators, their financial and reputational impact and the probability of occurrence through the provision of an exemplar risk register. Deborah Winwood 10/31/2011 Higher Level Skills Demand Led 2011 Training, Risk Management Contents Section 1 - Introduction .......................................................................................................................... 3 Background ............................................................................................................................................. 3 The rationale for the focus ..................................................................................................................... 4 Methodology........................................................................................................................................... 5 Section 2 - Risk Context .......................................................................................................................... 7 Benefits and Success ............................................................................................................................... 7 Benefits Management......................................................................................................................... 7 End Benefits .................................................................................................................................... 7 Project outputs ............................................................................................................................... 8 Project outcomes ............................................................................................................................ 8 Recovery of development costs .......................................................................................................... 9 Recovery of delivery costs .................................................................................................................. 9 Section 3 – Risk Analysis ....................................................................................................................... 10 The risk analysis .................................................................................................................................... 10 Background ....................................................................................................................................... 10 Assumptions...................................................................................................................................... 10 Categories ......................................................................................................................................... 10 Proximity ........................................................................................................................................... 11 Risk statements ................................................................................................................................. 12 Impact analysis.................................................................................................................................. 13 Probability analysis ........................................................................................................................... 15 Risk Rating ......................................................................................................................................... 15 Overall risk rating .............................................................................................................................. 16 Risk Appetite ..................................................................................................................................... 16 Risk Response Management ................................................................................................................. 16 Priority............................................................................................................................................... 17 Risk Maps .......................................................................................................................................... 18 Accountability ................................................................................................................................... 20 Summary ............................................................................................................................................... 22 Key Risk Factors................................................................................................................................. 22 Key success factors ........................................................................................................................... 22 Quotes ................................................................................................................................................... 23 Risks .................................................................................................................................................. 23 Benefits ............................................................................................................................................. 24 Appendix 1 – Data Collection Tool ........................................................................................................ 26 Appendix 2 – Example of first stage cause-consequence mapping ...................................................... 30 Appendix 3 – Example of early analysis of impact and probability ...................................................... 31 Appendix 4 – Sample of inherent probability data ............................................................................... 32 Appendix 5 – Glossary of Risk Terms .................................................................................................. 33 Final version 31/10/11 Page 2 Higher Level Skills Demand Led 2011 Training, Risk Management Section 1 - Introduction Background Engaging with the provision of demand led higher level skills courses is a high risk activity. Between 2006 and 2011 three regional Higher Level Skills Pathfinder Projects (HLSPP), funded by HEFCE, enabled significant employer led higher skills course development by mitigating the financial risk for HEIs through the provision of funding. This provided a test bed to trial the demand and response processes in a manner that encouraged the activity to become embedded more firmly in the region’s HEI strategies. The three HLSPPs had an overarching remit to stimulate the HEI response to employers higher level skills needs. Whilst each of the three pathfinders had different operating mechanisms they all funded and controlled a number of individual projects for their regional HEIs to produce employer led higher level skills training courses. The training courses developed ranged in duration, accreditation, level, delivery mechanisms, subject area, sector and learning hours. However, every one of them has provided information and lessons about the principles and parameters relating to the production of employer led provision. The debate about the use of the words “skills” and “training” in this context, is long over, therefore, in the context of this and associated documents the following terminology is used: 1. Higher skills – any learning and development of an individual, at level 4 or above equivalent, which is directly related to industry or business workforce competence. 2. New training course – used to describe any manner of learning developed for delivery, in response to specific employer workforce development demand, regardless of size, level, delivery style or content. Learning may be developed from scratch (bespoke), or through modification of existing materials. Delivery may be anything from one day workshops for standalone CPD, to major new ventures such as a full Masters level course. 