Aloha Proof Module Design Cabled Observatory Mechanical Presentation School of Ocean and Earth Science and Technology February 2006 Aloha Phase 1 Mechanical Systems Main Assemblies: Float Package Proof Module Cable Termination Frame Bottom Line: -Mechanicals have gone smoothly -Manufacturing and testing complete -Final assembly remains -Quick tour or three main assemblies Buoyancy Test •Float allows for the retrieval of the proof module . •Link between termination frame and proof module will be cut by ROV. Proof Module Electronics Housing Assembly Seawater Return Titanium Shackle Strong-back AT&T MUX Status: -Manufacturing completed -Passed pressure testing -Partially assembled UH Electronics Endcap (tube not shown) Hydrophone Proof Module Cable Termination Frame Status: -Manufacturing and tension testing complete -Waiting for Tyco/ODI cable harness for final assembly Termination Frame Tension Test -Frame is inverted inside railway 20Kpounds-Passed