STAFF REPORT TO: City Center Redevelopment Authority DATE: May 19, 2016 FROM: Chad Eiken, Director, Community and Economic Development Director Subject: Approval of a Seventh Amendment to the Disposition and Development Agreement (DDA) for the Vancouvercenter development, Phase 2, located northwest of the intersection of 6th and Washington Streets Objective: Amend the existing development agreement to extend the construction start and completion dates by approximately 10 months, replace the existing penalty for missing the construction start date with an extension fee and other developer guarantees, clarify city commitment regarding lease by developer of city-owned Block 10 for construction staging, and establish a termination date if the agreement terms are not met by December 31, 2017. Present Situation: Vancouvercenter is a two-and-a-half block mixed use phased development located immediately east of Esther Short Park. As the second major project in the Esther Short Redevelopment Area, Vancouvercenter has already played a significant role in the revitalization of the downtown core. The first of two phases, completed in 2004, is currently occupied and consists of: three towers, two of which are residential (6 stories and 7 stories, respectively, with a total of 224 units) and one tower which is occupied by office, retail and restaurant uses (11 stories, 106,000 square feet); a public plaza; and an underground 809-stall parking garage which is mostly owned by the City of Vancouver and used for tenant and public parking, including events at the Hilton Conference Center, located to the southwest of the project site. The proposal is to develop the second phase (Unit 1D in the original agreement) tower as a sixstory building which will consist of 110 apartment units (20% affordable; 80% market rate) with a minimum of 2,200 square feet of ground floor retail space. The building would be constructed on the deck above the parking garage. The existing DDA as amended in December of 2014 has a performance requirement that construction of the building must start no later than December 31, 2015, or the Developer would be required to pay a penalty of $800,000, and this deadline was not met. The penalty originated as an “extension fee” in the original DDA in 1999 to offset loss of anticipated tax revenues and net parking revenues during the extension period between phases. This extension fee was subsequently amended in 2000 (Amendment #1) to become an annual payment from the Developer to the City. Three amendments later, in 2006, the annual payments were eliminated and a deadline for commencement of the fourth tower (Unit 1D) was set for June 30, 2010, and a “penalty” for non-performance of $800,000 was added to the agreement (Amendment #4). In 2010, the date for commencement of the fourth tower was extended by five years to June, 2015 (Amendment #5). In January of 2015, the date for commencement of the fourth tower was extended by one year, to December 31, 2015 (Amendment #6). To date, the City has not attempted to collect any of the $800,000 penalty. In November of 2015, the Developer indicated that substantial progress had been made in preparing the architectural plans and studies as of December 2015, but due to personnel changes in the design and development team, was not able submit the construction plans in time to obtain building permits and start construction by the deadline. Additionally, the Developer stated that it had been challenging to obtain financing for the project and, consequently, additional time would be needed to meet their obligations. An application for a building permit and a complete set of architectural and structural plans were submitted for the fourth tower on April 11, 2016 and are currently being reviewed by City planners and building plans examiners. The Developer is still working to secure project financing and indicates that this should be in place by August but no later than October 2016. The CCRA Development Committee met to discuss the proposed amendment on three occasions: March 3, April 14 and May 5, 2016. The Committee also sought the advice of Steve Janik, attorney with Ball Janik LLP, who has provided advice on other downtown development agreements. Four key themes came out of the discussions with the Subcommittee: 1) a willingness to accommodate the developer’s request to move the construction start and end dates if certain conditions are met; 2) a strong desire for there to be substantial yet enforceable consequences if the project does not meet certain timelines; 3) in lieu of the existing penalty for non-performance, the developer should pay a meaningful extension fee; and 4) if the project does not proceed as proposed, then the entire agreement should terminate and the developer should landscape the building footprint to mitigate for visual impacts until a building can be constructed. The proposed Amendment #7 would not modify the scope, size, uses, or density of the project established by Amendment #6. Key aspects of the proposed amendment to the DDA are as follows: Section 2.1 Developer Guaranty and Extension Developer commits that building construction will commence no later than October 31, 2016 Developer commits that building construction will be substantially complete no later than October 31, 2017 Developer agrees to place funds in an escrow account to be controlled by City in an amount sufficient to cover estimated permit fees, impact fees, and system development charges pertaining to the project (approximately $430,000) no later than June 30, 2016. Any fees already paid by Developer may be deducted from the amount to be placed in the escrow account. City agrees to release funds to Developer when said fees are due for purposes of paying required fees and charges Any funds remaining in the account as of October 31, 2017 will be retained by the City of Vancouver Developer agrees to pay an extension fee to the City of $25,000 immediately following Council approval of Amendment #7 Section 2.3 Construction Staging Adds a deadline for execution of a lease of the south half of Block 10 for construction staging of no later than July 31, 2016 Lease will extend to March 1, 2017 (original completion date from Amendment #6) and may be extended on a month-to-month basis at the sole discretion of the City Section 2.4 Non-Performance (Previously “Penalty”) City agrees to eliminate the existing lump sum penalty of $800,000 for nonperformance to be replaced by a daily penalty If construction is not substantially complete by October 31, 2017, the Developer will pay the City $3,000 per day for every day that construction is found not to be substantially complete (defined later in the amendment) If Unit 1D does not proceed to construction by October 31, 2017, Developer commits to install landscaping within the footprint of Unit 1D to mitigate for visual impacts to the surrounding area until such time as building construction commences. A minimum of 8 deciduous trees are to be provided Section 2.5 Term (New Section) If the terms of Amendment #7 are not satisfied by December 31, 2017, the entire Disposition and Development Agreement and its seven amendments shall expire Section 3.3 Definitions A definition of “substantially complete” which leaves little room for interpretation has been added. This definition is in the Original DDA, but is included in this amendment since several commitments depend on a clear understanding of what is meant by substantially complete. Advantages: Additional time is given to Developer to obtain permits and begin construction, while ensuring that construction is complete by October 31, 2017 Developer agrees to pay an extension fee to the City of $25,000 Developer agrees to pay a daily penalty for non-performance of $3,000 per day if the deadline for substantial completion of construction is not met City maintains option to not renew a lease of Block 10 to Developer for construction staging after March 1, 2017 as needed, for example if an interested party were to purchase Block 10 for redevelopment If the terms of the amendment are not met by December 31, 2017, the DDA and all of its amendments would terminate, which provides a substantial incentive to the Developer to complete the project Disadvantages: Reference to a lump sum penalty of $800,000 for non-performance would be deleted and replaced with other assurances and penalties; however, the City’s primary goal is for the tower to be built soon, and imposing this penalty would put the project at risk of not being completed as proposed Budget Impact: No impacts anticipated. The $800,000 penalty, which will be eliminated, has never been included as anticipated revenue in any city budget. Action Requested: Subject to public testimony received, recommend approval of the Disposition and Development Agreement, Amendment #7, to City Council. Exhibits: 1. Aerial Photo of Project Site 2. Chart Summarizing Initial DDA and Amendment Provisions 3. Draft 7th Amendment to Vancouvercenter DDA 4. Existing 6th Amendment to Vancouvercenter DDA
© Copyright 2026 Paperzz