3. Development Project – the whole life cycle required to obtain, clarify, and agree the demand for specific workforce development through to the point of delivery of the new training course. For the purposes of clear explanation within these documents this is divided into stages, and breakdown of which can be found in Table 1. a. Feasibility b. Start up c. Initiation d. Development of training course e. Delivery of training course f. Closure Through this paper the use of the term HEI (Higher Education Institution) should be read to include those FECs (Further Education Colleges) whose remit includes the provision of higher level education. Final version 31/10/11 Page 3 Higher Level Skills Demand Led 2011 Training, Risk Management This paper is concerned with focussing on the key lessons learnt, through the pathfinder projects and other higher skills initiatives in respect of identifying and exploring failure and success factors for engaging in the development of new employer led training courses. In particular, it explores the inherent common risks and their indicators that have been identified, their financial and reputational impact and the probability of occurrence. It is envisaged that it will assist HEIs or FECs who have the opportunity, through employer engagement, to develop and provide new demand led training courses, to more consistently evaluate their probability of success. It will enable them to evaluate whether the proposed development project for a new training course falls within their “risk appetite” as it stands, what controls and/or actions could be taken to reduce the risk to within “risk appetite”, and as a consequence assist with the decision making process regarding whether to authorise and/or fund such a programme. Success, in this instance, means: Delivery according to plan; Return on investment; Sustainability; Contribution to HEI strategies; Customer satisfaction. The rationale for the focus Whilst the majority of the new training courses developed were considered a success, a number of them could be considered to be failures, either partial or total. Failure constitutes those development projects that did not meet expected quality, cost or time criteria. Since the purpose of the pathfinder projects, above all, was to experiment with processes and to provide funding to mitigate the risks associated with cost, those projects that did run over budget, ran over time or had low learner numbers on delivery were not classified as failures. Only those that failed to complete were classified as failures. However, the potential financial and reputational impact is high and in a commercial context, where funding is HEI internal or by the employer these factors should be considered a failure. Indeed a number of the development projects that were allowed to continue despite their status, would in a commercial context have been closed down. As in any project context, the main causes of course development failure are: 1. Insufficient attention to checking that a valid business case exists for the production of a new training course; 2. Insufficient attention to the quality at the outset and during development; 3. Insufficient definition of the required outcomes, leading to confusion over what the project is expected to achieve; 4. Lack of communication with the stakeholders (employers, other educational parties, awarding bodies, industry associations, external funders) and interested parties (potential future customers, employer trade associations), leading to a higher skills training course being delivered that does not meet the original employer needs/demand; Final version 31/10/11 Page 4 Higher Level Skills Demand Led 2011 Training, Risk Management 5. Inadequate definition and lack of acceptance of project management roles and responsibilities, leading to lack of direction and poor decision making; 6. Poor estimation of duration and costs, leading to projects taking more time and costing more money than expected; 7. Inadequate planning and co-ordination of resources, leading to poor scheduling; 8. Insufficient measurables and lack of control over progress, so that projects do not reveal their exact status until too late; 9. Lack of quality control, resulting in the delivery of learning products that are unacceptable to the employer or are unusable. HLSPP experimentation has provided the means to collate quantities of data relating to the risks and issues that arose, their impact and the lessons learnt. Issues that arose centred on 1. Feasibility and business development 2. Development project management 3. Risk management and identification of success criteria The issues that arose around how to successfully conduct feasibility have been addresses by the SW HLSPP through: Production of an Employer Engagement Toolkit that defines the processes, documentation and procedure for engaging an employer, conduction ONA (Organisational Needs Analysis), producing an outline training specification and accessing appropriate HE resources. Provision of a training package for staff employed in a business advisory role for higher level skills. http://ee-toolkit.oucpld.com Publication of three employer engagement reports: o Report 1 - Higher Skills Literature Review; o Report 2 - Employer Engagement with Higher Education; o Report 3 - Strategies for Effective HE Employer Engagement. Project management risks and issues should be addressed through the adoption (and appropriate training for staff) of recognised project management methodologies such as Prince2. However, there are no clear publications or tools to assist with or reflect upon the risk management associated specifically with development projects producing new higher skills training courses. Risks will impact on finance and reputation and may have serious consequences if not adequately managed. Therefore, it is the lessons learnt about risk management of this work, coupled with an analysis of the risks that arose or were identified and their impact on the success criteria that have been explored, analysed and expanded. Methodology Qualitative and quantitative data was collected arising from the 28 SWHLSPP and the 13 SW LCHS (Low Carbon High Skills Project) new training course development projects in the form of the progress and closure reports. Further quantitative data was collected from 65 projects, using a data collection form specific to risk analysis. These projects included input from the NW HLSPP, NE HLSPP Final version 31/10/11 Page 5 Higher Level Skills Demand Led 2011 Training, Risk Management and other national co-funded projects and HEI’s own project work. The data collection form was designed specifically for the purpose of producing this paper and its associated documents, and is available at Appendix 1. Final version 31/10/11 Page 6 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 1. This data was evaluated as part of a CC (cause – consequence) risk impact analysis to identify: Success criteria; Risk factors; Risk indicators; Probability of occurrence; Impact of risk on success criteria; Proximity of risk factors; Chains of events; Possible action to reduce the risk either the likelihood of occurrence or the impact; Potential contingency action that could take place should the risk occur. Where there were no apparent ways to treat the risk and it could be tolerated; Samples of the cause – consequence analysis map can be seen at Appendix 2.Appendix 2 – Example of first stage cause-consequence mapping. The information and findings have been provided in the form of: 1. This paper; 2. Exemplar risk register (used in conjunction with this paper, and as a reference tool with the toolkit); 3. Toolkit - Template risk register spreadsheet; 4. Toolkit – Risk management user reference guide. Final version 31/10/11 Page 7 Higher Level Skills Demand Led 2011 Training, Risk Management Section 2 - Risk Context Benefits and Success Benefits Management In order to fully analyse the potential impact of risks that may affect the development project for a higher skills training course it is necessary to clearly define the expected outputs, outcomes and benefits. The research report “Strategies for Effective HE-Employer Engagement” Bolden et al, Feb 2010, was completed as an output from the SWHLSPP. This report finds that active engagement with employers is regarded as a core aspect of the academic mission within all types of HEI; and that it is regarded as contributing positively to all forms of education, not just CPD and workforce development. The impact of successful employer engagement is seen to reach into strengthening the work experience and employability of all their students, the teaching and learning, progression routes, research activities and their brand image. In addition, the success and international recognition as researchers of their academic staff was stated as a priority in some instances. Therefore, if employer engagement activity is undertaken by an institution with the intention of responding to employers’ workforce development needs through the provision of higher level skills training, it is important to appreciate how it effectively contributes to the academic mission through benefits realisation. End Benefits Figure 1 below, shows the typical benefits that could be expected by an HEI as a result of engaging an employer(s) with the intention of producing and delivering a new employer led higher skills training course, together with the strategic objectives to which they contribute. The sequence required for benefits realisation, together with the business change/processes necessary for support are mapped. Complex interdependencies are identified, therefore, overall success relies not just on managing the risks throughout the development project, but on careful change management once the new training course has been achieved. It was apparent from the available data that a number of the SWHLSPP new training courses were not sustained beyond initial delivery, consequently, making no significant contribution to overall strategic objectives. This was attributed, by the development HEIs, to the fact that: “Marketing and sustainability was not built into the development project” “Confusion about where in the university the course sits after production, and whose responsibility it was” “No provision was made to integrate it into mainstream activity or with other E-E activity” “We lost our main employer contact due to restructuring and because we had pitched too low down in the organisation there was no executive level support to continue” Final version 31/10/11 Page 8 Higher Level Skills Demand Led 2011 Training, Risk Management Figure 1 Project outputs Success of the training course project outputs can be measured in terms of: 1. On time; 2. On budget; 3. To the defined quality criteria (level of learning, size of learning, type of learning, planned accreditation achieved, delivery mechanisms); 4. Projected number of learners on first delivery achieved. Project outcomes Expected outcomes from a project can be defined as: 1. Income generation from skills training activity, measured as: a. Recovery of development costs; b. Recovery of first delivery costs; c. Income generation from sustained delivery of new training course. 2. Enhanced relationship between businesses and the HEI to encourage a broader range of joint activity, measure as: a. Employer satisfaction with new training course; Final version 31/10/11 Page 9 Higher Level Skills Demand Led 2011 Training, Risk Management b. Learner satisfaction with new course; c. Take up of new course by other employer businesses; d. Readiness of employer(s) to discuss and consider other E-E activity. 3. Enhanced academic engagement with industry. Recovery of development costs The HLSP projects funded the costs associated with the development of new demand led higher skills training courses in the majority of cases, as did the Low Carbon High Skills Project. In several cases the projects went “over budget” due to scope change or poor initial costing/financial planning, but the funding was sufficiently flexible to be able to cover the additional costs. Therefore, the risks to the HEI associated with an overspend were of low impact in that context, but could not be considered low if the funding had been internal or from an employer. However, in the SWHLSPP once the development fund had been consumed, all further work associated with developing new courses was funded by the employers. In this situation control of costs and timescale were a much higher priority, since recovery of development costs was built into the training delivery price. Therefore, overspend was a much higher risk. Development costs associated with the SWHLSPP funded development projects were analysed in depth, as a separate piece of work. The findings are available in the report “Employer engagement: the costs of the development and delivery of work-based learning experiences” available to download from the HEFCE website as a public report. http://www.hefce.ac.uk/pubs/rdreports/2010/rd22_10/rd22_10.pdf Recovery of delivery costs For those course for which the employer or learner paid in full for delivery of the training, delivery costs ranged from £25 per learner day to £390 per learner day, with the average price being £157 per learner day. The higher price paid was for a one off bespoke leadership course, priced per course, rather than per learner. The majority of bespoke courses commissioned by an employer were priced per course and included the cost of any development /revision of curriculum materials. When broken down by course length: Final version 31/10/11 Page 10 Higher Level Skills Demand Led 2011 Training, Risk Management Section 3 – Risk Analysis The risk analysis Background Risk can be defined as uncertainty of outcome, and risk taking is inevitable when developing a new course. Risk management seeks to manage the projects exposure to risk, such that risks are identified, evaluated and potential exposure to undesirable effects are minimised. In managing the risk associated with a development project the risk impact analysis will provide an overall risk rating as well as individual risk scores. To arrive at a risk rating each risk factor must be identified, evaluated for impact and probability, assessed for possible action and considered for proximity. In order for the institutional risks to be fully analysed in terms of impact, it is first necessary to understand the desired outcomes and expected benefits to the institution of realising a success. The benefits map at Figure 1Error! Reference source not found. shows the outputs, necessary business support processes, intermediate and end benefits, together with their interdependencies and realisation sequence. Assumptions In analysing and evaluating the risk associated with new higher level course development the following assumptions have been made: 1. The development project is not part of a funded test group and as such the emergence of risks resulting in over budget or significantly over time would not be tolerated. 2. The work is being undertaken on a commercial basis. Categories To enable clarity of risk analysis and subsequent risk management the risks associated with responding to employer demand for higher level skills training through the development of a new training course have been allocated to seven high level categories. These are: 1. 2. 3. 4. 5. 6. 7. Main output risks. Strategic and commercial risks. Financial risks. Legal risks. Organisational and management risks. Project delivery risks (operational). Training delivery risks. Therefore, the final risk register contains a high level risk statement for each category, followed by a detailed breakdown of the individual risks that will contribute to it. Final version 31/10/11 Page 11 Higher Level Skills Demand Led 2011 Training, Risk Management Proximity A development project for a new training course can be divided into six clear stages. See Table 1 below. In addition to risks that could occur at any time throughout the life cycle of the project there are risks that are specific to a particular stage (risk proximity). As the project progresses and stages are completed, those stage specific risks are no longer considered active and are no longer significant in the overall project risk rating. Therefore, the likelihood is that as the project progresses to plan, the overall risk rating of the project will reduce. Table 1 – Project Stages Stage 0 1 Any time throughout the full lifecycle Feasibility 2 Start up 3 Initiation 4 Development of training course 5 Training course delivery Closure 6 Final version 31/10/11 0 allocated for use in proximity scale to indicate that the risk could occur at any point during the whole lifecycle of the project Identification of potential demand for a new training course through ONA (organisational needs analysis) Identification of options to meet the demand Assessment of the viability of HEI developing new training course to meet the demand Presentation of recommendation to employer and other stakeholders Preparation of business case Identification and in principle agreement with partners Identification of risks Outline planning and costing Production of outline training specification Liaison with partners and outline agreement for input into development and/or delivery Identification of funding source Preparation and submission of bids for funding ( where appropriate) Agreement to commence work Detailed TNA (training needs analysis) to refine training specification Appoint project manager Detailed time and resource planning and costing Establish steering groups Draw up and agree contracts with suppliers Establish employer interest groups Define quality of training course Refine and update the project risks Appoint project team resources Contracting with suppliers and SLAs with partners Final agreement to produce the training course Production of all materials for new training course delivery and assessment Provision of resources for delivery Course accreditation (where planned) Control of work Management of risks and issues Activities and communication to ensure sustainability of delivery Delivery of learning to employer(s) workforce Refinement of new training course Completion of all documentation for project, funders and employers Handover of materials and responsibility for delivery to appropriate faculty Handover of marketing for sustainability to relevant departments Page 12 Higher Level Skills Demand Led 2011 Training, Risk Management Risk statements The qualitative and quantitative data collected was “cause-consequence” map analysed to identify each factor’s effect on the project outputs, educational outcomes and institutional benefits. Thus a series of statements was produced in the format of risk factor, leading to and the result. Risk factor – an event that might happen; Leading to - the chain of events that could follow; The result – the effect on the outputs, outcomes and benefits. The risk statements that relate to the seven categories identified are detailed in Table 2 below. Table 2 – Seven High Level Risks Risk no/category. 1. Main output risks 2. Strategic and commercial risks 3. Financial risks 4. Legal risks 5.Organisational and management risks 6. Project delivery risks (operational) 7. Training delivery risks Risk Statement There is a risk that if the status of the development project associated with the new course exceeds defined tolerances and quality criteria leading to one or more critical success factors being compromised the project may be closed early or fail to meet its projected learner and financial targets resulting in loss of realised benefits There is a risk that without clear direction and explanation from the HEI and its project partners and suppliers of their strategic, aims and ambitions for the new training course leading to the viability and reliability of the new course being compromised; resulting in loss of financial investment, reputational damage or financial claw back There is a risk that without accurate and clear costing and budgetary control the working capital required to meet the plans will not be available; resulting in time delays, critical path impacts and potential overspend There is a risk that without properly consulted contracts, agreements and understandings in place between the HEI and its third party suppliers and partners it will lead to misunderstandings, inconsistencies and an inability to quantify performance of those providers; resulting in issues going un-noticed, breakdown in relationships and the new course fails to meet its objectives and benefits There is a risk that the HEI processes and management are insufficient to support the resourcing necessary to develop and deliver the new course leading to an inability to maintain development and/or delivery to the defined plans; resulting in time delays that will impact on critical paths, delaying the course start dates; and affecting employer and internal faculty relationships There is a risk that the curriculum and/or delivery mechanism of the delivered training course does not align with the original employer needs and demand, leading to employer and/or learner dissatisfaction with offered course; no take up of delivered course and/or degradation in employer relationship and loss of longer term benefits There is a risk that without effective marketing, curriculum planning and clear transition plans the new course will not be attractive to a wider audience than the commissioning employer or the HEI faculties will not be able to support ongoing delivery; resulting in low learner numbers initially and on an ongoing basis, failure to achieve a return on investment and failure to realise institutional benefits Each of these high level categories was then analysed in detail to list the detailed risk statements that contribute to it. See the Template Risk Register for all risk statements. Final version 31/10/11 Page 13 Higher Level Skills Demand Led 2011 Training, Risk Management Impact analysis The impact or severity factor is defined as a measure of the expected degree of loss or damage (impact) from the most severe event associated with a risk factor and is derived from the severity level. The severity levels are classified as severe, major, moderate, minor and low. See Table 33 below. Table 3 – Severity Levels Severe Major Moderate Minor Low An event that, if it occurred, would cause program failure (inability to achieve minimum acceptable requirements) An event that, if it occurred, would cause major cost and schedule increases. Secondary benefits/requirements may not be achieved. An event that, if it occurred, would cause moderate cost and schedule increases, but important requirements would still be met. An event that, if it occurred, would cause only a small cost and schedule increase. Requirements would still be achieved. An event that, if it occurred, would have negligible effect on program. The severity includes several impact types. Impacts are divided into primary and secondary. Primary impacts are those that are directly related to the immediate outputs of the new course development project, whereas secondary are those that are related to the institutional outcomes and benefits. See Final version 31/10/11 Page 14 Higher Level Skills Demand Led 2011 Training, Risk Management Table 4 below. Final version 31/10/11 Page 15 Higher Level Skills Demand Led 2011 Training, Risk Management Table 4 – Impact Types Delivery Schedule Total Nonrecovery of development costs or increase of costs greater than 15% that would cause termination Increase in costs greater than 5% Total failure of delivery with no learners Significantly low learner numbers, delivered without full cost recovery Cost increases of not more than 5% Learners drop out of assessment of course Small cost increases that, in most cases, can be absorbed by the project Lower numbers than predicted, but costs still recovered No loss No loss Moderate Secondary Reputational/o Educational pportunity Internal Major schedule Not sustainable overrun so severe that project would be terminated by funder or employer Permanent loss of employer regard within networks affecting further engagement with sector Prolonged loss of recognition for expertise in subject area Withdrawal of institutional support for this type of demand led course 5 Significant schedule increase of more than 15% that could lead to reduction in employer support and low learner numbers Schedule increase of not more than 15% that may lead to lower employer support Small schedule increase up to 10% that, in most cases, would be absorbed by the project No increase Not sustainable after first pilot delivery without significant further investment in revision and marketing Adverse publicity with one employer affecting further engagement with employer in all areas of institution Affects learner perception of institution’s expertise or flexibility Withdrawal of faculty support for this type of demand led course 4 Sustainable with some modification of course Loss of opportunity to exploit employer relationship in other business areas Minor, adverse complaints affecting number of learners provided Adverse affect on motivation of learners to enrol on further courses of study Loss of capacity to update other mainstream courses through integration 3 Missed opportunity for collaboration with other institutions Loss of opportunity to update academic’s “Employability” 2 Concern restricted and repairable Negligible Negligible 1 Content sustainable with additional marketing No loss Low Minor Sustainability Final version 31/10/11 Severity Factor Development cost Major Severe Severity Level Impact types (an event that if it occurs will cause ) Primary Page 16 Higher Level Skills Demand Led 2011 Training, Risk Management Probability analysis The probability or likelihood factor (Table 5) is defined as a measure of the chance of an impact at that selected level of severity actually being incurred. The likelihood is assessed, in the first instance, assuming preventative management controls and actions have not been applied. Then, residual risk likelihood is assessed and assigned after the consideration of the proposed management measures (risk reduction action). Thus two probability ratings are given for each risk. Table 5 – Probability Factor Rating Project Delivery Probability Factors Based on experience with similar projects, the event: Probability Factor Chance Could be expected to occur during the project delivery 6 74% - 99.9% Could easily be incurred and has generally occurred in similar projects 5 57% - 73% An even chance of occurring in similar projects 4 40% - 56% Known to happen in similar projects 3 23% - 39% Has occurred in a minority of similar projects 2 6% - 22% Conceivable, but has rarely occurred in similar projects 1 0%-5% A sample showing inherent probability data can be seen at Appendix 4, Appendix 4 – Sample of inherent probability data. Risk Rating Each determined risk rating, was assigned a qualitative classification as low, medium or high as outlined in Table 6 below. This was derived from the risk score calculated as impact x probability (see Table 7 ) Table 6 – Risk Rankings High impact and probability risks posing a severe threat to project success. They require detailed assessment and immediate comprehensive action bring within risk appetite to reduce the risk. Risks that pose a threat to the success of the project. Some immediate action may be required to reduce their impact and/or probability, together with a comprehensive action plan. Risks with low impact or low probability that require a less detailed assessment and that could be accepted/tolerated. Their status should be monitored periodically for changes. High Medium Low PROBABILITY Table 7 –Risk Score Range 6 5 4 3 2 1 IMPACT FACTOR Final version 31/10/11 6 5 4 3 2 1 1 12 10 8 6 4 2 2 18 15 12 9 6 3 3 24 20 16 12 8 4 4 30 25 20 15 10 5 5 Page 17 Higher Level Skills Demand Led 2011 Training, Risk Management Overall risk rating The overall risk rating of the development project is calculated as the sum of the risk ratings assigned to each individual risk. A total of 60 detailed risks have been documented. The maximum score is 60x30 = 1800 and the minimum is 60x1 = 60. This is then categorised as low, medium or high. (The template risk register creates the colour automatically, based on the number of risks entered in the register) High Medium Low >720<1800 >300=720 <300 Risk Appetite The risk appetite is the amount of risk that the organisation is prepared to accept, tolerate or be exposed to at any point in time. It is about taking well considered risks where the long term benefits are expected to be greater than any short term losses. The risk appetite is not quantifiable; each institution will have to make their own decisions about how much risk they are willing to accept at the point of authorising a project to develop demand led higher skills training. The risk toolkit that has been produced provides an evidenced analysis of the full scale inherent risk associated with this type of project, together with evidenced analysis of how much the risk can be reduced, to become residual risk, through the provision of countermeasures. The data available from the SWHLSPP, which due to the project being experimental and a “test bed” for response, enabled inherent probability, impact and proximity to be analysed. The overall inherent risk rating of a typical new course development project was found to be 579 (medium). This is probably too high to be within “risk appetite”, since it resulted in 75% running significantly over time, 18% going significantly over budget, 13% resulting in early closure, 31% had commissioning employers withdraw during development, 42% had low learner numbers on delivery and 30% did not achieve their planned delivery mechanisms/accreditation . However, with appropriate control measures and mitigating actions implemented this overall risk can be significantly reduced. Analysis of the data available from the Low Carbon High Skills Project training course development and other national co-funded project course development, in which appropriate action was put in place to reduce the probability and impact of risks, the overall risk rating was found to reduce to a residual rating of 263 (low). This resulted in 7% running overtime, 14% going a small amount over budget, 0% had employers withdraw during development, 0% early closures, 7% with low learner numbers and 0% failing to achieve planned delivery mechanisms/accreditation. Risk Response Management The risks described assume that no risk countermeasure action has been undertaken; they describe what may happen in a worst case scenario. However, with appropriate risk reduction management actions many of the risks can be reduced to within “appetite” prior to authorising and commencing Final version 31/10/11 Page 18 Higher Level Skills Demand Led 2011 Training, Risk Management the new course development activity. Therefore, where appropriate, risk reduction action has been suggested that will reduce the probability and impact. A further risk rating is then calculated, giving a residual risk score. All of the identified risks should be continually monitored to determine whether the probability rating is increasing or decreasing dependent upon project influencing factors and progress. As the project progresses, one or more of the suggested risk indicators may become apparent, that could be indicative of the probability increasing. Decisions to implement reduction or contingency action must then be taken to reduce the rating back to within “appetite”. At the point where the probability increases to maximum then the risk has materialised and it should be transferred to the project issues register and immediate contingency action taken to deal with it. To assist with the risk management decision making the evaluated risks contained in the risk register need to be assessed and monitored dependent upon their priority. Priority When prioritising which risks to deal with, at least these three aspects must be considered: Probability (how likely is it that the risk will happen). Impact (how serious will it be, if it does happen). Proximity (how soon it will happen). Risks that are high impact, high probability and high proximity need to be dealt with before the unlikely, low impact risks that won’t happen in the early stages of the project. A series of risk maps can be utilised to aid management decision making when determining which risks to action in terms of putting countermeasures in place and when. Final version 31/10/11 Page 19 Higher Level Skills Demand Led 2011 Training, Risk Management Risk Maps The risk bubble map shown in Figure 2 High Level Risks – Magnitude – Inherent and Residual below provides a graphic representation of the seven high level risks identified earlier in Table 2 – Seven High Level Risks. The x axis is derived from the probability of the risk materialising, the y axis the worst case impact should the risk materialise, the bubble size is derived from the risk rating (the magnitude). The shading indicates the risk classification. The blue bubbles are the full inherent risk and the red bubbles indicate how the risk is reduced if the suggested control measures for each of the contributory detailed risks are put in place. Figure 2 High Level Risks – Magnitude – Inherent and Residual To prioritise actions it is necessary to examine each of the seven categories in detail using the detailed risks contained in the risk register, not just for probability and impact but also to consider when they might occur (proximity). As an example high level risk number 2, which relates to strategic and commercial risks, can be graphically shown as probability x proximity x impact (magnitude) see Figure 3, whereas, Figure 4 shows the risks as impact x probability x risk rating. Final version 31/10/11 Page 20 Higher Level Skills Demand Led 2011 Training, Risk Management Figure 3 – Strategic and commercial risks proximity, residual and inherent Figure 4 – Strategic and Commercial Risks Magnitude, Residual and Inherent Final version 31/10/11 Page 21 Higher Level Skills Demand Led 2011 Training, Risk Management We can see from the above that to prioritise the order of actioning risk control measures: 1. Risk 2a is high risk and could occur during project start up, but, can be brought within risk appetite by significant reduction in the probability. 2. Risk 2h is a moderate risk and risk 2i is a high risk, both could occur during project initiation and can be brought within risk appetite by significant reduction in the probability. 3. Risks2g and 2d are moderate risks and both could occur during development of the course and can be brought within risk appetite by reduction in the probability. 4. Risks 2b, 2c, 2e, 2f are bordering on low risk, could occur during development of the course, though the implementation of countermeasures does little to reduce the residual risk. Another consideration at the point of prioritisation may be the cost associated with action taken. The suggested action to reduce probability, reduce impact and any contingency action that may be taken should the probability begin to increase, can be found in the template risk register. It should also be noted that dealing with risks 2a and 2i alone will reduce the aggregate risk associated with the high level risk 2, though not to the same extent as dealing with 2a, 2h, 2i, 2g and 2d. Priority could, therefore be assigned as: Priority High Medium Low Risk number 2a,2i,2h 2g, 2d 2b, 2c,2e, 2f Source of risk Project management, Employer, Employer External, Organisational External, Organisational, External, External Once priority has been assigned and decisions made about which risks require risk management control action and individual should be assigned responsibility for taking the action (documented on the risk register) and any re-planning of overall stage plans carried out. A full set of bubble maps covering all seven high level risk areas can be seen in the ‘Exemplar Risk Register” on the ‘Bubble maps’ sheet. Accountability The success of risk and issues management activity relies on the project board or steering group accepting full accountability for the management of the project risks together with the project manager accepting full responsibility for managing risks. This does not mean that the project manager should be responsible for carrying out all of the mitigating actions, this should be assigned to a person for whom the mitigating action is most appropriate. A risk owner is assigned responsibility for monitoring the risk and reporting any changing status to the project manager. The type of risk indicator that has been documented for monitoring is a good source of information on which to base the decision about who should own the risk. For example, the person best placed to monitor the status of risks associated with changes to HEI strategies and policies, may be a steering group member who is the most senior HEI manager. Whereas, for some of the delivery risks the most appropriate person could be someone in the “course registrations” department. Final version 31/10/11 Page 22 Higher Level Skills Demand Led 2011 Training, Risk Management A mitigating action owner is assigned responsibility for putting the actions in place and controlling their effect. For example, in the case of the HEI strategies risks, the reduction action is linked to communications plans and briefings, therefore, the project manager may well be the most appropriate person. Whereas, for risks linked to contracting it may be more appropriate to assign responsibility to the legal/contracting team. Because of the variety of different people involved with risk monitoring and control it is advisable that risk status monitoring and action progress is included in all regular progress monitoring and reporting processes. Final version 31/10/11 Page 23 Higher Level Skills Demand Led 2011 Training, Risk Management Section 4 - Conclusions Summary Comparison of data collected from the early stages of the HLSPP with data collected from later stages and other similar projects that commenced activity two or three years later, clearly shows that by acting on the lessons learnt in respect of project risks the probability of success can be significantly increased. Key Risk Factors The key risk factors that have been identified as having a significant effect on the success of a new course project include: Only one employer commissioning the new training course; Employer no funding or part funding development of new or revised materials; Late delivery of course; Low level of support within the commissioning employer organisation for the new course ; Lack of dedicated project manager; Lack of formal and workable HEI procedures to buy out/free up an academic’s time to develop new curriculum; Poor recording of employer skills gaps and course expectations; Lack of formal contracting; Lack of provision for marketing and customer relationship management. The other relevant risk factors that have been identified include: Lack of learner involvement; Lack of involvement of Sector Skills Councils/Professional bodies; No process for drawing up contracts/SLA agreement with employer; Poor planning when E learning is utilised; Complexity of validation not accounted for. Key success factors The key success factors, or action taken that significantly reduced the risk include: Courses commissioned by or involving more than one employer. A well argued business case and fully costed proposal made to the employer and agreed in writing. Employers funding or part funding development costs. Formal internal policies and working procedures for carrying out ONA, TNA and course specification. Formal policies and working procedures for enabling academics to engage with demand led course development and delivery. Final version 31/10/11 Page 24 Higher Level Skills Demand Led 2011 Training, Risk Management Appointment of an experienced project manager to control the whole life cycle. Alignment of new course subject matter with HEI/FEC areas of expertise and growth. Adoption of a formal project management methodology and techniques, such as Prince2 or similar to plan, monitor and control quality, budget, progress, communications, risks and issues, supplier management and contracting. Well planned sales and marketing plan, together with benefits realisation that includes all stakeholders internal (faculties and departments) and external (SSCs, trade associations, partner institutions). Irrelevant factors The following factors appeared to have little or no affect on the success of a new course project: Length of provision Level of provision Whether the course material/curriculum was bespoke or modification of existing. Quotes The following is a list of quotations relating to project risks and successes, from the institutions that provided data for the analysis of risk. Risks “The main contact in the employer company was made redundant and new contact had to be identified, once the company was able to refocus onto the project”. “Very little activity on course development in first half of 2009, due to the early retirement of the main contributor. This was the biggest cause of the delay to the project, as it was not possible to replace him due to the recession. This situation has now improved and the programme is moving as originally planned – but with approximately an eight month delay in timescales.” “Accredited training is expensive in terms of academic time and involvement, and it may not in the end be taken up once the most immediate learning needs have been met and the staff concerned returned to the workplace”. “Staffing can be volatile particularly if academics are only part time and liable to have various commitments”. “Allocation of IP rights - using multiple training providers to develop and deliver learning materials led to protracted discussions over materials and IP rights which have taken time to resolve. Lesson learnt is that it is better to start from day 1 with a contractual position on IP rights and allocation and ownership of them”. “It would seem that when people undertake a Training Needs Analysis their initial responses are not always the most accurate. There is a tendency for people to say what they think the researcher wants to hear and to answer from a slightly idealised perspective. When given the results and the implications of committing to the sort of project the results suggest is needed i.e. business study in this instance, people will then be more honest and vocal in their response. So TNA is possibly best done in segments to allow for false starts, revisions and a compatible and communicative relationship between researcher and subject to develop”. “Change of management structure – left a power vacuum in the organisation and no buffer against a very single focussed director. This slowed the pace of the project and made communications difficult”. Final version 31/10/11 Page 25 Higher Level Skills Demand Led 2011 Training, Risk Management “Employer engagement was an issue throughout the project, some Project Steering Group members failed to attend the second meeting and therefore did not make full use of opportunities to input into the modules’ development. More steering group meetings and regular updates would help to maintain employer engagement. Also appointing employer representative as Chair of Project Steering Group might help with sense of employer ownership and buy-in.” “Long time to get a formal partner agreement signed by key partners. In the early months this compromised the resource and time available to spend on the core curriculum development objectives of the project. To address partner buy-in at an early stage: include an initial propensity to partner workshop, in which all partners mutually establish their expectations, delineate resource issues and risks and institutional-level contingencies.” “Access to the in-house course materials was delayed by 4 months. Due to the innovative nature of the project, no University legal agreement templates were available. Time and resource had to spent on developing a tripartide agreement to define the role and responsibilities of the employer, institution and delivery partner. The need for contractual agreements needs to be considered at an early stage in the project”. “The length of time to come to validation event from the initial consideration has taken over 6 months and brought it into the window of end of year workload (marking and degree show) for the academic staff involved in the project – this has caused further delays and impacted on staff time availability for this project.” “Whilst adequate budget allocation was made to buy out the specialist academic time in reality it was incredibly difficult to find and attract a specialist consultant to backfill. This led to significant time delays that affected the critical paths of the project”. “The two modules were planned as 10 credit stand alone, this was not achieved because the delivery time and difficulty associated with validating from scratch made it unviable. We opted to incorporate them with an existing programme so that we could use a permitted change route instead”. Benefits “This project has brought substantial benefits in the form of an ongoing employer engagement project which now attracts co-funded student numbers. The project has also kept the HEI in close contact with a major player in the industry”. “Significant enhancement to reputation of HEI in terms of employer engagement and dealing with real issues”. “Significant relationship developed between BPC Applied Arts dept and Poole Pottery with future work placement and employment likely, mutual publicity potential and specialist teaching provision to BPC by master potter.” “Benefits to the University were seen to be better engagement with local organisations involved in management and planning of the marine and coastal environment; improvement of the knowledge locally and in the university; developing a reputation as an expert organisation in this area.” “One of the end results of this project is a very focussed and portable programme able to deliver great improvements to manufacturing and processing business organisations”. “Establishes the institution as a leader in the field of air quality and carbon management training. Creating employer engagement opportunities in the region and widening the network of external partners. Supporting the Centre’s research and reputation in the fields of air quality and carbon management. Supporting the Centre’s research and reputation in the fields of air quality and carbon management”. “Engagement with this project had given us the opportunity to address our key themes embedded within the college’s strategic plan. Which are explicitly: Innovation, Partnership, Quality and Agility”. “The project has provided the University with an opportunity to develop a unique model for the delivery of bite sized chunks of learning to meet a wide industrial base. It has also provided other departments within the Final version 31/10/11 Page 26 Higher Level Skills Demand Led 2011 Training, Risk Management University with a model for the development of curriculum and assessment which varies from the standard format and which can respond to the training needs of employers”. “The project has enabled the institution to understand, develop and embrace a much more flexible way to engage with and deliver training to local businesses. This has increased the number of businesses that we engage with and has increased the take up of HE level learning accordingly. Whilst we did not meet the intended outputs in terms of delivering stand alone accredited modules to learners, the material and modules have been absorbed into existing programmes and offered as options, which in turn has made the mainstream programme more flexible and attractive to learners.” Final version 31/10/11 Page 27 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 1 – Data Collection Tool Data collection tool - Demand led programme development Programme details, factors and drivers Strategic Aims and success factors that are applicable to your reasons for undertaking new demand let programme development Programme factors Output effects If Employer dropped out of development Engagement factors Factors that relate to the new programme being developed and/or delivered Revenue generation from initial delivery of programme Revenue generation from subsequent delivery of programme Full cost recovery of development costs Integration of developed material into other HEI programmes Use of employer contact for other activities such as KTP/research/placements Employer satisfaction with delivered programme Learner satisfaction with delivered programme Collaboration with other HEIs and/or professional bodies Increasing reputation with other employers and trade associations Increasing the engagement of academics with industry Building the recognition for specific expertise within the HEI community Encouraging first time HEI learners to engage more fully with other programmes of learning offered by your institution Planned length of development time (man-hours) if known Planned length of development time - output time in weeks (start to ready for delivery) Total budget for development of programme Development work funded by employer Development work internally funded by HEI Development work funded through other funding source - please state what Bespoke development Revised material/curriculum from existing training Off the shelf training with bespoke delivery mechanism Off the shelf training with existing delivery mechanism Level of provision (notional or actual) Short course/CPD accredited (HEI) (please specify length and level in comments) Short course/CPD professional body accreditation (please specify Professional body, length and level in comments) Short course/CPD unaccredited (please specify length in comments) Small programme accredited (please specify type, length and level in comments) Whole programme accredited (please specify type, length and level in comments) Total cost of delivering programme/training Price charged per learner (regardless of source of funds) Planned number of learners on first cohort Overspend on budget - please show as a percentage over budget Over time - please show as a percentage over time Under spend on budget - please insert the percentage under budget Under time - please insert the percentage under time Low learner numbers on first delivery - please show as percentage under High learner number on delivery - please show as percentage over No repeat business Not completed/closed early Planned accreditation not achieved Poor learner feedback Poor employer satisfaction Learners completed content but not assessment/accreditation Development costs not recovered Delivery costs not recovered Employer withdrew input into programme Impact score on 1-5 scale Comments Contingency action taken to replace Single employer - SME (5 - 250 employees) please state number of employees in the comments column) Single employer - large No employer involved Sector Skills Council (SSC) involved - please state which in the comments column Professional body or trade association involved - please state which in the comments column Final version 31/10/11 Page 28 Higher Level Skills Demand Led 2011 Training, Risk Management Employer funding development Delivery funded by employer Delivery funded by other source (i.e. Free to learner and employer) Please state source of funding Delivery funded by learner Full ONA and TNA carried out with employer(s) prior to commencing development work Clear Job/role descriptions/training plans for advisors Learners consulted during ONA/TNA Full proposal provided to and signed by employer ahead of development Multiple providers/partners involved Subject area/business sector (e.g. Creative industries, construction, engineering) please use the comments section to add Is this sector currently an area of economic growth? Clear internal strategy/process for academics to contribute to this type of programme development Is this subject area a current area of expertise for your HEI? Risks and issues that affected programme 1. Identify each of the following risks/issues that may have materialised during development of the programme, 2. then consider the impact of the factors that caused or contributed to the risk - please score on a scale of 1 to 5 (low is 1 and 5 is high) depending upon how much you consider it to have impacted 3. Please use the comments column to explain further the reasons or contributory factors. 4. If the risk/issue in column A was not applicable to the programme please leave the corresponding column C answers blank Development of material ready for delivery Risk that materialised Factors that caused or contributed to the risk materialising Score 1-5 Funding for External funding support changed due to strategic policy changes development Internal funding support changed due to strategic policy changes reduced or withdrawn Employer funding changed due to strategic changes Employer HEI has no processes for maintaining employer engagement during development changed Employer has no prior involvement with HE support for Employer sector market not buoyant programme Declining Company profit/turnover Employer goes out of business Changes to employer internal training strategies Changes to employer staffing structure No approval from senior management to engage with curriculum development No approval from senior management to commit learners to final programme Employer felt out of the process Employer unclear about delivery Inadequate business case Other - please explain Development Curriculum material being sourced from another provider - IPR issues over ran Use of other provider - HEI approval issues planned Curriculum material being sourced from Employer timescale More than one provider developing material (contract issues) More than one provider developing material (IRP issues) HEI resources (academic) not available as planned - please state reason e.g. Unable to buy out academic due to.... Partner resources not available as planned - please state reason Project management not available as planned HEI restructuring with no staffing contingency planned Physical resources not available E Learning, software/hardware issues Increase curriculum scope (not originally planned) Difficulty getting employer input Changed delivery requirements HEI strategy unclear Poor initial time planning Detailed ONA/TNA process unclear Other - please explain Development No original financial provision to buy out academic time overspend on Consultants had to be used to stay in timescale Final version 31/10/11 Page 29 Higher Level Skills Demand Led 2011 Training, Risk Management budget Employer driven increase to curriculum content Employer driven changes to delivery mechanism E learning software costs underestimated Poor initial financial planning Other - please explain Curriculum TNA inaccurate (Employer's process) misaligned with TNA inaccurate (HEI process) - please explain what, e.g. Incorrect level, content, size and why, employer e.g. Insufficient academic input demand Employer(s) did not maintain input via steering group requiring Employer(s) did not maintain input via direct curriculum input revision of Changed employer requirements - recession linked original planned Initial ONA provided as business case inaccurate due to quality of information - please explain scope or failure what might have contributed of programme Initial ONA provided as business case inaccurate due to quantity of information - please explain Other - please explain Delivery ONA inaccurate mechanism Resource availability misaligned with More effective methods identified and agreed employer Employer agreement not initially provided demand Other - please explain Planned No process to approve bite size learning accreditation Unable to meet professional body's requirements not achieved Final curriculum/assessment did not meet HEI quality requirements - please clarify, e.g. Level, size, content Insufficient funding planned into budget Employer pressure to not accredit Other - please explain Risks and issues that affected successful delivery of programme Low learner No contracted learners with employers at outset of development numbers on first Marketing to other employers not effective within timescale delivery Late delivery leading to employer loss Employer unable to fund (or individual for sole trader/self employed) Employer will not release learners to attend - please explain why Learners reluctant to register (where employer support is present) HEI registration process too slow Venue not attractive Other - please explain Learners did not No clear APEL policy and process complete Learners did not have sufficient time to complete assessment (employer cause) programme Assessment not completed due to insufficient opportunity (WBL) Prior learning levels Misalignment between delivery and assessment (staff) Cost of assessment No perceived value in assessment Other - please explain Delivery costs Pricing model incorrect not recovered Contract issue with employer Run as a loss leader Insufficient places sold Other - please explain Delivery not One employer specific -so further investment necessary to revise to more generic repeated Marketing not properly planned or executed Changed industry requirements Loss of employer contact due to staff changes in employer Loss of employer contact due to staff changes in HEI No clear indication of who owns programme/ where it sits within HEI faculties Predicted employer repeat delivery failed - please explain why HEI no interest Other - please explain Success Factors Please rate how successful you consider this programme to have been Final version 31/10/11 Page 30 Higher Level Skills Demand Led 2011 Training, Risk Management If 4 or 5, is this success attributable to any of the following factors? If 1, 2, 3, do you consider any of these would have made success more easily achievable Clear process for establishing how an employer will be kept engaged in the development Clear process for communicating with the employer(s) Clear process for initial ONA with an employer Clear process for negotiating level of learning Clear process for negotiating size of learning Clear process for negotiating type of assessment Detailed business case and proposal agreed by employer(s) up front Trained staff acting as advisors to employers during initial engagement and ONA Trained staff undertaking detailed TNA Alignment of programme content with HEI subject expertise Clear policy for engaging academic resources in development/delivery of demand led provision Clear costing model for development Clear costing model for delivery Dedicated project manager controlling development Clear marketing plans Involvement of Sector Skills Council(s) Involvement of trade associations/employer networks Academic champion Clear process for establishing contracts with employer(s) and other partners Clear process for approving other providers Effective due diligence on employer status/situation Final version 31/10/11 Page 31 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 2 – Example of first stage cause-consequence mapping Final version 31/10/11 Page 32 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 3 – Example of early analysis of impact and probability Final version 31/10/11 Page 33 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 4 – Sample of inherent probability data Final version 31/10/11 Page 34 Higher Level Skills Demand Led 2011 Training, Risk Management Appendix 5 – Glossary of Risk Terms Risk Term Meaning Risk Uncertainty of outcome, whether positive opportunity or negative threat Risk Framework The structure and methodology designed to be implemented across Aviva to ensure risk management is performed consistently across the Group. The uncertainty of outcome that exists prior to the application of any mitigating actions or controls – i.e. what could happen if we do nothing. The uncertainty of outcome that exists after the application of current mitigation actions and controls – i.e. where is the risk now, taking into account the controls currently in place (but not any planned future actions) Uncertainty associated with internal processes, people, systems, or external events. i.e. how we do things and the impact on us of external changes Uncertain financial impact due to changes in benefits realisation or future cash flows. i.e. is the new course worth what we expect and will we get the investment income we’re planning for? Uncertainty relating to impacts on our reputation Inherent Risk Residual Risk Operational Risk Financial Risk Reputational/ Educational Risk Emerging Risk Issue Events or changes which could happen in the future which we perceive might have a significant impact – often not fully understood in terms of impact or probability, but which require monitoring to enable us to prepare and respond appropriately. A holistic view of the key risks that need to be managed with a given business area. It should include all the major inherent risks and currently topical risks along with risks which, whilst still developing or speculative and difficult to quantify or assess, could become material (i.e. emerging risks). The risk environment should be derived through discussions with senior management who will own the risks. The Business Area Risk Report should include: A bubble map showing all the risks in the Risk environment and a second map with current high profile risks Narrative explaining the positioning of the high profile risks (i.e. which element of the scales have been used) Management’s view of whether the risks are within tolerance and, if not, what movement is required A summary of the status of Policies owned in that business area with rationale. (incorporating supporting Information on audit issues, breaches and similar (e.g. first line assurance) Clearly defined actions with an owner and time scale What exists when an uncertain outcome actually happens (i.e. a risk crystallises) Crystallise The process of an outcome ceasing to be uncertain and becoming an issue. Risk Register Risk Report Key Risk Indicator: Lead Lag Policies Identification Preventative Control An indicator (i.e. measure, ratio or assessment) that gives early warning that a business objective may not be achieved (at some time in the future). These can include: - Changes in the external risk environment - Impact of future internal change initiatives An indicator that measures the achievement of a business objective. These can include: - Variances from plan / target - Performance (including survey results) compared to target - Level of losses, errors or omissions Documents describing the principles and practices we must follow in managing governing and administrating the business. Process for discovering and documenting the risks faced. A process that stops a risk from crystallising into an issue. Final version 31/10/11 Page 35 Higher Level Skills Demand Led 2011 Training, Risk Management Risk Term Meaning Detective Control A process that identifies when a risk has crystallised in order for corrective action to be taken. Control adequacy Assessment of whether the control(s) are appropriately designed to mitigate the risk – i.e. if all the controls currently in place are operating effectively, will the risk be managed to within appetite/tolerance? Assessment of whether a given control is operating as it is designed to. Control Effectiveness Loss Event Impact Any issue that occurs that results in avoidable cost or reputational damage. These should be investigated and action taken to prevent repeat occurrences. A measure of how much risk we are prepared to take i.e. what is an acceptable level of risk for us? Risk Appetite (high level Group statements) Tolerance (lower level management discretion to accept / mitigate risks) A conscious decision, considering all the pertinent facts, not to take any further action to mitigate a risk. Quantification of the size of the risk – i.e. how much damage could it do ? Probability How likely is the risk to actually occur (crystallise) Risk Appetite/tolerance Risk Acceptance Four T’s: Treat (Reduce) Tolerate (Accept) Terminate (Avoid) Transfer (Transfer) - Final version 31/10/11 To put in place a containment or contingent control To accept there is an amount of risk in the activity but within tolerance / appetite The activity is too risky, we need to terminate or avoid the activity Transfer the risk to a 3rd party, e.g. Page 36
© Copyright 2026 Paperzz